Arup Journal Issue 1 2019

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 31

Issue 1 2019

The Arup Journal


Contents
4 Hong Kong-Zhuhai-Macao Bridge, 35 Brent Delta Platform Lift,
Greater China North Sea, UK
Designing the world’s longest sea crossing The world’s heaviest offshore lift
Naeem Hussain, Steve Kite, Samuel Kwan, was completed in just ten seconds
David Pegg, James Sze, Peter Thompson, – after years of planning
Fergal Whyte, Philip Wong, Ngai Yeung David Gration

14 BLOX, Copenhagen, Denmark 40 Rawang Bypass, Kanching


Turning a once-derelict section Forest Reserve, Malaysia
of Copenhagen’s waterfront into A transport solution that respects
a vibrant cultural hub the environment
Michael Bradbury, Chris Carroll Wan Anuar bin Wan Endut

20 Jaguar Land Rover 44 Leeds Flood Alleviation


Engine Manufacturing Scheme, UK
Centre, Wolverhampton, UK The first flood defence project in the
Reinterpreting the traditional factory UK to use movable weirs gives Leeds 100-
form to create a sustainable facility year storm flood protection
Mark Bartlett, James Finestone, Michael Nichols, David Wilkes
Philip Hives, Sean Macintosh,
Timothy Snelson, David Storer

28 Seattle Space Needle, USA 50 Amorepacific Headquarters,


A renovation of the iconic landmark respects Seoul, South Korea
its history and readies it for a long future Traditional Korean design provides the
Peter Alspach, Clayton Binkley, inspiration for a modern office building
David Okada, Kristen Strobel, Francesca Coppa, Eva Hinkers,
Cress Wakefield Julian Olley, Alexander Rotsch,
Nigel Tonks, Frank Walter

Seattle Space Needle, USA: Nic Lehoux

2 1/2019 | The Arup Journal 3


HZMB | HONG KONG, ZHUHAI, MACAO, GREATER CHINA

Strengthening
connections
The Hong Kong-Zhuhai-Macao Bridge (HZMB) is the world’s
longest sea crossing. It promotes connectivity in a fast-growing
region, significantly cutting journey times in the Greater Bay Area
Authors Naeem Hussain, Steve Kite, Samuel Kwan, David Pegg, James Sze, Peter
Thompson, Fergal Whyte, Philip Wong, Ngai Yeung

On 23 October 2018, Chinese President Along the way, the firm had to be mindful of
Xi Jinping opened the world’s longest sea the scheme’s impact on the surrounding
crossing, the 55km Hong Kong-Zhuhai- environment and wildlife, the effect of
Macao Bridge. Until then, travelling extreme weather conditions on the
between Hong Kong and Macao/Zhuhai programme and design, and the logistical
involved either a one-hour ferry ride challenges of coordinating and completing
(sometimes through bad weather such a large and ambitious scheme – the
conditions) or a four-hour detour over the HZMB took nine years to construct.
Humen Bridge, a crossing to the north of
the Pearl River Delta. With the opening of Developing a Greater Bay Area
the HZMB, it is now possible to make the The HZMB is part of a broader effort by
journey by car in a mere 40 minutes. the Chinese government to improve
connections between 11 cities on the
Arup performed a range of roles on the Pearl River Delta: Hong Kong, Macao,
project, including creating and developing Guangzhou, Shenzhen, Zhuhai, Foshan,
the concept and preliminary design for the
main bridge and tunnel, and proposing
environmentally friendly reclamation
solutions for artificial island construction.
Arup also worked on roads, tunnels,
viaducts and other associated infrastructure. 1: The 55km HZMB took nine years to construct

1.

4 1/2019 | The Arup Journal 5


HZMB | HONG KONG, ZHUHAI, MACAO, GREATER CHINA

2: It was necessary to construct a 6.7km tunnel to 4: Xxxxxx xxxxxxxxxx xxxxxxxx xxxxxxxxxxxxx 4: The HZMB project has significantly cut travel
allow unobstructed navigation channels (Lingding xxxxxxx xxxxxx xxxxxxxx xxxxx xxxxxx xxxxxxx times in the Greater Bay Area
and Tonggu channels) 5: Xxxxxx xxxxxxxxxx xxxxxxxx xxxxxxxxxxxxx 5: The Jiuzhou Bridge is a cable-stayed bridge
3: An S-curved alignment was used adjacent to xxxxxxx xxxxxx xxxxxxxx xxxxx xxxxxx xxxxxxx with central sail-like towers and a central single
Hong Kong’s Airport Island to avoid constraints 6: Xxxxxx xxxxxxxxxx xxxxxxxx xxxxxxxxxxxxx cable plane
relating to the airport runway and the Government xxxxxxx xxxxxx xxxxxxxx xxxxx xxxxxx xxxxxxx
Flying Service Headquarters

number of piers that needed to be built, the


Kong side of the crossing, and investigation spans were designed to be 85m for the
and reference design for the 12km link road. composite deck in the shallow water to the
west side of the crossing and 110m for the
The section of the main bridge and tunnel in steel deck in deeper water in the middle and
mainland Chinese territory was developed by on the eastern sides. At the crossing between
the HZMB Authority, a body jointly Hong Kong International Airport and Lantau
4.
organised by the three regional governments. Island, the span between piers is typically
The remaining sections of the link roads and 4. set at 75m, and up to 180m for crossing
BCFs were the respective responsibility of navigation channels and the headland
the three governments. between Sha Lo Wan and San Shek Wan.
2. A project of such significance had to be Arup designed a seismic protection system This meant fewer piers overall, and
Main bridge and tunnel aesthetically pleasing from all vantage that satisfies the local codes of the three therefore less disruption during construction.
Arup started working on the main bridge and points, as well as structurally sound in the areas the bridge runs through. The frictional Precast concrete shell construction was
tunnel in 2009 at the invitation of CCCC face of frequent typhoons that occur in the pendulum bearing absorbs the seismic adopted for the pile caps to reduce the
Highway Consultants, then known as the region. The design and construction needed energy in every bearing connection, thus amount of temporary works construction
Highway Planning and Design Institute to take environmental considerations into isolating the seismic action from the required, and therefore lessen the impact on
(HPDI). This process began with concept and account, in particular the impact on the foundation. The bridge decks are supported the environment.
preliminary design work. The overall route Chinese white dolphins that inhabit the by single column piers with wide heads, and
runs from the Hong Kong BCF, travels along waters along this route. the bases are buried deep in the seabed. The main logistical challenge of this part of
the northern part of Lantau Island, enters Single, rather than double, piers ensure that the project was that all construction needed
Hong Kong waters and then crosses five The bridge’s alignment was designed the dolphins’ habitat and the flow of water to take place in the sea. This meant that the
water navigation channels – Tonggu, to ensure the least possible obstruction under the bridge experience minimal construction materials had to be delivered to
Lingding, Qingzhou, Jianghai and Jiuzhou to the water flow, avoiding various site disruption. In mainland China, spans the site by marine vessels, and made
Port. A tunnel of 6.7km runs between the first constraints, while also enhancing the between piers are typically 50m, but to help working with in-situ concrete difficult.
two, where the distance over the two views for bridge users. To achieve the preserve water quality by minimising the The solution was to precast as many of the
channels was too wide for a long-span bridge. latter, horizontal curves were added.
Three cable-stayed bridges cross over the last To further improve the overall aesthetic
three channels. The total bridge length of the HZMB, Arup proposed that all
(including the three cable-stayed bridges and the bridges over the navigation channels
the shallow and deep water viaducts) is be supported by cables, and that central
22.9km. The crossing then reaches the towers of different shapes be placed
artificial island where the Zhuhai and Macao between each span, each with a nautical
BCFs are located. theme. The main span of the 268m
Jiuzhou Bridge has two symmetrical
3. In total, the crossing is 55km long – 29.6km central towers shaped like sails; the
for the main bridge and tunnel, a 13.4km link Jianghai Bridge, comprising two 258m
Zhongshan, Dongguan, Huizhou, Jiangmen Zhuhai, Macao and Hong Kong. In Zhuhai, road in Zhuhai territory and a 12km link road main spans, has three towers that
and Zhaoqing. The intention is to create an which is part of China’s Guangdong in Hong Kong territory. Arup collaborated resemble dolphins; and the 458m
economic and business hub, the ‘Greater Province, Arup carried out the preliminary with the HPDI on the design of the elements main span Qingzhou Bridge has towers
Bay Area’, and to better connect Hong design for the main crossing, which consists on the Chinese mainland side and worked shaped like the letter H, which feature
Kong and Macao to the Chinese mainland. of a bridge and a tunnel. In Macao, the firm alone on the design for the elements on the cross-bracing like a Chinese knot.
was responsible for the overall planning and Hong Kong side. The main bridge is a dual The first of these is the most visually
Three elements the preliminary and detailed design for the three-lane carriageway with hard shoulders exposed, as it can be seen from the
The HZMB project comprised three key BCF infrastructure and the link road. In (total width 33.1m), designed for a maximum restaurant-filled Zhuhai promenade.
elements: the main bridge and tunnel; the Hong Kong, Arup’s role included planning, speed of 100km/h. The tunnel under the It therefore has the most striking design
boundary crossing facilities (BCFs); and the investigation and detailed design of the Tonggu and Lingding navigation channels is of all the bridges. The depth of the bridge
link roads connecting the three regions. 130ha of land reclamation to create an made up of 33 tunnel elements, each deck was kept constant throughout,
Works spanned three geographical areas, artificial island for the BCF on the Hong measuring 180m x 38m x 11m. to offer visual harmony.
5.

6 1/2019 | The Arup Journal 7


HZMB | HONG KONG, ZHUHAI, MACAO, GREATER CHINA

6: Arup developed a non-dredged method of


Formation level +5.5mPD
reclamation and seawall construction for the
SWL
Hong Kong BCF artificial island
2v:2.5h Existing seabed
Fill 7: The Hong Kong BCF is located on an artificial
Rock fill
island to the north-east of Airport Island
8: The composite section of seawall was
1v:3h 1v:3h Marine
Sand fill
deposits
constructed using a series of 32m diameter
Dredged level
cofferdams without the need for dredging

Alluvium ˜105m
Band drains

Formation level +5.5mPD


for the Hong Kong Link Road. This is a
Fill Public fill
dual three-lane highway connecting the
Rock fill HZMB with the Hong Kong BCF. It
comprises a 9.4km bridge section, a 1km
Marine
deposits tunnel section through Scenic Hill and a
1.6km at-grade section on reclaimed land at
the east coast of Airport Island. The
Alluvium alignment is curved, as the bridge had to
Cell diameter ˜40m avoid various site constraints, in particular
the airport facilities, operational
7.
6. requirements and developments. Moreover,
the airport is developing a third runway to
the northern side of the island, so infringing Island before reaching the BCF, with and the headland between Sha Lo Wan
elements required as possible, including the in Hong Kong. Typically, land reclamation formed by 200 straight steel sheets, were on this space was not an option. Placing construction beginning on this phase of the and San Shek Wan. This area of headland
pile cap shells, piers and deck segments. projects such as this involve fully dredging driven through the soft marine sediment layer the Hong Kong Link Road on Lantau Island project in 2012. is a designated site of archaeological
A floating concrete batching plant was used the mud from the seabed and then laying down to the underlying alluvial layer to form was also out of the question, as this is an interest, so to avoid negative environmental
to supply the in-situ concrete needed to down fill materials. Hong Kong’s waters are cofferdams. These cofferdams were linked by area of forests and natural beauty and is of The bridge section is made up of more impacts on this zone, no bridge pier or
construct the foundation piles. full of sediment, which traps a lot of water, two steel arcs made of similar steel sheet pile great ecological value. Arup designed the than 5,700 precast bridge deck segments, additional construction works were
and so is not easy to squeeze dry for segments. These were backfilled to form a road to run along the narrow marine channel arranged in 115 spans. The viaduct features proposed in this area. A special lifting
Hong Kong BCF consolidation. This full dredging method is robust structure without the need for south of Airport Island and north of Lantau long spans crossing two navigation channels frame was used for installation of the
On the Hong Kong side, Arup’s design relatively quick, but it would have required dredging. Although cellular structures on a deck segments for this span.
included using a reclaimed area of 150ha to a large amount of filler materials to replace similar scale have been used elsewhere, few
form an artificial island – 130ha to the dredged mud. Moreover, when sediment have been used with the kind of deep, soft On the western side, where it faces
accommodate the Hong Kong BCF and is dredged, it then has to be disposed of in soils encountered on this project. open water, the viaduct spans are
20ha for landfall of a connection road sea-based mud pits, a challenge complicated typically 75m. The western navigation
known as Tuen Mun-Chek Lap Kok Link by the fact that much of this sediment can be This innovative design meant that the soft channel has three 150m spans to allow
(TMCLKL). Arup initially began working contaminated. There was no space in Hong marine sediment on the seabed could be left two separate one-way navigation
on this element of the project in 2006 by Kong for a new mud pit, so Arup developed untouched. The reduction in construction channels for shipping below the bridge
identifying the best possible site for the a method for constructing the seawall for the work meant there was less impact on water deck. At the southern side, the viaducts
BCF. This area had to include clearance and land reclamation without dredging. quality and less disruption to the marine run inside the channel between
transport facilities. Ultimately, it was habitat, because of reduction of marine traffic Airport Island and Lantau with spans
decided that the BCF should be placed to the Building on the firm’s experience in ground volume during construction (which was cut in excess of 100m to minimise the
north-east of Hong Kong’s Airport Island treatment methods and seawall building by half) and the reduction in suspended number of piers and reduce hydrodynamic
(an artificial island linked to Lantau), at a techniques, Arup developed two types of particles in the sea by 70%. The non-dredged impact to the water channel. The span
point convenient for travellers arriving into non-dredged seawall: a composite steel cell process significantly reduced adverse impacts length is extended to 180m for crossing
or departing from Hong Kong by air. This and rubble mound seawall, and a simple on the environment. the navigation channel and the headland.
choice of location also avoided the need to rubble mound seawall. For both types, the These long spans were a particular
reclaim land near the major sea channel to design solution required treatment using The completed reclamation was tested by challenge. The team considered various
the north of the airport. stone columns – 53,000 in total, each 1m in two severe typhoons that hit the area before options for the design. A cable-stayed
diameter – inserted into the soil to create a the BCF became operational. Both the bridge was not viable because of the
A particularly innovative element of the drainage path for water in the soft sediment seawall and land reclamation remained height restrictions imposed by the airport,
project was the development of an to dissipate. These were compacted-gravel intact under these conditions. and a composite steel and concrete deck
environmentally friendly non-dredged piles, installed using a vibratory method of was rejected for cost, maintenance and
method of reclamation and seawall construction. Hong Kong Link Road aesthetic reasons. Precast concrete
construction to create the artificial island for Arup conducted the feasibility study, segments were ultimately used – this was
the Hong Kong BCF and the TMCLKL. On the composite section of the seawall, 85 preliminary and reference design, contract the longest span of this type of bridge in
This was the first time this method was used circular cells, each 32m in diameter and procurement and construction supervision Hong Kong at completion.
8.

