Patel Profiles PVT LTD: Supply Progress Plan Year Month Week

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

PATEL PROFILES PVT LTD SUPPLY PROGRESS PLAN Description & Drawing No Rigid Dummy Ba

Year 2014 2015 2015 2015


Month December January February March
Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Material availablility Plan
Material Testing Plan
Cutting & Grinding Plan
Fabrication Plan
TAC Inspection Plan
Welding Plan
Stage Inspection Plan
Heat Treatment Plan
Sandblasting & Primer Plan
Compenents machining Plan
Free Issue Plan
Compenent inspection Plan
Work shop Assembly & Board Piping Plan
Final painting Plan
Final Inspection & Test Documents Plan
Readness for shipment Plan
d Dummy Bar Storage Assembly -3041001.1
2015
April Completion Date
16 17 18 19 20
06.12.2014
13.12.2014
29.12.2014
08.01.2015

15.01.2015

20.01.2015
27.01.2015
10.02.2015
10.02.2015
14.02.2015
20.02.2015
28.02.2015
04.03.2015
10.03.2015