Professional Documents
Culture Documents
Mandvi DPR (Iwmp III)
Mandvi DPR (Iwmp III)
Table of Contents
Chapter-I : Project Background ..................................................................................................................................................................................................... 14
Table no.1: Basic project information ............................................................................................................................................................................................ 16
Need of Watershed Development Programme:- ........................................................................................................................................................................... 17
Table no.2: Weightage of the project .............................................................................................................................................................................................. 17
Table no:2.1 Criteria and weightage for selection of watershed ................................................................................................................................................... 18
Table no.3: Watershed information ............................................................................................................................................................................................... 20
Table no.4: Developmental programmes running in the project area: .......................................................................................................................................... 21
Table no. 5: Previous Watershed programmer in the project area:............................................................................................................................................... 22
Project Implementing Agency ....................................................................................................................................................................................................... 24
Table no. 6: Detail of PIA:................................................................................................................................................................................................................ 27
Table no. 7: Staff at PIA level .......................................................................................................................................................................................................... 28
Basic Information of Project Area:- ............................................................................................................................................................................................... 30
Table no. 8: Land use pattern: ........................................................................................................................................................................................................ 31
Soil and Topography ..................................................................................................................................................................................................................... 33
Table no. 9: Soil type and topography: ........................................................................................................................................................................................... 34
Table no. 10: Flood and drought condition: ................................................................................................................................................................................... 35
11. Edaphic Factors ....................................................................................................................................................................................................................... 36
Table no. 11.1: Soil Salinity/Alkalinity (Salinity ingress) .............................................................................................................................................................. 36
Land and Agriculture:- .................................................................................................................................................................................................................. 37
5C1A4a1f, 5C1A4a1e, 5C1A4a1h, 5C1A4a1d, 5C1A4a3b, 5C1A4a3a, 5C1A4b1g, 5C1A4b1e, 5C1A4a1b as their respective codes. The total project area of the
watershed is about 7741 ha. out of which 5000 ha is proposed for treatment under Integrated Watershed Management Programme (IWMP).
The nearest town is Mandvi which is taluka place and also about 12 kms. from project area villages. All villages are well connected with pacca roads
except kalmoi village. The project consists 13 no. of villages. Mainly Chaudhari, Vasava, Gamit all ST communities are the primary inhabitants of the
villages. The livelihood of these people is primarily based on rain fed agriculture, animal husbandry and wage labour.
small & marginal farmers, ground water status, area under rain fed agriculture, drinking water situation in the area, productivity potentials of the land,
The rains in this area are comparatively good but due to Geohydrological situation, the moisture index is low. Drinking water is not a major
problem even though people are facing crises during summer season.
iii Actual wages 5 Actual wages are Actual wages are equal to
significantly lower than or higher than minimum
minimum wages (5) wages (0)
iv % of small and marginal 10 More than 80%(10) 50 to 80%(5) Less than 50 %(3)
farmers
v Ground water status 5 Over exploited (5) Criteria (3) Sub critical (2) Safe (0)
vi Moisture index/DPAP /DDP 15 -66.7 & Below (15) -33.3 to -66.6(10) 0 to -33.2 (0)
Block
DDP Block DPAP block Non DPDAP/DDP Block
vii Area under rain-fed 15 More than 90% (15) 80 to 90 %(10) 70 to 80% (5) Above 70%(Reject)
agriculture
viii Drinking water 10 No Source(10) Problematic village(7.5) Partially covered(5) Fully Covered(0)
x Productivity Potential of the 15 Land with low Lands with moderate Lands with high
xiii Cluster approach in the hills 15 Above 5 micro – 3 to 5 micro 2 to 3 micro watersheds
(more than one contiguous watersheds in cluster watersheds in cluster in cluster (5)
micro-watersheds in the (15) (10)
project)
The following works have been taken up under the scheme during last two years.
(1) MGNREGS: There are about 3615 job card holders. Pond deepening and widening of road works, construction of road, and desilting of three check
dams, Drainage percolation tank with cost of 5.30 lakh has been completed till date.
(2) Prehariyali/ Hariyali watershed programme: Under IWDP project, total area of 900 ha in total project area have been treated where all activities
related to soil and water conservation measures have been taken care. Two solar street-light installed so far under IWDP to promote non conventional
source of energy in each village.
(3) Total Sanitation Campaign (TSC): 338 toilets in BPL Houses and 798 toilets in APL houses in project villages have been constructed under TSC
programme in the project area.
(4) Indira Awas Yojana: There are 1159 houses have been constructed in the villages of Project area. 5 in Kalmoi, 159 in Khodamba,85 in Patal,
100 in Uteva , 110 in Titoi, 77 in Amba 55 in Pardi , 68 in Karvali, 94 in Regama ,100 in Fali 198 in Kolsana, 74 in Kasal and 34 in Kalibel under IAY.
(5) WASMO/Sector reform: In the project villages 40 % of the houses get water by tap connection under WASMO programme.
Rural Development
1 TSC Sanitation 2004-05 13 3038 HH
Dept.
Rural Development
2 Indira Avas Yojana Housing 1992-93 13 1398 HH
Dept.
Rural Development
3 NREGS Employment 2007-08 13 3615 HH
Dept.
Govt of Gujarat
4 WASMO Water facilities 2003-04 5 1215 HH
The Social Forestry Division, Surat is the PIA of Patal Project. It was sanctioned as a PIA on 1st Feb 2009 under a Memorandum of
Understanding(MoU) between the DWDU,Surat(District Level Nodal Agency) and Forest Department to implement the work approved in the detailed
project report. The Social Forestry has dedicated and experienced staff comprising Deputy Conservator of Forest.Assisant Conservator of Forest and Range
forest Officer at Mandvi and Watershed Development Team (WDT) of agriculture expert, community mobilization expert, Civil engineer, accountant,
computer operator and messenger.The Watershed Development Team has their office at Forest quarters, Van darpan, near health center, Mandvi.
The objective of the Social Forestry Division, Surat is supervising, planning, implementing, documenting and promoting watershed
development project and related development activities in the project area.
b) To provide necessary technical guidance for preparation of development plan for the watershed.
f) To encourage adoption of low cost technologies and build upon indigence technical knowledge.
g) To monitor and review the overall project implementing and set up institutional arrangement for post-project operation & maintenance & further
Strength:-
Strong linkages with national and state level institutions, agriculture universities, and NGOs for capacity building technical guidance.
Weakness:-
No permanent staff.
Opportunities:-
Awareness generation among the illiterate through IEC activities by usage of new ICT activities.
Usage of new technologies of watershed modelling and GPS for monitoring the watershed activities.
Threates:-
Fax 0261-2651643
E-mail surdwduiwmp3@gmail.com
Assistant
Project
2 K. A. Rathod 57 M conservator of Bsc ,LLB 30 yrs 42000
Management
forest
Supervision of
3 Amrat chaudhri 57 M R.F.O. Bcom 28 yrs 17000
works
5 yrs &3
3. Santilalbhai Vasava 41 M WDT-Civil Diploma in civil civil work 10000
months
Computer
7 Raksha 25 F Data entry Operater BA with computer 4 yrs 7000
operating
total area of the project is 7741.30ha out of which 5000 ha. will be treated under IWMP. The area is having moderate to gentle slope.
The net geographical area of Patal watershed project is 7741.30 ha, out of which 19% is forest area which is about 1544.12ha. The area is having
sparse vegetation due to over grazing. Due to murum soil vegetative cover is affected. About 4466.98 ha land is under agriculture, out of which 986 ha
(22%) is irrigated through canal(5%) , Open Well and Bore(17%) rest of the agriculture rain fed. There is about 7 percent of wasteland of which 4 per cent
is cultivable.
Wasteland
Names of Geographical Area Land under Rainfed Perm-anent
Forest Area Non-
Sr. No. villages of the village agricultural use area pastu-res Cultivable
cultivable
soil is Reddish brown to dark in hilly area, very dark grayish brown to dark brown & dark to Yellowish brown . The depth of soil is moderate to deep
about 25 to 75 cm. The predominant texture of soil is heavily dominated by clay particles. The fertility of soil is poor with less Nitrogen while Phosphorus
is medium, Potash is also medium. The order of soil is mainly Inceptisols, Vertisols, and Entisols. The topography of the area is moderate ranging from 10-
The area is dependent on rain fall . The rain fall is normal. The average rain fall of this area is about 1488 mm (from past five year data).
