COST ESTIMATE FOR THE CONSTRUCTION OF PROPOSED BUILDING AT RAJARHAT,

AT PREMISES
Unit Action
Price of the AreaCivil
Entire :1, Plot No AC 223 works must be indicated below and this is
& Structural
mandetory. BOQ will be supplied at the time of finalisation of contract.
(Rates Base on WB. PWD. Sch. of Rates-2002 & 2007, including its addenda and corrigenda, )
Vendor may kindly add the left out items along with Unit Rate. Calculation basis shall be as perDetail Drawings/
Final Drawings/accepted additions alterations made at site
SL. NO. DESCRIPTION OF ITEM QNT. UNIT UNIT PRI

1 Supplying fitting fixing of sign-board, made of 25mm th 1


sal plank & on all sides of sal batten 50mm x 32mm.
a) mm x 600 mm size of board. ( Oppotional) No
[Ref: PWD Sdle item no.-47(ii), P-504, Section -1T]

2 Earth work in excavation of foundation trenches


in all sorts of soil (including mixed soil but
excluding laterite or sand stone) including
removing, spreading or stacking the spoils
within a lead of 75m as directed, inclding
necessary trimming of the trench sides,
ramming of surfaces, bailing out of subsoil
water, as per drawing ( Foundation Area X Depth).
a) Depth of excavation up to 1.50 m in bldg. fdn. 350.00 M3

b) Depth of excavation up to 1.50 m in UGR/ Fdn. M3


Boundary wall, drain etc.
[Ref: PWD Sdle item no.-1(a), P-64, Section -1A]

c) Depth of excavation 1.5 to 3.0 m in UGR. M3


[Ref: PWD Sdle item no.-1(b), Section -1A] 160.0

3 Filling in foundation by silver sand in layers


not exceeding 150 mm. As directed &
consolidating the same by thorough saturation
with water ramming complete. Including
the cost of supply of sand. ( Foundation Area X Depth) M3
a) Sand Fill bellow fdn.(M.R) 170

b) Filling in plinth to raise level by silver sand,


in layers. M3
[Ref: PWD Sdle item no.-3, P-66, Section -1A]

4 Digging Earth in R.C.C Ring Well ( Foundation Area X Depth).


a) Upto 3 m. below G.L. M

b) Beyond 3 m. upto 6 m. below G.L. M

c) Beyond 6 m. upto9 m. below G.L. M


[Ref: PWD Sdle item no.-1Ai(a,b,c), Section -1S Page-468]
5 Earth work in back filling in foundation treanches
or plinth with good earth in layers not exceeding
150mm . Including watering & ramming etc.
layer by layer complete With earth obtained from
excavation of foundation. ( Foundation Area X Depth)

a) In Bldg. Foundation 100.00 M3

b) In Boundary wall, Drain, UGR ( 4.5Mx2Mx1.825M). Etc. M3


[Ref: PWD Sdle item no.-2a. Section -1A] Page-64

5.1 Suppling, laying of Polithene Sheet ( 150 gm/Sq Meter) over


DPC or below flooring or roof terrancing in foundation trench `22.7 M2
( P-136 Item 13)

5.2 25 mm thick damp proof course with cement


concreate and ad mixure of water proofing
compound as per manufacturing spcn. Over a coat
of polymer lease paint double cleaned
complete as described/directed 11.7

Page-2
SL. NO. DESCRIPTION OF WORK QNT Unit

6 Earth work in filling in ground to raise the ground


level by good earth.
a.) With carried earth arrenged by the
contractor within a radius exceeding 5 km
but not exceeding 10 km including cost of
carried earth. 85.00 M3
[Ref: PWD Sdle item no.-2c(iv), P-66, Section -1A]

7 Single brick flat soling including ramming &


dressing bed to proper level and filling the joints
with powdered earth or local sand including cost
of all materials.
a). In Foundation & Plinth M2

b) In Boundary wall, Drain, UGR( 4.5Mx2Mx1.825M). Etc. M2


[Ref: PWD Sdle item no.-1, P-80, Section 1C]

8 P.C.C. (1:3:6) with 32mm graded stonechips in

a) Plinth of ground floor 17.000 M3

b) In Boundary wall, Drain, UGR ( 4.5Mx2Mx1.825M). Etc. M3


[Ref: PWD Sdle item no.-14/I/A(a), Section 1C]

9 Hire and labour charges for shuttering with


necessary staging up to a height of 4.0m
using stout props , hardwood planks, requ-
bracing including cost of wirenail, including
stripping off the same as per specifications
for straight or curved R.C.C members .
a) for 9to12 mm thick plyboard of good quality.

i) In foundation & Plinth 252.00 M2

ii) In ground floor up to ground floor roof 506.00 M2

iii) In 1st floor up to 1st floor roof 518.000 M2

iv) In 2nd floor up to 2nd floor roof 518.000 M2

v) In 3rd floor up to 3rd floor roof 519.000 M2

vi) In 4th floor up to 4th floor roof 519.000 M2

vi) In 5th storey above roof ( Stair oom) 230.000 M2

vii) In Sixth Storey above roof (M/C Room) M2

viii) In Boundary wall, Drain, UGR ( 4.5Mx2Mx1.825M). Etc. M2


[Ref: PWD Sdle item no.-16(c), P-94, Section -1C]

