Professional Documents
Culture Documents
Lean Manufacturing in The Job Shop - 5 Steps To Building A Value Network Map
Lean Manufacturing in The Job Shop - 5 Steps To Building A Value Network Map
Lean Manufacturing in The Job Shop - 5 Steps To Building A Value Network Map
Some lean tools, though, don’t work so well in job shops’ high-mix, low-volume environment.
A job shop has various customers that order different quantities of different products that all
have different lead times, routings, bills of materials (BOMs), outside vendor operations, and
due dates. TPS concepts like line balancing, level loading, right-sized machines, and single-
piece part flow can be extraordinarily difficult or impossible to achieve, at least if one goes by
their traditional definitions and uses. In particular, a lean tool borrowed from TPS that’s
difficult, perhaps impossible, to adapt to the custom fabrication environment is value stream
mapping (VSM). Because this tool—intended to highlight and help prioritize improvement
opportunities that will eliminate waste and shorten lead times—does not work in any job shop,
industry really needs a viable alternative.
Still, this doesn’t mean the concepts behind value stream mapping can’t be applied to a job
shop. A job shop is a complicated entity that does not repeatedly produce orders for just one
or even a handful of value streams, but instead a network of interconnected value streams
that I call a value network map. The interconnectedness between the value streams exists
because of the kind of BOMs a job shop has and the assembly requirements. Job shops also
have part routings that share one or more common machines.
https://www.printfriendly.com/p/g/uGSYME 1/6
08.08.2019 Lean manufacturing in the job shop: 5 steps to building a value network map
To implement lean manufacturing, you need to overcome two age-old “elephants in the room”:
creating an efficient factory layout and implementing effective scheduling of daily operations
by taking into consideration capacity constraints, such as the constraints of machines, labor,
materials, and tooling. Value network mapping (VNM) can help you tame both elephants
effectively and efficiently.
But managing a custom fabrication operation, you know your shop doesn’t produce just one
product or product family. (In fact, most will tell you that they wish they knew the product
families that exist in their product mix.) A traditional VSM cannot handle product variety or
demand variation. It cannot map a large number of dissimilar manufacturing routings involving
dozens of different work centers. Nor can it map the complete multilevel BOM of any complex
product. Worse yet, VSM provides a single day’s snapshot of part flow that, as anyone in
custom fabrication knows, cannot represent the dynamic system that is their shop floor. Work
loads and routings on the shop floor can look entirely different from one day to the next.
To create one, you can refer to the basic idea behind the steps used to create a VSM, but then
take a different approach to each. This new approach helps account for the high-product-mix,
low-volume reality of the job shop.
https://www.printfriendly.com/p/g/uGSYME 2/6
08.08.2019 Lean manufacturing in the job shop: 5 steps to building a value network map
Figure 1
To create a value network map, you need to
extract a complete, indented BOM detailing
every component that goes into a product or
group of products. (A partial view of a
multipage BOM is shown.)
This is by far the most complicated step for any job shop. A full-blown statistical analysis is
ideal, of course. But if resources aren’t available for this, your shop can simply identify a
single product or product family, such as one that represents a common job the shop
processes, like an enclosure—in the “sweet spot,” a successful product that helped your
shop get to where it is today.
Creating a map around the complete BOM and operations process chart for this product
could help leverage the shop’s strengths for future growth. And, of course, the process can be
repeated for other products using the software tools mentioned earlier.
To map a single product or product family, the analysis is much simpler. From your enterprise
resource planning (ERP) system, you can start by simply extracting the BOM for a key bread-
and-butter product. Note that you need to extract the complete, indented BOM of the product
(see Figure 1).
To create a VNM, start with a product-process matrix. This essentially maps the value
streams for the products in the identified product family. With the BOM in hand, identify the
components and subassemblies made in-house, which become the final product that ships
out the door; then obtain the detailed routings for the components, subassemblies, and the
final product from incoming raw materials to outgoing product.
Identify the specific stations on the final assembly line to which each of the in-house
assemblies and subassemblies are delivered. With this information, develop an operations
process chart that identifies how each and every component and subassembly flows from
https://www.printfriendly.com/p/g/uGSYME 3/6
one work center to the next (see Figure 2).
08.08.2019 Lean manufacturing in the job shop: 5 steps to building a value network map
Chart each part number in the assembly against the work centers they flow through. You’ll
probably notice that a fair number of part numbers flow through the same machines (Figure
3). That is, they have similar, possibly identical, routings. This helps you identify part families,
which in turn helps you to develop your future-state material flow in its entirety.
3. Create flow
You now have a good picture of how products flow between work centers, as well as the
future state you want to achieve. For instance, this future state could come about by
implementing multiple component-producing cells that replenish inventory in a supermarket
from which the welders pull kits of parts to produce the subassemblies that go into the final
product.
Armed with this information, your shop can now start modifying the existing facility layout—at
least to the extent possible—to align it with the existing product flow (see Figure 4).
Figure 2
This operations process chart shows how
all the components in each of the three
major subassemblies that constitute the
final product flow from one process to the
next.
A cascading cellular layout is a combination of the traditional cellular and process layouts;
however, it keeps different processes close together—eliminating excessive walking and
transportation—but allows operators the freedom to choose machines that work best. In a
virtual cell, machines that can’t be moved easily (so-called monuments) may still be far apart,
but remain in a “virtual cell,” meaning the tooling, fixtures, and support services for those
machines are dedicated mainly to one product or a range of products.
Regardless of the layout you design for the upstream portion of your custom fabrication
https://www.printfriendly.com/p/g/uGSYME
facility, when those components get delivered to the welding booths (or other departments 4/6
08.08.2019 Lean manufacturing in the job shop: 5 steps to building a value network map
locations that will receive components or subassemblies. Designating locations helps your
shop to efficiently build the kits of components that must be delivered to the different welding
cells.
4. Establish pull
In custom fabrication and elsewhere, production capacity is not infinite. This is where
strategies like finite capacity scheduling and drum-buffer-rope (DBR) scheduling, based on
the ideas behind the theory of constraints, can help. Regardless of the method, scheduling
should always factor in the capacity of the bottleneck, or constraint, work centers.
From your ERP system you can extract the setup and cycle time for each value-added
operation for the product you’re mapping. You then can use this data to generate a Gantt
chart, which provides a visual production schedule that shows the start and finish time for
every operation, subject to queuing delays at shared resources and finite capacity constraints
at bottleneck resources. A Gantt chart helps to put constraint processes into stark relief, be it
welding, outsourced plating or heat treating, or anything else. The Gantt chart is the
multiproduct multimachine alternative to the single timeline that shows at the bottom of any
VSM where a single product is always mapped (see Figure 5).
If a custom fabricator or job shop has reliable data available in their ERP system and the
desire to grow more competitive and, ultimately, attain world-class delivery, they should give
VNM a serious look.
https://www.printfriendly.com/p/g/uGSYME 6/6