Professional Documents
Culture Documents
Surface Preparation: Contruction
Surface Preparation: Contruction
Surface Preparation: Contruction
CONTRUCTION
Surface Preparation | Manufacturing | Transport | Placement | Compaction | Quality
Assurance | Specifications | Segregation & Temperature Differentials | References
Surface Preparation
Before a pavement is placed the surface to be paved must be prepared. Pavements
constructed without adequate surface preparation may not meet smoothness
specifications, may not bond to the existing pavement (in the case of overlays) or may
fail because of inadequate subgrade support.
Preparing the subgrade and granular base course for new pavement. This can
involve such activities as subgrade stabilization, over-excavation of poor subgrade,
applying a prime coat or compacting the subgrade.
Preparing an existing pavement surface for overlay. This can involved such
activities as replacing localized areas of extreme damage, applying a leveling
course, milling, applying a tack coat, rubblizing or cracking and seating.
Generally, subgrade support can be increased by one or several of the following means:
Subgrade Elevation
After final grading (often called fine-grading), the subgrade elevation should generally
conform closely to construction plan subgrade elevation. Large elevation discrepancies
should not be compensated for by varying pavement or base thickness because (1) HMA,
and aggregate are more expensive than subgrade and (2) HMA compacts differentially –
thicker areas compact more than thinner areas, which will result in the subgrade elevation
discrepancies affecting final pavement smoothness.
Prime coats are generally not required in a crushed aggregate/flexible pavement structure.
Prime coats may be appropriate for use as a wearing and weatherproof surface on
roadbeds that have been graded but cannot be paved right away. Generally, prime coats
represent an unneeded expense (they do not promote much bonding and do not
accomplish much that an overlying HMA layer does not do), and a potential
environmental problem (if cutbacks are used). HAPI does not recommend the use of
prime coats for these reasons.
Prime Coats
The graded subgrade or the top granular base layer can be prepared with a prime coat. A
prime coat is a sprayed application of a cutback or asphalt emulsion applied to the surface
of untreated subgrade or base layers in order to (Asphalt Institute, 2001):
Repair
To maximize an overlay’s useful life, failed sections of the existing pavements should be
patched or replaced and existing pavement cracks should be filled. If an existing
pavement is cracked or provides inadequate structural support these defects will often
reflect through even the best-constructed overlay and cause premature pavement failure
in the form of cracks and deformations. Small areas of localized structural failure in the
existing pavement should be repaired or replaced to provide this structural support (see
Figure 3). If the existing pavement contains areas of inadequate subgrade support, these
areas should be removed and the subgrade should be prepared as it would be for a new
pavement.
Existing pavement crack repair methods depend upon the type and severity of cracks.
Badly cracked pavement sections, especially those with pattern cracking (e.g., fatigue
cracking) must be patched or replaced because these distresses are often symptoms of
more extensive pavement or subgrade structural failure (TRB, 2000). Existing cracks
other than those symptomatic of structural failure should be cleaned out (blown out with
pressurized air and/or swept) and filled with a crack-sealing material when the cracks are
clean and dry (TRB, 2000). Cracks less than about 0.375 inches in width may be too
narrow for crack-sealing material to enter. These narrow cracks can be widened with a
mechanical router before sealing. If the existing pavement has an excessive amount of
fine cracks but is still structurally adequate, it may be more economical to apply a general
bituminous surface treatment (BST) or slurry seal instead of filling each individual crack.
Tack Coats
A tack coat is a thin bituminous liquid asphalt, emulsion or cutback coating applied
between HMA pavement lifts to promote bonding (see Figures 4 and 5). Adequate
bonding between construction lifts and especially between the existing road surface and
an overlay is critical in order for the completed pavement structure to behave as a single
unit and provide adequate strength. If adjacent layers do not bond to one another they
essentially behave as multiple independent thin layers - none of which are designed to
accommodate the anticipated traffic-imposed bending stresses. Inadequate bonding
between layers can result in delamination (debonding) followed by longitudinal wheel
path cracking, fatigue cracking, potholes, and other distresses such as rutting that greatly
reduce pavement life (TxDOT, 2001).