10 Extra for staging beyond 4 m. in any floor (Mode of


measurement : Area in plan X mean height of 12.600 M3
staging upto soffit of shuttering above initial 4 m.)
[Ref:PWD Sdle item no.-16(e),Section-1C,Pg-94]

Page-3

SL. NO. DESCRIPTION OF WORK QNT Unit

11 Reinforcement for reiforced cement concrete


supply of reinforcement bars , straightning
and removal of loose rust, cutting to requis-
ite length bending to correct shape, placing
in proper position and binding with 16gauge
black annealed wire at every intersection
including cost of wire as per drawing and
design, complete in tor / ribbed steel ( TATA-Tiscon).

i) In foundation & Plinth 9.82 MT

ii) In ground floor up to ground floor roof 7.85 MT

iii) In 1st floor up to 1st floor roof 8.205 MT


iv) In 2nd floor up to 2nd floor roof 7.835 MT

v) In 3rd floor up to 3rd floor roof 7.835 MT

vi) In 4th floor up to 4th floor roof 7.470 MT

vi) In 5th storey above roof ( Stair Room) 1.970 MT

vii) In Sixth Storey above roof( M/C Room) MT

viii) In Boundary wall, Drain, UGR( 4.5Mx2Mx1.825M). Etc. MT


[Ref: PWD Sdle item no.-19(a)/(i), P-96, Section -1C]

12 Cement concrete grade M-25 (mix not leaner than


1:1.5:3) with well graded stone chips (20mm.grade)
excluding shuttering & reinforcement. complete
design of concrete mix as per I.S.I code.
Cement- ACC/ULTRATECH) Including placement
of conduit pipe along with elcerical cables,
communication calbes as specified in the
specification attached and as per cabling layout.

i) In foundation & Plinth 102.00 M3

ii) In ground floor up to ground floor roof 50.00 M3

iii) In 1st floor up to 1st floor roof 57.00 M3

iv) In 2nd floor up to 2nd floor roof 57.000 M3

v) In 3rd floor up to 3rd floor roof 57.100 M3

vi) In 4th floor up to 4th floor roof 57.100 M3

vi) In 5th storey above roof ( Stair Room) 17.100 M3

vii) In Sixth Storey above roof ( M/C Room) M3

viii) In Boundary wall, Drain, UGR( 4.5Mx2Mx1.825M). Etc. M3


[Ref -PWD Sdle. Item no- 8(a), P- 84, Section-1C]

12.1 Ordinary Cement Concreate grade M 15 mix(4:2:1)


with well graded stone chips ( 20 mm size)
excluding shuttering and reinforcement, Including placement
of conduit pipe along with elcerical cables,
communication calbes as specified in the
specification attached and as per cabling layout.

a) In foundation and Ground Floor 22.22 M3


b) 5th Floor 7.94 M3

Page-4

SL. NO. DESCRIPTION OF WORK QNT Unit

13 Extra for using water proofing & plasticising


admixture @ 0.2% by weight of cement (or at
manufacturer,s specified rate) In RCC.
Note:- Payment on Volume of Concrete.
Volume of Concrete;
(M.R)
i) In foundation & Plinth 84.00 kg

ii) In ground floor up to fifth floor roof 244.00 kg

14 250 mm thick brick work with non modular ist


class bricks in sand cement mortar (4:1) in
superstructure
aa) in Foundation & Plinth 2.700 M3
a) In Gr. Floor 5.000 M3
b) In 1st Floor M3
c) In 2nd Floor M3
d) In 3rd Floor M3
e) In 4th.Floor M3
f) In 5th. Floor (Stair Room) M3
g) In 6th. Floor (M/C room) M3
h) In 7th. Floor (Above M/C Room Roof) M3
i) In Boundary wall, Drain, UGR( 4.5Mx2Mx1.825M). Etc. M3
(Ref: PWD Sdle item no.25(b) & 31a&b Section 1C, Page No- 102/104 )
Including placement
of conduit pipe along with elcerical cables,
communication calbes as specified in the
specification attached and as per cabling layout.

15 200 mm thick Brickwork with non modular bricks


in sand cement mortar (4:1) in superstructure
a) In Gr. Floor M3
b) In 1st Floor 24.000 M3
c) In 2nd Floor 24.000 M3
d) In 3rd Floor 24.000 M3
e) In 4th.Floor 24.010 M3
f) In 5th. Floor ( Stair room) 9.200 M3
f) In 6th. Floor (M/C room) M3
(Ref: PWD Sdle item no.50(b) & 52a&b , Section 1C, Page no.- 112/114)
& Item No 31, Page 108
Including placement
of conduit pipe along with elcerical cables,
communication calbes as specified in the
specification attached and as per cabling layout.

Page-5

SL. NO. DESCRIPTION OF WORK QNT Unit

16 125 mm thick brickwork in sand cement mortar (3:1)


with 1st class bricks in superstructure.
a) In Gr. Floor 38.000 M2
b) In 1st Floor 34.000 M2
c) In 2nd Floor 34.000 M2
d) In 3rd Floor 34.000 M2
e) In 4th.Floor 34.000 M2
f) In 5th. Floor (Stair Room) 52.000 M2
g) In Boundary wall, Drain, UGR( 4.5Mx2Mx1.825M). Etc. M2
(Ref: PWD Sdle item no.34&46/i/a&b, Section 1C,Page no.- 104)
Including placement
of conduit pipe along with elcerical cables,
communication calbes as specified in the
specification attached and as per cabling layout.