This uneven distribution is leading to runoff of soil every year to the stream and rivulets. Mandvi taluka have "Goradu" Soil. The soil testing analysis results
have revealed that the project has content of nitrogen and phosphorous foundless. Content of potash has normally found adequate. There is a vast scope of
organic farming in the area there is a need of proper IEC activity between farmers.
2005 2002 mm 37 26 30 18
2006 1989 mm 38 28 32 20
2008 1267 mm 38 26 29 22
2009 913 mm 39 27 28 20
Irrigation
The irrigated area is 986.01 ha, which is 22 % of the total agricultural area of the village. Main source of irrigation is from previously
constructed pond, check dams or wells/borewell. A few farmers of Patal Project get irrigation to their field by check dams and from earthen dams which
were previously constructed by different departments. Some farmers of Uteva, Titoi and Kalmoi get water for irrigation from the main dugout pond cum
earthen dam.
Total
1514.4 1679088 1108.74 1223.82 682495 557.68 777.4 305463 392.93
Total
153.4 76948 501.62 58.4 40560 694.52 147.84 41665 281.82
Quality of Seeds: Good quality seed, fertilizer and pesticide are important factor in agriculture productivity. The use of good quality leads to higher land
productivity. In project villages, however, there are two limitations in the use of fertilizer. First these fertilizers are most useful in irrigated condition. The
agricultural land of the cluster villages however totally depend on rainfall. In villages mostly farmers use nitrogenous fertilizers especially urea. This has
resulted in disproportionate use of fertilizer depleting the quality of land.
Traditional farming methods: This is the factor that leads low productivity. There is lot of ignorance about the use of new farming methods and
technologies such as multiple cropping.
Lack of Rural Credit: Farmers face so many problems for rural credit and it leads to low agricultural productivity. Farmers need credit mainly for the
purchase of various inputs such as seed, fertilizers, and pesticides and for repair of implements. They use long term credit for buying land, and for investment
to improve the quality of land, buying the new implements and improving irrigation facilities.
Livestock:
The project area has 1267cows and 3538 buffaloes while the other domestic animals include 1242 bullocks and 748 goats. This show there
is an ample potential for producing organic manures and promote organic farming in this area. But there is need to make farmer understand the
advantages of using organic manures and practice organic farming. The need for integrating the animal husbandry with promotion of organic
farming needs to be given high priority. The productivity of milk is so less due to lack of availability of good quality of fodder due to less per capita land
availability.
3 Patal 268 244550 115 125925 370475 10 1320 215 149 206 -
9 Regama 229 208963 155 169725 378688 139 18348 223 193 6 -
Total 3538 3228420 1267 1387365 4615785 748 98736 1572 1239 1496
2 Khodamba Pastures 40 40
Forest 16 16
3 Patal Pastures 49 49
Forest 6 6
Forest 3 3
13 Kalibel Pastures 10 10
Forest 14 14
Migration pattern:
Migration of the villagers is observed mainly from November to May when they do not have any work to do. The agricultural labourers find some
employment during the monsoon season in their own village. Large numbers of villagers migrate in semi-bonded areas such as Surat and Bharuch to work
as cane-cutters in the sugar co-operatives. They even migrate as agricultural labours i.e. for construction works. The income they earn during the migration
period ranges from Rs. 4500 per month.
Poverty
The villages have a acute of poverty due to lack opportunity in various pockets of villagers. Nearly 46.02 per cent of the total household are poor of which
30 per cent lies 0-16 while other 70 per cent are in 16- 20. There is a ample need of developing various livelihood opportunity to increase the standard of
life of these poor.
Watershed Activities
Several studies have identified that there is a dire need of a systematic and scientific approach to deal with watershed development. The
common guidelines generate a fresh and flexible framework for the next generation watershed development.
Cluster Approach
This envisages a broader vision of Geo-hydrological unit which involves treating a cluster of micro-watershed. The Patal project consist of
four micro-watersheds namely 5C1A4a1g, 5C1A4a1f, 5C1A4a1e, 5C1A4a1h, 5C1A4a1d, 5C1A4a3b, 5C1A4a3a, 5C1A4b1g, 5C1A4b1e, 5C1A4a1b as their
respective codes. Further Patal watershed project is in continuation with other watershed programme namely IWDP.
(2)Baseline survey
To access the impact of any watershed development programme a detailed baseline survey has to be constructed. This acts a benchmark for
any intervention during and post implementation of any development programme. A detailed baseline survey was been undertaken which involved
household census survey, Bio-physical survey and village level data collection from Talati-cum mantri. Household census survey includes a detailed
questionnaire which was been filled by visiting each and every house-hold in the village. This gave in the details of the demographic profile of the village,
the literacy percentage, SC/ST population, number of BPL household, cattle population, net consumption rate in the village, and average milk production of
the castles and varies schemes running and their benefits.
Bio-physical survey was been undertake to identify various natural resources available in the village. It included the soil typology, well in
the area, crop taken in the field, cropping pattern, fertilizer used and various sources of irrigation in the field.
The primary data was generated through questionnaire surveys in all the villages. The questionnaire was structured so as to derive the
information related to the objectives set forth. Mostly talked to head of the families.
Farmers, Agricultural labours, Diamond polishing workers, handicraft unit workers, electric drum making units and workers of thresher units.
Cattle Breeders
Landless labour
The questionnaire was divided into nine modules through which information is extracted pertaining to
Village details
Population details
Productivity of farms
The secondary data was obtained through Census reports (2001). Data pertaining to social profile is also collected through Census reports. Secondary data
related to different kinds of capital assets were collected from different departments of Government agencies such as Revenue Office, Primary Health
b) Field to field Survey: Field to field survey was also carried out in the farms, community land, pasture land and land under Gram Panchayat. It also
includes the soil profiles, no of wells in the area, crop taken in the field, cropping pattern, fertilizer used and various sources of irrigation in the field. The
details of agriculture as well as pasture lands of the village where the existing condition and structures to be proposed, were written down. Almost all the
farmers of the village were there to support the survey team. The purpose of the survey was also to understand water availability, patterns of water use
and peoples’ understanding & perceptions about both surface and groundwater resources in this area. Village agreements will be done on the basis of such
detailed work. This also survey looked at the pattern of surface and groundwater use and the basic understanding of farmers regarding groundwater
recharge and discharge. This understanding was expected to help in improved planning for any watershed programme and to develop longer-term
protocols of groundwater management in respective areas.
c) Demand survey: To know about the livelihood pattern of the village and the present status and practice capacities required are discussed. Quantitative
involved also on possible micro enterprise development for sustainable development of village extensively for SC/ST and landless/migrated poor people.
The past experience of watershed has given tremendous input to focus on creating accountability of the stakeholders towards the
programme. This has created an emphasis to include all the stakeholder communities and their local and indigenous Technological knowledge (ITK) while
planning for any activity. Participatory approach Provide a new path for planning, implementing, monitoring and post-withdrawal activities with a
complete accountability of the stakeholders. This decrease the effort of the ground staff i.e. WDT members and involves more of villagers as implementers.
Various PRA techniques like resource mapping, social mapping, and season calendars were used to understand the physical and social orientation of the
village in general and watershed in specific. These tools put the villagers ease than the complicated questionnaires. Various tools like matrix ranking, vane
diagram were used to indentify various local vegetation (apt for af forestation ), fodders crops, various institution and their significance in the life of the
farmers.
In order to understand the social, economic and political aspect of all the villages of the cluster, we conducted Participatory Rural Appraisal
(PRA) exercise with the help of the villagers. It was really a useful tool to appreciate the village in its totality. We had the opportunity to interact with more
than 600 numbers of people in each village. To reach a concrete conclusion we requested a few villagers for focused discussion and it was entertained. As
per their convenience we conducted focused group discussion at the Community hall and Panchayat Bhavan ground. In majority of the discussion, we
listened to them carefully and tried to appreciate the discussion. Output generated through these exercise is placed below
Social Map: - After this exercise we came to know the approximate location of different institution of the village. During this exercise we also had informal
discussions with the participants about the importance of these institutions. Important location pointed out during this exercise was Community Centre,
Panchayat Bhavan, temple, Primary School etc. We cross checked all the location.