Leveling
The existing pavement should be made as smooth as possible before being overlaid. It is
difficult to make up elevation differences or smooth out ruts by varying overlay
thickness. HMA tends to differentially compact; a rule of thumb is that conventional
mixes will compact approximately 0.25 inches per 1 inch of uncompacted thickness
(TRB, 2000). Thus, thicker pavements will compact more. Therefore, before applying the
final surface course the existing pavement is typically leveled by one or both of the
following methods:
Applying a leveling course. The first lift applied to the existing pavement is used to
fill in ruts and make up elevation differences. The top of this lift, which is relatively
smooth, is used as the base for the wearing course. Leveling course lifts need to be
as thick as the deepest low spot but not so thick that they are difficult to compact.
Because it is not the final wearing course, leveling course elevation and grade are
sometimes not tightly specified or controlled. However, contractors and inspectors
alike should pay close attention to leveling course thickness because an excessively
thick leveling course can lead to large overruns in HMA and thus large overruns in
project budget.
Milling (also called grinding or cold planing). A top layer is milled off the existing
pavement to provide a relatively smooth surface on which to pave. Milling is also
commonly used to remove a distressed surface layer from an existing pavement.
Milling machines are the primary method for removing old HMA pavement surface
material prior to overlay (see Figures 1 and 6). They can be fitted with automatic
grade control to restore both longitudinal and transverse grade and can remove most
existing pavement distortions. After milling, pavement surfaces should be cleaned
off (see Figure 2) before any overlay is placed otherwise dirt and dust may decrease
bonding between the new overlay and the existing pavement. Milling also produces
a rough, grooved surface, which will increase the existing pavement’s surface area
Prevent the slabs or sections from moving by stabilizing the material beneath them.
This involves drilling holes in an unstable PCC slab or section and injecting an
asphaltic or cementitious material to fill any underlying voids. Typically, this
method is only an option for isolated instances of instability. It does not work well
as a general roadway treatment.
Make the overlay structure strong enough to resist cracking. This usually
involves extra granular base layers between the flexible overlay and the existing
rigid pavement or extremely thick flexible layers, both of which are often not
cost effective. Even if these types of preventative measures are used, they
still cannot be guaranteed to prevent reflective cracking. Generally, a HMA
overlay of about 4 to 6 inches can significantly retard the onset of joint reflection
cracking.
Crack/break and seat the underlying rigid pavement. This involves breaking the
underlying rigid pavement into relatively small pieces (on the order of about 1 ft 2 to
2 ft2) by repeatedly dropping a large weight. The pieces are then seated by 2 to 3
passes of a large pneumatic tire roller.
Rubblize the underlying rigid pavement. This involves reducing the underlying rigid
pavement to rubble. This rubble is then used as a high quality base course to
Manufacturing
HMA is produced in a plant that proportions, blends, and heats aggregate and asphalt to
produce an HMA that conforming to job mix formula (JMF) requirements. There are two
basic types of HMA plants commonly in use today: the batch plant, and the drum plant.
Batch plants produce HMA in individual batches while drum plants produce HMA in a
continuous operation.
Figure 1: Covered Batch Plant in Hilo Figure 2: Drum Plant at Kapa'a Quarry
Batch Plants
Batch plants, which produce HMA in individual batches, are the older of the two types of
HMA production facilities; it was not until the 1970s that drum plants became a popular
HMA production option. Currently about 70 percent of all operational HMA plants in the
U.S. are batch plants while only about 5 percent of all newly manufactured plants in the
U.S. are batch plants (Roberts, et al., 1996). This means that as older batch plants are
retired they are more likely to be replaced by new drum plants, which can provide greater
mobility and production capacity. Typical batch quantities range from 1.5 to 5 tons of
HMA and each batch can take 15 - 45 seconds to make.