17 Extra over item no.-16, for using HB. Netting at every


third layer in any floor M2
(Ref: PWD Sdle item no.35, Section 1C,Page no.- 104)

18 Brickwork (75mm thick) in sand cement mortar (3:1)


with 1st class bricks in superstructure including HB.
Netting in every alternate layers.
a) In Gr. Floor 27.000 M2
b) In 1st Floor 120.000 M2
c) In 2nd Floor 120.000 M2
d) In 3rd Floor 129.000 M2
e) In 4th. Floor 129.000 M2
(Ref: PWD Sdle item no.38b& 46/ii/a, Section 1C,no.- 106)
and Item 46 ( i), page 114
Including placement
of conduit pipe along with elcerical cables,
communication calbes as specified in the
specification attached and as per cabling layout.

19 Plastering with cement sand mortar on


wall or concrete surfaces, including cost of.
scaffolding, staging etc.
a) 25 mm thick (1:6) external wall surface
i) In Gr Floor 90.0 M2
ii) In 1st Floor 215.0 M2
iii) In 2nd Floor 215.0 M2
iv) In 3rd Floor 215.0 M2
v) In 4th Floor 215.0 M2
vi) In 5th Storey above roof 189.0 M2
vii) In 6th Storey above roof M2
viii) In 7th Storey above roof M2
ix) In Boundary wall, Drain, UGR( 4.5Mx2Mx1.825M). Etc. M2
[Ref: PWD Sdle item no.1(i)a& 4a/a, Section 1( I )]
Including placement
of conduit pipe along with elcerical cables,
communication calbes as specified in the
specification attached and as per cabling layout.

20 b) 15 mm thick (1:4) internal wall surface


i) In Gr Floor 205.0 M2
ii) In 1st Floor 511.0 M2
iii) In 2nd Floor 511.0 M2
iv) In 3rd Floor 551.0 M2
v) In 4th Floor 551.0 M2
vi) In 5th Storey above roof 115.0 M2
vii) In 6th Storey above roof M2
[Ref: PWD Sdle item no.1(ii)b&4b/a, Section 1( I )]
Including placement
of conduit pipe along with elcerical cables,
communication calbes as specified in the
specification attached and as per cabling layout.

Page-6

SL. NO. DESCRIPTION OF WORK QNT Unit

21 c) 10 mm thick (1:4) on ceilling surface.


i) In Gr Floor 375.0 M2
ii) In 1st Floor 210.0 M2
iii) In 2nd Floor 210.0 M2
iv) In 3rd Floor 210.0 M2
v) In 4th Floor 210.0 M2
vi) In 5th Storey above roof 50.0 M2
vii) In 6th Storey above roof M2
[Ref: PWD Sdle item no.1(ii)c&4b/a, Section 1( I )]
and Item 4 page 346
22 Making V-groove line (about 12mmx12mm) in plastered surface
a) External Wall surface 24.0 %M
[Ref: PWD Sdle item no.11, Section 1(I)]

23 Applying cement based synthetic multifunctional


rubber emulsion (Like SIKA LATEX) having adhessive
and waterproffing properties by mixing with water
in proportion (1bonding agent:4water:6cement)
(In two coats)
a) On toilet floors and wall surface up to lintel ht. 151.0 M2
b) On roof & all terrace surface, Inner surface of 228.0
the UGR( 4.5Mx2Mx1.825M) and OHR (8000L) M2
[Ref: PWD Sdle item no.64, Section 1(C)]

24 Neat Cement Punning about 1.5mm thick


a) on internal surface of OHR(8000L) & .
UGR( 4.5Mx2Mx1.825M) Foundation & Plinth 25.0 M2
[Ref: PWD Sdle item no.7, Section 1(I)]

25 35 mm thick Artificial stone flooring as per


specification.
a) In ground floor 145.0 M2
[Ref: PWD Sdle item no.3/iii, Section 1(D)]
b) Above roof at 6th storey M2
[Ref: PWD Sdle item no.3/iii, Section 1(D)]

25.1 25 mm thick Artificial stone flooring as per Spcn.


a) Ground Floor 76.0 M2
b) 5th Floor 23 M2

26 Post-constructional antitermite measures:-


a. Antitermite treatment to the out side of foundation with
chemical emulsion by addmixing chloropyrifos emulsifi
able concentrates (1% concentration ) with water by
weight, drilling 12mm.dia holes in concrete or masonry
apron at an interval of300mm. To a depth, of 300mm or
more as close to the plinth wall as possible and the che-
mical emulsion pumped into those holes to soak the soil
bellow at arate of2.25litres/liner metre compleat as per
speoification laid down in para 4.3.1.1 of code I.S.-6313
(PART-III)1981 60.4 Mtr.
[Ref: PWD Sdle item no.-2(b), Section -1R]

b Antitermite treatment to the junction of wood work and


masonry walls with chemical emulsion . The shutters are to
be sprayed with emulsion on both side all wooden fixtures
like allmirahs,racks etc are also to be throughly
sprayed with chemical emulsion. 79.4 M2
(Ref: PWD Sdle item no.2d Section 1R, )
Page-7

SL. NO. DESCRIPTION OF WORK QNT Unit

27 8 to 10mm thick Vitrified tile in approved shade


and brand in floor, skirting, set in Cement Sand
mortar(1:3), filling the joints with white cement
mixed with pigment matching with the shade of
the tile complete, (Size of tile 600x600)
in floor of Toilets. 68.0 M2
[Ref: PWD Sdle item no.17, Section 1( R )]