8 1/2019 | The Arup Journal 9


HZMB | HONG KONG, ZHUHAI, MACAO, GREATER CHINA

11: At Scenic Hill, whole tunnel box jacking was


used where the tunnel went under railway tracks,
as there were stringent settlement requirements in
this area
12: The southern section of the TMCLKL travels
over 2km of water between Lantau Island and the
Hong Kong BCF

9.
11. 12.

9: The Hong Kong Link Of the 725 piles used for this section of the When carrying out the box jacking, tunnel form to connect to the existing Lung The northern section is 5km in length and
Road was a complex project, 65 are on land (with a diameter of the team came up against extremely Mun Road in Tuen Mun and the future Tuen includes a sub-sea twin-bore tunnel between
part of the project, due 2.8m) and the remaining 660 are at sea, and hard bedrock that had to be excavated Mun Western Bypass. the BCF and landfall at Tuen Mun. Typically
to the geography of have diameters of 2.3m, 2.5m or 2.8m. The manually, as blasting was not an option 14m in diameter and reaching depths of up
the area and various
piles range from 7m to 107m in length. for the section underneath the railway. Arup was one of the designers for the to 60m below ground level, each tunnel
design constraints
An additional smaller tunnel was contractor of the southern section of the accommodates two lanes of traffic. They
10: To avoid any Part of the link road is tunnelled, minimising excavated inside the main tunnel, using TMCLKL, which comprises about 9km of were originally designed to connect with
construction footprint
the visual impact for local residents. It runs round-the-clock construction, to increase elevated viaducts. The southern section traditional cut-and-cover launch and
in an area of
archaeological interest
through Scenic Hill, under both the Airport the rock excavation faces and accelerate between Lantau Island and the BCF artificial reception shafts at either end within the
at Sha Lo Wan Express railway and the Airport Road. the overall rock excavation. This was island travels over 2km of water. The section newly formed reclamations. However, to
Headland, a special Different construction methods were used done at the same time as the box jacking that travels over land passes over existing speed up construction, the contractor’s
segment lifting frame for different sections of the tunnel. Drill and on the other side, so the work could railway lines at skewed angles, requiring design team modified the tunnel design at
was used to install the blast was utilised at Scenic Hill where the progress as efficiently as possible. spans of up to 100m. The viaduct structures the northern landfall by shifting the launch
bridge deck segments rock was particularly hard; mining were designed as prestressed concrete shaft 400m further north. This replaced the
techniques were used underneath Airport TMCLKL girders, which were constructed using the deepest section of cut-and-cover structure by
Road where the flow of traffic to the airport A new road was also required to precast segmental method. The southern extending the bored tunnel, significantly
needed to be maintained during tunnelling; accommodate the anticipated rise in traffic connection viaduct was designed with a reducing the amount of excavation and
whole tunnel box jacking – a controlled between Lantau Island and the North-West seagull theme: the supporting piers over the lateral support works required at this
shallow underground excavation process New Territories, a region of new towns and water are shaped like the maritime birds, location. The exit tunnel, which included an
that causes minimal disruption – was used development in Hong Kong, which will also with the span lengths gradually increasing additional climbing lane, was formed using
under the railway where there were railway serve as an alternative route to the airport. from the Lantau shore towards the Hong the world’s largest tunnel boring machine
tracks with stringent settlement requirements The proposal was for this link road to start Kong BCF to imitate seagulls flying over (TBM), which is 17.6m in diameter. To
to be adhered to; and an open cut-and-cover at the North Lantau Highway at Tai Ho, the sea. The longest span is 200m where create a large enough shaft to launch the
method was used in the new reclamation before running through the Hong Kong the viaduct spans the Tung Chung TBM (which required clear headroom of
area where there were fewer constraints. BCF. The road then travels northwards in navigation channel. 20m), Arup designed a bespoke caterpillar
10.

10 1/2019 | The Arup Journal 11


HZMB | HONG KONG, ZHUHAI, MACAO, GREATER CHINA

13: Arup developed the caterpillar diaphragm wall to combine these BCFs into a single board – created a working environment that With Hong Kong a well-known financial
cofferdam, creating sufficient unobstructed space artificial island of approximately 220ha. supported shared thinking, knowledge centre, Macao a major tourist destination,
to launch the world’s largest TBM In 2009, Arup won the detailed design exchange and critical review, leading to a and abundant development opportunities in
14: The 70ha Macao BCF is located on an consultancy to design the BCF’s design that was best tailored to the client the Pearl River Delta and the Greater Bay
artificial island infrastructure after developing the functional and the region’s needs. Area, the whole area is experiencing
layout of the 70ha Macao BCF. Arup considerable growth. The HZMB will
was responsible for designing the facility’s Increased connectivity encourage the connection of people and
viaducts, underpasses, roadworks, utility The HZMB provides the shortest link developments in this area. Being an
tunnel, drainage and sewerage, and between Hong Kong, Macao and the impressive structure in its own right, the
functional buildings. Arup also undertook western Pearl River Delta region. The bridge is also a tourist attraction, providing
the detailed design for the link road connection between Hong Kong, Macao magnificent views. It is hoped that this
diaphragm wall cofferdam – the first of its connecting the BCF to the new artificial and Zhuhai has been greatly improved, ambitious project will be the catalyst
kind used in Hong Kong. This cofferdam island, referred to as Reclamation A, significantly cutting the time it takes for for further growth and integration in the
comprised a series of circular interconnected which is located at the east of people and cargo to travel across the bay. area for years to come.
cells that formed an unobstructed strut-free Macao Peninsula.
excavation area by making use of hoop
stresses within the diaphragm walls to Management
maintain lateral stability. A project of this scale presented major Authors de Infra-estruturas, Macao SAR Government;
challenges when it came to management Naeem Hussain was the bridge design leader Hong Kong-Zhuhai-Macao Bridge Authority;
The twin-bored tunnels are connected by and logistics. Arup appointed a core for the HZMB main bridge. He is Arup’s global Gammon Construction Limited; Dragages-
cross-passages at 100m intervals that serve management team to focus on issues bridge design leader and an Arup Fellow. He is Bouygues Joint Venture
as a means of escape and allow access such as risk management, design a Director in the Hong Kong office.
between the tunnels during an emergency. coordination, cost control, planning Arup team
The original design had the mechanical and reviews, handling vast amounts of Steve Kite is Arup’s East Asia region highways Faux Abad, Andrew Armstrong, Sean Arnold,
electrical (M&E) equipment required for documents, interfaces and resources, business leader. He is an Associate Director in Che-Hung Au, Lukasz Bies, Eric Chan, George
the Hong Kong office. Chan, Ivan Chan, Ken Chan, Simon Chan,
tunnel operation located in every alternate and conducting quality assurance.
Li-Ling Chen, Fergus Cheng, Justin Cheung,
cross-passage. This would have resulted in Kayla Cheung, James Chim, Franki Chiu, Issac
Samuel Kwan was the Project Manager for the
two different cross-passage sizes, one with It was crucial to have a project and design TMCLKL southern viaduct section and the Choi, Timo Chow, Harry Clements, James
a larger diameter to facilitate the equipment review before every milestone, to make sure deputy Project Manager for the Hong Kong Link Collins, Derrick Dai, Mark Darlow, Ian Davis,
13.
rooms and the escape passage. To simplify everything was on the right track. A review Road. He is an Associate Director in the Hong Mark de Melo, Alex de Oliveira, Mo Ezzat, Corey
construction, Arup modified the design to panel was set up and the budgets were Kong office. Fan, Alfred Fong, Mike Ford, Henry Fung,
relocate the M&E equipment. By making assessed and refined to achieve the most Matthieu Galland, Nilda Galvez, Stephen Hope,
use of the void space created by the circular cost-effective solutions. Arup’s highly David Pegg was the Project Director for the Min Huang, Miro Huang, Erica Hui, Naeem
tunnel form, the equipment was placed collaborative approach – bringing a broad TMCLKL southern viaduct section and is a Hussain, David Ingram, Chris Jackson, Piers
within a service gallery in the carriageway range of disciplines and stakeholders on Director in the Hong Kong office. James, Sze James, Jesper Jensen, Duncan
Johnston, Gerald Kam, Micheál Killeen, Steve
inside the main tunnel with M&E islands
James Sze led the infrastructure team on the Kite, Samuel Kwan, Irene Lai, Isis Lai, Jack
every 200m. This allowed all the cross- Lam, Kaitlin Langdon, Michael Lau, Conor
detailed design for the man-made island for the
passage sizes to be the same smaller size, Hong Kong BCF. He is a Director in the Hong Lavery, Sam Law, Kitty Lee, Koon-Yu Leung,
facilitating easier operation and Arup technical services: Kong office. Terence Leung, Brian Li, Yingyan Li, Jeffrey Lo,
maintenance by providing a separate service Hong Kong Kin-Wang Lo, Ken Lu, Danny Lui, Lin-Fat Mak,
corridor for maintenance purposes only. Hong Kong BCF Reclamation: Feasibility Peter Thompson was the Project Manager for Laura Merry, Chryso Metta, Amanda Mo, Polly
Study, Overall Planning, Environmental the twin-bore tunnel section of the TMCLKL. He Mok, Alex Morris, Fokker Ng, Sandra Ng,
A mini-TBM was used to construct Impact Assessment, Preliminary and Detailed is a Director in the Hong Kong office. Declan O’Shea, Josh Palmer, David Pegg, Sue
the cross-passages, rather than mined Design, Construction Contract Procurement Poo, Jacek Przysiezny, Victoria Richardson,
construction with ground freezing and Supervision Fergal Whyte was the Project Director for the Emily Roberts, Rob Ryan, Denis Shapley, Victor
Hong Kong BCF: Feasibility Study, Overall HZMB main bridge and the Hong Kong BCF, Shea, Dora Shum, Michelle Shun, Gopal
(traditionally used for sub-sea tunnels).
Planning, Environmental Impact Assessment, and the Project Manager for the Hong Kong Srinivasan, Raymond Sy Guan, James Sze,
This method reduced construction risk, Sherry Tang, Peter Thompson, Tom Tong,
Preliminary Design Link Road. He is a Director in the Hong Kong
improved efficiency and significantly cut Hong Kong Link Road: Feasibility Study, office and a member of the Arup Group Board. Eric Tsang, Iris Tse, Alessandra Villa, Mark
construction time. This was the first project Overall Planning, Environmental Impact Wallace, William Wei, Fergal Whyte, Heather
in Hong Kong to use a mini-TBM for Assessment, Preliminary and Reference Philip Wong was the Project Director for the Wilson, Christopher Wong, Desmond Wong,
cross-passage construction. Design, Design & Build Contract Macao Link Road and the Project Manager Josephine Wong, Philip Wong, Tim Wong,
Procurement and Supervision for the Macao BCF. He is a Director in the Alastair Woodland, Christian Wrede, Ngai
Macao BCF and link road TMCLKL: Feasibility Study, Detailed Design Macao office. Yeung, Damon Yung, Cesar Zamora, Heng
In 2006, Arup was appointed by the Macao Zang, Ying Zhou.
government to undertake a feasibility study Zhuhai Ngai Yeung worked on the HZMB main
for the Macao BCF and the associated link HZMB Main Bridge Preliminary Design bridge and is an Associate Director in the Image credits
Hong Kong office. 1-3, 5, 12: Marcel Lam Photography
roads to the city. The original scheme had 4, 6-9, 11: Arup
Macao
proposed two separate BCFs for Macao Macao BCF infrastructure: Overall Planning, Project credits 10: Dragages-China Harbour-VSL JV
and Zhuhai, on two artificial islands. Arup Preliminary and Detailed Design Clients Highways Department, Hong Kong SAR 13: Dragages-Bouygues JV
rationalised this complex plan, following Macao Link Road: Detailed Design Government; Gabinete para o Desenvolvimento 14: CHEC
the decision by the Chinese government
14.

12 1/2019 | The Arup Journal 13


BLOX | COPENHAGEN, DENMARK

Building BLOX 1: BLOX is part of a new waterfront development


in Copenhagen’s harbour area
2: The development provides outdoor spaces for
use by the public
3: The initial solution for the unconventional grid
BLOX has helped reconnect a section of Copenhagen’s waterfront with the city by redeveloping structure required 48 trusses
4: Arup rationalised the layout, developing a scheme
a decades-old derelict site and turning it into a lively urban creative hub and public space that had an interconnecting framework of 18 trusses

Authors Michael Bradbury and Chris Carroll

Located in a prime section of Copenhagen’s cantilevers, long spans, unaligned grids and Arup provided structural, building services and
harbour area, BLOX is a six-storey mixed- double height volumes. The building was façade engineering; sustainability consultancy
use building that is part of an exciting officially opened by the Queen of Denmark services; ICT and AV; vertical transport;
waterfront regeneration in the city. The in May 2018. security; and daylighting, from inception to
27,000m2 venue is the new home for the detailed design. The firm produced design 2.
Danish Architecture Center (DAC) and Working in close collaboration with the solutions for and provided input on topics
BLOXHUB, a new creative workspace Office for Metropolitan Architecture including energy efficiency, carbon neutrality,
initiative for companies, research (OMA), Arup’s engineering expertise helped materials and embodied carbon. Arup also Its location, locked in by the harbour and within the building. The staggered pattern number of one- and two-storey deep trusses
institutions and organisations involved shape a complex regeneration project that sought to address socioeconomic issues. canal, with a busy arterial road bisecting the that forms the building’s terraced landscape with depths varying from 2.4m to 8.4m. These
in sustainable urban development. overcame the constraints that challenged the site, presented considerable challenges for shape, the road through the building and the create large column-free spaces within the
viability of the site for development. BLOX Site development development. Most recently, the site included deep basement car park all put considerable building and also bridge over the road.
The building features an auditorium, spans over and under the busy Christians Philanthropic association Realdania invested a 350-space street-level car park and a small constraints on where columns could be
exhibition spaces, cafés and offices, as well as Brygge ring road, with the site perimeter in BLOX to help regenerate this section of the children’s playground. located and how loads could be transferred The structural frame comprises steel beams
22 apartments across the top floors, and framed on two sides by the city’s harbour waterfront and strengthen the connection down to the foundations. and columns with precast concrete floor
recreational indoor and outdoor areas. These wall and the Frederiksholms canal. Located between the inner city and the harbour. Structural frame planks. The structural floor plate depth is
differing spaces are arranged as a series of close to a series of historic buildings, the Originally, the site was home to the royal Arup worked closely with OMA to With a conventional grid structure not feasible typically 400mm, with the beams located
stacked cubes that form a terraced landscape, ground works in particular had to be dealt brewery, Kongens Bryghus. The buildings rationalise the structural layout so that it because of the overlapping volumes and within the depth of the planks to reduce the
requiring a structural scheme with significant with sensitively. were demolished after a fire in the 1960s. would support the series of stacked volumes column-free spaces required, Arup developed overall floor volume. The planks in the offices
a scheme comprising an interconnected were grouted together without the need for a
system of transfer structures. By using a structural screed topping.
number of interventions such as downstand
beams, trusses and hangers, an initial 48 truss Due to the complex interface between the
solution was developed. With a working trusses, Arup’s structural team devised a
scheme in place, the challenge was to reduce construction sequence in collaboration with
the number of trusses to ensure construction the main contractor, Züblin. To determine the
viability and improve efficiency. stresses that would build up in the steel frame
during its assembly, Arup created a digital
Through further detailed design and model of the construction sequence.
rationalisation, the grid was re-aligned and the
trusses optimised, with Arup’s final scheme an With the transfer structures and complicated
interconnecting framework of 18 steel trusses load paths, it was crucial that deflections were
that typically span 30m. They include a controlled as stresses became locked in while

1. 3. 4.