Drum Plants
Drum plants, which produce HMA in a continuous manner, generally offer higher
production rates than batch plants for comparable cost. Typical production rates for drum
plants vary between about 100 tons/hr up to over 900 tons/hr depending upon drum
design.
Truck Types
There are three basic truck types used for mix transport classified by their respective
HMA discharge methods:
End dump. End dump trucks unload their payload by raising the front end and
letting the payload slide down the bottom of the bed and out the back through a
tailgate (see Figure 1 and Video 1). They are the most popular transport vehicle
type because they are plentiful, maneuverable and versatile.
Bottom dump (or belly dump). Bottom dump trucks unload their payload by opening
gates on the bottom of the bed. Internal bed walls are sloped to direct the entire
payload out through the opened gates. Discharge rates can be controlled by the
degree of gate opening and the discharge is usually placed in an elongated pile,
called a windrow, in front of the paver by driving the truck forward during
discharge. Windrows require a special material transfer vehicle (MTV) to feed the
HMA into the paver.
Live bottom (or flo-boy). Live bottom dump trucks (see Figure 3) have a conveyor
system at the bottom of their bed to unload their payload. HMA is discharged out
the back of the bed without raising the bed. Live bottom trucks are more expensive
to use and maintain because of the conveyor system but they also can reduce
segregation problems and can eliminate some detrimental types of truck bed – paver
contact (because the bed is not raised during discharge).
Transport Considerations
There are several mix transport considerations, or best practices, that are essential to
maintaining HMA characteristics between the production facility and the paving site.
These considerations can generally be placed into four categories:
Loading at the Production Facility. Truck beds should be clean and lubricated with
non-petroleum products to prevent the HMA from sticking to the truck bed.
Petroleum based products, such as diesel fuel, should not be used because of
environmental issues and because they tend to break down the asphalt binder. HMA
should be discharged into the truck bed so as to minimize segregation. Dropping
HMA from the storage silo or batcher (for batch plants) in one large mass creates a
single pile of HMA in the truck bed. Large-sized aggregate may roll off this pile
and collect around the base. Dropping HMA in several smaller masses (three is
typical) at different points in the truck bed will help minimize the segregation risk.
Truck transport. Truck transport affects HMA characteristics through cooling.
HMA is usually loaded into a truck at a fairly uniform temperature between 250°F
to 350°F. During transport, heat is transferred to the surrounding environment and
HMA temperature drops. However, cool HMA provides excellent insulation and
thus transported HMA tends to develop a cool thin crust on the surface that
surrounds a much hotter core. Things such as air temperature, rain, wind and length
of haul, insulated truck beds and truck tarps can affect the characteristics and
temperature of this crust.
Unloading at the paving site. HMA should be unloaded soon after it arrives at the
paving site in order to minimize mix cooling. Also, on jobs with more than one mix
type the inspector and/or foreman should be certain the correct mix is loaded into
the paver.
Operation synchronization. Truck transport should be planned such that the HMA
transport rate (expressed in tons/hr) closely matches plant production rate and
laydown rate. Traffic affects HMA delivery rates because it affects truck speed.
Especially in congested urban areas, heavy and/or unpredictable traffic may
Placement
Mix laydown involves everything used to place the delivered HMA on the desired
surface at the desired thickness. The asphalt paver is the principal machine involved in
mix laydown and is assisted by the material transfer vehicle (MTV) in some instances.
Placement Considerations
There are, of course, many considerations to take into account when placing HMA. Many
are dependent upon local materials, weather, crew knowledge and training, and individual
experience. This subsection presents a few of the basic considerations that apply in
virtually all situations:
Lift thickness. A "lift" refers to a layer of pavement as placed by the asphalt paver.
In order to avoid mat tearing (which generally shows up as a series of longitudinal
streaks) a good rule-of-thumb is that the depth of the compacted lift should be at
least twice the maximum aggregate size and three times the nominal maximum
aggregate size (TRB, 2000).
Longitudinal joints. The interface between two adjacent and parallel HMA mats.
