Diameter Pasir Min. 0.088
Diameter Pasir Min. 0.088
Diameter Pasir Min. 0.088
INTAKE
Area = 8,554 Ha Elevasi pintu barrage
NFR = 1.09 L/det/ha
eff. = 0.65 L/det/ha
DR = 1.69 L/det/ha
Qd = 8,554 x 1.69 = 14.42 m3/detik
+ 68.76 dekzerk
Elevasi pintu bendung + 65.26
Jarak Pengendapan
Diameter fraksi pasir D= 0.088 mm
Kecepatan endap Ws = D g D2 / 18 u
percepatan gravitasi g= 9.81 m/det2
D= 1.65
koefisien viskositas u = 1,01 x 10-6 m2/det
Ws = 0.007 m/det
h/w < L/v
L > h/w x v = 52 m
Q = 7.21 m3/det
Vf = 1.50 m/det ~ kecepatan pembilasan
A = 4.81 m2
hf = 0.24 m
p = 20.48
R = 0.23
k = 50
hc = (q2/g)1/3 = 0.24 m
Vc = 1.52 m/det
Fr = V / ( g .h )0.5 = 0.98 < 1 ~ sub kritik ok
I√ R = 3.02E-03
Discharge m /det
3
7.21 7.21 7.21 14.42 H = 2.31
+ 64.53 z = 0.10
Distance, L m 160 210 210 1,130 62.63 H = 1.81 + 64.43 Mayang P/C water level design
Hydraulic gradient I =z/L =( V/k/R0.667)2 0.000092 0.000007 0.006226 0.000027 62.49 62.75 H = 2.42
Roughness coeff. k, lining 50.00 50.00 50.00 40.00 62.61 62.61 h = 2.73 62.11 existing
Side slope m 0.00 0.00 0.00 1.00 61.83 61.83 0.28
Bed width b m 6.50 20.00 20.00 13.00 1.45 61.80
Water depth h m 2.00 2.00 0.24 2.73 D2 = 3.88
Freeboard wmin m 0.85 0.85 0.85 L = 160 L = 210 61.30
Canal high H=h+w m 2.85 2.85 3.58 Total = 370 58.23 existing
n= b/h 3.25 10.00 83.25 4.76 1,130
Flow area A = (n+m) h 2 m2 13.00 40.00 4.81 43.00
Wetted perimeter p = (n+2(1+m2)0.5 ) h m 10.50 24.00 20.48 20.73
Hyd radius R=A/p m 1.24 1.67 0.23 2.07
Sediment capacity I√ R 1E-04 8E-06 3E-03 4E-05
Velocity V > 0.30 m3/det 0.55 0.18 1.50 0.34