28 20 to 25mm thick Kota stone in floor, skirting, set


in Cement Sand mortar(1:4), filling the joints with
white cement mixed with pigment matching with the
shade of the stone complete, (Size of slab 600x600)

a) On kitchen and Stairs, 704.0 M2

b) On open terrace, Roof etc. M2

[Ref: PWD Sdle item no.28, Section 1( D )]

29 Marble in floor set in cement sand


mortar(1:2), filling the joints with white cement
mixed with pigment matching with the shade of
the marble complete, ( Size of slab > 0.40m2 )
20 to 25mm thick with Doongri, Aranga,
Baldevgarh, Agaria, Morwar etc.

a) floor loby, stair, passage inside the building, etc M2

b) Main entrance loby, toilets etc. M2

M2

[Ref: PWD Sdle item no.23(c/i), Section 1( D )]

30 Supplying fitting fixing of granite slabs 10 to12mm


thick, of slab size up to 0.10m2 in skirting, border
Kit. Counter, etc. set in cement sand mortar(1:4),
filling the joints with white cement mixed with pig-
ment matching the shade of the granite complete. 14.300 M2
[Ref: PWD Sdle item no.32, Section 1( D )]

31 Supplying fitting fixing of 1st quality porcelain tile


of any size in dado in toilet and kitchen, dining etc.
set in cement sand mortar(1:4), filling the joints with
white cement mixed with pigment matching with
the shade of the tile complete.
Coloured decorative any shade other than white. 289.6 M2
[Ref: PWD Sdle item no.16/iii, Section 1( D )]

32 Supplying Fitting Fixing of wooden frame for doors


as per drawing with 1st class best Indian teak. M3
(Ref: PWD Sdle item no.1(a), Section 1G, Page-208)

a) with Siliguri Sal 5.5

b) with 1st Class Teak ( M.R) 0.9

Page-8

SL. NO. DESCRIPTION OF WORK QNT Unit

33 Supplying fitting fixing of 35mm thick solid flush


door decorative type one side teak vinered and
other side laminate finish, complete.
a) Ground Floor M2
b) 1st Floor M2
c) 2nd Floor M2
d) 3rd Floor M2
e) 4th Floor M2
f) 5th Floor (Above Roof) M2
[Ref: PWD Sdle item no.105/a & 95, Section 1(G)]

34 Glazed shutter of doors as per design with sheet ( at balcony)


glass of 5.0mm thick with teak bead and nails
including fitting fixing complete in ground floor
a) 50 mm thick shutter with teak wood
i) 1st Floor 9.3 M2
ii) 2nd Floor 9.3 M2
iii) 3rd Floor 9.3 M2
iv) 4th Floor 9.3 M2
[Ref: PWD Sdle item no.98 & 95, Section 1(G)]

35 Supplying fitting fixing of teak wood cover moulding


(50mm x 37.5mm) Mtr.
[Ref: PWD Sdle item no.53a, Section 1(G)]

36 Supplying fitting fixing of teak wood corner moulding


(50mm x 12mm) Mtr.
[Ref: PWD Sdle item no.53 & 54, Section 1(G)]

37 Wood work in upper rails of railing, hand rail of


staircase etc. including supplying, fitting fixing
complete, with 1st class indian teak wood. 0.1 M3
[Ref: PWD Sdle Item No.5/a, Section 1(G)]

38 Supplying fitting fixing of Hydarulic door closer of


approvrd quality as per ISI Standard, heavy type. Each
[Ref: PWD Sdle item no.43 , Section 1(G)] ( Opptional))

39 Supplying fitting fixing of Brass door stopper of


approvrd quality and make. Each
[Ref: PWD Sdle item no.39/i , Section 1(G)]( Opptional)

40 Supplying fitting fixing of Stainless Steel Hinge of


approved make for fixing of door shutter including
cost of S.S. screws complete ( Opptional)
a) 125mm long Each
a) 100mm long 859.0 Each
[Ref: Non Sdle item no.-1]

41 Supplying fitting fixing of Stainless steel mat finish tower bolts


of approved make to fixi on the door shutter including
cost of S.S. screws complete ( Opptional)
a) 300mm long Each
b) 200mm long Each
c) 150mm long Each
[Ref: Non Sdle item no.-2]

Page-9

SL. NO. DESCRIPTION OF WORK QNT Unit

42 Supplying fitting fixing of Godrej Mortice lock with


latch and keys -6 lever including the cost of S.S.
screws complete 8.0 Each
[Ref: PWD Sdle item no.36/a, Section 1(G)]

43 Supplying fitting fixing of Godrej latch without keys


including the cost of S.S.screws complete 24.0 Each
[Ref: Non Sdle item no.-3]