Improperly constructed longitudinal joints can cause premature deterioration of
multilane HMA pavements in the form of cracking and raveling.
Handwork. HMA can be placed by hand in situations where the paver cannot place
it adequately. This can often occur around utilities, around intersection corners and
in other tight spaces. Hand-placing should be minimized because it is prone to
Asphalt Paver
The asphalt paver is a self-propelled formless (does not require side forms) laydown
machine with a floating screed (see Figures 1, 2, 3 and 4). HMA is loaded in the front,
carried to the rear by a set of flight feeders (conveyor belts), spread out by a set of augers,
then leveled and compacted by a screed. This set of functions can be divided into two
main systems:
Tractor. The tractor contains the material feed system, which accepts the HMA at
the front of the paver, moves it to the rear and spreads it out to the desired width in
preparation for screed leveling and compaction. The tractor moves using rubber
tires (see Figures 1 and 2) or tracks (see Figure 3).
Screed. The most critical feature of the paver is the self-leveling screed unit, which
determines the profile of the HMA being placed (Roberts et al., 1996). The screed
takes the head of HMA from the material delivery system, strikes it off at the
correct thickness and provides initial mat compaction. Figure 5 shows screed
components and the six basic forces that act upon the screed to determine its height
and, thus, pavement thickness.
Paver speed. If a paver speeds up and all other forces on the screed remain constant,
the screed angle decreases to restore equilibrium, which decreases mat thickness
(think of what happens to the ski angle of a water skier as boat speed increases).
Material head. If the material head (the amount of material in front of the screed)
increases (either due to an increase in material feed rate or a reduction in paver
speed), screed angle will increase to restore equilibrium, which increases mat
thickness.
Tow point elevation. As the tow point rises in elevation, the screed angle increases,
resulting in a thicker mat. As a rule-of-thumb, a 1-inch movement in tow point
elevation translates to about a 0.125 inch movement in the screed's leading edge.
Without automatic screed control, tow point elevation will change as tractor
Figure 6: Screed Reaction to a Manual Decrease in Screed Angle (after TRB, 2000)
Figure 7: Stringline
Compaction
Compaction is the process by which the volume of air in an HMA mixture is reduced by
using external forces to reorient the constituent aggregate particles into a more closely
spaced arrangement. This reduction of air volume produces a corresponding increase in
HMA density (Roberts et al., 1996).
Although percent air voids is the HMA characteristic of interest, measurements are
usually reported as a measured density in relation to a reference density. This is done by
reporting density as:
Pavement air voids are measured in the field by one of two principal methods:
Cores (Figures 2 and 3). A small pavement core is extracted from the compacted
HMA and sent to a laboratory to determine its density. Usually, core density results
are available the next day at the earliest. This type of air voids testing is generally
considered the most accurate but is also the most time consuming and expensive.
Nuclear gauges (Figures 4 and 5). A nuclear density gauge measures in-place
HMA density using gamma radiation. Gauges usually contain a small gamma
source (about 10 mCi) such as Cesium-137 located in the tip of a small probe,
which is either placed on the surface of the pavement or inserted into the pavement.
Readings are obtained in about 2 - 3 minutes. Nuclear gauges require calibration to
the specific mixture being tested. Usually nuclear gauges are calibrated to core
densities at the beginning of a project and at regular intervals during the project to
ensure accuracy.
Mat temperature is crucial to both the actual amount of air void reduction for a given
compactive effort, and the overall time available for compaction. If a mat's initial
temperature and cool-down rate are known, the temperature of the mat at any time after
laydown can be calculated. Based on this calculation rolling equipment and patterns can
be employed to:
Take maximum advantage of available roller compactive effort. Rollers can be used
where the mat is most receptive to compaction and avoided where the mat is
susceptible to excessive shoving.
Ensure the mat is compacted to the desired air void content before cessation
temperature is reached. This can be done by calculating the time it takes the mat to
cool from initial temperature to cessation temperature. All compaction must be
accomplished within this “time available for compaction”.