(iii) Seasonal Diagram:- With this exercise we came to know about the major engagements of villagers across the twelve months of the year. We found
that rainfed agriculture and animal husbandry keep them busy at least for seven to eight months of the year. About drinking water they informed that,
situation in the month of March to June is really difficult as they get water once in three days.
(iv) Tree matrix:- We came to know about different trees of the villages and their respective utilities as fruit, fuel, fodder, medicine , timber etc. Major
trees pointed out by villagers under this exercise were Pipal, Neem, Bor, Lemon, Banyan and Pipara etc. Taking into consideration all the utilities it was
found that the tree having maximum utility is Chiku and lemon.
(v) Crop Pattern:- Agriculture is the primary source of liveihood for more than 70% household . After this exercise we came to know that there are two
major cropping pattern Kharif and partially in Rabbi. Under Kharif cotton, ground nut and fodder crops and in rabi, major crops grown are wheat, cumin,
gram and vegetables.
(vi) Income-Expenditure Pot: - Under this exercise we came to know about the different sources of income of villagers and how the money earned by the
villagers is being spent under different heads. It was found that major source of earning among villagers are farming, dairy, service etc. Major expenditure
component were food, fuel, fodder, schooling of children, medicines, festivals, relatives, and paan etc.
Another curiosity in our mind was about the political institution of the village. Apart from different institution discussion was concentrated
about gram panchayat issue. Here the major discussion point was participation of women and deprived section of the society in the decision making
The whole purpose was to identify the employment opportunities available during the different seasons in a year, income, expenditure,
crisis management, daily activities and time allotted to each activity, the leisure time of men and women, and market network for agricultural produce etc.
In the gender analysis, an attempt was made to find out the gendered division of labour, the status of women in relation to the right to use, to own and sell
different household properties, the means of production of the household, and the role and participation of women in decision-making at intra household
and community levels.
To identify different problems faced by villagers a separate focussed discussion was carried out. The villagers were grouped in to different
types as shown below to know all the details of the village in a stipulated time.
Large farmers
Landless farmers
Women
Problems Identification
After analysis the information collected during PRA exercise, the main problems identified as
Drinking Water
Migration
Sanitation Problems
Use of various high science tools has been promoted at various stages of watershed development.
Geographical Information System (GIS) has been used for prioritization process. Various layer maps were created like Geo-morphological,
Soil, BPL population, ST/ST population, Ground water status, and Drinking water situation slope percent. These were all given proper weight ages
according to the DoLR specification. This helped in prioritization of various watershed areas.
Planning
A action plan matrix was been formulated by State Level Nodal Agency(SLNA) taking into account various features like the slope percent,
soil depth, Soil Texture, Soil erosion in the area for wasteland, forest land and agriculture land.
Global Positioning System (GPS) was used to identify each and every water conservation structures available in the project area. This will be
used to create a map. Contour map of vertical interval of 1 meter at a scale of 1:8000 was used for identifying various location specific for soil and water
conservation structures.
C) Hydrological modeling
Hydrological modeling technique was being used for locating drainage, stream length, flow direction, sink, and Flow accumulation. This
model overlaid over cadastral map hell to calculate the catchment area of each structures like the check dam etc. This has helped to remove the human
error which generally occurring while calculating the catchment area of a check dam.
Table no. 30: Details of Scientific Planning and Inputs in IWMP projects
S. No. Scientific criteria/ inputs used Whether scientific criteria was used
Planning
Cluster approach Yes
Whether technical back-stopping for the project has been arranged? If yes, mention the name of the
Yes
Institute
Baseline survey Yes
Hydro-geological survey Yes
Contour mapping Yes
Participatory Net Planning (PNP) Yes
Remote sensing data-especially soil/ crop/ run-off cover -
Ridge to Valley treatment Yes
Online IT connectivity between
#NDVI - Ratio of the differences of the response of vegetation in the near infrared & red regions of the electromagnetic spectrum
Date of
Educa-
Sr Registratio Name of Function
Any tional
. Names of n as a Member Designatio M/ S Land G /s
ST SF MF LF UG SHG othe qualifi
N WCs Society n F C -less P assigned
r -
o. (dd/mm/ #
cation
yyyy)
Dilipbhai L.
President M ¡ - ¡ - - - - - 8th -
Gamit
Laljibhai D. ¡ ¡ - - - - - - -
Secretary M 12th
Chaudhari
Santilalbhai J. ¡ - - - - - -
Member M ¡ - - civil
Vasava
Sudhaben P. ¡ ¡
Member F - - - - - - - 12th -
Chaudhari
Taraben A. ¡ - - - - - ¡ - - -
Member F 9th
Chaudhari
Watershed
Under Nitaben R. ¡ - - - - - ¡ -
5 committee Member F - 12th
Progress Chaudhari
Titoi
Ashokbhai K. ¡ ¡ -
Member M - - - - - - 8th -
Chaudhari
Ishwarbhai S. ¡ - - - -
Member M ¡ - - - - 7th
Chaudhari
Arjunbhai C. ¡ - -
Member M ¡ - - - - - - BA
Chaudhari
Virsinhbhai R. ¡
Member M - ¡ - - - - - BA -
Chaudhari
Harsanbhai B. ¡ - - - - - - -
Member M ¡ 7th
Chaudhari
Mohanbhai M. ¡ - - - - - - -
Member M ¡ 9th
Chaudhari
Vijaybhai P. ¡ ¡ - - - - - - -
Secretary M B ed
Chaudhari
Santilalbhai J. ¡ - - - - - -
Member M ¡ - - Civil
Vasava
Sarmilaben P. ¡ ¡
Member F - - - - - - - BA -
Chaudhari
Ilaben V. ¡ - - - - - ¡ - - -
Member F 10th
Watershed Chaudhari
Under
8 committee Chetanbhai T. ¡ - - - - - ¡ illiterat -
Progress Member M -
Karvali Rathod e
Virsinhbhai M. ¡ ¡ -
Member M - - - - - - 10th -
Chaudhari
Dipakbhai U. ¡ - - - illiterat -
Member M ¡ - - - -
Halpati e
Ishwarbhai G ¡ - -
Member M ¡ - - - - - - 7th
Halpati
Vadsibhai D. ¡ illterat
Member M - ¡ - - - - - -
Chaudhari e
Machhabhai M. ¡ - - - - - - -
Member M ¡ 7th
Chaudhari
Self Help group are motivated, small homogeneous group organised together through highly successful of credit and thrift activities. Self Help Group
initiative especially for women to uplift their livelihood. Generally self help group includes landless and marginal sized farm women, BPL household, SC/ST
women.
SHG initiative in Patal watershed was being organized by having a focused group discussion between various homogeneous communities of women
based on their livelihood separately. Each group discussed their basic problems with their facilitators. The major problems identified are:
Lack of proper credit facilities due to low intervention of formal financial credit institutes.
Excessive exploitation of weaker section by money lenders.
Lack of attitude of saving among poor people due to complex and rigid conventional financial institution structure.
Lack of small micro- loans without collaterals and high interest rates.
Lack of knowledge on credit, Thrift activity and banking.
With a view point of these problems it was planned to organized these women to a in to group consisting of 12 to 20 to each groups. With
detailed discussion with some of the local NGOs working in the area like SEWA, it was planned to have some capacity building training regarding SHG
activities. It was also proposed to have some livelihood activities which will promote women empowerment this included spices packing, embroidery
activities with forward and backward linkage. This will ultimately lead into a better human development in the village.