44 Supplying fitting fixing of stainless steel mat finish


door handle of approved quality and make inclu- 32.0 Pair
ding the cost of S.S.screws complete
[Ref: Non Sdle item no.-4]
45 Supplying profiles of required section made of
aluminium alloy extrusions confirming to IS-733-
1983 and IS-1285-1975, anodised with required
thickness in bronze colour mat finished confirming
to IS-1868-1983, for fabrication of sliding or
casement window complete as per design and drawing.( Opptional)
A) 15 micron colour anodising
a) 2 Track sliding window
i) Bottom Frame M
[Ref: PWD Sdle item no.4B/a/i, Section 1(R)]
ii) Top and side frame M
[Ref: PWD Sdle item no.4B/a/ii, Section 1(R)]

c) Shutter for all track sliding window


i) Bottom and top member M
[Ref: PWD Sdle item no.4B/d/i, Section 1(R)]
ii) Style members M
[Ref: PWD Sdle item no.4B/d/ii, Section 1(R)]
iii) Interlocking members M
[Ref: PWD Sdle item no.4B/d/iii, Section 1(R)]

d) Fixed Glazing
i) Top, bottom and side member M
[Ref: PWD Sdle item no.4B/g/i, Section 1(R)]
ii) Mullion M
[Ref: PWD Sdle item no.4B/g/ii, Section 1(R)]
iii) Glazing Clip M
[Ref: PWD Sdle item no.4B/g/iii, Section 1(R)]

e) Louvered window
i) Top, bottom and side member M
[Ref: PWD Sdle item no.4B/h/i, Section 1(R)]
ii) Louver Section M
[Ref: PWD Sdle item no.4B/h/ii, Section 1(R)]

46 Labour Charge for fabrication and installation ( Opptional)


i) 2 Track siliding window M2
[Ref: PWD Sdle item no.5/A/i, Section 1(R)]
iii) Fixed Glazing M2
[Ref: PWD Sdle item no.5A/iv, Section 1(R)]
iv) Louvered Window M2
[Ref: PWD Sdle item no.5A/v, Section 1(R)]

Page-10

SL. NO. DESCRIPTION OF WORK QNT Unit

47 Supplying PVC Rollers for sliding windows as per


direction of the EIC.( Opptional) Each
[Ref: PWD Sdle item no.9, Section 1(R)]

48 Supplying EPDM Gasket of approved make and


brand as per direction of the EIC.( Opptional)
i) For sliding window
a) T shapped EPDM Gasket for frames M
[Ref: PWD Sdle item no.11/i/a, Section 1(R)]
b) U shapped EPDM Gasket for glass M
[Ref: PWD Sdle item no.11/i/b, Section 1(R)]

49 Supplying Maruti Lock -100m Pair


[Ref: PWD Sdle item no.10, Section 1(R)]

50 Supplying Bouble free float glass of approved make


and brand as per direction of the EIC.
i) 5 mm thick clear glass M2
[Ref: PWD Sdle item no.12/iii, Section 1(R)]
ii) 5 mm thick smoke glass M2
[Ref: PWD Sdle item no.12/iv, Section 1(R)]

51 Supplying fitting fixing of MS. Grill made of MS.


square bars, flats etc. complete.
i) Window Grill, stair railing, veranda grill etc.
a) Ground Floor 67.0 Kg
b) 1st Floor 566.0 Kg
c) 2nd Floor 566.0 Kg
d) 3rd Floor 566.0 Kg
e) 4th Floor 566.0 Kg
f) 5th Floor (Above Roof) Kg
[Ref: PWD Sdle item no.10/a/i , Section 1(F)]
ii) Grill gate and stair railing
a) Ground Floor Kg
b) 1st Floor Kg
c) 2nd Floor Kg
d) 3rd Floor Kg
e) 4th Floor Kg
f) 5th Floor (Above Roof) Kg
[Ref: PWD Sdle item no.10/b/i , Section 1(F)]

52 Rendering wall or ceilling surfaces with white putty


made of any approved brand and make, complete 2964.0 M2
[Ref: Non Sdle item no.-5] or with plaster of paris
Item 5, Pg 364

53 Supplying and Applying of Wodden primer


of any approved brand and make, complete 513.0 M2
[Ref: PWD Sdle item no.7, Section 1( K )]

54 Supplying and applying of Synthetic enamel paint


of any approved brand and make, complete
High Gloos in two coats other than white.
a) On timber Surface 513.0 M2
[Ref: PWD Sdle item no.8A/a/iv Section 1( K )]
b) On metal/ steel surface 175.0 M2
[Ref: PWD Sdle item no.8A/b/iv Section 1( K )]

Page-11

SL. NO. DESCRIPTION OF WORK QNT Unit

55 Supplying and applying of Paint on external wall surface


a) Cement base paint one coat M2
[Ref: PWD Sdle item no.14/ii Section 1( J )]
b) Weather Coat Paint three coat M2
[Ref: Non Sdle item no.-6]

56 Supplying applying of Metal Primer (Red Lead) of any


approved brand and make, complete
a) Two Coats 175.0 M2
[Ref: PWD Sdle item no.10/b, Section 1( K )]

57 Supplying and applying of Cement primer of any


approved brand and make, complete 2964.0 M2
[Ref: PWD Sdle item no.21, Section 1( K )]

58 Supplying and applying of Acrylic Emulsion paint


made of any approved brand and make, complete
a) Two Coats M2
[Ref: PWD Sdle item no.9/b, Section 1( K )]

59 French polish on wood work including preparation of


surfaces, colour as per direction of EIC.
i) On new surfaces M2
[Ref: PWD Sdle item no.18/a, Section 1( K )]

60 Lacqer finish on polished surface including preparation of


surfaces, colourless mat finish as per direction of EIC.
i) On polished surfaces M2
[Ref: Non Sdle item no.-7]

61 Appling protective & decorative texure 100% premium


Acrelic finish exterior paint of approved quality as per manufacturers
specification and as per direction of ETC over one coat of
cement based primer complete 1200.0 M2