14 1/2019 | The Arup Journal 15


BLOX | COPENHAGEN, DENMARK

5, 6 & 7: Aerial photos showing the construction of


BLOX. The road crosses the site supported on a
section of the building’s ground floor slab
8: Careful construction sequencing was required,
as only very limited closures of the Christians
Brygge road were allowed

elements were constructed. These stresses and


displacements were taken into account when
developing the construction sequence and
temporary propping arrangements, with a
5. 6. number of trusses fabricated with pre-cambers
to take into account deflections.
10.
Arup adopted 3D design from the start. This
was crucial in dealing with the complexity of
the layout and building services. The design
team was commissioned during construction
to produce an integrated BIM model that 9.
was issued to the client and their facilities
management team for use after handover.

Bridging over and under the road 9: BIM model of the exhibition hall showing the
One of the key elements to developing the site layout of the trusses
was to design a scheme that could span over 10: The exhibition hall being set up for an event
and under the ring road, allowing pedestrians
11: The precast concrete floor in the hall has a
access to the harbour without having to cross reinforced concrete structural topping. This assists with
a road that is used by more than 25,000 acoustics as well as the floor’s dynamic performance
vehicles a day. 11.

7. Traffic on Christians Brygge crosses the site


supported on a section of the building’s sheet pile wall was installed to allow the the required air handling systems. Car engines Ambitious sustainability targets were
ground floor slab. To ensure this traffic does basement excavation and construction of the are switched off as vehicles are delivered and set to address all aspects of the design,
not cause noise or vibration issues within the permanent piled basement walls. returned to the stacked parking bays via the construction and operation of the building.
building, 575mm deep precast pre-stressed horizontal and vertical stacker system, This included reducing energy demand by
concrete bridge beams with a 75mm concrete Using secant pile construction, the basement keeping exhaust fumes to a minimum. 50% compared with local regulations.
topping span onto isolating bearings on the wall comprises interlocking bored concrete BLOX achieves the Low Energy Class
supporting walls and a spine beam. Careful 880mm diameter piles at 1.1m centres, Exhibition floor rating, with primary energy usage of under
sequencing was required during construction, providing both the permanent and temporary The main exhibition floor’s structural depth is 40 kWh/m²/year. This meets the LE2015
as only very limited road closures were support for the basement excavation. 2m, with the floor at this level spanning almost energy target under Danish regulations.
allowed by the local authority. Prior to the Following basement construction the berm 24m over the road. This span is achieved with
trusses that span above the road being erected was removed. Further out into the harbour a a 1.6m deep plate girder, supported on steel The desire to create an energy-efficient
during overnight road closures, a crash deck rubble reef was put in place to protect the columns. A reinforced concrete structural building significantly influenced Arup’s
was built over the road to protect vehicles. harbour wall and building from collision with topping to the precast concrete floor increases building services design. The building
marine traffic. the structural mass for acoustic attenuation, is served by Copenhagen’s district
The basement is 16m below ground at its although it is also beneficial for the floor’s heating system, and the city’s district
deepest and required excavation adjacent to Automated car parking dynamic performance. cooling system was extended towards
the harbour, canal walls and a number of In the basement there is a fully automated the site. The system is based on seawater
historic buildings founded on timber piles. 350-space public car park. It was a local An assessment was made of footfall-induced cooling and the use of residual heat from
A detailed basement construction sequence authority requirement to retain parking on the vibrations that could occur from the exhibition electricity generation.
and de-watering process were implemented to site and minimise the number of vehicles floor to ensure vibration transfer did not
ensure construction did not adversely affect entering the city centre just north of BLOX. adversely affect the other areas of the building. In addition to meeting the LE2015
these buildings. The three-storey underground parking facility Arup’s footfall analysis showed the typical energy target, other key sustainability
can handle up to 180 cars an hour. accelerations were within acceptable limits. strategies include:
The eastern and southern site boundaries were • solar photovoltaic panels at roof level, which
originally retained by timber and stone block Using an automated car stacker system has Sustainability produce 145,000 kWh/year;
quay walls with ground anchors. As part of significantly lessened the space requirements Sustainability was a key driver for the project. • use of lower emission heating, cooling and
the construction sequence, a berm was placed within the basement compared with a more Arup’s Sustainable Project Appraisal Routine ventilation systems;
in the water in front of the existing harbour traditional car park. This reduced the volume (SPeAR) was used to track the sustainability • a full materials assessment, screening all
wall to act as a temporary prop while the of excavation required, simplified basement elements and help make important decisions main materials for embodied carbon, life
ground anchors were removed. A temporary construction around the road and minimised during the design process. cycle and recyclability;
8.

16 1/2019 | The Arup Journal 17


BLOX | COPENHAGEN, DENMARK

12: BLOX is made • appropriate intake and exhaust locations 15: Arup used its Sustainable Project Appraisal
up of a series of and separations to ensure effective Routine (SPeAR) to track sustainability throughout
stacked volumes ventilation (a particular challenge the project
13: 3D rendering of given the proximity to the road); 16: BLOX has helped to transform a previously
vibration analysis • a high performance building envelope; neglected section of Copenhagen’s waterfront
for events in the • low water consumption; and 17: ‘Ove Arup and the Philosophy of Total
exhibition hall • improved local amenities and activation Design’ exhibition
14: BIM model of public spaces.
of the building
services BLOX is close to public transport, adding to Ove Arup exhibition
its sustainability credentials. The mixed-use
development promotes social integration, as From October 2018 to February 2019, the
the publicly accessible pedestrian route Danish Architecture Center hosted an
running through the building creates a new exhibition on Ove Arup that celebrated the
link between the city and the harbour. pioneering work and ongoing legacy of the
Anglo-Danish engineer and designer.
The mechanical services required careful
design to manage the variety of uses for 15. 16. The exhibition, ‘Ove Arup and the
the different spaces within the building. Philosophy of Total Design’, was first
The layout is predominantly office space shown at the Victoria and Albert (V&A)
around the building’s perimeter, with the insulated façade. The performance of Transformation Museum, London, in 2016 and provided
large DAC exhibition space, auditorium the façade required careful consideration BLOX has transformed this section of an overview of Ove Arup’s vision of ‘Total
and conference facilities located at the in order to achieve the correct level of Copenhagen’s waterfront into an inviting Design’. The exhibition revealed Arup’s
centre of the building. The ground floor light transmission into the building to space for people to visit. In addition to collaborative approach to problem-solving
includes a gym, restaurant and some retail meet required lighting levels under providing the new pedestrian link between in the built environment by harnessing
spaces. Along with the basement car park, Danish regulations, while also maintaining the city and the harbour, a new urban the creativity and technical prowess
12. each of these areas have different drivers the appropriate U-value (thermal) and playground offers a safe space for play of engineers, architects, urban
and requirements from a comfort and G-value (solar gain). Eight façade during the day, turning into a stage or planners, designers, consultants and
occupancy level. configurations were assessed across amphitheatre seating in the evening. technical specialists.
criteria including energy, daylight, cost, The building draws in visitors and is a
Plant and building services maintenance and aesthetics to determine landmark publicly orientated mixed-use The exhibition featured archival materials
The mixed-use nature of the building, and the the preferred option. building in the Danish capital. from iconic projects such as the Sydney
constraints of the road, meant that locating Opera House and the Centre Pompidou in
plant and developing the building services Paris. Also displayed were digital exhibits
distribution strategies were critical to overall featuring simulations and augmented
space planning and developing an efficient reality that captured some of the most
Authors Duncan, Russell Fraser, Lesley Gale, Kieran Giblin,
floor plate. Plant areas were located in Michael Bradbury was the Project Manager and Andrew Grant, Duncan Gray, Ning He, John innovative infrastructure projects Arup has
various parts of the building. The basement lead building services engineer. He is an Heath, Stuart Hitchcock, Ed Hoare, Christina contributed to in recent times. They
has the main connections to the district Associate Director in the London office. Hsieh, Dan Ingall, Craig Irvine, Ben Jones, Ben included a specially commissioned
heating and cooling, along with ventilation Kaggwa, Adri Kerciku, Vivien Kwan, Amy Leitch, immersive installation about the Øresund
plant that serves the basement and the Chris Carroll was the Project Director. He is a Ben Lewis, Roland Li, Alexandra Lindesay- Bridge and a recreated Arup SoundLab®
13. restaurant areas. Additional plant is located Director in the London office. Bethune, Di Liu, Ian Lockwood, Georgina presenting a range of acoustic studies,
under the auditorium, with smaller plant areas Lockwood, Paul Lynch, Mani Manivannan, Adam including of the BLOX building and
Project credits Martin, Nina McCallion, Ben Moss, Sheyda Okke,
serving the offices and apartments. Copenhagen city.
Client Realdania Julian Olley, Jean Parker, Dean Payne, David
Architect OMA Penn, Stuart Pennington, Clare Perkins, Dan
With quite a deep plan for the building, Pook, Tony Pullen, Rob Quail, Nihal Rajapakse,
Local architect CF Muller
chilled ceilings were used in the majority Vincenzo Reale, Tony Ricchetti, Amelia Rushford,
Traffic, environmental issues, fire, risk
of areas for cooling, with fresh air provided analyses and local engineer of record COWI Anokhee Shah, Amy Shen, Jamie Shewan, Tania
through the floor (along with distribution Contractor Züblin Smith, Julian Sutherland, Mark Thomas, Mutlu
for power and data). Chilled beams were Structural, building services and façade Ucuncu, Nick Unsworth, Manja Van De Worp,
used around the perimeter to provide engineering, and sustainability consultancy John Verniers, James Whelan, Robin Wilkinson,
additional cooling at the façade. services, ICT and AV, vertical transport, Giovanni Zemella.
security, daylighting Arup:
The main exhibition space uses Yasmin Alam, Francis Archer, Marcus Arvidsson, Image credits
displacement vents to distribute air, with Bibi Banjo, Jonathan Ben-Ami, Daniel Bergsagel, 1, 10, 16: Rasmus Hjortshøj
Michael Bingham, Kimberley Blackburn, Philip 2: Søren Svendsen
sidewall displacement vents used in the
Bogan, Michael Bradbury, Alexis Brown, Emma 3, 4, 8, 9, 13-15: Arup
auditorium. The restaurant and apartments 5-7: BLOX/Dragør Luftfoto
Brunton-Reed, Giorgio Buffoni, Chris Burgess,
have their own dedicated systems. Tony Campbell, Stuart Carey, Chris Carroll, Andrea 11, 12: Delfino Sisto Legnani and Marco
Charlson, Mark Chen, Anna Coppel, Dominic Cappelletti/OMA
Detailed thermal analysis was key to Coyle, James Dare, Rica Dela Cruz, Andrew 17: Camilla Hylleberg
17.
achieving a naturally ventilated and highly
14.

18 1/2019 | The Arup Journal 19


JAGUAR LAND ROVER ENGINE MANUFACTURING CENTRE | WOLVERHAMPTON, UK

Driving sustainability Drawing on decades of experience in the


design of industrial buildings, Arup
reinterpreted the traditional factory form
The focus on a low-carbon strategy meant a
wide range of sustainable features were
incorporated within the facility. These
to create a functional, flexible and include the largest roof-mounted
sustainable facility for Jaguar Land photovoltaic (PV) array in the UK;
Total design used to create a showcase for sustainability in a flexible highly automated Rover. Arup’s architecture and transpired solar collector cladding; solar
manufacturing facility engineering teams provided innovative panels for heating domestic hot water;
low-energy design solutions for the engine natural ventilation; displacement ventilation
Authors Mark Bartlett, James Finestone, Philip Hives, Sean Macintosh, Timothy Snelson, David Storer manufacturing centre, a facility that has to provide cooling; lighting control with
achieved a BREEAM ‘Excellent’ daylight dimming; variable speed drives
sustainability rating. to minimise pump and fan power
consumption; heat recovery on air handling
By providing an appealing, environmentally units (AHUs); grey water recycling; and
controlled working environment, Arup created storm water attenuation.
a facility centred around worker wellbeing.
Arup designed the building so there are visual The first phase of the facility was handed
connections between the different areas, over just 24 months after the design team
breaking down the barriers between factory appointment. The next two phases followed
floor and administration areas and making as in a continuous sequence from 2013 to
much use as possible of natural light. The 2017. Arup provided architecture, transport
traditional factory north-light windows at roof planning, environmental engineering,
level are complemented by 2m high windows landscaping and access advice for the first
at ground level. These bring daylight deep two phases, together with civil, structural,
into the production areas and provide views of geotechnical, fire and building services
the external landscaped areas. engineering for all three phases.

1: The facility has a


BREEAM ‘Excellent’
sustainability rating
2: The building is
centred around
worker wellbeing,
with barriers
between the factory
floor and admin
areas broken down
as much as possible
1. 2.

20 1/2019 | The Arup Journal 21


JAGUAR LAND ROVER ENGINE MANUFACTURING CENTRE | WOLVERHAMPTON, UK

Layout 3: The traditional


Arup developed the overall facility layout factory north-lights
in conjunction with Jaguar Land Rover by work in conjunction
mapping out the engine manufacturing with large ground-
process including equipment, people, level windows to
provide abundant
materials, waste and transport movements.
natural light
The first two phases of the project
incorporated three linked, rectangular 4: The staff support
buildings are bright,
buildings. Efficiency in configuration
naturally ventilated
coupled with future building flexibility two-storey buildings
underpinned the layout of the large factory
5: The building grid
halls (machine and assembly halls) and
layout is arranged to
the connecting smaller two-storey staff allow future changes
support buildings. in assembly line
configuration
The architectural form of the facility – with
the saw-tooth roof profile commonly used
on warehouses and factories around
Wolverhampton – helped with the
engineering solution. The north-lights allow 4.
diffused natural light into the building but
limit heat gain. The south-facing elements
of the roof, set at a 30° angle, are used to
support the large PV array. The underside of
the roof provides the primary route for
distribution of services at high level,
minimising the requirement for service runs
in the floor slab and maximising production
flexibility in the factory for future changes.