(i) Landless 0 0 0 0 0 0 0 0 0
(ii) SF 0 26 26 0 26 26 0 26 26
1 0 2 0 2
(iii) MF 0 0 0 0 0 0 0 0 0
(iv) LF 0 0 0 0 0 0 0 0 0
Total 0 26 26 0 26 26 0 26 26
(i) Landless 0 8 8 0 8 8 0 3 3
(ii) SF 0 21 21 0 21 21 0 9 9
3 0 2 0 2
(iii) MF 0 0 0 0 0 0 0 0 0
(iv) LF 0 0 0 0 0 0 0 0 0
Total 0 29 29 0 29 29 0 12 12
(i) Landless 0 1 1 0 1 1 0 1 1
(ii) SF 0 10 10 0 10 10 0 3 3
5 0 2 0 2
(iii) MF 0 14 14 0 14 14 0 5 5
(iv) LF 0 0 0 0 0 0 0 0 0
Total 0 25 25 0 25 25 0 9 9
(i) Landless 0 0 0 0 0 0 0 0 0
(ii) SF 15 19 34 15 19 34 0 10 10
7 1 2 0 3
(iii) MF 0 5 5 0 5 5 0 0 0
(iv) LF 0 0 0 0 0 0 0 0 0
Total 15 24 39 15 24 39 0 10 10
(i) Landless 0 4 4 0 4 4 0 4 4
(ii) SF 9 5 14 9 5 14 4 9 13
9 1 1 0 2
(iii) MF 1 5 6 1 5 6 1 5 6
(iv) LF 1 0 1 1 0 1 0 0 0
Total 11 14 25 11 14 25 5 18 23
(i) Landless 0 2 2 0 2 2 0 2 2
(ii) SF 0 5 5 0 5 5 0 3 3
11 0 1 0 1
(iii) MF 0 4 4 0 4 4 0 2 2
(iv) LF 0 0 0 0 0 0 0 0 0
Total 0 11 11 0 11 11 0 7 7
(i) Landless 0 0 0 0 0 0 0 0 0
(ii) SF 10 18 28 10 18 28 6 10 16
12 1 2 0 3
(iii) MF 2 5 7 2 5 7 0 0 0
(iv) LF 0 0 0 0 0 0 0 0 0
Total 12 23 35 12 23 35 6 10 16
In case of check dam all the beneficiary of the individual check dam where involved as user group members.
In case of Vermi compost all the individual beneficiaries of animal husbandry are considered as potential members.
Membership was on voluntary and democratic.
Focused group discussion was conducted to between the user groups to discuss the above conditions and to select potential members.
It was advocated that each group to formulate certain internal rules and have a feeling of ownership with community spirit.
(i)Landless 0 0 0 0 0 0 0 0 0
(ii) SF 22 0 22 22 0 22 22 0 22
1 4 0 1 5
(iii) MF 4 0 4 4 0 4 4 0 4
(iv) LF 2 0 2 2 0 2 2 0 2
Total 4 0 1 5 28 0 28 28 0 28 28 0 28
(i)Landless 0 0 0 0 0 0 0 0 0
(ii) SF 28 2 30 28 2 30 28 2 30
2 5 0 1 6
(iii) MF 19 2 21 19 2 21 19 2 21
(iv) LF 10 1 11 10 1 11 10 1 11
Total 5 0 1 6 57 5 62 57 5 62 57 5 62
(i)Landless 0 0 0 0 0 0 0 0 0
(ii) SF 55 5 60 55 5 60 38 2 40
4 7 0 2 9
(iii) MF 13 2 15 13 2 15 7 1 8
(iv) LF 6 1 7 6 1 7 0 0 0
Total 7 0 2 9 74 8 82 74 8 82 45 3 48
(i)Landless 0 0 0 0 0 0 0 0 0
(ii) SF 46 4 50 46 4 50 40 5 45
5 5 0 1 6
(iii) MF 13 2 15 13 2 15 10 2 12
(iv) LF 11 0 11 11 0 11 0 0 0
Total 5 0 1 6 70 6 76 70 6 76 50 7 57
(i)Landless 0 0 0 0 0 0 0 0 0
(ii) SF 54 3 57 54 3 57 22 3 25
6 7 0 2 9
(iii) MF 12 3 15 12 3 15 5 2 7
(iv) LF 8 2 10 8 2 10 0 0 0
Total 7 0 2 9 74 8 82 74 8 82 27 5 32
(i)Landless 0 0 0 0 0 0 0 0 0
(ii) SF 27 3 30 27 3 30 10 0 10
8 6 0 2 8
(iii) MF 11 3 14 11 3 14 5 0 5
(iv) LF 7 1 8 7 1 8 0 0 0
Total 6 0 2 8 45 7 52 45 7 52 15 0 15
(i)Landless 0 0 0 0 0 0 0 0 0
(ii) SF 56 3 59 56 3 59 10 2 12
9 5 0 1 6
(iii) MF 16 2 18 16 2 18 7 0 7
(iv) LF 5 0 5 5 0 5 0 0 0
Total 5 0 1 6 77 5 82 77 5 82 17 2 19
(i)Landless 0 0 0 0 0 0 0 0 0
(ii) SF 27 2 29 27 2 29 12 2 14
10 6 0 0 6
(iii) MF 9 1 10 9 1 10 6 0 6
(iv) LF 14 1 15 14 1 15 0 0 0
Total 6 0 0 6 50 4 54 50 4 54 18 2 20
(i)Landless 0 0 0 0 0 0 0 0 0
(ii) SF 17 2 19 17 2 19 5 0 5
11 6 0 1 7
(iii) MF 15 1 16 15 1 16 3 0 3
(iv) LF 3 0 3 3 0 3 0 0 0
Total 6 0 1 7 35 3 38 35 3 38 8 0 8
(i)Landless 0 0 0 0 0 0 0 0 0
(ii) SF 30 3 33 30 3 33 15 2 17
12 6 0 1 7
(iii) MF 19 2 21 19 2 21 7 0 7
(iv) LF 12 2 14 12 2 14 0 0 0
Total 6 0 1 7 61 7 68 61 7 68 22 2 24
(i)Landless 0 0 0 0 0 0 0 0 0
(ii) SF 34 1 35 34 1 35 3 0 3
13 5 0 1 6
(iii) MF 13 1 14 13 1 14 0 0 0
(iv) LF 7 0 7 7 0 7 0 0 0
Total 5 0 1 6 54 2 56 54 2 56 3 0 3
Table no.34: Entry point activities (EPA) (All financial figures in lakh Rs.)
Sr. Estimated cost
Names of Villages Amount earmarked for EPA Entry Point Activities planned
No. Unit (Nos) (lac)
Bore/Hand pump repairing 1 0.11
1 Kalmoi 0.29
Pipeline (mtr) 60 mtr 0.18
Bore/Hand pump repairing 8 0.82
2 Khodamba 1.41 Well repairing 1 0.39
Checkdam Repairing 1 0.20
Bore/Hand pump repairing 8 1.10
3 Patal 3.42 Pipeline (mtr) 650 mtr 1.94
Bore repairing 1 0.38
Bore/Hand pump repairing 8 0.50
4 Uteva 3.02 Well Repairing 1 0.70
Checkdam Repairing 1 1.82
Bore/Hand pump repairing 9 0.80
Pipeline (mtr) 200 mtr 0.60
5 Titoi 2.01
Hawada 1 0.33
Well Repairing 4 0.28
#One of the following may be entered in columns: Completed (ii) in progress (iii) just started (iv) not started
In a watershed, the slopes falling from the ridge to the beginning of the plains are called ridge area. It is very important to treat the higher
reaches of the ridge has this is where the major water resources originate. This involves mainly highly and forest region in the watershed. Various
watershed managing structures should be build to arrest the erosion and degradation of forest with grasses in upper ridges.
1. Contour trench
2. Gabion
3. Grass seedling/plantatation
1. Contour Bunds/Trench
Contour bund/trenches are a simple, low-cost method of checking the velocity of runoff in the ridge area of any watershed. A contour trench
is a trench dug along a contour line. A contour line is an imaginary line that joins together points of the same elevation. Digging a trench along a line that is
at the same level increases the chances of containing runoff for a longer period of time within the trench. If bunds/trenches were not to follow a contour,
such digging could actually increase the possibility of soil erosion because there would be a rise in the velocity of runoff following upon an increase in the
slope of the land. In the ridge area of a watershed a contour bund/trench is a simple and inexpensive solution to slowing down surface runoff and reducing
soil erosion.
