1. The FORMAT – A (Page 217 of SOR 2014) to evaluate Issue Rate and Cost at Site of bitumen /
CRMB / bituminous emulsion issued by the Department is replaced by the following :
FORMAT – A
Format for analysis of rates of Bitumen / Bitumen Emulsion / CRMB supplied by Department
Step - 1 Basic Cost of materials including all taxes at the nearest source of the manufacturer as per Table I – 2. ` (A)
Step – 2 Necessary cost for loading, unloading & stacking. ` (B)
Step – 3 Necessary carriage cost from source of the manufacturer to different departmental godowns. ` (C)
(Vide Appendix–I)
Step – 4 Add storage charge for storing the materials at departmental godowns / stackyard ( @ 1% of (A)) ` (D)
Departmental Issue Rate = (A) + (B) + (C) + (D) ` (E)
Step – 5 Add loading, unloading and carriage charges from departmental godowns / stackyards to the work site. ` (F)
Step – 6 Deduct cost of container (Vide Note I-3, Table I-2) ` (G)
(in case of packed bitumen, CRMB or bituminous emulsion is considered to be used)
Rate of Material at Site = (E) + (F) – (G) = ` (H)
Deduct Contractor’s Profit already included in the analysis of the rate of the item (A) X 1/10 = ` (I)
Rate of Bitumen to be added to the item rate (H) - (I) = ` (J)
Note : 1 Unchanged.
Note : 2 The Total marked J is the net cost of the bitumen to be added to the item concerned to arrive at the complete rate of the ite m.
2. The FORMAT – D Case-(I) & Case-(II) (Page 218 of SOR 2014) to evaluate Issue Rate and Cost
at Site of Cement issued by the Department is replaced by the following :
FORMAT – D
Format for analysis of rate of items involving use of cement supplied by Department.
CASE-( I ): For items , Where costs of cement is to be included in the item rate :-
Step – 1 Rate of item as per relevant section of this Schedule. ` (A)
Step – 2 Add : Cost of cement = (Quantity of cement) x (Issue rate of cement vide Item no. 1, column – 4, Table I ` (B)
– 1 of the Schedule of Rates, 2014.).
Note: The quantity of cement shall be as per Section – 3 of this schedule of rates.
Step – 3 Deduct Contractor’s Profit already included in the analysis of the rate of the item= (B) X 1/10 = `( C )
Final rate of item = (A) - (C) = (D)
CASE-( II ) : For items , where costs of cement is already included to the item rate to arrive at the complete cost::
1
Volume III : Road & Bridge Works 1st Corrigenda & Addenda to PWD (WB), SOR: 2014
3. The FORMAT – F (Page 219 of SOR 2014) to evaluate Issue Rate and Cost at Site of Steel issued by the
Department is replaced by the following : FORMAT – F
Format for analysis of rate of items involving use of Steel supplied by Department.
For items, where costs of steel is to be included in the item rate to arrive at the complete cost :
2
1st Corrigenda & Addenda to PWD (WB), SOR: 2014 Volume III : Road & Bridge Works
4
1st Corrigenda & Addenda to PWD (WB), SOR: 2014 Volume III : Road & Bridge Works
.Construction wing should add cost of 1.02 MT (considering
2% wastage) of steel to arrive at the final consolidated rate.
Rate (`)
Section Item / Sl. No. Description Unit (All districts except (Darjeeling
Darjeeling Hill Area) Hill Area)
Chapter 12 12.23 Cost of boring using drilling mud to stabilized the bore and
(Page - 289) (New) flushing the bore of excess mud with fresh drilling fluid for
the portion of the pile above cutoff level and up to the level of
island for providing RCC cast in situ bored pile in position
including the cost of mobilization and hire charges of all
equipment necessary for boring.
(a) Using hydraulic piling rig with power unit and complete
accessories including cost of shifting of machinery from one
bore location to other, removal of excavated earth with all
lifts and lead up to 1 km by tipper trucks:
(i) 750 mm. diameter pile. metre 2549.00 -
(ii) 800 mm. diameter pile. metre 2737.00 -
(iii) 900 mm. diameter pile. metre 3217.00 -
(iv) 1000 mm. diameter pile. metre 3873.00 -
(v) 1200 mm diameter pile. metre 4352.00 -
(vi) 1500 mm diameter pile. metre 4439.00 -
(b) Using tripod, winches and other accessories including
shifting of all machinery from one bore location to another
and removal of excavated earth with all lifts and lead upto
150 m.
(i) 750 mm. diameter pile. metre 1080.00 -
(ii) 800 mm. diameter pile. metre 1084.00 -
(iii) 900 mm. diameter pile. metre 1108.00 -
(iv) 1000 mm. diameter pile. metre 1159.00 -
(v) 1200 mm diameter pile. metre 1210.00 -
(vi) 1500 mm diameter pile. metre 1261.00 -
Chapter 17 17.05 B. v) Collection of Undisturbed soil sample from the bore hole to
(Page - 310) be made by the concerned Division / Party at their cost.
(iv) 30.0m-40.0 m each 570.00 610.00
(v) 40.0m-50.0 m each 680.00 730.00
Superintending Engineer
Planning & Monitoring Circle, PWD &
Convenor, Combined Schedule
Committee of PWD.