Site works and foundations


Following an enabling works package that
included soil/cement ground stabilisation,
Arup was able to design straightforward
foundations with pad footings and ground-
bearing concrete slabs. Steel-fibre-reinforced
concrete slabs, ranging between 250mm and
350mm thick, are used in the factory halls
and were designed to provide flexibility for
equipment layout. In the staff support
buildings, which have lower levels of
loading, mesh-reinforced concrete slabs,
ranging between 150mm and 175mm thick,
are used. The site incorporates an extensive
sustainable drainage system, featuring
porous paving, swales and storm water
attenuation ponds that control discharge to
5.
the surface water system.

Factory frame
The factory halls are based on a single- services the roof can support. The bracing optimised all the truss members. The wind
storey braced frame, supporting multi-span is kept at the perimeter, which allows for the analysis carried out on the roof took into
mono-pitched roofs, with trusses designed subdivision of bays and means the assembly account the roof’s specific geometry and
for multi-bay continuity. The north-lights lines can be reconfigured if required in peak wind direction for the site, allowing
are formed using steelwork trusses that future. Arup developed a loading manual for uplift loads on the roof to be reduced by up
span 30m. In the machine hall, the grid is Jaguar Land Rover that sets out the design to 70% for the majority of the surface
30m by 15m, with a 30m by 30m grid load locations and magnitudes. area. These design processes resulted in
in the assembly halls. This arrangement significant savings, minimising the
facilitates the production areas currently In designing the roof trusses, Arup took steelwork roof tonnage. At 28kg/m2, the
required by the client, giving clear spans the structural analysis output and, using roof weight is light for a 30m-span roof
without compromising the quantity of automated member utilisation checks, that supports the quantity of services
3.

22 1/2019 | The Arup Journal 23


JAGUAR LAND ROVER ENGINE MANUFACTURING CENTRE | WOLVERHAMPTON, UK

energy consumption and providing located 3m above floor level. To reduce amount of work required to be carried out
significant carbon savings. airborne contamination within the machine at height.
and assembly halls, the supply air is filtered
This Colourcoat Renew SC cladding system, through class F9 filters – the level below a Energy monitoring
developed by Tata Steel and the University cleanroom environment. Arup developed an energy management
of Swansea’s Innovation Centre, heats 5m3/s system in conjunction with Jaguar Land
of supply air, producing carbon savings of A gas-fired heating system, rather than Rover to allow the client to monitor building
1 tonne per 5m of solar collector. The a more traditional water-based system, energy consumption and energy used in each
Machine Hall (30m x 15m Grid) Assembly Hall (30m x 30m Grid)
system has also been used on the third phase was used to serve the production halls. process of engine production. The system
Building Access – Main Halls Building Access – Main Halls of the project. A water-based system would have had design included the communication
the potential for significant heat and infrastructure for the process equipment to
Dynamometers pumping losses due to the length of the support Industry 4.0 implementation, as well
As part of the engine testing regime, a pipe runs required for a facility of this size. as the metering and monitoring mechanisms
sample of engines produced at the factory The gas heating system overcame this for all the building utilities. Arup’s Building
are tested using dynamometers. Arup issue, particularly as the gas distribution Performance and Systems team were
worked with Jaguar Land Rover to design system was already required to serve commissioned after handover to carry out
the system that takes the energy generated process equipment. monitoring of the energy performance in the
during testing and feeds it back into the operational building and collate feedback
building’s energy distribution system. Where possible, high-level services were from users. This work identified
supplied using modular technology. Arup’s opportunities to reduce further electricity
Heating and cooling detailed design allowed for modules to be and gas consumption.
The machine hall is heated from an all-air manufactured off-site to facilitate a quick
system with the heating diffusers located 3m and safe installation on-site. This method Digital design
above the factory floor. Six AHUs supply allowed for factory inspections prior to The structural steel frame design was highly
85m3/s of air to the space. This volume of delivery on-site, and also reduced the automated. Optimisation of design input to
Clear Way Finding & Access Strategy Daylighting & Roof Design air is required to maintain a 20°C
Building Access – Offices & Staff Support Facilities Natural Light & Dynamic Roof Form temperature in the machine hall, and also to
provide make-up air to supplement the
6. extract system that removes the oil mist
created during the engine manufacturing
process. Fresh air, with 0.25 air changes per
required for this highly automated Renewable energy hour, is also fed into the machine hall for
manufacturing facility. Total design As part of an initial energy study, Arup staff comfort levels. During the winter
identified the potential for significant carbon months, the manufacturing equipment in the
Staff support areas Arup applied its total design philosophy savings by using a roof-mounted PV array machine hall provides heat to the space,
The connecting staff support buildings are to deliver technically creative and and solar thermal installation on the façade. with gas-fired AHUs providing top-up heat
bright, naturally ventilated two-storey sustainable solutions at speed. as required. In the summer, vents in the
spaces. Arup designed the bulk of the heavy Innovation, collaboration and worker More than 21,000 PV panels were installed north-light windows can be opened to expel
plant – servicing the factory halls – to be wellbeing is at the heart of the success on the south-facing areas of the roof. These hot air, helping to reduce extract energy.
located at the first floor and on the roof. This of this facility, which has won provide over 5.3MW of power – equivalent
gives easy access to plant for maintenance numerous awards. to 30% of the facility’s energy requirements The assembly halls are heated and cooled
and avoids the need to put heavy plant on – and reduce the factory’s carbon footprint using a displacement ventilation system,
the long-span roof trusses. The structure 2018 by at least 2,400 tonnes per year. Further with five AHUs supplying 71m3/s of air. To
supporting the plant consists of precast Structural Steel Design Awards: power is supplied via a ground-mounted PV maximise the facility’s future flexibility and
hollowcore concrete slabs. The exposed Winner, Project of The Year array, added as part of the most recent phase adaptability in relocating process plant and
thermal mass of the concrete slab soffit World Architecture Awards: of works. Solar thermal panels also provide layouts, the displacement terminals are
helps with moderating temperatures in the Shortlisted, Production Energy and heating for domestic hot water.
office areas, further reducing energy costs. Recycling Category
Solar cladding
Arup’s architectural design of the staff 2017 The factory features a transpired solar
support areas provides a working CIBSE Building Performance Awards: collector cladding system, which is used to
environment that brings people together by Winner, Project of the Year preheat the supply air to the staff changing
providing visual transparency and social Royal Institute of British Architects facility. Used on the south-facing façade of
spaces. These areas have natural light and Awards: Winner, West Midlands the staff support building, the outer steel
ventilation, with glazing providing Sustainable Award and Regional Award layer of the system is a dark perforated
transparency between the office areas and profiled steel sheet. It is separated from the
factory floors. Automated dimming controls 2014 inner insulated layer by an air cavity. Solar 6: Arup, in conjunction with the client, developed
for the lighting system reduce the need for Royal Institution of Chartered energy warms the perforated steel skin and an overall facility layout that focused on efficiency
artificial light, creating further energy Surveyors National Awards: the air in the cavity, and a fan at high level and future building flexibility
savings, with LED lights specified in the Regeneration Project of the Year draws the warm air out. This preheated air 7: The assembly hall has a 30m x 30m
most recent development phase. feeds the AHUs in these areas, reducing structural grid
7.

24 1/2019 | The Arup Journal 25


JAGUAR LAND ROVER ENGINE MANUFACTURING CENTRE | WOLVERHAMPTON, UK

8: Arup’s design of the


staff support areas
provides a working
environment that
brings people
together by providing
visual transparency
and social spaces
9: Drawing on
decades of
experience in the
design of industrial
buildings, Arup
reinterpreted the
traditional factory
form to deliver a
functional, flexible and
sustainable facility

9.

Authors Architecture, transport planning, environmental, Liebana, Mark Lusher, Sean Macintosh, Colin
Mark Bartlett was the lead electrical engineer and landscaping, and access advice (Phase 1 and Magner, Alice Malaiperuman, Rajiv Malik, Natalia
the Project Manager for the third phase of the 2); civil, structural, geotechnical, security, Mambrilla, Mei-Yee Man Oram, Ann Marie Aguilar,
development. He is an Associate Director in Arup’s sustainability, fire and building services Barbara Marino, Tony Martin, Curtis Martyn, Paul
Midlands Campus in the UK. engineering (for all three phases) Arup: Matthews, Alex May, Andrew McAleer, Rachael
Muhammad Abdullah, Jorge Albert, Mehdi McAteer, Chris McCarthy, Gary McCarthy, Laura
James Finestone was the Project Director for the Alhaddad, Steve Allen, Simon Anson, Dimitri Mino, Jessica Monk, Philip Monypenny, Mostafa
first phase of the development. He is Arup’s Argyros, Nohman Awan, Yiannis Baltagiannis, Andy Moradalizadeh, Adina Nimas, Julia Novitchenko,
Europe region leader for architecture and is based Barnes, Daniel Barnes, Greg Barnes, Mark Bartlett, Carlos Nunes Baptista, James O’Hanlon, Johnny
in the Milan office. Gill Blackburn, Mark Bowen, Richard Boyd, Tom Ojeil, Nick Olson, Petra O’Sullivan, Constance
Brooks, Gemma Broughton, Alexis Brown, Alex Pang, Yesol Park, Yona Park, Andy Payne, Tom
Philip Hives was the lead mechanical engineer and Bunn, Kevin P Burke, Josh Chapman, Sean Pearce, Anett Pengelly, Oliver Pengelly, Ryan Perry,
Project Manager for the second phase of the Chapman, Wayne Charles, Sam Collett, Carl Chris Powell, Jan Pratt, Sean Preece, Georgie
8. development. He is an Associate Director in Arup’s Collins, Jose Pedro Conceicao Dos Santos, Tiago Price, Danny Quartermaine, Mario Querol, Jon
Midlands Campus in the UK. Contins Teixeira, John Corbett, Tian Coulsting, Rhodes James, Colin Roberts, Paul Robinson,
Arron Croft, Dominic Cropper, Sebastian Alberto Rossi, Luca Rossi, Dave Runaghan, Anand
Sean Macintosh is a Senior Architect in the Cumpatescu, Hal Currey, Hazel Dalton, James Sagoo, Tanvir Saini, Neil Scott, Andrew Sherratt,
London office. Davies, Sean Davies, Steven Davies, Matthew Michael Shuster, Lee Smith, Tim Snelson, Joaquin
the analysis models was driven from carried out BIM management services data tagging of equipment and services
Davis, Jo Dicken, Natalia Duffy, John Edgar, Ed Soria Diaz, Chris Stanford, Michael Stevens,
spreadsheets, to minimise the risk of manual on behalf of the main contractor, for use post-occupancy. This ensured Elbourne, Karim Elgendy, Steve Fancourt, David Calvin Stewart, Susanne Stolper, David Storer,
Timothy Snelson was the lead structural engineer
input errors. Subsequent results from the Interserve. The subcontractors’ work the client’s facilities management team and Project Manager for the first phase of the Farmer, Ben Fenech, James Finestone, Kate Craig Stott, Eric Sturel, Mike Summers, Steven
analysis were post-processed through was coordinated throughout the delivery could utilise all the design information development. He is an Associate Director in the Fletcher, Bob Flynn, Helen Foti, Sally Friswell, Swan, Martin Tarnowski, Thomas Taverner, Scott
spreadsheets for utilisation checks. Designing of the project, and also with the fit-out embedded within the model. London office. Carolyn Gallehawke, Amparo Galvan Nieto, Thirtle, Xing Tong, Bernard Travers, Sara Turnbull,
in this digital environment allowed changes requirements of the highly specialised Andrew Gardiner, Stephen George, Marten Ryan Turner, Tijl Uijtenhaak, Dora Vagiou, Michael
to be incorporated into the design as the client robotics used for engine manufacturing As the manufacturing process changed David Storer was the Project Director for the second Gessen, Andrew Gibbon, Daniel Goodreid, Jack Wadsworth, Julie-Anne Walker, Killian Walsh, John
updated their manufacturing requirements (which were designed by PowerTrain during the design phase, the digital and third phases of the development. He is a Director Goulding, Aidan Griffin, Paul Grosvenor, Craig Walton, James Watts, Marcos Watts, Chris Webb,
during the design process. The structural for Jaguar Land Rover). The design design elements were used to take in those based in Arup’s Midlands Campus in the UK. Harkness, Mike Haydon, Christopher Hayward, Luke Webster, Mel West, David Wheatley, Joe
model was produced directly from the model was integrated with the process changes to minimise the potential of any Andy Heath, Cameron Heggie, George Hemsley, Wheelwright, Deborah White, Sam Williams, John
Project credits John Higginson, Philip Hives, Thomas Howes, Woodman, Darren Wright, Mat Wright, Evangelos
analysis model and exported to Tekla and equipment model. This allowed delay. For example, when another 30m bay
Client Jaguar Land Rover Ltd Callum Hulme, Alan Jefcoat, Ian Jenkins, Joao Zacharis, Akhtar Zaman, Dima Zogheib.
software for production of the fabrication coordination of process machinery and was added to the building, the automated Jesus, Ben Johnson, Matt Jones, Elida
Project manager Stace
drawings, thereby saving the steelwork services, along with the building services work flow enabled the design checks to be Quantity surveyor (AECOM – formerly Davis Karaivanova, Abdullah Khan, Michael Kinney, Image credits
fabricator significant modelling time. and structural frame. The fully integrated carried out quickly. The models were Langdon) Maciej Krezolek-Shrewsbury, Martin 1, 7: Jaguar Land Rover
model was issued as part of the completed updated to reuse already manufactured steel, Main contractor Interserve Construction Ltd Kuzmanov, Jason Kwong, Samantha L Godden, 2, 3, 8, 9: Simon Kennedy
The complete building was modelled project’s operation and maintenance and the new bay was inserted as the (Phase 1 and 2); Vinci (Phase 3) Oliver Lawrie, David Lee, Matt Lewis, Alvar 4, 5, 6: Arup
in BIM. At construction stage, Arup manual and included specification and penultimate bay.