Objectives
1) Slowing down the velocity of runoff
2) Checking soil erosion
3) Improving local soil moisture profile
2. Gabions Structure
Gabion structures are rock and wire dams constructed across drainage lines with a catchment area of 50-500 ha. They are also constructed
to reinforce highly erodible stream embankments. The main aim of constructing gabion structures is to reduce the velocity of water flowing through the
drainage line. By reducing the velocity of runoff, gabion structures help in -
1.Reduction in soil erosion
2. Trapping silt, which reduces the rate of siltation in water harvesting structures in the lower reaches of the watershed.
3. Increasing recharge of groundwater and
4. Increasing the duration of flow in the drainage line. Therefore, the capacity of the water harvesting structures created
downstream on the drainage line is utilized more fully as they get many more refills.
The second tier treatment is the slope treatment. This is generally agricultural land or waste lands. These are generally water conservation or surface water
storage structures. These being highly labour intensive will involve more of manual labour so schemes like National Rural Employment Guarantee Scheme
(NREGS) can be taken. Following structures has been proposed in the project villages.
1. Check dams/Causeway cum check dams
1. Check dams
Check dams are constructed across small streams having slope the selected should have sufficient thickness of permeable bed or weathered
formation to facilitate recharge of stored water within short span of time. The water stored in these structures is mostly confined to stream course and the
height is normally less than 2m and excess water is allowed to flow over the wall in order to avoid scouring from excess runoff water cushions are provided
at downstream side. To harness the maximum run off in the stream series of such check dams are to be constructed to have recharge on regional scale in
project villages.
Artificial Recharge of ground water is one of the most efficient ground water management tools for ensuring sustainability of ground water
resources. Keeping in view the concen on problems of over exploitation of ground water resourses in the country as well as to ensure sustainable water
resources management and assured irrigation facilities in the affected areas, activity “Artificial Recharge to ground water through Dugwell” has been
prepared.
Item -2 : Filling in foundation with concrete of cement, sand and metal (up to 5 Cm. Size) in following proportion(1:4:8) incl… smooth finishing etc. for lead
50 mt. And lift 1.5 mt.
Total 0.644 Cm
Item -3 : Providing and laying burnt brick (conventional size) masonry for foundation in ordinary Portland cement…etc.cop
Chamber 2 X 2.27+1.77 X 1.90 X 0.23 3.531 Cm
1 X 1.56 X 1.80 X 0.23 0.646 Cm
Total 4.177 cm
Item -4 : Filling in foundation with concrete of cement , sand and metal (up to 5 cm. Size ) in following proportion (1:2:4) incl.. Smooth finishing etc. for
lead 50 mt. And lift 1.5 mt.
Chamber 1 X 2.50 X 2.00 X 0.10 Av. 0.500 Cm
Total 0.500 cm
Total 36.00 Sm
Item -6 : Providing , Filter sand of effective size and uniformity coefficient and required F/S and U/C etc. comp.
Chamber 1 X 1.56 X 1.04 X 1.20 1.947 Cm
Total 1.947 Cm
Item -7 : Providing , filter gravel of effective size and Uniformity Coefficient and required F/S and U/C ….etc. comp.
Chamber 1 X 1.56 X 1.04 X 0.60 0.973 Cm
Total 0.973 Cm
Item -8 : Providing supplying and fixing of slandered length of ISI mark Rigid Un-plasticized PVC pipe incl. cost of solvent cement and other material etc.
complete 6 kg/cm 2 no. of 110 mm dia. Pipe.
Proposed target
Proposed target
Augmentation/ repair of
Construction of new structures Total target
S. Village existing structures
Type of structures
No. name Area to Area to Area to
be Storage Estimated be Storage Estimated be Storage Estimated
No. No.
irrigated capacity cost(Rs) irrigated capacity cost(Rs) irrigated capacity cost(Rs)
(ha) (ha) (ha)
Proposed target
Proposed target
Proposed target
Augmentation/ repair of
Construction of new structures Total target
existing structures
Sr.
Village name Type of structures
No. Area to Area to Area to
be Storage Estimated be Storage Estimated be Storage Estimated
No. No.
irrigated capacity cost(Rs) irrigated capacity cost(Rs) irrigated capacity cost(Rs)
(ha) (ha) (ha)
Table no.37.2: Activities related to water conversation in the project areas (all financial figures in lakh Rs.)
Proposed target
Augmentation/ repair of existing
Construction of new structures Total target
structures
Sr. Village Storage
Type of structures Area to Area to Area to
No. name Storage capacity Storage
be Estimated be Estimated be Estimated
No. capacity(in No. (in capacity(in
irrigated cost irrigated cost irrigated cost
1000 Cmt) 1000 1000 Cmt)
(ha) (ha) (ha)
Cmt)
Checkdam - - - - 1 5 40.00 3.00 5 40.00 3.00
2 Khodamba
Dugwell recharge - - - - 3 - - 0.60 0.60
Total 2 5 40.00 3.60 5 40.00 3.60
Table no.37.4: Activities related to water conversation in the project areas (all financial figures in lakh Rs.)
Proposed target
Augmentation/ repair of existing
Construction of new structures Total target
structures
Sr. Village Storage
Type of structures Area to Area to Area to
No. name Storage capacity Storage
be Estimated be Estimated be Estimated
No. capacity(in No. (in capacity(in
irrigated cost irrigated cost irrigated cost
1000 Cmt) 1000 1000 Cmt)
(ha) (ha) (ha)
Cmt)
Checkdam - - - - 2 20 60.00 6.00 20 60.00 6.00
4 Uteva
Dugwell recharge - - - - 3 - - 0.60 0.60
Total 5 20 60.00 6.60 20 60.00 6.60
Table no.37.6: Activities related to water conversation in the project areas (all financial figures in lakh Rs.)
Proposed target
Augmentation/ repair of existing
Construction of new structures Total target
structures
Sr. Village Storage
Type of structures Area to Area to Area to
No. name Storage capacity Storage
be Estimated be Estimated be Estimated
No. capacity(in No. (in capacity(in
irrigated cost irrigated cost irrigated cost
1000 Cmt) 1000 1000 Cmt)
(ha) (ha) (ha)
Cmt)
Checkdam - - - - 2 20 60.00 6.00 20 60.00 6.00
6 Amba
Dugwell recharge - - - - 2 - - 0.40 0.40
Total 4 20 60.00 6.40 20 60.00 6.40
Table no.37.8 Activities related to water conversation in the project areas (all financial figures in lakh Rs.)
Proposed target
Augmentation/ repair of existing
Construction of new structures Total target
structures
Sr.
Village Storage
No Type of structures Storage Storage
name Area to be Area to be capacit Area to be
. capacity(i Estimate Estimate capacity(i Estimate
No. irrigated No. irrigated y (in irrigated
n 1000 d cost d cost n 1000 d cost
(ha) (ha) 1000 (ha)
Cmt) Cmt)
Cmt)
Checkdam - - - - 2 18 60.00 6.00 18 60.00 6.00
8 Karvali
Dugwell recharge - - - - 2 - - 0.40 0.40
Total 4 18 60.00 6.40 18 60.00 6.40
Table no.37.10 Activities related to water conversation in the project areas (all financial figures in lakh Rs.)
Proposed target
Augmentation/ repair of existing
Construction of new structures Total target
S. structures
Village
No Type of structures Storage Storage
name Area to be Storage Area to be Area to be
. Estimated capacity Estimated capacity(i Estimated
No. irrigated capacity(in No. irrigated irrigated
cost (in 1000 cost n 1000 cost
(ha) 1000 Cmt) (ha) (ha)
Cmt) Cmt)
10 Fali Dugwell recharge - - - - 3 - - 0.60 0.60
Total 3 - - 0.60 0.60
Table no.37.12 Activities related to water conversation in the project areas (all financial figures in lakh Rs.)
