225727019-Revised-Estimate Page 1 of 3
150mmØ x 6.00m G.I. Pipe, Sch. 40 1 pc. 4,660.00 4,660.00
25mm Teflon Tape 4 rolls 22.00 88.00
150mmØ Dry Type Fire Hydrant w/ 63mmØ Hose Connector and 1 unit 98,000.00 98,000.00
1-100mmØ Hose Pumper Outlet (Commercial Type)
16mmØ x 6.00m Deformed Reinforcing Steel Bars 3 pcs. 370.00 1,110.00
12mmØ x 6.00m Deformed Reinforcing Steel Bars 1 pcs. 219.00 219.00
10mmØ x 6.00m Deformed Reinforcing Steel Bars 4 pcs. 122.00 488.00
#16 G.I. Tie-wire 1 kgs. 65.00 65.00
Portland Cement 4 bags 220.00 880.00
Sand 0.50 cu.m. 800.00 400.00
Gravel 1 cu.m. 800.00 800.00
Concrete Neutralizer 1 qrt. 84.00 84.00
Liquid Tile Primer 1 qrt. 156.00 156.00
Liquid Tile Top Coat White Gloss 0.50 gal. 787.00 393.50
Red Tinting Color 1 pint 100.00 100.00
Thalo Blue Tinting Color 1 pint 100.00 100.00
Raw Sienna 1 pint 100.00 100.00
Lamb Black 1 pint 100.00 100.00
Red Lead Paint 0.50 gal. 440.00 220.00
Paint Blue (QDE) 0.50 gal. 520.00 260.00
Liquid Tile Reducer 1 qrt. 92.00 92.00
2" Paint Brush 2 pcs. 28.00 56.00
12mm thk x 1.20m x 2.40m Ordinary Plywood 1 pc. 550.00 550.00
3pcs. - 2" x 2" x 8' Coco Lumber 8 bd.ft. 17.00 136.00
1" C.W. Nail 0.50 kgs. 65.00 32.50
4" C.W. Nail 0.50 kgs. 65.00 32.50 138,859.00
b. Labor:
1 Pipe fitter 3 days 341.00 1,023.00
4 Laborer 3 days 317.00 3,804.00 4,827.00
TOTAL DIRECT COST OF FIRE HYDRANTS 143,686.00
c. Concrete Cutting/Demolition & Excavation Fee 236.25 sq.m. 40.00 9,450.00 9,450.00
TOTAL COST OF CONCRETE CUTTING & DEMOLITION 112,908.00
225727019-Revised-Estimate Page 2 of 3
Water Proofing Compound 76 pcs. 65.00 4,940.00
Hacksaw Blade 25 pcs. 60.00 1,500.00
No. 16 G.I. Wire 3 25 pcs. 75.00 1,875.00 126,575.00
b. Labor:
2 Steelmen 13 days 366.00 9,516.00
1 Masons 13 days 366.00 4,758.00
4 Contractual Laborers 13 days 317.00 16,484.00 30,758.00
b. Labor:
2 Masons 15 days 366.00 10,980.00
10 Contractual Laborers 15 days 250.00 37,500.00 48,480.00
S U M M A R Y
I. MOBILIZATION: 15,000.00
II. PIPELINES & APPURTENANCES: 860,301.50
III. FIRE HYDRANTS: 143,686.00
IV. TRANSFER OF SERVICE CONNECTIONS (INDIVIDUAL TYPE TAPPED ON SECONDARY LINE): 51,036.00
V. CONCRETE CUTTING & DEMOLITION: 112,908.00
VI. VALVE BOXES: 174,693.00
VII. BACKFILLING & CONCRETE RESTORATION: 447,028.58
VIII. DEMOBILIZATION: 15,000.00
SUB-TOTAL 1,819,653.08
Overhead Expenses, Price & Physical Cont. & Misc. 9,810.92
TOTAL PROJECT COST Php 1,829,464.00 1,829,464.00