26 1/2019 | The Arup Journal 27


SEATTLE SPACE NEEDLE | SEATTLE, USA

A dramatic refresh of
Seattle’s Space Needle
The use of cutting-edge techniques in the renovation of Seattle’s most iconic
structure has readied it for the next 50 years of its life, and means that the original
concept for the Space Needle has finally been achieved
Authors Peter Alspach, Clayton Binkley, David Okada, Kristen Strobel, Cress Wakefield

A landmark on the Seattle skyline, the The general contractor, Hoffman team. Arup provided on-call support to the 2.
Space Needle was built for the 1962 World’s Construction, worked around the clock on a contractor that at times included three-shift
Fair and stands 605ft (184m) above the city. tight schedule that avoided the peak tourist support for the 24-hour construction period.
It is the globally recognised symbol of Seattle season. The Atmos stayed open to the public
and attracts more than 1.3 million visitors throughout. This 11-month period required 520ft level
per year. The Space Needle Corporation constant communication and collaboration The work at the 520ft level included installing
engaged architectural firm Olson Kundig to between the owner, contractor and design new stairs, an accessible lift and increased
help them create a new vision that would interior glazing, as well as the replacement of
preserve the building’s historic exterior while the exterior safety barriers at the external deck
revolutionising the guest experience and with glass vertical barriers featuring integrated
clarifying the original conceptual design glass ‘Skyriser’ benches. One of the primary
vision. Arup collaborated closely with the
Space Needle goals of this work was to restore the
architects on the renovation, designing a renovation facts transparency envisioned in the conceptual
3.

seismic retrofit, accessibility upgrade and sketches for the original design, while making
modernisation of building services. The firm 605 Height of the Space Needle, in feet all public areas step-free and fully accessible
provided structural, mechanical, electrical for the first time.
and plumbing engineering, as well as 1,300,000 Visitors to the Space Needle
building physics and fire consulting. each year The quest for transparency extended beyond 1. Existing Truss

the exterior skin – Olson Kundig wanted an


The Space Needle structure consists of three 176 US tons of glass used in the open plan with as few obstructions as possible
main components – the Pavilion Level at its renovation between guests’ first steps from the elevator
605ft
base, the Skyline Level at 100ft, and the and the expansive skyline view. This inside-
2. Build Retrofits
iconic ‘Atmos’ 500ft above the Seattle 196 Percent increase in the out transparency was a major driver for the
streetscape. Within the Atmos, the guest amount of glass installed
520ft
building services modifications throughout the
experience is focused on two main areas: the at the Space Needle 500ft
Atmos. One of the most impactful
520ft level that includes the exterior components was a tightly coordinated reroute
3. Demolish Existing
observation deck and the 500ft level featuring 360 Degrees of of the kitchen exhaust ducts from their vertical
‘The Loupe’ – the world’s first and only uninterrupted views path through the observation level space to a
rotating glass floor. Connecting the two are of the Puget Sound region more hidden vertical course near the core.
the ‘Oculus Stairs’, two open half-moon
shaped staircases made of wood, steel and 50 Experts from around At the exterior, the knee-high wall and wire 4. Completed Truss
glass that terminate in a glass-floored oculus. the world to advise caging at the edge of the observation deck 4.
on the renovation were replaced with new glazed barriers and 1: The iconic Space Needle was built for
From the tower’s Atmos, visitors can now integrated bench seating. The modifications the 1962 World’s Fair. At 605ft, it is a
enjoy expansive and unobstructed 360° views 500 Workers involved required retrofit work at each of the 48 highlight of the Seattle skyline
of Seattle’s skyline, as well as look straight in the renovation existing radial trusses that support the 2: 3D section of the ‘Atmos’, showing new
down through the new rotating glass floor. To observation deck. The top chord of 15 of the Oculus Stairs and increased glazing
achieve these views, 176 US tons (160 tonnes) 100,000,000 Dollars existing trusses was removed and lowered to 3: Some 176 US tons of glass was
100ft
of structural glass was installed, increasing the spent on the first allow for the new staircases and lift pit. Arup installed during the renovation
glazed area by nearly 200%. The new design phase of the designed the retrofits to be installed without 4: Sequence showing modifications made
expands the publicly accessible area by 9%, renovation the need for shoring. This allowed the to 15 of the 48 radial trusses supporting
all within the existing building space. contractor to modify the trusses, while the observation deck
1.

28 1/2019 | The Arup Journal 29


SEATTLE SPACE NEEDLE | SEATTLE, USA

5. 6. 7. 10. 11.

5: Repairs were made to parts of the existing maintaining public access to the observation allowed the damaged tubes to be cut away and Arup created a detailed finite element model they be cleanly detailed and as small as no longer an option, as the cavity below
structure that were found to have corrosion damage deck throughout construction. new sections welded in place without any of the canoe beams to determine their lateral possible, to minimise any visual obstruction. the rotating floor was now visible.
6 & 7: The knee-high walls were replaced with additional shoring. The modification also torsional buckling capacity and ability to
glazing to optimise views When standing on the observation deck, the included architectural detailing to improve resist the increased weight of the rotating floor Providing thermal comfort across the range The air distribution approach was refined to
8: Arup carried out detailed flexural buckling guests’ view to ground level is through the drainage and prevent future water intrusion. with reduced out-of-plane bracing. Several of possible operating conditions was the incorporate separate linear supply diffusers
analysis of the canoe beams signature ring of louvers, also known as the retrofits were installed to strengthen the focus of Arup’s mechanical design in this for heating at the perimeter windows, cooling
9: Construction sequence for installation of the halo, that gives the Atmos its distinctive flying 500ft level existing canoe beams, with welds added to the space and required careful consideration supply diffusers toward the interior and a
Oculus Stair opening saucer shape. During construction, significant The 500ft level was redeveloped into a flexible bottom flange to allow the structure to support due to the increase in the glazed surface return airflow path at the centre of the
corrosion, water infiltration and freeze/thaw space that can serve as either an observation clamps for rope-access maintenance loading. area at this level. The original heating, structure. All air distribution elements
damage was discovered in the rectangular deck or dining area. The original (opaque) ventilation and air conditioning system are coordinated with the sculpted ceiling
tube sections of the halo structure that make rotating floor at this level was replaced with The The existing strap bracing diaphragm below the provided heating at window sills from fan contour. Arup’s building physics team used
up the last panel of the radial trusses Loupe – a new glazed floor and soffit that rotating floor was replaced with stainless steel coil units located in the cavity below the computational fluid dynamic (CFD) analysis
supporting the observation level. With the allows views through the structure to the ground tension rods. As these rods are visible below the rotating floor and cooling via large round to optimise the design and ensure a
building opened up and these zones accessible 500ft below. The new design also includes taller glass floor, it was architecturally important that ceiling diffusers. Underfloor services were comfortable guest experience.
via scaffolding, Arup was able to conduct a windows and updated architectural finishes.
full survey of all trusses. The team designed a Steel plate shear walls have replaced the
retrofit scheme including a temporary support existing concrete wall to improve seismic
structure that relied on adjacent trusses and performance and allow penetrations that 10: The glazed area was increased by 200%,
8. increase circulation and improve access. providing visitors with magnificent
unobstructed views
The structure of the building at this level 11: CFD analysis of air distribution at the
consists of a 66ft diameter box-section ring 500ft level
beam that rests on top of the main tower legs. 12: 3D model showing the complex
Inboard of the ring beam, six radial box beams interaction of building services in the Atmos
connect the ring beam and legs to the central
core of the tower. Outboard of the ring beam,
48 tapered radial built-up beams, dubbed
1.1.Existing
Existing 1. Existing
1. Existing
Framing1.
Framing Existing
Framing
Framing Framing 2.2.Demo
Demo 2. Demo
2. Demo
Slab
Slab 2. Demo
Slab Slab Slab 3.3.Shore
Shore 3. Shore
3. Beams
Shore
Beams 3. Shore
BeamsBeamsBeams 4.4.Install
Install 4. Install
4. Beams
Install
Beams 4.
Beams
and
andInstall
Beams ‘canoe
and andbeams’ for their shape, cantilever out
andBeams
and
andDemo
Demo and Demo
and Demo and Demo Core Core Core
CoreConnections
Connections
Core Connections to support the rotating floor.
Connections
Connections

The original building design used the area


under the rotating floor to house building
services and relied on a combination of
flat-strap bracing and metal deck to brace the
canoe beams against buckling. As the new
rotating floor was to be completely transparent,
all services needed to be moved out of this
5.5.Demo
Demo 5. Demo
5. Demo
Beams
Beams BeamsBeams
5. Demo Beams 6.6.Install
Install 6. Install
6. Beams
Install
Beams 6. Install
Beams Beams Beams7.7.Pour
Pour 7.Slab
Back
7.Back
Pour Pour
7. Slab
Slab
Back Pour
Back Back
Slab Slab 8.8.New
New 8. New
Framing
8.Framing 8.
New FramingNew
Framing area and the existing structure renovated to
Framing
accommodate the view.
9. SEQUENCING
SEQUENCINGSEQUENCING
SEQUENCING
SEQUENCING 12.

30 1/2019 | The Arup Journal 31


SEATTLE SPACE NEEDLE | SEATTLE, USA

13, 14 & 15: The Oculus Stairs connect the 520ft


and 500ft levels. They encircle a central opening
that culminates in the glass floor oculus

to move without significantly damaging the


floor framing above and below.

Services upgrade
A comprehensive building services upgrade was
required due to the age of the building as well
as the extent of interventions across all the
levels in the Atmos. The main service level is
between the 520ft and 500ft levels, with plant
located between the radial trusses supported off
14. 15. the storey-deep ring girder.

In a more conventional building of this


The creation of the rotating glass floor means rectangular tube stringer beam, all of which is The connection of the stair to the surrounding size, a single air handling unit (AHU)
there is a fully glazed cavity between this floor hidden behind an architectural wood slat wall. primary structure was carefully considered would serve the floors above and below.
and the lower glazing that wraps under the Each stair tread is fabricated out of folded under both normal and seismic loads. Under Due to space constraints, eight smaller
building structure. Dust build-up and cleanliness 0.75in (20mm) thick plate that cantilevers out normal conditions, the stair columns are AHUs are located between the radial trusses
of this cavity was a major concern and led Arup from the stringer beam, creating the appearance connected to the floors above and below, to serve this function. This space outboard
to incorporate a dust control fan system that that the stair floats within the oculus opening. providing the necessary stiffness to control of the ring girder also accommodates
circulates and cleans the cavity air. The design vibration and deflection of the treads. Under ducts, variable-air-volume boxes, piping,
of the system used CFD to determine the airflow The opening itself was created by cutting out seismic loading, the stair itself can resist the electrical distribution equipment and
rates and design of the nozzle providing dust one-sixth of the existing floor framing at each applied loads; however, the floor framing that lighting power supplies.
control, as well as to help understand thermal level. Because this framing stabilised a it connects to cannot resist the resulting forces
comfort due to the glass floor. storey-deep ring girder between the service from the stair frame while the two floors are Arup carried out detailed coordination to
and observation levels, the sequencing of this linked together but trying to move separately. incorporate all this equipment in the truss
Oculus Stairs work was important in order to maintain The challenge was to make a structure that space while improving maintenance access.
The Oculus Stairs are a set of two new curved stability throughout. The framing for the was stiff during normal conditions to control New access doors at the service level upgrade
feature staircases that connect the main public opening was designed such that new primary the footfall response, but flexible under a the previous floor hatches (which had meant
520ft and 500ft levels, along with the edge beams could be installed adjacent to the seismic load. To achieve this, Arup designed that access was previously only available from
intermediate service level. The stair encircles existing girders prior to the existing members the top connection of the stair column to the level above). With the redesign, a clear
a central opening of 6ft x 12ft (1.8m x 3.6m) being cut away. The new beam connections to incorporate a shear pin that is calibrated to walking path was established, eliminating the
through each floor that culminates in the glass the central core rely on the remaining portion break away during a large seismic event. The need to step over truss chords at each bay;
floor oculus that allows visitors a view to of the existing girders in order that all the stair remains stable, albeit more flexible, AHU access doors were located between truss
ground level 500ft below. The Oculus also work points remain unchanged. without this top connection intact, and is free chords, greatly improving accessibility.
gives visitors views of the structure, and the
elevator and counterweight operations.

These stairs are highly trafficked, as most 16 & 17: Stair top connection
visitors arrive on the 520ft level and walk down detail – shown under normal and
the staircase to exit via the elevator lobby on the seismic loading
500ft level. With the staircase such an important
circulation path, Arup paid particular attention
to its dynamic response across a range of
loading conditions. The finished stair looks light
but feels solid underfoot.

The structural frame of the stair is made up of


steel tube columns with a plated, curved
13. 16. 17.

32 1/2019 | The Arup Journal 33


SEATTLE SPACE NEEDLE | SEATTLE, USA

plant, varying kitchen exhaust volumes based


on real-time cooking needs and implementing
100% free cooling with outside air at all levels.

Century Project
The redevelopment was dubbed the ‘Century
Project’ and was just that – a comprehensive
renovation that looks back to the structure’s
historic vision and first half century of
operations to set the stage for the next 50 years
and beyond. Final phases of the project will
include updating the elevators, repainting and
a roll out of a new dining experience at the
500ft level on The Loupe.

Authors
Peter Alspach was the Project Director. He
is a Principal in the Seattle office.

Clayton Binkley is a structural engineer in


the Seattle office.

David Okada is a mechanical engineer in the


Seattle office.
18.
Kristen Strobel is a structural engineer in the
Seattle office.
18: One of the aims of the increased glazing at the In addition to increased maintainability, the
observation level was to achieve the transparency services upgrades brought the Atmos up to Cress Wakefield was the Project Manager.
envisioned in the original design current code requirements across all She is an electrical engineer in the
19: The glazed floor in The Loupe disciplines. This was no small feat from an Seattle office.
energy perspective, with the redevelopment
Project credits
having a glazing increase of almost 200%.
Client Space Needle Corporation
There was no special energy code concession Architect Olson Kundig: Design
for the iconic status or unusual nature of the Principal Alan Maskin and Project
building. To show compliance, the renovation Architect Blair Payson
was compared not just to the existing condition General contractor Hoffman Construction
but requirements for new construction, Development manager Seneca Group
including the prescriptive 30% window-wall Glazing consultant Front
ratio and fully insulated floors. Structural, mechanical, electrical and
plumbing engineer Arup:
A performance-based compliance path was Peter Alspach, Emaan Ammar, Mia Areaya,
Clayton Binkley, Hans-Erik Blomgren, Ingrid
selected, trading off energy-efficiency
Chaires, Judy Coleman-Graves, Molly Curtz,
measures for the shortcomings of the Cormac Deavy, Abdullah Drake El, Georges
historical envelope and expanded glazing. El Chammas, Tom Firth, Jon Franzese, Alexej
Arup performed detailed analysis of thermal Goehring, Andrew Haines, Brent Johnson,
bridging in the building structure, de-rating Brian Markham, Brian McLaughlin, Kirk
the building envelope for all the locations Nosho, David Okada, Hilary Pherribo, Nick
where steel elements penetrated the building Sherrow-Groves, Kristen Strobel, Cress
insulation, including the service level trusses, Wakefield, Declan Walsh, William Watson,
girders and beams below the 500ft level, and Lucas Whitesell, Sarah Wolfe, Sarah
within the roof. Generally, as much insulation Wondrasek, Gavin Xue.
as possible was added to the opaque areas of
Image credits
the building, and points of thermal bridging 1, 13, 18, 19: Nic Lehoux
were addressed where possible to improve 2: Olson Kundig
the envelope performance despite the increase 3: Space Needle LLC
in glazing. 4, 5, 8-12, 14, 16, 17: Arup
6, 7: Space Needle LLC and Olson Kundig
Energy-efficiency measures included installing 15: Space Needle LLC and Rod Mar
efficient domestic hot water and space heating
19.