MultiCool, developed by Professor Vaughn Voeller and Dr. David Timm, is a Windows
based program that predicts HMA mat cooling. MultiCool can be used to predict the time
available for compaction and is available on the National Asphalt Pavement Association's
A Guide for Hot Mix Asphalt Pavement CD-ROM or for download at several locations:
Compaction Equipment
There are three basic pieces of equipment available for HMA compaction: (1) the paver
screed, (2) the steel wheeled roller and (3) the pneumatic tire roller. Each piece of
equipment compacts the HMA by two principal means:
1. By applying its weight to the HMA surface and compressing the material
underneath the ground contact area. Since this compression will be greater for
These two means are of compacting HMA are often referred to collectively as
“compactive effort”.
Steel wheel rollers (see Figures 6 and 7) are self-propelled compaction devices that use
steel drums to compress the underlying HMA. They can have one, two or even three
drums, although tandem (2 drum) rollers are most often used. The drums can be either
static or vibratory and usually range from 35 to 85 inches in width and 20 to 60 inches in
diameter. Roller weight is typically between 1 and 20 tons (see Figures 5 and 6).
Some steel wheel rollers are equipped with vibratory drums. Drum vibration adds a
dynamic load to the static roller weight to create a greater total compactive effort. Drum
vibration also reduces friction and aggregate interlock during compaction, which allows
aggregate particles to move into final positions that produce greater friction and interlock
than could be achieved without vibration. As a general rule-of-thumb, a combination of
speed and frequency that results in 10 - 12 impacts per foot is good. At 3000
vibrations/minute this results in a speed of 2.8 - 3.4 mph.
Pneumatic tire rollers are self-propelled compaction devices that uses pneumatic tires to
compact the underlying HMA. Pneumatic tire rollers employ a set of smooth tires (no
tread) on each axle; typically four or five on one axle and five or six on the other. The
Compaction Sequence
HMA compaction is typically accomplished by a sequence of compaction equipment.
This allows each piece of equipment to be used only in its most advantageous situation
resulting in a higher quality mat (both in density and in smoothness) than could be
produced with just a single method of compaction. A typical compaction sequence
consists of some or all of the following (in order of use):
Screed. The screed is the first device used to compact the mat and may be operated
in the vibratory mode. Approximately 75 to 85 percent of TMD will be obtained
when the mix passes out from under the screed (TRB, 2000).
Rollers. Generally a series of two or three rollers is used. Contractors can control
roller compaction by varying things such as the types of rollers used, the number of
roller used, roller speed, the number of roller passes over a given area of the mat,
the location at which each roller works, and the pattern that each roller uses to
compact the mat. Approximately 92 to 95 percent TMD will be obtained when all
rollers are finished compacting the mat. Typical roller position used in compaction
are:
o Breakdown Roller. The first roller behind the screed (see Figure 10). It
generally effects the most density gain of any roller in the sequence.
Breakdown rollers can be of any type but are most often vibratory steel wheel
and sometimes pneumatic tire.
Quality Assurance
Quality has become one of the most important consumer decision factors in the selecting
among competing products and services. This is true not only for individual consumers
but also for large corporations, government organizations and the taxpaying public as a
group. In its broadest sense, quality is a degree of excellence: the extent to which
something is fit for its purpose. In the narrow sense, product or service quality is defined
as conformance with requirement, freedom from defects or contamination, or simply a
degree of customer satisfaction.
Quality assurance. All those planned and systematic actions necessary to provide
confidence that a product or facility will perform satisfactorily in service. Quality
assurance addresses the overall problem of obtaining the quality of a service,
product, or facility in the most efficient, economical, and satisfactory manner
possible. Within this broad context, quality assurance involves continued evaluation
of the activities of planning, design, development of plans and specifications,
advertising and awarding of contracts, construction, and maintenance, and the
interactions of these activities.