SANTARY & PLUMBING WORKS,

SL. NO. DESCRIPTION OF WORK QNT Unit


1 Supplying fitting fixing of GI ( M) pipes of TATA make
with all necessary accessories specials viz. socket,
bend, tee, union, cross, elbo, nipple, long screw,
reducing socket, reducing tee, short piece etc.
fitted with clamps including cutting pipes making
thread, complete in all respect including the cost of
jointing materials and two coats of painting in any
position above ground.

i) 3/4 inch mm dia medium quality m


ii) 1 inch mm dia medium quality m
iii) 32 mm dia medium quality m
[Ref: PWD Sdle item no.1/d/ii, Section A-(II)]
v) 40 mm dia medium quality m
[Ref: PWD Sdle item no.1/e/ii, Section A-(II)]
vi) 50 mm dia medium quality m
[Ref: PWD Sdle item no.1/f/ii, Section A-(II)]
viii) 80 mm dia medium quality m
[Ref: PWD Sdle item no.1/h/ii, Section A-(II)]

2 Supplying fitting fixing of GI pipes of TATA make


with all necessary accessories specials viz. socket,
bend, tee, union, cross, elbo, nipple, long screw,
reducing socket, reducing tee, short piece etc.
fitted with clamps including cutting pipes making
thread, complete in all respect including the cost of
jointing materials and two coats of painting for
underground works.

i) 25 mm dia medium quality m


[Ref: PWD Sdle item no.2/iii, Section A-(II)]
ii) 32 mm dia medium quality m
[Ref: PWD Sdle item no.2/iv, Section A-(II)]

3 Supplying fitting fixing of peet's valve fulway


gunmetal standard pattern best quality of approved
brand bearing IS-Marking with fittings complete.

i) 20 mm dia each
[Ref: PWD Sdle item no.4/viii, Section A-(II)]
ii) 25 mm dia medium quality each
[Ref: PWD Sdle item no.4/vii, Section A-(II)]
iii) 32 mm dia medium quality each
[Ref: PWD Sdle item no.4/vi, Section A-(II)]
iv) 40 mm dia medium quality each
[Ref: PWD Sdle item no.4/v, Section A-(II)]
v) 50 mm dia medium quality each
[Ref: PWD Sdle item no.4/iv, Section A-(II)]
vii) 80 mm dia medium quality each
[Ref: PWD Sdle item no.4/ii, Section A-(II)]
Page-SAN-2
SL. NO. DESCRIPTION OF WORK QNT Unit

4 Supplying fitting fixing of CP. over brass Bib cock/


angular stop cock ( Gate Valve) of tested brand and approved
make complete.
i) 1/2 inch dia delux heavy type each
ii) 3/4 inch dia delux heavy type each
iii) 1.5 inch dia delux heavy type each
iv) 2 inch dia delux heavy type each
[Ref: PWD Sdle item no.8/b/i, Section A-(II)]

5 Supplying fitting fixing of CP. over brass concealed


stop cock of tested brand and approved make
complete.
i) 1/2 inch mm dia delux heavy type each
ii) 1 inch mm dia delux heavy type each
iii) 1.5 inch mm dia delux heavy type each
iv) 2 inch mm dia delux heavy type each
[Non Schedule Irem No-1]

6 Supplying fitting fixing of CP. over brass bottle trap


of tested brand and approved make complete.
i) 40 mm dia heavy type each
[Ref: PWD Sdle item no.-19/ii , Page-92, Section A-(IV)]

7 Supplying fitting fixing of CP. over brass basin mixer


of tested brand and approved make complete.
i) 15 mm dia delux heavy type each
i) 20 mm dia delux heavy type each
i) 25 mm dia delux heavy type each
i) 30 mm dia delux heavy type each
[Ref: PWD Sdle item no.-23/i , Page-94, Section A-(IV)]

9 Supplying fitting fixing of CP. over brass Shower


rose of tested brand and approved make complete.
i) 15 mm dia x 125mm each
ii) 20 mm dia x 125mm
iii) 25 mm dia x 125mm
iv) 30 mm dia x 125mm
[Ref: PWD Sdle item no.3/a/i, Section A-(II)]

10 Supplying fitting fixing of pocelain low down cistern


(Capacity-10.0 Lits) with inlet, overflow, brackets,
with all internal fittings of tested brand and approved
make complete.
i) Silver Gray each
[Ref: PWD Sdle item no.4 & NB: (b) , Page-70, Section A-(III)]

11 Supplying fitting fixing of PVC. low down cistern


(Capacity-10.0 Lits) with inlet, overflow, brackets,
with all internal fittings of tested brand and approved
make complete. each
[Ref: PWD Sdle item no.10 , Page-72, Section A-(III)]

12 Supplying fitting fixing of rain proof CI. Tank cover


500 mm dia with locking arrangements of tested
brand and approved make complete. each
[Ref: PWD Sdle item no.12 , Page-72, Section A-(III)]

13 Supplying fitting fixing of vitreous china best quality


wash basin of approved make, with brackets,( Opptional)
CP. over brass Waste (32mm dia), CP. over brass
Pillar Cock(15mmdia), approved quality PVC. Waste
Pipe 900mm long complete.
i) 450mmx300mm White each
[Ref: PWD Sdle item no.-2/i , Page-84, Section A-(IV)]
ii) 550mmx450mm White each
[Ref: PWD Sdle item no.-2/ii , Page-84, Section A-(IV)]
ii) 550mmx450mm Silver Gray each
[Ref: PWD Sdle item no.-2/ii & NB: (b), Page-86, Section A-(IV)]

