EPRF - II REVAMP PROJECT (ERP)

ZISHAN ENGINEERS (PVT.) LTD.

SITE ACTIVITY REPORT

SUNDAYS & HOLIDAYS

Name: S. Q. Sanaullah Designation: Sr. Mech Supervisor

Sr. No. Time In: 9:30 Time Out: 16:30 Date: Sunday 4-Aug-19

2
3
4
5
EPRF - II REVAMP PROJECT (ERP)

ZISHAN ENGINEERS (PVT.) LTD.

SITE ACTIVITY REPORT

SUNDAYS & HOLIDAYS

Name: Jamal Bakht Designation: Sr. Mech Supervisor

Sr. No. Time In: 9:30 Time Out: 16:30 Date: Sunday 25-Aug-19

1 Pipe welding inspection (Report # 326 Total Joints Inspected 27)


2 R. T. Films Review (Total Number of Joints 39)

3 Tank (T-923) inside heating coil welding inspection.

4 Punch point check of test pack # Petro-PKG-030


5 Insulation inspection of EA-606, EA-615, EA-616 & EA-617.
6 Hydrotesting of test pack # Petro-PKG-090
EPRF - II REVAMP PROJECT (ERP)

ZISHAN ENGINEERS (PVT.) LTD.

SITE ACTIVITY REPORT

SUNDAYS & HOLIDAYS

Name: Shams Soomro Designation: Welding Inspector

Sr. No. Time In: 9:30 Time Out: 16:30 Date: Sunday 25-Aug-19

1 Pipe Fit-up inspection (Report # 236,total diainch inspected 37").


2 Gi pipe fitup inspection(Report # 15,16,17,18,19,total joints inspected 105)
3