Quality control. Those quality assurance actions and considerations necessary to
assess production and construction processes so as to control the level of quality
being produced in the end product. This concept of quality control typically
includes sampling and testing by the contractor to monitor the process but usually
does not include acceptance sampling and testing by the agency/owner. Also called
process control.
Acceptance. Sampling, testing, and the assessment of test results to determine
whether or not the quality of produced material or construction is acceptable in
terms of the specifications.
Independent assurance. A management tool that requires a third party, not directly
responsible for process control or acceptance, to provide an independent assessment
of the product and/or the reliability of test results obtained from process control and
acceptance testing. The results of independent assurance tests should not be used as
a basis of product acceptance.
Quality control, acceptance and independent assurance are wholly separate components
of quality assurance. It is difficult, if not impossible, to influence one component, solely
through actions within another component. For instance, acceptance procedures are
essentially monitoring methods used to determine whether or not a particular process is
meeting quality standards. As such, they can be used to accept or reject material based on
its quality but they should never be used as a method to control or improve quality;
quality will not necessarily improve based on increased or stricter monitoring alone. In
short, no amount of inspection changes the quality of a product or service (IQA, 2001).
Quality control (process control) is used to control and systematically improve quality.
Furthermore, independent assurance test results should not be used for acceptance or
quality control. If they are, the tests are no longer independent and should not be used as
if they were.
Specifications
Specifications are used (1) to convey information concerning desired products from a
buyer to a seller or potential seller, (2) as a basis for competitive bidding for the delivery
of products, and (3) to measure compliance to contracts. Typically, four types of
Method Specifications
A method specification outlines a specific materials selection and construction operation
process to be followed in providing a product. In the past, many construction
specifications were written in this manner. A contractor would be told what type of
material to produce, what equipment to use and in what manner it was to be used in
construction. This type of specification allows for a greater degree of competition than
the proprietary product specification, but as long as the structure is built according to the
materials and methods stipulated, the owner bears the responsibility for the performance.
Although widely used, method specifications have several key disadvantages. First, they
tend to stifle contractor innovation because there is virtually no incentive to develop
better, more efficient construction methods. Second, since they are not statistically based
and 100 percent compliance is usually not possible, method specifications usually
required “substantial compliance,” a purposely vague and undefined term that can lead to
disputes. For instance, if a method specification requires that four roller passes be made
over the entire pavement, what happens if 98% of the pavement received four roller
passes and the other 2% received only three roller passes? Does this meet the
specification? Finally, spot checks of material quality, which are often used in method
specifications, do not reflect overall material quality because they are taken from
subjectively determined non-random locations. Since they are not random, these spot
checks have no statistical validity and therefore do not reflect overall material quality.
Despite their flaws, method specifications are still widely used on the local agency level
(e.g., counties, small cities, towns, etc.). In general, this is because they are familiar,
straightforward to write and can be implemented with minimal agency involvement.
Local agencies often lack the expertise and resources required to use statistical
specifications or warranties.
End-Result Specifications
An end-result specification is one in which the final characteristics of the product are
stipulated, and the contractor is given considerable freedom in achieving those
characteristics. In their roughest form, they specify minimum, maximum or a range of
Performance Specifications
Performance specifications are those in which the product payment is directly dependent
upon its actual performance. Typical of these specifications are warranty, limited
warranty and design-build-operate contracts. Contractors are held responsible for the
product performance within the context of what they have control over. The contractor is
given a great deal of leeway in providing the product, as long as it performs according to
established guidelines. In this case, the contractor assumes considerable risk for the level
of service the product provides by paying for or providing any necessary maintenance or
repair within the warranty period.
Aggregate Segregation
Aggregate segregation is the non-uniform distribution of coarse and fine aggregate
components within the HMA mixture. There are two basic types of aggregate
segregation:
1. Coarse segregation. Occurs when gradation is shifted to include too much coarse
aggregate and not enough fine aggregate. Coarse segregation is characterized by
low asphalt content, low density, high air voids, rough surface texture, and
accelerated rutting and fatigue failure (Williams, Duncan and White, 1996).