Page-SAN-3
SL. NO. DESCRIPTION OF WORK QNT Unit

15 Supplying fitting fixing of Stainless Steel Sink


complete with waste fittings of approved make.( Opptional)
i) Sink Only each
[Ref: PWD Sdle item no.-6a(ii) , Page-86, Section A-(IV)]

16 Supplying fitting fixing of approved brand PVC.


Connector white flexible with both ends coupling
with heavy CP. over brass Nut 15 mm dia complete
ii) 600mm long each
[Ref: PWD Sdle item no.-10(iii) , Page-88, Section A-(IV)]

17 Supplying fitting fixing of approved brand PVC.


Waste Pipe white flexible with one end coupling
with heavy CP. over brass Nut 15 mm dia complete
i) 900mm long each
[Ref: PWD Sdle item no.-12(iii) , Page-90, Section A-(IV)]
18 Supplying fitting fixing of approved quality CP. over
brass flange complete. each
[Non Schedule Irem No-3]

19 Supplying fitting fixing of approved quality CP. over


brass extension piece (15mm dia, 75mm long)
complete. each
[Non Schedule Irem No-4]

20 Supplying fitting fixing of approved quality CP. over


brass grating (125mm dia,) complete. each
[Non Schedule Irem No-5]

21 Supplying fitting fixing of approved quality HDPE


pipe (Working pressure-6.0Kg/cm2) m
i) 40mm dia
[Ref: PWD Sdle item no.-26A(i) , Page-44, Section A-(II)]

22 Arranging municipal pipeline water supply connection


to the UGR. with ferrule dia between 20mm to 32mm
as approved excluding the official charges as demaded
by the KMC, but including all incidental charges. Ls
[Non Schedule Irem No-6]

23 Supplying fitting fixing of Centrifugal pump of approved


make and brand to lift water from the UGR.to OHR.
complete (Capacity-2.0HP.) Ls
[Non Schedule Irem No-7]

24 Supplying fitting fixing of HCI pipes confirming to


IS-3989 and IS-1729 with necessary jointing materials
and painting two coats of approved paint, complete.
a) With Lead caulked joint.
i) 100mm internal dia m
[Ref: PWD Sdle item no.1/b/ii, Section B-(II)]

Page-SAN-4

SL. NO. DESCRIPTION OF WORK QNT Unit

25 Supplying fitting fixing of HCI single branch equal


confirming to IS-1729 with necessary jointing materials
and painting two coats of approved paint, complete.
a) With Lead caulked joint.
i) 100mm internal dia with door each
ii) 100mm internal dia without door each
[Ref: PWD Sdle item no.2/b/ii, Section B-(II)]

26 Supplying fitting fixing of HCI double branch equal


confirming to IS-1729 with necessary jointing materials
and painting two coats of approved paint, complete.
a) With Lead caulked joint.
i) 100mm internal dia with door each
ii) 100mm internal dia without door each
[Ref: PWD Sdle item no.3/b/ii, Section B-(II)]

27 Supplying fitting fixing of HCI bend confirming to


ISS with necessary jointing materials and painting
two coats of approved paint, complete.
a) With Lead caulked joint.
i) 100mm internal dia with door each
[Ref: PWD Sdle item no.4/b/ii, Section B-(II)]
ii) 100mm internal dia without door each
[Ref: PWD Sdle item no.5/b/ii, Section B-(II)]

28 Supplying fitting fixing of HCI offset confirming to


ISS with necessary jointing materials and painting
two coats of approved paint, complete.
a) With Lead caulked joint.150mm projection
i) 100mm internal dia each
[Ref: PWD Sdle item no.7B/b/ii, Section B-(II)]

29 Supplying fitting fixing of HCI Trap confirming to


ISS with necessary jointing materials and painting
two coats of approved paint, complete.
a) With Lead caulked joint.150mm projection
i) 100mm internal dia P-Trap without AS horn. each
[Ref: PWD Sdle item no.14/A/a/iii, Section B-(II)]
ii) 100mm internal dia S-Trap without AS horn. each
[Ref: PWD Sdle item no.14/B/a/iii, Section B-(II)]

30 Supplying fitting fixing of HCI extension piece for


using in Trap only confirming to IS-3989 with all
necessary jointing materials and painting two coats
of approved paint, complete.
a) With Lead caulked joint.
i) 100mm internal dia x150mm each
[Ref: PWD Sdle item no.15/a/i, Section B-(II)]
ii) 100mm internal dia x300mm each
[Ref: PWD Sdle item no.15/a/iii, Section B-(II)]
iii) 100mm internal dia x450mm each
[Ref: PWD Sdle item no.15/a/v, Section B-(II)]
Page-SAN-5

SL. NO. DESCRIPTION OF WORK QNT Unit

31 Supplying fitting fixing of salt glazed stoneware pipe


with cement jointing (3:1) including excavation up to
1.5m depth in all sorts of soil but excluding
concreting at bottom and sides.
i) 150mm dia m
[Ref: PWD Sdle item no.16/iii, Section B-(II)]
i) 225mm dia m
[Ref: PWD Sdle item no.16/ii, Section B-(II)]

