Sr.

Yesterday Works Today Targets


No.
1 BOQ for Main Boulevard Rate Analysis of P/L Curb Stones
2 Rate Analysis of Clearing and Grubbing Rate Analysis of P/L curb stone for foot path
Rate of Providing, laying, cutting, jointing,
3 Rate Analysis of Natural Ground Compaction testing & disinfecting class "B" HDPE pipe
Rate of Backfilling carefully the excavated
4 Rate of Asphalt Wearing Course material
5 Rate of Asphalt Base Rate of 32mm PE pipe for house connection
6 Rate Analysis of Earthwork Rate of Installation of Saddle Clamp.
7 Rate Analysis of Laying of Subbase Rate of Installation of 32mm male elbow.
7 Rate Analysis of Laying of W.B.M Rate of Installation of Tee pipe.
8 Rate of Excavation for W.S pipes Rate of Installation of End Plug.
Rate of Providing & fixing C.I. sluices valves
and making their chambers i/c C.I. surface box
9 Rate of P/L sand cushion for trench etc.
Rate of Installation of Fire Hydrant
Rate of Installation of Air Relif Valve