Proposed target
Augmentation/ repair of existing
Construction of new structures Total target
structures
Sr. Village Storage
Type of structures Area to Area to Area to
No. name Storage capacity Storage
be Estimated be Estimated be Estimated
No. capacity(in No. (in capacity(in
irrigated cost irrigated cost irrigated cost
1000 Cmt) 1000 1000 Cmt)
(ha) (ha) (ha)
Cmt)
12 Kasal Dugwell recharge - - - - 2 - - 0.40 0.40
Total 2 0.40 0.40
Table no. 38: Activities related to livelihoods by Self Help Groups (SHGs) in the project areas
Major activities of the SHGs
Names of
Sr. No. Average annual income from
Villages Name of activity No. of SHGs involved
activity per SHG
Animal Husbandry 1 0.48
Vermi compost 1 0.50
Baj dalia Machine 1 0.45
Washing Powder 1 0.72
1 Kalmoi
Crop demonstration 10 0.408
Drip irrigation 1 1.80
Horticulture 7 3.60
Pasture Development 6 0.36
Animal Husbandry 1 0.48
Vermi compost 1 0.50
2 Khodamba
Baj dalia Machine 1 0.45
Washing Powder 1 0.72
Executing
Type of treatment Type of land Target
agency
(i) UG Estimated cost
(iii) No. of Expected
S. Village (i) (ii) (ii)SHG (Rs. in lakh)
Name of structures (iii) (i) (ii) Others units month &
No. name Ridge Drainage (iii)
Land Pri- Commun (pl. (No./ year of
area line Others
dev. (L) vate ity specify cu.m./ M W O T completion
(R) (D) (pl.
) rmt) (mm/yyyy)
specify)
Nala plug R D P C - UG 17 - - - 0.85 may-2012
pacca nala plug - D - C - UG 12 - - - 4.80 Jan-2012
Gabion structure - D - P - - UG 10 - - - 2.50 Apr.-2012
Check wall - D - P - - UG 9 - - - 13.00 Apr.-2012
4 Uteva
Land levelling - - L P - - UG 15(ha) - - - 3.00 may-2011
Staggered Trench R - - - C - UG 1 - - - 1.50 Dec-2013
Check Dam - - L - C - UG 2 - - - 6.00 Jun-2013
Dugwell Recharge - - L P - - UG/SHG 3 - - - 0.60 may-2011
Total 31.75
Executing
Type of treatment Type of land Target
agency
(i) UG
(iii) No. of Estimated cost Expected
S. Village Name of (i) (ii) (ii)SHG (Rs. in lakh)
(iii) (i) (ii) Others units month &
No. name structures Ridge Drainag (iii)
Land Pri- Commu (pl. (No./ year of
area e line Others
dev. (L) vate nity specify cu.m./ M W O T completion
(R) (D) (pl.
) rmt) (mm/yyyy)
specify)
Nala plug R D - P C - UG 15 - - - 0.75 may-2012
pacca nala plug - D - - C - UG 18 - - - 7.20 Jan-2012
Gabion structure - D - P - - UG 15 - - - 3.75 Apr.-2012
5 Titoi Check wall - D - P - - UG 6 - - - 9.00 Apr.-2012
Land levelling - - L P - - UG 14(ha) - - - 2.80 may-2011
Check Dam - - L - C - UG 1 - - - 3.00 Jun-2013
Dugwell Recharge - - L P - - UG/SHG 3 - - - 0.60 may-2011
22.1
Total
0
Name of Executing
Type of treatment Type of land Target
structures agency
(i) UG
(iii) No. of Estimated cost Expected
Village (i) (ii) (ii)SHG (Rs. in lakh)
(iii) (i) (ii) Others units month &
name Ridge Drainag (iii)
S. Land Pri- Commu (pl. (No./ year of
area e line Others
No. dev. (L) vate nity specify cu.m./ M W O T completion
(R) (D) (pl.
) rmt) (mm/yyyy)
specify)
Nala plug R D - P C - UG 6 - - - 0.30 may-2012
pacca nala plug - D - - C - UG 4 - - - 1.60 Jan-2012
Gabion structure - D - P - - UG 6 - - - 1.50 Apr.-2012
11 Kolsana Check wall - D - P - - UG 2 - - - 3.00 Apr.-2012
Land levelling - - L P - - UG 15(ha) - - - 3.00 may-2011
Check Dam - - L - C - UG 1 - - - 3.00 Jun-2013
Dugwell Recharge - - L P - - UG/SHG 2 - - - 0.40 may-2011
11.0
Total
5
Executing
Type of treatment Type of land Target
agency
(i) UG Estimated cost Expected
(iii) No. of (Rs. in lakh) month &
S. Village Name of (i) (ii) (ii)SHG
(iii) (i) (ii) Others units year of
No. name structures Ridge Drainag (iii)
Land Pri- Commu (pl. (No./ completio
area e line Others
dev. (L) vate nity specify cu.m./ M W O T n
(R) (D) (pl.
) rmt) (mm/yyyy
specify)
)
Nala plug R D L P C - UG 10 - - - 0.50 may-2012
pacca nala plug - D L - C - UG 11 - - - 4.40 Jan-2012
Gabion structure - D - P - - UG 8 - - - 2.00 Apr.-2012
12 Kasal Check wall - D - P - - UG 3 - - - 4.50 Apr.-2012
Land levelling - - L P - - UG 16(ha) - - - 3.20 may-2011
Staggered Trench R - - - C - UG 1 - - - 1.50 Dec-2013
Dugwell Recharge - - L P - - UG/SHG 2 - - - 0.40 may-2011
14.7
Total
5
(i) UG
Name Name of Expected
S. (i) (ii) (iii) (iii) (ii)SHG Estimated month &
of structure/
No. Ridge Drainage Land (i) (ii) Others Area No. of cost year of
village work
area line dev. Private Community (pl. (iii) (ha) plants completion
Others (Rs. in
(R) (D) (L) specify) lakh) (mm/
(pl. yyyy)
specify)
Farm
- - L P - UG,SHG 2000 0.06 march2012
1 Kalmoi forestry
While promoting various income generation activities, agro-based activities have advantages because of the following reasons:
4. As over 50-60 % of the rural families own land and livestock, income generation activities can be initiated immediately without heavy
capital investment.
5. Risk of failure due to improper technology, poor quality, low demand and poor price recovery are very low. Hence, the chances of success
are high.
6. Infrastructure required for promotion of on-farm activities has been very well established. Hence, the entrepreneurs can progress even in
backward regions, which are deprived of regular power supply and electronic information connectivity. It is therefore advantageous to tap all
the opportunities to promote various on-farm activities. The experience has confirmed that the best strategy to promote income generation
activities through SHGs is to analyze the on-going agro-based activities undertaken by the members and introduce suitable interventions to
enhance the production. There are also excellent opportunities to improve post production management of the produce through grading,
storage, processing and marketing. Various micro-enterprises activities through UG and Self Help Groups will be promoted. The list of micro-
enterprises taken up by various SHGs is presented below. Among these activities, agriculture followed by animal husbandry, Khakhara making
units and food processing. However, over a period of time, agriculture, animal husbandry and food processing supercede the trade as man y
The Boer goat is a large framed animal with mature weights between 260-380 lbs. for males and 210-265 lbs. for females. The
potential for growth is outstanding. Under intensive performance tested conditions, males averaged 80 lbs. at 3 months of age; 160 Lbs. at 8
months; 222 Lbs. at 12 months; 257 Lbs. at 18 months; and 313 Lbs. at 25 months. Females averaged 63 Lbs. at 3 months; 139 Lbs. at 12
months; 165 Lbs. at 18 months; 220 Lbs. at 24 months.
The Boer goat is capable of attaining an average daily gain of over 400 gr. or 0.88 Lbs. daily in feed lot situations. The Boers
average daily gain potential on pasture or rangeland is outstanding and offers great possibilities for selecting to improve growth rates.
The Boer goats dressing weight percentage is over 50%. Comparead to South African sheep, the Boer goat had the higher
dressing percentage with carcasses having more total tissue in the fore arm, neck and ventral trunk, and less tissue in the hind limb.
Boer goats seem to yield a carcass superior to Angora, dairy and over meat goats and that fat content and muscling of Boer goat
carcasses compared favourably with those of specialized mutton producing breeds.