34
BRENT DELTA PLATFORM LIFT | NORTH SEA, UK

1.

A heavyweight lift This was the first major decommissioning


project in the North Sea using Allseas’
single lift technology to remove the
entire topside of a large offshore platform
It took just ten seconds to lift the topside of Shell’s Brent in one piece. The topside housed the
accommodation block for staff, a
Delta oil and gas platform clear from its concrete base, yet helipad, processing facilities, power
generation, compression, flare and the
this was the culmination of years of planning, design and drilling and operational areas, along with
structural works to the platform, and a record-breaking event associated equipment. Its safe removal
enabled dismantling onshore, significantly
Author David Gration reducing offshore risk exposures.

The size of the task was reflected in the


use of the world’s largest construction
1: Allseas’ Pioneering Spirit carried out the world’s vessel, Allseas’ Pioneering Spirit,
heaviest offshore lift when it removed the Brent undertaking what was at the time the world’s
Delta platform topside heaviest offshore lift.

1/2019 | The Arup Journal 35


BRENT DELTA PLATFORM LIFT | NORTH SEA, UK

2: Underdeck and GBS legs of Brent Delta strengthening works required post-cut, prior 6: Section through
3 & 4: 3D non-linear finite element model of to the removal of the topside of the platform Loading Plate
the concrete ring
transition piece, strengthening and concrete shaft from its supporting structure. 650x650x65 beam showing the
80
800 Steel Ring Beam connection details of
5: Shear restraint inspection at the manufacturer 160mm deep L800x500x70x40
Topside removal design development existing Transition
the steel ring beam
(S460)
Arup began the project with a workshop, Piece 40 760
7: Shell’s Brent
which resulted in over 30 design proposals. Delta platform in

70
Using a qualitative assessment, these the Brent field prior
to topside removal
Arup supported the decommissioning of were then rationalised down to the five Grout

500
the platform by designing the strengthening most viable solutions. Following scoping

250

430
required to enable cutting the three calculations and after agreeing relevant
supporting concrete legs to allow the selection criteria with the client, Arup used

100
separation of the topside from its supporting a trade-off matrix to select the preferred 300 M20 Grade 8.8

base. Arup determined that strengthening option for detailed design.


works were required at the cut locations
and designed the shear restraint system that Using a variety of skills, including first Existing Concrete
Ring Beam
provided this necessary strengthening. principles structural design, non-linear
analysis, laser scanning and wave simulation,
This design made it possible for the platform Arup designed a system that was both
to be de-manned several months before the structurally effective and reduced installation
topside removal. Arup also designed the complexity. The scheme involved cutting
concrete caps for the legs – which were the legs just below the topside to facilitate
put in place after the topside was removed its removal. Non-linear analysis was used
2. – and worked on the strengthening of the to simulate the post-cut situation, with a 3D
infrastructure in the receiving harbour to non-linear finite element model developed for
ensure it could accommodate the massive the concrete legs, associated steel transitions 6.
topside structure for dismantling. sections and proposed remedial works to
facilitate the lift. justifiable frictional capacity of the cutline. disengage during the lifting process without
Brent oil and gas field platforms To resolve this issue, Arup designed a shear manual intervention.
The Brent oil and gas field,186km north- This cutting work had to take place ahead of restraint system that allowed the topside to
east of the Shetland Islands, is one of the the removal of the topside due to the limited safely remain in place after the cut. Arup designed the restraint to carry the circa
largest fields in the North Sea. The field has weather window available for the topside 20MN shear force per leg across the cutline
four platforms – Alpha, Bravo, Charlie and lift and the availability of the Pioneering Shear restraint system from the topside transition piece into the
Delta – situated in 140m deep water. The Spirit, the only lifting vessel that could There were several complex design concrete leg and down into the GBS. A steel
topside of the Delta platform was made up accommodate such a significant load. Arup’s requirements for the shear restraints. ring beam (circa 40 tonnes of steel per leg)
of a plate girder deck structure connected analysis found that the shear forces that The system had to be installed in a simple was connected to the concrete ring beam at
via 5.5m deep steel transition sections to a needed to be transferred across the cutline manner offshore, the topside needed to be the top of the leg just below the 160mm-
concrete ring beam at the top of each of the between the legs and the topside exceeded the kept in place after cutting, and it had to deep flange of the 5.5m tall steel transition
three concrete legs. These legs were in turn piece (TP). Made up of eight steel fabricated
connected to a concrete gravity base structure angle sections that follow the internal
3. 4. (GBS) on the seabed. The Brent Delta topside shape of the concrete ring, the steel beams
had a footprint of 72m by 47m, with a 44m formed a continuous compression ring. Twin
height to the helipad and an overall weight loading plates were shop welded to the ring
of approximately 24,200 tonnes. beam in each of the eight corners.

Decommissioning To create the required load bearing


Traditionally, platforms have been connection between the TP and the
dismantled offshore on a module by compression ring, a corner plate was
module basis, but with Brent Delta, Shell positioned between the loading plates.
took the decision to remove the topside These elements were machined in the shop
in one single operation. This allowed the but put in position offshore. A trial assembly
de-construction work to take place onshore was built in the shop to check the accuracy
in a more controlled environment, where of the manufactured elements.
detailed inspection and dismantling could
be undertaken efficiently, and reduced In the installed condition under shear load,
personnel exposure due to the significantly the TP flange contacted the corner plates,
smaller workforce required. which in turn contacted the loading plates.
In this way the load was transferred
Arup was commissioned by the offshore from the TP flange into the steel ring
contractor Allseas to develop, from concept beam. This load was transferred around
through to detailed stage, the design for the the steel ring beam in compression and then
5. 7.

36 1/2019 | The Arup Journal 37


BRENT DELTA PLATFORM LIFT | NORTH SEA, UK

8: Topside being lifted clear of the concrete legs


9 & 10: Plan showing the shear restraint system
11: Concrete legs following topside removal but
prior to cap installation
12: Concrete leg caps being lowered into place on
top of the legs
13: The Pioneering Spirit moves clear of the
concrete legs following its successful lift of the
platform topside

the shear restraints, Arup provided technical


support to both Allseas and Shell.

The shear restraints were designed to


withstand all-season waves. This allowed the
legs to be cut and the platform de-manned well 11. 12.
in advance of the topside lift, which reduced
the offshore risk exposure for the workforce.
1m thick. The cutting sequence was Over a 12-hour period the vessel was Onshore harbour works
Cutting the legs determined based on a review of the positioned under the topside, with each lifting Arup was involved in supporting Shell to
After Shell decommissioned the pipework expected weather window during the cutting beam aligned to touch the designated lifting ensure the harbour infrastructure was capable
and equipment within the legs and installed operation. Holes were drilled at specified points. Hydraulics enabled positive contact to of receiving the topside, performing an
8. the steel shear restraint system, the shaft centres through the concrete ring beam. be kept with the topside, all the while taking independent technical review of the detailed
cutting could proceed well in advance of A diamond wire was then threaded through into account the movement of the vessel. The design of the receiving quay and the critical
the topside lift. Cut UK had conducted all two adjacent holes before the cutting ballast was removed from the vessel before structural interfaces with the Iron Lady barge.
into the concrete ring beam and the legs Rather than tailoring the components to the onshore cutting trials in preparation for process began. the operation, which meant that virtually all Arup reviewed site investigations around the
below. The shear restraint provided no the individual internal leg dimensions executing the diamond wire cutting offshore of the topside weight could be taken before quayside, attended the quay upgrade works
vertical fixity between the TP and the for each leg, the dimensions were laser on the Delta platform. Lift the short lift – which lasted just ten seconds – and witnessed piling.
concrete ring beam, so no disengagement scanned internally, with the steel ring beam The lift was carried out by Allseas’ took the topside clear of the legs.
of the shear restraint was required before the fabricated slightly smaller than the internal The cut was made just below the TP flange Pioneering Spirit in April 2017. Specifically Next steps
topside was lifted. This minimised health diameter. This simplified installation works plate, cutting through the grout and the designed for the single lift installation and The topside platform was transported 388 The design developed by Arup reduced work
and safety risks by avoiding the need for offshore by allowing common components post-tensioned bolts that connected the plate removal of oil and gas platforms, the twin- nautical miles to within five miles of the offshore, minimised cost and health and
any manual intervention during the lifting to be used and enabled them to be assembled to the concrete ring beam, but above the hulled vessel is 382m long by 124m wide shore and the decommissioning yard. As safety exposure, and facilitated the heaviest
process, a critical part of the brief. This to tighter tolerances. Once installed, the gap post-tensioned tendons anchored within the and can accommodate lifts of up to 48,000 the water depth at the Able UK Seaton Port offshore lift to date. The Brent Delta platform
design solution allowed the topside to be between the ring beam and the concrete leg concrete ring beam at the top of the legs. tonnes. A 122m long and 59m wide slot in in Teesside was insufficient to accommodate is one of an estimated 600 installations to
lifted with no personnel on the platform was filled with cementitious grout, which the bow of the vessel was used to position the Pioneering Spirit, the topside was be decommissioned in the North Sea over
– and some months after the platform had accommodated any surface irregularities. Diamond wire cutting was deployed inside around the platform, with the lift using eight transferred via the 200m by 57m wide the next 30 to 40 years. The lessons learned
been de-manned. During the fabrication and installation of the 14m wide legs, which are approximately sets of horizontal lifting beams. cargo barge Iron Lady. The platform is from Brent Delta will be invaluable for future
currently being dismantled and recycled projects that involve concrete GBSs.
with the aim of re-using over 97% of the
material in the platform.
Author
Concrete leg caps David Gration was the Project Director. He is
Following the topside lift, with the legs a Director in Arup’s Advanced Digital
sitting close to 20m above the sea, concrete Engineering team based in the London office.
leg caps designed by Arup, each weighing
approximately 300 tonnes, were placed on Project credits
top of the legs. Owner Shell UK
Main contractor Allseas
Each cap has three installation guides. Arup: Ian Ashcroft, Giacomo Caleffi,
Jac Cross, Andy Gardner, Kazuma Goto,
These helped to position the caps when
David Gration.
lowered from a crane on a moving vessel.
As well as closing off the top of the leg, Image credits
one of the covers provides a foundation for 1, 8, 11-13: Allseas
the navigation aid used to alert passing ships 2, 5, 7: Shell UK Ltd
of the presence of the concrete legs and 3, 4, 6, 9, 10: Arup
GBS below.
9. 10. 13.

38 1/2019 | The Arup Journal 39


RAWANG BYPASS | KANCHING FOREST RESERVE, MALAYSIA

Preserving Malaysia’s natural heritage Malaysia has undergone rapid economic


growth in recent decades, with a rising
population and increased vehicle
ownership placing escalating pressure
Rawang) into a new dual carriageway with
2m-wide paved shoulders. The second
element was the construction of a
completely new section of road – a bypass
on its road infrastructure. to divert the traffic north around Rawang
town centre. The final section of the project
An elegant solution to traffic congestion ensured minimal environmental impact on Rawang, a former mining town founded in was building a trumpet interchange and
a world-renowned heritage site the 19th century that has become a base for upgrading the 2km federal road on the north
commuters to Kuala Lumpur, was side of Rawang leading to Serendah, a
Author Wan Anuar bin Wan Endut particularly affected by road congestion. popular tourist spot.
Located 23km north of the capital on Federal
Route 1 – the oldest national highway in The project was tendered as a design and build
Malaysia – its position on this major contract and was awarded in 2003 to a
thoroughfare made it a traffic bottleneck. partnership between Arup and local company
The journey to Kuala Lumpur could take Panzana Enterprise Sdn Bhd. Arup provided
over two hours at rush hour. Vehicles using full engineering services, and was the full-time
the road travelled through the centre of site supervision consultant for the project.
Rawang, a route lined with shops, roadside
parking and eight traffic signal junctions. Kanching Forest Reserve
The team started on the detailed design in
Alleviating this problem was identified as 2004. Sections 1 and 3 were relatively
a priority as far back as 1997 by the straightforward and progressed smoothly,
government’s highways planning division. but Section 2 was far more challenging. This
The Asian financial crisis around this time part of the project entailed building a bypass
meant the project was put on hold, before the around Rawang that, under the government’s
plan to construct the 19km Rawang Bypass original plan, cut through Kanching Forest
was revived in the early 2000s. Reserve. This hilly forest is an area of
outstanding natural beauty and ecological
Bypass route value. Referred to locally as Taman Warisan
The project was divided into three sections. (‘heritage forest’), it is a rich reserve of
The first comprised upgrading the existing waterfalls, flora and fauna, and attracts
federal road, transforming the single lane eco-tourists from around the globe. It teems
carriageway (starting at Selayang with wildlife, including rare and protected
Interchange just outside Kuala Lumpur and plant species such as the Giam Kanching
ending at the Templer Park area just outside tree, of which only 400 are left in the world.

1: The Rawang Bypass


travels through the
Kanching Forest
Reserve, with the
road almost at treetop
level for sections of
the route
2: Map showing
Federal Route 1,
an important north-
south thoroughfare
in Malaysia
1. 2.

