DEWA CONTRACT: 0172 ROP No: 2019/ 32

WEEKLY ROLL OVER PROGRAMME-CIVIL DATE:.03/08/2019

132/11kV GARDEN CITY SUBSTATION SHEETS: 2

PROG % ROLLED UP PROGRESS [%] - WEEK NO - 31 ROLLED UP PROGRESS [%] - WEEK NO - 32 ROLLED UP PROGRESS [%] - WEEK NO - 33 REMARKS
Sl.No Description of Activities
SAP ID Jul-19 Jul-19 Jul-19/Aug-19
CUML % UPTO
WEEK No.30 Sat Sun Mon Tue Wed Thu FRI Sat Sun Mon Tue Wed Thu FRI Sat Sun Mon Tue Wed Thu FRI
PLN'D % ACH'D% PLN'D % PLN'D %
27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

BASEMENT

Ground Floor

CAPACITOR BANK ROOMS

1 Floor Screeding (1) 000800001531-0840 50% 50% 50%

2 Floor Epoxy screed & Painting (1, 2 & 3) 000800001531-0850 0% 40% 30% 40% 30%

First Floor
Offloading room

3 Floor Epoxy Screed 000800001531-2410 40% 20% 80%

Battery Room

4 Fixing of Tiles in Battery Rooms 000800001531-3620 10% 40% 30% 50%

STAIRCASES

Prepration and painting work along wall and


5 000800001531-4160 70% 15% 5% 15% 10%
ceiling at Staircase No.1

ROOF Works

Roof

Roof Upstands / Plinths ( Pent house


6 000800001531-2160 40% 20% 10% 25% 25%
Blockworks)

EXTERNAL FINISHING

7 Elevation -1 External Plastering works 000800001531-5200 5% 10% Scaffolding Erection in progress

8 Elevation -2 External Plastering works 000800001531-5200 Backfilling completed

9 Elevation -3 External Plastering works 000800001531-5200 40% 25% 10% 25% 25% Plaster preparation In progress

ET 1,2 & 3

10 Fair facing - Basement walls 000800001531-4390 30% 70% 40% 30%

Format No- 4G79371-Q0010-Y151B 1 of 2


PROG % ROLLED UP PROGRESS [%] - WEEK NO - 31 ROLLED UP PROGRESS [%] - WEEK NO - 32 ROLLED UP PROGRESS [%] - WEEK NO - 33 REMARKS
Sl.No Description of Activities
SAP ID Jul-19 Jul-19 Jul-19/Aug-19
CUML % UPTO
WEEK No.30 Sat Sun Mon Tue Wed Thu FRI Sat Sun Mon Tue Wed Thu FRI Sat Sun Mon Tue Wed Thu FRI
PLN'D % ACH'D% PLN'D % PLN'D %
27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

11 Epoxy painting - plinth basement at Internal Rooms 000800001531-4380 30% 60%

FIRE PUMP ROOM

FWT-Slab Form work, Reinforcemnt and


12 000800001531-5110 65% 25% 35%
Concreting

13 Screed Flooring ( Including Foundations) 000800001531-4900 25% 50% 25% 50%

14 Epoxy Flooring and Skirting 000800001531-4910 10%

SHUNT REACTOR

15 Wall painting works 000800001531-2020 75% 100%

Corbal works in progress


16 Fairfacing of trench walls & corbel beams 000800001531-2010 25% 75%

GATE HOUSE

Flooring works & Foundations in Security


17 000800001531-5770 40% 30% 30% 30% Formwork to be done after FWT works
Room ( Above SR roof)

18 Plastering Works in Security Room 000800001531-5710 50% 0% 50% 50%

BOUNDARY WALL

19 Block works- boundary wall works 000800001531-5400 70% 15% 15%

20 Plastering Works-Internal sides 000800001531-5310 5% 10%

MAN POWER PLANNED FOR THE ACTIVITIES

Steel fixer 15 15 15 15 15 15 15 15 15 15 15 15

Carpenter 20 20 20 20 20 20 20 20 20 20 20 20

Scaffolder 15 15 15 15 15 15 15 15 15 15 15 15

Mason 45 45 45 45 45 45 45 45 45 45 45 45

Helper 30 30 30 30 30 30 30 30 30 30 30 30

TOTAL 125 125 125 125 125 125 125 125 125 125 125 125

Designation: Civil Site Manager Planned progress


Signature : Actual Progress

EPE Comments: