Professional Documents
Culture Documents
Lesson Learned-Projects Use
Lesson Learned-Projects Use
Impact /risk
Related Work breakdown AREAS/ACTIVITI Priority Change : - Doc's/ policy/ Remarks
SR NO. Documents reference Observation date OBSERVATIONS/ISSUES LESSON LEARNED ( +ve or Action initiated
structure ES (1,2 &3) cost sheet/ specification ( Change implementation )
-ve )
1. immediate
action QMS Ref. 8.5.6, Control of
Reference of Quality 2. Within change. All results relating
Specific Activity i.e. concrete Observation Date Action taken as a result of effect on In all activities/Only in specific
observation, NCRs, Civil work good or bad observation Elaborate Lesson Learned Define its impact one week to the review of changes are
pouring and Close date Area or Activity, (End Action taken) activity
Site Instructions etc. 3. retained as documented
Within one information.
month
The steel for the tower foundation was improperly stored and Proper storage of
Steel was raped in tarpaulin and
prone to rust. Rusting not only cause decrease in area of steel but material saved the There has been no change in Already defined mehod is adopted
3 Material storage Site instruction Not Available Civil work Improper storage of steel
also weakens the bond between concrete and steel. Proper storage material from
Immediate polythene sheets to avoid rust and
work procedure. and got the required results.
damage
of material should be ensured to avoid rusting of steel damage
The NCR was raised because of constructing first and second layer
of access road with wrong thickness. The thickness should be As corrective action ,we properly
Thickness of first and second layer was We had to do extra There has been no change in Already defined mehod is adopted
5 Construction of Access road. NCR Not Available Civil work
not correct
according to IFC drawing .We invested more time and money to
work
Immediate leveled the surface and got require
work procedure. and got the required results.
fix the issue .Proper monitoring of site activities can reduce the thickness.
chances of such mistakes
Inspection procedure
No change is required, only
Improper installation of space Proper site supervision is required to install the space proper spacing Immediate Space dampers were installed as per remained same.However,we
8 Line hardware installation Site Instructions Not Available Electrical work already defined mehod is adopted
damper damper as per specification was maintained Action standard instructed the supervisors to
and got the required results
double check the work