40 1/2019 | The Arup Journal 41


RAWANG BYPASS | KANCHING FOREST RESERVE, MALAYSIA

3: Part of the bridge travels over the existing federal 7: The Rawang Bypass reduces peak time
trunk road. In order not to disrupt traffic, a cantilever journeys to Kuala Lumpur by 90 minutes
method of construction was used at this point
4: Box girder construction was used for the bridge
section above the federal trunk road
5: Typical bridge deck cross-section at pier location
6: To avoid extensive earthworks and minimise
deforestation, the high-level bridge deck was
constructed using a movable scaffolding system
Foundation and pier construction
Having determined a more sustainable route
for the bridge, it was important that the
Department and NGOs such as the World
construction process also had a minimal
Wildlife Fund (WWF).
impact on the area by avoiding extensive
earthworks and deforestation. For the
Arup devised an elegant solution to the
construction of the pier foundations, Arup
problem: an elevated bridge structure over
devised a method that avoided using heavy
the outer fringes of the forest, moving the
3. machinery on site, reducing disturbance to 7.
route initially suggested by the Public Works
the forest’s ecosystem. With the mountainous
Department down to the foothills of the
terrain, it would have been difficult to
In 2005, the state government designated the revisit the concept design and review the forest. This ensured that the bypass would However, the 51st to the 53rd spans required breathtaking views over the forest, the
manoeuvre large machinery on site. This
forest as an official heritage site, meaning no road alignment. For Arup, the challenge was be located at the edge of the heritage area, a different construction method. With the bridge has received resounding public
would have required removing trees and
major development that could affect the to redesign this vital bypass to minimise reducing the need for forest clearance. bridge at this point travelling over the approbation and the approval of
levelling the ground, with this latter activity
reserve’s ecology was allowed. deforestation, ensuring little impact on the existing federal trunk road near Templer Park organisations concerned with protecting
having the potential to cause soil erosion.
environment during the construction phase This amended route required the road at a skewed angle, an MSS could not be used wildlife and preserving the environment.
Finding a solution and after handover. structure to be raised significantly above the Rather than using piled foundations, which due to the large 114m span between piers. In Arup’s strategy for the construction meant
Although the road was an essential part ground to match the vertical alignment of require large drilling equipment, light addition, as an MSS is an underslung system, that deforestation and earthworks were
of improving Malaysia’s transport Finalising the design took almost a year the other sections of the road. The final machinery was used to dig caisson foundations. steel frames hung below the bridge had the minimised. Passing high amid the treetops,
infrastructure, the risk was that any and involved an intense process of engaging design included a 2.7km elevated structure The construction works could therefore be potential to interfere with the headroom of the elevated bridge respects the ecosystem
construction work would require extensive with the Malaysian central government and supported by piers that are up to 58m tall. spread over a smaller area than would otherwise vehicles travelling on the road below. A more below, as well as easing congestion in the
deforestation, resulting in an unacceptable other interested parties. Through meetings, This makes it the longest and highest bridge be necessary. This method required only a conventional balance cantilever method of adjacent town, cutting peak journey time
impact on the natural environment. The presentations and public hearings, Arup in Malaysia, with vehicles on this section of narrow 50m corridor for the construction of the construction was used at this location, with through this area by 90 minutes. In
Malaysian Public Works Department, which gathered input from public representatives, the road almost level with the treetops of the foundations and bridge piers. The foundations the remainder of the spans built using completing the project, Arup has designed a
commissioned the project, requested Arup local authorities, the country’s Forestry surrounding forest. range between 1.7m and 6m in diameter, and traditional inverted-T post-tensioned beams. piece of infrastructure suitable for the needs
were dug using jack hammers and hydraulic of Malaysia’s ambitious, fast-growing
rock breakers. The piers were built using Arup’s design allowed the project to progress economy, without causing damage to the
slipform construction, allowing each pier to be as quickly and efficiently as possible, ensured country’s ancient natural heritage.
constructed quickly, safely and accurately. minimal disturbance to the forest’s ecological
system and permitted access for animals to
Movable scaffolding system travel below the bridge during construction
With the need to avoid extensive earthworks and following completion of the works.
and deforestation fundamental to the choice Author
of construction method, a movable Collaboration Wan Anuar bin Wan Endut was the Project
scaffolding system (MSS) was adopted to Teamwork was key to the project’s Director and is the Managing Director for
Arup in Malaysia.
construct the high-level bridge deck. The successful completion. A project office was
MSS provided a quick, reliable and set up near the site, allowing Arup to work Project credits
economical solution for construction of the under the same roof with the client, the Client Malaysian Public Works Department
4. elevated bridge. This was the first time this contractor and other team members. (Jabatan Kerja Raya). Thanks to Haji Abd.
method was used in Malaysia. Rahman bin A. Aziz as Superintending
Monthly meetings took place on site, where Officer’s Representative
With an MMS, a hydraulically operated giant external stakeholders were also invited, Bridge engineering, infrastructure and
steel gantry, formwork and platform slides including utilities companies, representatives geotechnical design, electrical
from pier to pier, enabling the beams and of the local council, Forestry Department engineering and construction supervision
concrete slabs to be constructed from the top officials and, when there were particular Arup: Wan Anuar bin Wan Endut, Wong Chee
of the piers. Once each section is completed, issues to address, NGOs. This meant that all Thong, Ng Say Gim, Muhd Khairul Asyraf bin
Abd Rani, Mohd Nazri bin Mat Daud,
the formwork is released and pushed to the concerned parties were kept abreast of the
Adlie bin Mohd Ali, Muhd Bazli bin Omar,
next pier, meaning that workers, equipment project’s progress. Azeri bin Ahmad.
and materials have minimal impact at ground
level. In total, 50 sections of 40m span were Safeguarding Malaysia’s natural heritage Image credits
constructed using this method. Two 600-tonne The Rawang Bypass opened to great All images: Arup
gantries were used for the installation. acclaim in November 2017. For its
5. 6.

42 1/2019 | The Arup Journal 43


LEEDS FLOOD ALLEVIATION SCHEME | LEEDS, UK

Lowering Leeds city centre flood risk The first phase of the Leeds Flood
Alleviation Scheme was completed at the
With the rejection of this original scheme,
there was a risk that the flood alleviation
end of 2017. The works have significantly initiative would be removed completely from
reduced the risk of floods that have the the list of national infrastructure spending
The Leeds Flood Alleviation Scheme is one of the largest flood defence potential to cause devastating physical priorities. For Arup, whose Leeds office is
projects in the UK and the first in the country to use movable weirs and economic damage to the heart of located on the River Aire, getting involved in
the city. developing a new scheme was an
Authors Michael Nichols and David Wilkes opportunity to propose a more sustainable
Previously, 3,500 residences and 500 solution. The firm, working together with
commercial city centre properties were at high Leeds City Council, developed an alternative
risk, as were key access routes to the train proposal more in keeping with the city’s
station area, data and telecommunications character and landscape. Arup focused on
infrastructure, electricity sub-stations and reducing obstructions that were causing
more than 300 acres of developable land. water levels to rise, meaning the length,
visual impact and cost of the riverside
In 2015, Storm Eva hit the city, with the defences could be significantly reduced.
resulting flooding causing an estimated
£37 million worth of damage. This By identifying which flood defence
highlighted the importance of completing measures would provide the most immediate
the flood alleviation measures as quickly benefits and developing the project in stages,
as possible. The first phase of the scheme Arup believed it could make substantial
provides protection to the city without improvements on a smaller budget, adding
compromising the character of the more sophisticated measures when further
waterfront, with careful interventions funding was secured – an attractive proposal
maintaining the important connection during a time of economic recession.
between the city and the River Aire.
The design comprised three main elements:
Scheme development the removal of the river’s two main
In 2011, the UK government’s Department navigation weirs, replacing them with
for the Environment, Food and Rural Affairs, moving mechanical weirs that allow the
and the Treasury, rejected a proposal from a water level to be better controlled; installing
different firm for a £190 million flood scheme 10km of linear defences in the form of walls
due to the excessive cost. That scheme along 5km of the city centre waterfront,
advocated the construction of 3m high walls embankments and landscape improvements;
and embankments. While these would have and the removal of a 600m-long man-made
provided flood protection, they would have island that separated the river and canal,
also severed the physical connection between thus eliminating a bottleneck for water flow.
the city and the waterfront. Such high walls
would have had a negative effect on the café In November 2011, the Environment
and bar culture along the river, and a pleasant Agency commissioned Arup to develop the
waterfront walking and cycling route would scheme further and the project subsequently
have been lost. secured funding. With Leeds due to connect

1: Completed Crown
Point replacement
weir – part of
the Leeds Flood
Alleviation Scheme,
which provides
100-year storm
flood protection
2: Arup developed
a web-accessible
BIM model for
the scheme
1. 2.

44 1/2019 | The Arup Journal 45


LEEDS FLOOD ALLEVIATION SCHEME | LEEDS, UK

Working from this common data environment


ensured that the project team, including the
client, the design and build contractor and
other stakeholders, had access at all times to
the most up to date project information. This
helped to manage workflows and speed up
P4 the approval process. It enabled better
coordination and collaboration, allowed the
early mitigation of any critical issues before
4500
Scour site works commenced and reduced risk
protection
overall. The model also helped provide
Eel pass greater certainty regarding the construction
costs. Following completion of the works, all
this information was made available to the
Fish
client and their team who were responsible
Pass
Turbine
for maintaining the flood alleviation
infrastructure after completion.
3.
Min 36700

P3 The design team of Arup, Leeds City


with the High Speed 400 2 (HS2) rail
400 link, and environment, the project team could digitally Council and the Environment Agency
with the city’s South Bank being one of navigate the complete scheme, including the was based in the same building. Following
11800
Europe’s largest city centre regeneration flood defence walls, proposed weirs, and the contract appointment, the contractor
initiatives, the flood alleviation scheme was new and existing bridges. They could call up and their designer joined the project team
B

Eel pass
identified by the UK government as an project data that was linked to the model, on site. This structure ensured there was 9.
important strategic
P2 project. such as drawings and photographs. good collaboration across the complete
11800
project team.
Digital construction and collaboration The aim was to ensure that everyone involved Aire valley was home to industries such as
Min. 8200

Arup developed a web-accessible interactive in the project had a sound understanding of Replacing the weirs carpet and cloth making, and coal mining.
Building Information Modelling (BIM) the scheme’s fundamentals and access to all The existing masonry weirs on the river
P1
model for the scheme. Through this virtual the technical information whenever needed. dated from the Victorian era, when the River These fixed weirs made the river navigable
through the city centre, forming an
important trade and passenger route linking
Min 12400

Fish bywash 22.600


22.320 Top of weir
Hull, the Humber ports and Liverpool with
several cities and market towns. The weirs
channel P4
Pier

4500
Weir design to include
curved abutment plate
7.
kept the river level high enough to allow
Scour
to match pier
large barges carrying industrial cargo to
Min. 6200

Eel/elver pass protection Steel gate

Existing weir to be
demolished
Eel pass
Steel plate attached to pier
navigate the waterway. However, when the
14895

21000

Strap water level increased during flood


B

18.527 or lower Bladder Scour


conditions, the weirs hindered the flow,
Fish
Pass
Turbine 18.40 or lower protection significantly increasing flood risk.
17.800 or lower
Existing sluice structure and
Min 36700

pier to be demolished
P3 The previous scheme did not seek to change
Scour protection(to be designed
these weirs; however, Arup saw them as a
1602

400 400

11800
Seepage cut-off as
crucial element of the flood management
strategy. The firm proposed replacing the
Concrete base structure
needed
B

Eel pass

existing weirs at Knostrop and Crown Point


P2
with movable mechanical weirs. These would
maintain the river at a navigable level in
11800
Min. 8200

5. normal conditions, but could be lowered in


P1
3: Storm Eva caused an estimated £37 million of advance of extreme weather conditions,
flood damage in Leeds when it hit in 2015 thereby reducing the flood risk. The
4: The detailed plan for the new weir at Knostrop mechanical gates control the water level using
Min 12400

bottom-hinged steel plates supported on


Fish bywash 22.600
channel 22.320 Top of weir
Pier
shows the elements aimed at encouraging local
Weir design to include
curved abutment plate
to match pier
wildlife, such as eel and fish passes bladders, which can be inflated or deflated with
air to lift the gates up or down as required.
Min. 6200

Eel/elver pass Steel gate

Existing weir to be
demolished Steel plate attached to pier
5: The water level is controlled using bottom-
14895

21000

Strap
hinged steel plates supported on inflatable
B

18.40 or lower
18.527 or lower Bladder Scour bladders. These movable weirs can be lowered in
protection

Existing sluice structure and


advance of extreme weather, thereby reducing
17.800 or lower
7 & 8: The mechanical weir at Knostrop, shown
pier to be demolished

Scour protection(to be designed


flood risk raised and lowered during construction
1602

6: Arup used physical models of the weirs to test 9: Crown Point replacement weir
Seepage cut-off as
needed
Concrete base structure
flow patterns under construction
4. 6. 8.

