Professional Documents
Culture Documents
Satip Nde LPT 01
Satip Nde LPT 01
00 30-Jun-17
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
1.0 DOCUMENT REVIEW SPECIAL PROCESS (NDE) REQUIRES BEST QUALITY PRACTICE, CPI & EFFICIENT METHODS IN PROCEDURES. PROPOSE BEST METHODS.
SAIC-LPT- SAIC-LPT-
1.1 LPT Procedures (Technique) RH RH NDE work is per approved Technique Proc.
2001 2001
SAIC-LPT- SAIC-LPT-
1.2 LPT Personnel Qualification Review RH RH Maintain Current Roster/CVs for NDE Techs.
2002 2002
SAIC-LPT- SAIC-LPT-
1.3 NDE Process Control Procedure* RH RH *Combine all NDE Methods applicable
2010 2010
2.0 EQUIPMENT
Visual Insp & Verification of LPT mat'ls SAIC-LPT- SAIC-LPT- Use SATR-NDE-2010
2.1 W* S
(Cleaner, Penetrant, Developer, etc) 2003 2003 Each day checked against In-Process work.
Storage, Handling & Preservation of LPT SAIC-LPT- SAIC-LPT- *Safety Checks are done for each In-Process application
2.2 W* S
materials (*See Safety Check) 2003 2004 listed below
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
3.0 APPLICATION IN-PROCESS VERIFICATION = DAILY SUPERVISION BY CONTRACTOR* (*Prime/Sub) OF NDT SERVICE PROVIDERS, & SAEP-1160 DATABASE UPDATES
Use SATR-NDE-2002
Water Washable Color Contrast (Visible SAIC-LPT- SAIC-LPT-
3.3 W* S * Prime Contractor & any Subcontractor
Dye) Penetrant Examination 2006 2006
** Notification as shown. See Notice.
Use SATR-NDE-2002
Solvent-Removable Color Contrast SAIC-LPT- SAIC-LPT-
3.4 W* S * Prime Contractor & any Subcontractor
(Visible Dye) Penetrant Examination 2007 2007
** Notification as shown. See Notice.
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
NOTICE (SAEP-1160, Section 9.2): Use of Welding and NDT SAICS 9.2.1 One SAIC per day per activity is required for production welding on a daily or continual basis, e.g., fit-up, in-process, and final
inspection. Applicable weld numbers must be entered in Remarks Box on the appropriate SAIC. 9.2.2 Special welding activities such as branch connections, tie-ins, sleeve installation, hot-tap welding, and
temperature tie-ins will require a separate IR per weld per activity in accordance with the applicable SATIP. 9.2.3 NDT subcontractors must complete NDT Checklists on a daily basis per above but not as an IR
with the exception of the start of NDT activities. SAIC-W-2008 details SAEP-1160 Data Reqmts for Welding with NDE Control per SAIC-LPT-2010.
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection