Professional Documents
Culture Documents
Work Scheduling in Bridge Construction PDF
Work Scheduling in Bridge Construction PDF
In
Bridge Construction
Work Scheduling
• Work scheduling is a tool of planning of project, which decide
in advance about what to do and when to do considering how
to do and who is to do .
• It is a time phased plan for performing the work necessary to
complete the project
• It is a graphical representation of plan which shows the
starting and completion dates of each activity and the
sequential relationship among the various activities
• It
– Predicts project completion time and activity completion time
– Controls financing and payment
– Serves as a record
– Helps to plan resources required for construction
– Supports to cash management
Scheduling Tools
Different Scheduling Tools
Milestone chart
Improved bar chart in which important events are shown
Steps for preparing Bar Chart
1. Break down the whole project in to various activities or sub activities
Identify different works within the activities
Prepare a schedule for the activities involved in detail engineering survey and design
of a bridge using Bar Chart
Time required
S.N. Activities/Works
(Days)
Document preparation for tendering of
1 3
Detail survey and design works
2 Call for tender 10
6 Gological/Goetechnical Investigation 14
7 Hydrological Study 5
8 Design and detailing 35
9 Submission and approval of report 9
Duration / Time
S.N
Activities/Works Mangsir 2069 Paush 2069 Falgun 2069
.
1 2 3 4 1 2 3 4 1 2 3 4
Document preparation for tender 3 days
1
Detail survey and design works
2 Call for tender 10 days
Gological/Goetechnical 14 days
6
Investigation
Draft report Approval of
7 Hydrological Study 5 days submission report
1 Diversion of stream
Construction of platform of
2
well
Fabrication and placement of
3
well curb
Form works of well up to 3 m
4
height
Bar cutting and bending up to
5
3 m height
Reinforcement layout in well
6
up to 3 m height
Concreting of well steining up
7
to 3m height
Dredging and sinking of well
8
up to 3m height
9 Concreting of lower plug
1 Diversion of stream
Construction of platform of
2
well
Fabrication and placement of
3
well curb
Form works of well up to 3 m
4
height
Bar cutting and bending up to
5
3 m height
Reinforcement layout in well
6
up to 3 m height
Concreting of well steining up
7
to 3m height
Dredging and sinking of well
8
up to 3m height
Labour 4 4 7 3 5 5 4 4 6 2 5 1 1 1 0 0 0 2 2 2 2 2 2 4 4 6 2 4
Mason 1 1 1 1 2 2 2 2
Carpenter 1 1 1 1 1 1 1 1
Bar bender 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Welder 1 1 1 1
Critical Path Method (CPM)
It is a logical representation of different activities and their
interrelationships in a diagrammatic form (Network Diagram).
• Initial event should be one in network diagram and should contain only
out going arrow.
• Until and unless all activities leading to an event are completed no
event is occurred.
• Until and unless the preceding events are completed no activity is
started.
• Network path shall not be turned back. Event should not be dependent
on the succeeding events.
• Before reaching the objective, every activity should be completed.
• Final event should be only one.
• Network should contain all constraints and interdependencies
• In network, time flows from left to right
• The length of an arrow in a network diagram does not represent time.
• Number given to a preceding event should be smaller than the number
given to the succeeding events.
Example on Critical Path Method of Scheduling
A bridge requires six intermediate piers consisting of concrete cap supported by steel
piles. All piles will be driven before any caps are started. Sequential information about
the activities of this project is given below. Draw network diagram
Days require
Proceeded Followed
Activity for the
by by
activity
A Drive piles - B 20
B Erect forms for caps 1 and 2 A C,E 4
C Place reinforcement for caps 1 and 2 B D,F 2
D Place concrete for caps 1 and 2 C G 2
E Erect forms for caps 3 and 4 B F,H 4
F Place reinforcement for caps 3 and 4 C,E G,I 2
G Place concrete for caps 3 and 4 D,F J 2
H Erect forms for caps 5 and 6 E I 4
I Place reinforcement for caps 5 and 6 F,H J 2
J Place concrete for caps 5 and 6 G,I - 2
Network diagram
2 days C
2 days 2 days
F I
4 7 9
2 days D
2 days 2 days
G J
8 10 11