Thus, it is not surprising that with their excellent growth and carcass qualities many well known goat specialists listed the Boer
goat as one breed that could make a major contribution to increasing productivity of meat goats worldwide.
A good meat goat should also be fecund and prolific. More kids born per doe will result in greater profit margins for the
producer. The ovulation rate for Boer goats ranges from 1 to 4 eggs per doe with a mean of 1.7 (plus or minus .9). A normal kidding rate of
200% is common for the Boer goat. This is higher than most other goat breeds, thus the Boer goat can be considered a prolific breed. This
conclusion was also reached in New Zealand and Australia, based on the number of super ovulated embryos (9) harvested from the Boer goat
donor program.
The Boer goat reaches puberty early, usually about 6 months of age for males and 10-12 months for first-mating females. The
Boer goat has an extended breeding season and it is possible to achieve 3 kidding every 2 years.
The wide spread problems of soil degradation and desertification are threatening agricultural sustainability. Throughout the
project village large populations of domestic animals producing large amounts of organic wastes. These organic residues, or ‘waste materials’,
can be transformed more quickly and into a more useful vermi-compost, available for urban and land application. Nutrients within vermi-
composted material are readily available to plants, and can be added to agricultural land to improve soil structure and fertility or used as good
quality and marketable additive to potting soil or plant growth media. The process of composting crop residues using earthworms comprise
spreading the agricultural wastes and cow dung in layers as 1 m wide and 0.3 m high beds of required length. Earthworms are introduced in
between the layers @ 350 worms per m3 of bed volume. The beds are maintained at about 40 - 50% moisture content and a temperature of 20
- 30° C by sprinkling water over the beds. The earthworms being voracious eaters consume the biodegradable matter and give out a part of the
matter as excreta or vermi-castings. The vermi-casting containing nutrients are rich manure for the plants.
Eisenia fetida, Eudrilus eugeniae, and Perionyx excavatius are some of the species for rearing to convert organic wastes into
manure. The worms feed on any biodegradable matter ranging from coir waste to kitchen garbage and Vermi-composting units are ideally
suited to locations / units with generation of considerable quantities of organic wastes. One earthworm reaching reproductive age of about six
weeks lays one egg capsule (containing 7 embryos) every 7 - 10 days. Three to seven worms emerge out of each capsule. Thus, the
multiplication of worms under optimum growth conditions is very fast. The worms live for about 2 years. Fully grown worms could be
separated and dried in an oven to make 'worm meal' which is a rich source of protein (70%) for use in animal feed.
Location
All villages of Vad project have lots of animal so it can become good composting center as well as good source of livelihood.
Vermicompost is very suitable for fruit, flower and vegetable as well as cereal crops. It increases quality and quantity of product in per unit
area.
Market/Use
Vermi compost is a valuable input for sustainable agriculture and wasteland development. This also can be used widely in pot
culture and in home gardens. Several farmers are successfully using vermi-comost. Vermi compost has more nutrient compare to other
manures and fertilizer so by the use of compost we can reduce the use of chemical fertilizer. Vermi compost not only supply nutrient but also
improve quantity of hormones for plant growth, improves the soil structure leading to increase in water and nutrient holding capacities of soil.
Scientific bed size proposed here is 10ft by 3 ft by 2.5 ft. The whole bed area should be above the ground. The bed should have a
uniform height over the entire width to the extent possible to avoid low production owing to low bed volumes. The proper bed width should
not be more than 4.5 ft to allow easy access to the centre of the bed.
Land
About 500 square ft of land is required to set up a vermi compost production unit in each village. It should have at least one super structure
to cover the 10 beds. It should have an arrangement for watering and other equipments as required because moisture is very essential for
compost production. Land can be taken from Gram panchayat on lease of at least 10-15 years.
Seed Stock
This is very important thing because worms multiply at the rate of 350 worms per m 3 of bed space over a period of 6 month to a year.
Fencing
The entire area has to be fenced to prevent the stray animals and other unwanted elements. These could be estimated based on
the length of the periphery of the farm.
Water Supply System
We have to maintain always 50% moisture content, there is need to plan for a water source, lifting mechanism and a system of
conveying and applying the water to vermi-beds. Drippers with round the clock flow arrangement would be quite handy for continuous supply
and saving on water. Such a water supply/application system requiring considerable initial investment, however, reduces the operational
Farm machinery and implements are required for cutting the raw material in small pieces, conveying shredded raw material to
the vermi-sheds, loading, unloading, collection of compost, loosening of beds for aeration, shifting of the compost. Costs of providing necessary
implements and the machinery have to be included in the project cost.
Training will be provided to all the stakeholders by KVK which can be divided in to two categories and shown below.
A. Theoretical
• Vermi-culture
• Vermi-castings
• Vermi-compost
• Marketing Avenues
• Application of vermicomposting
• Production Methods
• Raw Materials
• Tank
• Vermi-bed
• Harvest
• Quality Analysis
The production can be achieved at block level and district level also. Any co-operatiive agency or Organisation does not sell this
Product so Market linkage is necessary for this product which will be created by manufacturer.
1) This enterprise can be installed at district head quarter. On this basis rental cost can be estimated.
Manufacturing Process :
CMC, Acid Slurry, Sodium Silicate etc. can be used for the manufacturing of detergent washing Powder. Mixture of this material is changed in
soponification. After the process, the product can be cut in various in sizes and manufacturing stamp will be punched on the product.
Detergent Powder:
Different types of powder, colours, Slurry and powder is mixed and mixture is shaked well. After grading this powder, packing is done.
Production Capacity :
The daily production capacity of Detergent soap is 100 Kg and production capacity of detergent powder is 70 Kg.
Permission :
Land/infrastructure:
About 300 to 400 Sq. Ft. room is needed for this enterprise.
Plant/machinery/instruments etc.
soap making
Machine
tray etc.
Total 50000
3 Operating Cost :
Production Cost :
1 Row material 26000
Total 33400
Total 36100
Production Capacity
B) Land/Infrastructure :
start his activity in his own land by using Approx. 900 Sq. Mt. carpet area.
3 Seeds 2600.00
4 Maintenance 15000.00
8 Marketing/transporting 23800.00
Total : - 140000.00
To empower and create opportunities for empowerment in the project villages by creating a new skill, which mainly is a Sewing
machine to make a tailoring work. We have statutory organisation engaged in promoting and developed tailoring work to village’s womens in
the rural areas, thereby strengthening the rural economy of the district. If undertakes activities like skill improvement, transfer of technology,
research & development, marketing, etc., in the process of generating employment/self-employment opportunities in rural areas. Training will
be provided by our selected training organisation about 30 womens. This Project under women’s are making a pillow cover, Blanckets (Razai),
and embroidered dress, saries and other clothe veriaty etc.
This Project also make creative and designing clothes for childrens and ledies and this project to very usefully to village’s
women become a successful entrepreneur.
This objective could be accomplished by establishing enterprises that are based on the locally available resources and referably
indigenous knowledge. Self Help Groups (SHG), each with 20-30 members, will be motivated and proper training will be provided for each
micro enterprise activity which will improve the quality of their own lives as well as the lives of those around them.
Field survey findings indicated that Clothes to Surat market and Mandvi market in many people purchese. It is a big market
centre for clothes. Training got after women’s making pillow cover, blanket, embroidered dress, saries and Clothes variety etc. sale to Market.
Production Capacity
Land/Infrastructure :
A person can start his activity in his own house by using Approx. 300 Sq. Ft. carpet area.
Total : - 109000
Total : - 6100.00
Total : 10900.00
Training Content
A. Theoretical
• Market development.
B. Practical
Mandap Decoration is most important in this era for marriage function, Social Occasion or festival celebration like Navratri
Mahotsav. Mandaps are used in various size and various types on these occasions. Generally Mandap means a sitting arrangement of 100 to
1000 or more persons.
Asumptions :
One big room is required to keep accessories of mandap and no training is required for this enterprise.
Benefit Capacity :
Approx. monthly income of Rs. 10000 can be obtained from this enterprise.
No permission is needed.
