This document contains 6 entries listing site instructions that were issued by Trans Icon Surabaya to PT TBP between November 2018 and July 2019. Each entry includes the instruction number, date issued, description of the instruction, status, date received by the contractor, and notes on how it was sent. The instructions covered topics such as strutting work, mock-up walls, wall beam installation, excavation monitoring, and SAP. All instructions were closed and sent to PT TBP via email.
This document contains 6 entries listing site instructions that were issued by Trans Icon Surabaya to PT TBP between November 2018 and July 2019. Each entry includes the instruction number, date issued, description of the instruction, status, date received by the contractor, and notes on how it was sent. The instructions covered topics such as strutting work, mock-up walls, wall beam installation, excavation monitoring, and SAP. All instructions were closed and sent to PT TBP via email.
This document contains 6 entries listing site instructions that were issued by Trans Icon Surabaya to PT TBP between November 2018 and July 2019. Each entry includes the instruction number, date issued, description of the instruction, status, date received by the contractor, and notes on how it was sent. The instructions covered topics such as strutting work, mock-up walls, wall beam installation, excavation monitoring, and SAP. All instructions were closed and sent to PT TBP via email.
This document contains 6 entries listing site instructions that were issued by Trans Icon Surabaya to PT TBP between November 2018 and July 2019. Each entry includes the instruction number, date issued, description of the instruction, status, date received by the contractor, and notes on how it was sent. The instructions covered topics such as strutting work, mock-up walls, wall beam installation, excavation monitoring, and SAP. All instructions were closed and sent to PT TBP via email.
001 /A-28/PRO/TJP/TIS - TBP/XI/ 2018 6 November 2018
002 /A-28/PRO/TJP/TIS - TBP/I/ 2019 9 January 2019 003 /A-28/PRO/TJP/TIS - TBP/I/ 2019 29 January 2019 004 /A-28/PRO/TJP/TIS - TBP/II/ 2019 12 February 2019 005 /A-28/PRO/TJP/TIS - TBP/III/ 2019 04 Maret 2019 006 /A-28/PRO/TJP/TIS - TBP/III/ 2019 9 July 2019 SITE INSTRUCTION TRANS ICON SURABAYA
DESKRIPSI STATUS TGL DITERIMA KONTRAKTOR
Pengajuan Penawaran Pekerjaan Strutting CBP Close 7 November 2018 Mock Up Waller Beam Close 10 January 2019 Perkuatan Mock Up Waller Beam Close 7 February 2019 Pekerjaan Pemasangan Waller Beam Close 18 February 2019 Monitoring Pekerjaan Galian Close 04 Maret 2019 SAP Close 10 July 2019 KETERANGAN Terkirim by Email Ke PT TBP Terkirim by Email Ke PT TBP Terkirim by Email Ke PT TBP Terkirim by Email Ke PT TBP Terkirim by Email Ke PT TBP Terkirim by Email Ke PT TBP