Typically, coarse segregation is considered the most prevalent and damaging type
of segregation, thus segregation research has typically focused on coarse
segregation. The term “segregation” by itself is usually taken to mean “coarse
segregation.”
2. Fine segregation. Occurs when gradation is shifted to include too much fine
aggregate and not enough course aggregate. High asphalt content, low density,
smooth surface texture, accelerated rutting, and better fatigue performance
characterize fine segregation (Williams, Duncan and White, 1996).
The chief detrimental effects of segregation on HMA performance are: reduced fatigue
life, rutting, raveling, and moisture damage. These effects can cause a severe reduction in
pavement life. More information on segregation causes and cures can be found in
Segregation Causes and Cures for Hot Mix Asphalt (QIP-110) by AASHTO and NAPA.
References
Suggested Reading
Asphalt Institute. (2001). HMA Construction. Manual Series No. 22. Asphalt Institute.
Lexington, KY.
Transportation Research Board (TRB). (2000). Hot-Mix Asphalt Paving Handbook 2000.
Transportation Research Board, National Research Council. Washington, D.C.
Antigo Construction (2001). MHB Badger Breaker ®. Web page on the Antigo
Construction Web site. (http://www.antigoconstruction.com/specs-mhb.html)
Asphalt Recycling & Reclaiming Association (ARRA). (2001). Web page cold planning
FAQ section. (http://www.arra.org/CPFAQ.htm)
Brown, E.R. and Brownfield, J.R. (1988). Investigation of Rutting and Segregation of
Asphalt Mixtures in the State of Georgia. Georgia Department of Transportation.
Cross, S.A. and Brown, E.R. (1993). Effect of Segregation on Performance of Hot-Mix
Asphalt. In Transportation Research Record 1417. Transportation Research Board,
National Research Council. Washington, D.C. pp. 117-126.
Hughes, C.S. (October 1984). Importance of Asphalt Compaction. Better Roads, Vol. 54,
No. 10. pp. 22-24.
The Institute of Quality Assurance (IQA). (2001). Web site FAQ section.
(http://www.iqa.org)
Kennedy, T.W.; McGennis, R.B. and Holmgreen, R.J. (1987). Asphalt Mixture
Segregation; Diagnostics and Remedies. Proceedings of the Association of Asphalt
Paving Technologists, Vol. 56. pp. 304-329.
National Center for Asphalt Technology (NCAT). (2001). Asphalt Paving Level II:
Module 4, Surface Preparation. PowerPoint side show prepared for the Florida
Department of Transportation. Construction Training Qualification Program, National
Center for Asphalt Technology.
Roberts, F.L.; Kandhal, P.S.; Brown, E.R.; Lee, D.Y. and Kennedy, T.W. (1996). Hot
Mix Asphalt Materials, Mixture Design, and Construction. National Asphalt Paving
Association Education Foundation. Lanham, MD.
Scherocman, J.A. and Martenson, E.D. (1984). Placement of Asphalt Concrete Mixtures.
Placement and Compaction of Asphalt Mixtures, F.T. Wagner, Ed. ASTM Special
Technical Publication 829. American Society for Testing and Materials. Philadelphia,
PA. pp. 3-27.
Williams, R.C.; Duncan, G. and White, T.D. (1996). Hot-Mix Asphalt Segregation:
Measurement and Effects. In Transportation Research Record 1543. Transportation
Research Board, National Research Council. Washington, D.C. pp. 97-105.
Willoughby, K.A.; Mahoney, J.P.; Pierce, L.M.; Uhlmeyer, J.S.; Anderson, K.W.; Read,
S.A.; Muench, S.T.; Thompson, T.R. and Moore, R. (2001). Construction-Related
Asphalt Concrete Pavement Temperature Differentials and the Corresponding Density
Differentials. Washington State Department of Transportation. Olympia, WA.
http://www.wsdot.wa.gov/ppsc/research/CompleteReports/WARD476_1FinalCyclicSeg.
pdf.