Land/Infrastructure :
Approx. 400 to 500 Sq. Ft. space is needed. Rs. 600 monthly rental is assumed for this purpose.
Total 98000
Production Cost
Sr Particular Price
no
1 Raw Material 400
5 Packing Cost
Income 3000.00
Other Details:
2) As mandap service is a business of 8 months, total bank installment is calculated as 8 month basis.
- - - - -
1 Kalmoi
- - 0 0 -
Total for project
2 Khodamba Waste land Plantation 1 1.30 500
Pasture Silvi
1 0.025 1000
land Pasture
Total for project 2 1.325 1500
3 Patal Wasteland Plantation 2.60 1020
Pasture Silvi
0.05 800
land Pasture
Total for project 2.65 1820
4 Uteva Waste land Plantation 2 2.60 1345
Pasture Silvi
2 0.05 1200
land Pasture
Total for project 4 2.65 2545
5 Titoi Waste land Plantation 1 1.30 987
Pasture Silvi
1 0.025 776
land Pasture
Gram
Waste land 1 2.00 1243
Vatika
Total for project 3 3.55 3006
6 Amba Waste land Plantation 1 1.30 567
Pasture Silvi
1 0.025 454
land Pasture
Pasture Silvi
2 0.05 1345
land Pasture
Pasture Silvi
1 0,025 567
land Pasture
Pasture Silvi
1 0,025 250
land Pasture
Total for project 1.55 395
Pasture Silvi
1 0,025 425
land Pasture
BUDGET
2 Monitoring
(2%) 12.00
3 Evaluation
TOTAL 600.00
Total 5.20
Total 5.69
Total 3.89
Total 4.01
Total 4.48
Total 3.47
Total 3.59
Total 3.83
Total 3.60
Total 4.89
Total 6.72
Total 4.26
Total 4.98
EXPECTED OUTCOMES
This programme also aims simultaneously to improve the living conditions of the user communities. Employment opportunities
will be created to the people living in the watershed through different soil and water conservation activities and livelihood activities. Self
employment would be created by providing the people with cash support in the form of direct livelihood activities like agriculture, animal
husbandry and enterprise development.
Total 12761 8351239 0 5436600 8364000 15 8595 0 5597 8613 1 428 0 280 431
• Increasing the frequency of cultivation – new water harvesting structures often permits cultivation of a second crop, or ‘lifesaving’
• Adopting new technologies, such as improved varieties of staple crops, higher levels of input use and higher yields; shifts to the
• Expansion of cultivated areas – soil and water conservation interventions can bring new land into production.
All of the above tend to generate increased demands for labour. These may be provided initially from farm family sources and
Employment opportunities in the local area as mentioned below will ensure lessening seasonal migration from the area.
Table no. 54: Details of average ground water table depth in the project areas (in Feet)
Expected Increase/decrease
S. No. Names of Villages Sources Pre-Project level
(Post- Project)
17-18 ft 21-25ft
Kalmoi, Khodamba, Patal,
Uteva, Titoi, Amba, Pardi, Open wells
1
Karvali, Regama, Fali,
Kolsana, Kasal, Kalibel Bore wells 25-30 ft 30-40 ft
6.1. 5: Crops
Due to additional availability of water in new structures, farmers will be able to grow vegetable crops during non rainy seasons.
Even after taking rainy season and post rainy season crops into consideration, they will get a good price for vegetables in summer also. Most
farmers with large families will prefer to grow vegetables, as the crops need timely availability of human labour to harvest and encash the
market potential. The planned earthen bunds would preserve some moisture in the soil. Also the proposed soil and water conservation
activities will bring more areas under cultivation. New agricultural practices, new technology, organic farming etc will be demonstrated in the
villages. This will help in additional area coming under cultivation and increasing productivity too. The farmers can take more than one season
of crops. Different varieties of crops can be taken.
2 Kharif
Rabi
4 Uteva Kharif
Rabi
5 Titoi Kharif
Rabi
6 Amba Kharif
Rabi
7 Pardi Kharif
Rabi
8 Kharif
9 Kharif
10 Fali Kharif
Rabi
11 Kolsana Kharif
Rabi
12 Kharif
13 Kharif
1 Kalmoi 0 23
2 Khodamba 0 8
3 Patal 3 8
4 Uteva 3 6
5 Titoi 0 15
6 Amba 5 1
7 Pardi 7 13
8 Karvali 5 13
9 Regama 1 3
10 Fali 0 4
11 Kolsana 0 5
12 Kasal 4 7
13 Kalibel 3 9
1 Kalmoi 10 28
2 Khodamba 2 8
3 Patal 1 4
4 Uteva 3 10
5 Titoi 0 2
6 Amba 0 3
7 Pardi 1 4
8 Karvali 1 4
9 Regama 0 2
10 Fali 0 3
11 Kolsana 0 3
12 Kasal 0 2
13 Kalibel 0 4
Linkages
The direct livelihood activities need good forward and backward support. Without such support system the activities may fail to
deliver the desired results. These linkages would involve credit, machinery, input supply, marketing, etc.
Backward linkages
Seed certification
Credit institutions
Extension services
Nurseries
Tools/machinery suppliers
Labour
Forward linkages
Harvesting/threshing machinery
Road network
Transport facilities
Markets / Mandis
Labour
Sensitise village
communities to
involve children and
youth in
development.
Identification and
promotion of non-
timber forest
produce based
income generation
activities
A Web-based CIS System is being developed for monitoring and evaluating the project in its planning & implementation phases.The system
would be available on a public domain and can be accessed by all the stakeholders of the project. The system shows theentire state of Gujarat and all of
those areas selected over the next 18 years. Filtering allows the user to zoom onto one particularproject. Details related to soil type, Land-use classification,
inhabitation etc., can be obtained village-wise. Furthermore, survey-numberwise details related to ownership, irrigation source, yield etc., can also be
accessed by the users of the system. This system is being usedfor pooling up the details obtained from the DPR. In other words, the DPR is made available
online in the form of a database which willhelp the stakeholders know areas of importance viz., already treated areas/historical works in the area,
proposed areas for treatmentetc., for further treatment and planning. The system would also show the satellite imageries of various years from the project
inceptionstage to the project closing stages. This allows the user to evaluate the effectiveness of the treatment and thereby plan correctivemeasures for the
project area. The system would serve as an aiding tool to the planners and evaluators for judging the efficacy of theproject.
Yet another component of the Web-based CIS system is the Mobile based Monitoring & Evaluation System, which will help the ground staff
alias WDTs (Watershed Development Team) to transmit information from the ground level to the central server. Also, any higher-up official in charge of the
project can obtain information regarding the project area on their mobile phone by means of an SMS. The system works in the following manner. The WDT
equipped with a GPS instrument marks the latitudelongitude information of various treatment areas during the DPR. The probable sites are then
transferred onto the central server. During the works phase, any progress in the treatment area is reported to the server by means of an SMS by the WDT.
Similarly, any nodal officer or higher-up official can view the progress in a project by means of summarized reports generated over frequent periods of
time.
Vigilance and Monitoring Committees
1. For every work sanctioned under the Scheme, there should be a local vigilance and monitoring committee, composed of members of the locality or village
where the work is undertaken, to monitor the progress and quality of work while it is in progress. The Gram Sabha will elect the members of this
committee and ensure that SC/STs and women are represented on it.
2. The Implementing Agency should apprise this committee of estimates regarding the work, time frame and quality parameters. The final report of the
committee should be attached along with the Completion Certificate of the work, and should also be placed at the next meeting of the Gram Sabha in the
Panchayat where work has been executed.
3. Local beneficiary committees may also be constituted for effective articulation of their entitlements and their access to them.
The PIA members will be responsible for ensuring that local monitoring committees/beneficiary committees are constituted.
It is planned that for SC/ST, BPL population the contribution will be taken in form of voluntary labour and the fund for labour will be diverted to the WDF.
Various user groups will be formed in village. These user groups will collect user charges according to the designated rules formed during
the formation of user group. These funds will be transferred to the WDF funds as per these formulated rules. The secretary of watershed comittee (WC)
shall maintain the records of the following.
MAP
CHAPTER – 8