32 Supplying fitting fixing cement jointing (3:1) with


jute gasket soaked in cement mortar .
a) Stoneware Bend
i) 150mm dia each
[Ref: PWD Sdle item no.17/a/iii, Section B-(II)]
i) 225mm dia each
[Ref: PWD Sdle item no.17/a/ii, Section B-(II)]

33 Supplying fitting fixing of yard gully with approved


HCI grating complete
i) 225mmx150mm with 230mm grating each
[Ref: PWD Sdle item no.20/i, Section B-(II)]

34 Encasing 100 mm HCI /Stoneware pipe with 75 mm


thick cement concrete (6:3:1) with jhama khoa all
around. m
[Ref: PWD Sdle item no.21, Section B-(II)]

35 Supplying fitting fixing of SW master Trap


i) 225mmx225mm each
[Ref: PWD Sdle item no.22, Section B-(II)]

36 Supplying fitting fixing of orissa pattern water closet


in glazed virified china ware of approved make
excluding the cost of fixing concrete, complete
i) 580mmx440mm silver gray each
[Ref: PWD Sdle item no.5/i& NB:-b, Pge-168, Section B-(III)]
ii) 530mmx440mm white each
[Ref: PWD Sdle item no.5/ii, Section B-(III)]

37 Supplying fitting fixing of EPWC in glazed virified


chinaware of approved make with necessary bolts
nuts etc. complete
i) With P Trap silver gray each
[Ref: PWD Sdle item no.4a & NB:-b, Pge-168, Section B-(III)]
ii) With P Trap white each
[Ref: PWD Sdle item no.4a, Section B-(III)]
iii) With S Trap white each
[Ref: PWD Sdle item no.4b, Section B-(III)]

38 Supplying fitting fixing of closet seat of approved


make with lid and CP. Hinges, rubber buffer and
screws supplied, fitted and fixed complete.
a) EPWC Bestolite (solid type) white. each
[Ref: PWD Sdle item no.10/a/iv, Section B-(III)]

Page-SAN-6

SL. NO. DESCRIPTION OF WORK QNT Unit

39 Supplying fitting and fixing 32mm dia Polythene flush


pipe of make with necessary fixing materials and
clamps complete..
a) EPWC Bestolite (solid type) white. each
[Ref: PWD Sdle item no.10/a/iv, Section B-(III)]

40 Supplying fitting fixing of bevelled edge 5.5mm thick


mirror together with CP nuts etc.
a) 600mmx450mm each
[Ref: PWD Sdle item no.17/ii, Section B-(III)]

41 Supplying fitting fixing of glass self, ordinary type


with 5.5 mm thick sheet glass
a) 600mmx125mm each
[Ref: PWD Sdle item no.18/a/ii, Section B-(III)]

42 Supplying fitting fixing of liquid soap holder of


approved make
a) cromium plated each
[Ref: PWD Sdle item no.19/a, Section B-(III)]

43 Supplying fitting fixing of towel rail with two brackets


of approved make
a) cromium plated over brass
i) 25 mm dia 600m long each
[Ref: PWD Sdle item no.22/a/ii, Section B-(III)]

44 Supplying fitting fixing of soap tray


a) pocelain soap tray recessed type of size
150mmx150mm each
[Ref: PWD Sdle item no.24/ii, Section B-(III)]
45 a) Construction of inspection pit of inside measurements
600mmx600mm up to 600mm(depth) with 250 mm
thick at 1st Class brick work (1:6) on all sides,
bottom of the pit consisting of 100mm thick cement
concrete (6:3:1) with jhama khoa over a layer of FBS,
inside outside plaster and inside suface finished
with IPS and top covered with one 560mm dia RCC.
manhole cover of approved make supplied fitted fixed
with RCC. slab including necessary excavation ,
filling the side of the pits with earth obtained from
excavation complete in all respect. each
[Ref: PWD Sdle item no.1, Section B-(IV)]

Page-SAN-7

SL. NO. DESCRIPTION OF WORK QNT Unit

46 Construction of inspection pit of depth 1.5 mm inside


with 250mm thick at 1st Class brick work (1:6) on
all sides, bottom of the pit consisting of 100mm thick
cement concrete (6:3:1) with jhama khoa over a layer
of FBS, inside outside plaster and inside suface finished
with IPS and top covered with one 560mm dia RCC.
manhole cover of approved make supplied fitted fixed
with RCC. slab including necessary excavation ,
filling the side of the pits with earth obtained from
excavation complete in all respect. 1.0 each
a) 1050x750 (inside) chamber including fitting and
fixing of SW. master trap of 225 dia.
[Ref: PWD Sdle item no.1, Section B-(IV)]

47 Arranging municipal sewer line connection including


preperation and sanction of HD. Plan from KMC.
excluding the official charges as demaded
by the KMC, but including all incidental charges. Ls
[Non Schedule Irem No-1]
Vendor may kindly add the left out items along with Unit Rate. Calculation basis shall be as perDetail Drawings/
Final Drawings/accepted additions alterations made at site
Plint area is the built up covered area of the building measured at floor level of each storey ( G+4). Plint
area is calculated by taking the external dimensions of the building at the floor level excluding plinth off-sets,
if any courtyard, openareas, balconies cantilever projections are not included in the plinth area. Suported
porches ( other than cantilevered) are included in the plinth area. The excavation shall be pade only on the
basis of the plinth area.

Signature and Stamp of the Organisation


% rate w.r.t PWD