013753
HANDLING HAULING & D 11095
STRINGING OF LINE PIPES 006
B 06.06.2019 Client comments incorporated Anuj Soni Akash Dhobi Pintu Patel
A 03.06.2019 Draft Issued for Client review Anuj Soni Akash Dhobi Pintu Patel
Rev. Date Description Prepared by Checked by Approved by
Page 1 of 6
JOB PROCEDURE P.013753
HANDLING HAULING & D 11095
STRINGING OF LINE PIPES 006
TABLE OF CONTENTS
1.0 PURPOSE………………………………………………………………………………………………………………………3
2.0 SCOPE………………………………………………………………………………………………………………………....3
3.0 REFERANCE……………………………………………………………………………………………………………….....3
4.0 EQUIPMENT & MATERIAL…………………………………………………….............................................3
5.0 METHODOLOGY………..……….……………………………………………………………………………………....3-5
6.0 HEALTH, SAFETY & ENVIRONMENT…………………………….…………………………………………………..5
7.0 QUALITY ASSURANCE PLAN……………………………………………………………………………………………6
8.0 APPENDICES/FORMATS………………………………………………………………………………………………….6
Rev. B – 06.06.2019 City Gas Distribution Project Torrent Gas Pvt Ltd Page 2 of 6
JOB PROCEDURE P.013753
HANDLING HAULING & D 11095
STRINGING OF LINE PIPES 006
1.0 PURPOSE
The purpose of this work instruction is to establish guidelines and requirements to control the
transportation, storage, handling, hauling and stringing of line pipe activity to be used in the
Torrent GAS CGD Project.
2.0 SCOPE
The scope covers to provide a detailed description of line pipe transportation, storage, handling,
hauling and stringing activities for the construction of the Torrent GAS CGD Project.
3.0 REFERENCES
Following documents in totality or in part shall form the reference documents:
• PMC SPEC No.:
• Alignment sheets.
• GAS TRANSMISSION AND DISTRIBUTION PIPING SYSTEMS ASME B 31.8
• Standard for Welding of pipelines & related facilities – API 1104.
• Oil Industry Safety Directorate OISD 141
5.0 METHODOLOGY
Rev. B – 06.06.2019 City Gas Distribution Project Torrent Gas Pvt Ltd Page 3 of 6
JOB PROCEDURE P.013753
HANDLING HAULING & D 11095
STRINGING OF LINE PIPES 006
The pipe shall be placed on a suitable support so that damage to the coating and
deformation of pipes can be avoided.
Loading & unloading of pipes shall be executed by the trained personnel with special care
in order to avoid damages to coating, body and bevel of pipes.
Supports and padding material shall be arranged so as to prevent possible movement of
cargos in order to prevent transported pipes to secure the cargo slings of wire with plastic
coating shall be used.
A Route Risk Assessment for Transportation of Pipes have to be conducted and relevant
records must be submitted to authorized TGPL representative.
Handling & Loading in the pipe yard shall be carried out by competent riggers and crane
operators. Every effort shall be made to load the pipe at the pipe yard. The driver of the
trailer’s should have the competent licence.
Rev. B – 06.06.2019 City Gas Distribution Project Torrent Gas Pvt Ltd Page 4 of 6
JOB PROCEDURE P.013753
HANDLING HAULING & D 11095
STRINGING OF LINE PIPES 006
5.4 Stringing
Unloading of pipe shall be performed using crane on site.
Qualified operator shall operate the equipment.
Rubber padded pipe lifting clamps shall be attached to the lifting slings.
Two guide ropes shall be attached to both end of lifting clamp.
Stringing shall be taken up in the stretches where the ROW is graded.
Line pipe shall be unloaded from the pipe trailers and evenly strung along the ROW. The stringing
foreman is responsible for stringing the line pipe. The pipe shall be supported by sandbags/soft
soil bags free from stone and covered with a plastic film or on wooden supports or dry germ free
straw with plastic film which shall be positioned in such a way to prevent its rolling off into the
Ditch/ROW, stringing of pipe shall only be carried out in day light after clearing & grading.
The height of the supports will be minimum 500 mm and minimum two supports to be provided
on each pipe. The pipe shall be stacked as a slope so that during rain mud doesn’t collect inside
the pipes.
Rolling, dropping, dragging the pipes shall not be allowed along the ground; however some
rolling on the sand bags/soft soil bags will be allowed in order to position the helical seam.
The pipe shall be stung along pipeline route as per specified AFC Alignment Sheets/drawings for
proper placement of pipes by spec., thickness, grade & class & other specifications. Pipe shall be
laid in such a way to minimize interference with the normal use of ROW, track, service road etc.
Stringing shall not interfere with tarmac roads, graded roads & livestock passages.
The stringing engineer/foreman assisted co-ordinate by a crew consisting of riggers and
crane operators shall co ordinate and control stringing operations.
After stringing along ROW the pipes shall be checked for bevel & coating damages.
A record shall be maintained, on the way bill which has pipe no, heat no, wall thickness &
lengths etc, of the approximate location by the stringing engineer/foreman.
Rev. B – 06.06.2019 City Gas Distribution Project Torrent Gas Pvt Ltd Page 5 of 6
JOB PROCEDURE P.013753
HANDLING HAULING & D 11095
STRINGING OF LINE PIPES 006
Note: In case of any conflict between the requirements of this procedure and PMC Specification
The later shall govern, until and unless specific intention is meant.
Rev. B – 06.06.2019 City Gas Distribution Project Torrent Gas Pvt Ltd Page 6 of 6