46 1/2019 | The Arup Journal 47


LEEDS FLOOD ALLEVIATION SCHEME | LEEDS, UK

10: In order to ensure the connection between the national flood defence schemes. The
city and the River Aire was maintained, flood- movable weirs allow a significant reduction
proof glazed units were installed along a stretch of in the height of the walls and embankments
the riverbank most used by the public within the city compared with the previously
11: Natural flood alleviation methods were also proposed scheme. Together with terracing
used, such as planting trees and landscaping, this maintains physical and
12: The Trans Pennine Trail was relocated so that visual connectivity with the waterfront.
it now crosses the river on a 70m span bridge
installed to connect the trail and the north bank of The scheme’s success has protected the city
the Aire centre from flooding – providing a 100-year
storm standard of protection up to 2069,
taking into account climate change – and
There are many high-quality public areas ensured that the development of Leeds
along the River Aire, so a priority was to South Bank can progress with confidence.
preserve these and the relationship between This project has the potential to create
people and the water. As the movable weirs 35,000 jobs and 4,000 homes, and will
reduce the flood water level in the city house the terminus of HS2.
centre, this means that the walls could be
much lower than the previously proposed Arup’s scheme has enhanced the area’s
3m height. Arup’s design ensured the natural habitat, encouraging local wildlife to
majority of the walls were less than 1.2m flourish. The new weirs include fish and eel
high and were clad in stone and brickwork passes that allow baby salmon to come
to match their surroundings. In the areas down the river and for mature adult fish to
10. most used by the public and near residential 12. swim back up. It also provides a habitat for
areas, flood-proof glazed units were mammals such as otters and beavers. For the
In normal conditions, the gates are at a 45° temporary weir was installed upstream at installed to make sure that views of the river bottleneck. Its removal was another element rainfall and high river levels. The 275km2 first time in about 200 years, there is now a
angle, which maintains the high river level Knostrop, which allowed construction work could be maintained. A testament to the in Arup’s strategy to prevent flooding by model – one of the biggest of its kind in small otter population living in Leeds city
and allows for navigation. However, as the to be undertaken in a safer manner in project’s success was that a very active eliminating blockages rather than relying on Europe – brought together all the elements of centre. In addition, as part of the natural
waters rise, the gates can be progressively shallower water, and ensured the flood risk residents’ committee with properties along excessively high flood protection walls. To local and highway drainage and both the flood management techniques used by Arup,
lowered towards the riverbed over a to surrounding properties was not increased the river was satisfied by the result. facilitate the removal of the island, Arup current and historical water company records. over 700 trees have been planted.
two-hour period, removing the barrier to during construction. designed the diversion of the Trans Pennine It created a detailed picture of Leeds and its
flows and greatly improving water Eliminating another barrier Trail (used by walkers, cyclists and horse flooding hotspots. This means that measures By improving river accessibility and
conveyance. This reduces high-flow water Linear defences in the city centre The final element of this phase of the flood riders across the Pennines). The trail was can be designed in the future to tackle spot securing the future of local leisure and
levels by 2m at the weir locations and by The second element of the scheme was to alleviation scheme was the removal and relocated by creating a new 1km walkway surface water flooding in Leeds, which has a business establishments, Arup’s flood
approximately 1m in the city centre. build flood defences on each river bank to relocation of a man-made island at on the left bank of the river that included high river flow and intense local rainfall alleviation scheme has also added to local
protect a 5km section of the city centre, as Knostrop, which separated the river and the measures to encourage wildlife and plantlife (1,025mm per year over 152 days). employment in the city. It has created 150
Mechanical weirs are used in other countries the water level could still rise above the Calder and Hebble canal along a 600m and improved public wayfinding and direct jobs and will safeguard 22,000 more
– in the US and Canada, for example – but original riverbank during a flood event. stretch. This eliminated a water flow interpretation of the environment. The cutting edge over the next ten years, supporting further
typically to control the flow of water into The implementation of this £50 million growth and regeneration of the Leeds
hydroelectric plants. Arup’s scheme in Leeds, The trail needed to cross the Aire, so a scheme puts Leeds at the cutting edge of regional economy.
using weirs developed by Dryhoff, is the first locally manufactured bridge was installed
time movable weirs have been used as part of at the weir location connecting the diverted
a flood alleviation scheme in the UK. trail with the north bank of the river.
Weighing approximately 150 tonnes and Authors Dean, Paul Dickens, Mike Dobson, Stephanie
Michael Nichols was the Project Manager and is Dye, Mike Farrer, Nick Ferro, Paige Garside,
Configuring the system’s layout and spanning approximately 70m, the bridge Libby Gibson, Arlene Goode, Llew Hancock,
an Associate Director in the Leeds office.
installation correctly was crucial. As part of was designed by Arup, Knight Architects David Hardy, Milly Hennayake, Dean Hogg,
the design process, Arup used both digital and the BAM Nuttall/Mott MacDonald David Wilkes was the Project Director. He is an James Holloway, Sophie Hornsby, Jon
and physical models of the weirs to test the joint venture. Associate Director in the Leeds office and is Horrocks, Lan Huang, Andera John, Michael
various flow patterns ahead of construction. Arup’s Global Flood Resilience Leader. Jones, Christian Junge-Filipek, Jenny Lightfoot,
Some 180,000 tonnes of material was Jou Lin Ng, Amy Martin, Mark Matthews, Will
In addition, the 3D digital model helped excavated during the re-shaping and Project credits McBain, Michael Nichols, Alex Nicholson,
plan the weir construction sequence. The re-grading of the river. This was reused Client Leeds City Council Daniel Patten, Matthew Peacock, Miguel Piedra
model was also used to create a video that on a local development site and also for Contractor BAM Nuttall Lara, Novlet Pitter, Ruairi Revell, Felicia
Civil, water, geotechnical, mechanical, Rhodes, Victoria Robinson, Marcus Shepherd,
showed how the weirs worked, illustrating the diversion of the Trans Pennine Trail,
electrical, structural engineering services in Paul Simkins, Paul Smith, Hannah Smith, Alex
the process to the wider public. resulting in a saving of £6 million. Smith, Veronika Stoyanova, Martyn Tattersall,
addition to hydraulic design, commercial
management, environmental impact Trevor Taylor, Lee Wallace, Jen Whelan, David
Arup worked with the design and build Integrated urban drainage model assessment Arup: Daniel Aspden, Chris Baker, Wilkes, Sam Wright.
contractor to design the system, which had In addition to minimising flood risk from the Luke Ballantyne, Niall Bourke, Adam
to meet strict requirements for control of river, Arup created a digital model to identify Broadhead, Eric Buffin, Olly Carlton, Oliver Image credits
flood risk and needed to maintain navigation the risk of residual surface water flooding Clarke, Paul Davies, Richard Deakin, Alan All images: Arup
during construction. For example, a issues, looking at the combination of heavy
11.

48 1/2019 | The Arup Journal 49


AMOREPACIFIC HEADQUARTERS | SEOUL, SOUTH KOREA

Beauty and innovation


A sustainable modern building that draws on traditional Korean design to
provide a headquarters for one of Asia’s largest cosmetics companies
Authors Francesca Coppa, Eva Hinkers, Julian Olley, Alexander Rotsch,
Nigel Tonks, Frank Walter

Founded in 1945, Amorepacific is the largest 5th Floor


beauty and cosmetics company in South
Korea and one of the biggest in Asia. Towards
the end of 2017, the company moved into its
new headquarters in the centre of Seoul, on a
site that has been occupied by the cosmetics
giant for over 60 years. The new building is
an elegant 110m tall cube centred around a
courtyard, part of which is glazed to provide
natural light into the atrium below. With its
striking outer façade of vertical fins, the
building is a distinctive and innovative take
on office accommodation.

Inspired by references to traditional Korean 11th Floor


courtyard architecture and with energy
efficiency and wellbeing at the centre of its
design, the building is punctuated by three
large openings on the 5th, 11th and 17th
floors. These are landscaped with gardens
and terraces, and open onto an inner central
courtyard that features a reflecting pool. The
openings allow natural light and ventilation
to enter the heart of the building, and frame
dramatic views across Seoul.
3.

The architectural design was led by David


Chipperfield Architects (DCA), with Arup
collaborating with DCA on the design of the 17th Floor
building, supported by a team of Korean
consultants on the project delivery. Arup’s
London and Berlin offices provided all technical
engineering services, including structural
engineering, building services, geotechnical,

1: The Amorepacific headquarters, which combine


traditional Korean architecture and technological
innovation, are based in the centre of Seoul
2 & 3: There are three openings at different levels
of the structure
4: Daylight analysis of the 17th floor
1. 2. 4.
Technical issues
50 1/2019 | The Arup Journal 51
AMOREPACIFIC HEADQUARTERS | SEOUL, SOUTH KOREA

combining shading and ventilation with 7: A 70mm deep reflecting pool covers the atrium
permanent access for cleaning and glazing in the courtyard
maintenance. This is a bespoke composite 8: Solar gain is controlled primarily by vertical fins
system in which every component has been that form a brise-soleil. The access walkways also
designed from first principles. The system provide additional solar shading
contributes to the look, feel and operation of
the headquarters. Within the building, Arup
and DCA designed many systems that were
specifically developed for the project, and
even patented the modular LED luminaire
system used throughout the building.

The building incorporates renewable energy


technologies, including solar panels and generous enough to accommodate large
geothermal heat pumps that work together with floor-plates, a novel design was required to
energy recovery devices to minimise energy avoid deep plan spaces that place occupants
consumption. Rainwater harvesting, wastewater unacceptably far from windows, natural light
treatment, low-flow water fittings, and extensive and ventilation.
public amenity and landscaped terraced gardens
further support the sustainable building concept. The key to unlocking this solution lay in
This commitment to sustainability secured traditional Korean architecture, where living 7.
LEED Gold certification for the headquarters spaces were arranged around a courtyard.
5.
in May 2018. Placing a central courtyard within the building Daylight factor (%)

created a quadrangular floor-plate, drawing 12.5 10 7.5 5 3 2.5 2 1.5 1

Inception daylight into an open, well-lit and naturally


Amorepacific’s brief was clear in its aspiration to ventilated dual aspect working environment.
create a headquarters with presence and character 1
that evoked the brand values of the company, In a significant adaptation of the traditional
which seek to celebrate Asian beauty by blending form, large horizontal openings were inserted
traditional wisdom, fine ingredients and into three façades. This was necessary to 2
technological innovation. The headquarters were provide a greater connection between the inner 3
to comprise 80,000m2 of office space, with courtyard and the outside of the building. These
numerous amenities for staff and the public, openings bring light, ventilation, exterior views
including a museum (located in the basement), and an enhanced sense of openness to the inner
an archive, tea room, restaurants, retail spaces, courtyard. They also create space for
product testing spaces and a 450-seat auditorium. landscaped elements in the upper reaches of the
building. The introduction of nature at an
DCA invited Arup to team up for the design elevation high above the Seoul streetscape 1 Vertical fins (shading)
competition in 2010, during which many of provides pleasant recreational spaces for staff
2 Horizontal grille (access and shading)
the key massing, shape and design principles and visitors. Voted by staff as their favourite
3 Internal blinds (glare protection) Workspace area Corridor Ancillary
were established. Collaboration was so close areas of the building, they contribute to a areas
during this phase that the completed project greater sense of wellbeing, as well as enhancing
bears a significant resemblance to the the biodiversity of the development. 8.
competition entry, despite a further three
years of continuous design refinement and As sunlight strikes the courtyard floor in all
6. value engineering leading up to the start of seasons, during design development a glazed impact of the prevailing wind direction, wind Façade
construction in 2014. floor was introduced to admit daylight into the movements down the façade onto the The orientation of the building is such that
spacious atrium below. A 70mm deep reflecting entrances and traffic noise. For example, the elevations stand at an angle towards the cardinal
5: The three openings in the building’s façade building physics, acoustics, vertical transport, The winning submission proposed a pool in the courtyard covers the atrium glazing, largest horizontal opening, which faces points. The 52° north-south orientation results in
contain landscaped elements, providing natural fire, wind, lighting and façade design. sustainable and technologically advanced adding to the calming atmosphere and south-east towards Yongsan Park, was all sides of the building being exposed to direct
spaces for staff high above the city building influenced by tradition. The design enhancing the aesthetics of the space. strategically placed in relation to the prevailing solar gains, with the south-east and south-west
6: The atrium’s glazed ceiling ensures the space Arup focused on incorporating passive allowed for abundant natural daylight and wind direction to reduce the effect of façades receiving more solar exposure than the
receives natural daylight environmental design solutions such as natural ventilation – something not common in Motorised ventilation louvers at high and low downdrafts above the main entrance. The north-east and north-west façades.
daylighting, shading, building massing, Seoul high-rise office buildings, which tend to level ventilate the perimeter spaces in spring mid-level opening is located on the Hangang-
orientation and natural ventilation into the early rely on artificial lighting and air conditioning. and autumn. Underfloor mechanical ventilation daero highway. The opening’s elevation Responding to this challenge led the design team
concepts. These design solutions significantly serves the central floor zone and provides shields the courtyard from traffic noise. The to customise an engineered response to reduce
reduced energy demand within the building, and Layout mixed mode ventilation. uppermost opening is placed on the north-east energy consumption that also became a
improved occupant comfort and wellbeing. To mediate between the adjacent Yongsan Park façade, where prevailing wind and down-wash signature feature of the building: vertical fins
and surrounding high-rise developments, the Wind effects are less critical. In this orientation, the that form a brise-soleil, which is connected to
DCA and Arup developed a fully integrated team developed a 22-storey (above ground), Arup optimised the locations of the large elevated opening also overlooks the city, the building by accessible walkways, wrapping
façade and environmental moderating system, medium-rise building. While the site was horizontal façade openings, modelling for the giving views towards Namsan Mountain. all elevations. As well as adding to the building’s

52 1/2019 | The Arup Journal 53


AMOREPACIFIC HEADQUARTERS | SEOUL, SOUTH KOREA

reduce solar gains and, consequently, reduce the large façade openings, the down-wash 11: BIM model of the building services showing the
the energy consumed by the building’s impact at entrances and, crucially, to be able cores positioned at the four corners of the building
cooling systems. to refine the structural robustness of the 12: The building’s arrangement around a central space
exposed parts of the fins. The fins have allows natural daylight to flood into the courtyard, which
There was little codified guidance for pinstripe surface protrusions along their is landscaped with various natural elements
designing such large elements. Typically, wind vertical axis that become visible only when
loads are anticipated to be greatest at the near the building. While these make a strong
corners and edges of a building, where wind visual contribution – purely rounded shapes
speed accelerates. However, the configuration can be difficult to process visually – Arup
of the brise-soleil affects these predictions: the introduced the 3mm linear protrusions to
presence of the fins provides resistance to the encourage vortex shedding. Micro turbulence
wind and the repeating pattern of fins could created by wind passing over the stripes
provide sheltering effects near the corners. reduces deflection and vibration effects as well
Surrounding buildings create additional as improving robustness.
turbulence, which can result in significantly
increased wind loads at the building’s corners. Arup integrated the structural and the shading
performance needs in determining the fin
In order to optimise the fins’ design, Arup patterns, recommending appropriate sizes and
conducted a series of wind tunnel tests of the weights of fins for different locations around
brise-soleil at different scales to determine the the building. For example, shallow fins were
9.
response to wind effects. dominant in locations with lower wind
pressure and deeper fins were prioritised at the
The fins’ size meant they could not be corners of the building.
distinctive appearance both during the day and modelled at normal wind tunnel testing scales
at night, this system maximises transparency, of 1:400–1:300. Arup’s wind specialists Walkways
controls daylight and provides views out across developed a customised approach to testing. A typical challenge for external shading, which
Seoul. It also assists with managing the solar Preliminary small-scale, whole-building is exposed to the elements, can be the
heat gain within the building. testing in South Korea was followed up by difficulty of maintenance and cleaning. For 11. 12.
1:70 scale fin tests in Europe’s largest Amorepacific’s headquarters, the layer of
Arup performed daylighting and structural atmospheric boundary layer wind tunnel in vertical fins is separated from the building’s
testing to optimise the geometry and pattern of Milan, Italy. The design of the fin section was glazing by a series of grillages at each floor external moving parts, greatly simplifying its culture where work arrival and departure times ‘twin lift’ system, with hall-call control, over
the fins. The system comprises approximately further refined to an aerofoil shape with level that serve the triple function of horizontal maintenance requirements. and lunch times are commonly punctual, often a conventional ‘double deck’ system is an
1,150 aluminium fins in four sizes – 450mm, tapering edges, with additional testing carried shading, fin support and access walkways. leading to lengthy waiting times. increase in capacity and reduction in waiting
350mm, 250mm and 200mm deep. Although out at this stage of the design. These allow the outside of the windows to be Vertical transport time, as well as a reduction in energy
these have a uniform appearance, the fins are cleaned easily and give access to the fins and The latest advances in lift technology have been The central courtyard arrangement precludes consumption. This application is the largest
grouped in patterns that vary around the This combination of tests enabled Arup to motorised ventilation louvers for inspection used in order to provide a high level of service the use of a central lift and staircore. Instead, of its kind in the region.
building, tuned for orientation, based on predict the behaviour of wind at the edges of and maintenance. The external shading has no and reduce waiting times, thereby facilitating cores are positioned at the four corners of the
sun-path solar exposure. For example, on the rapid mobility around the building while floor plates and comprise five passenger lift Courtyard, atrium and glazed floor
north-east and north-west façades, direct solar minimising the lift core sizes. Waiting times are shafts, and one service and one firefighting lift. By locating the stair and lift cores in the
exposure is minimal during summer months nine seconds in normal service and 15 seconds Each passenger lift shaft contains two lift cars corners of the building, it became possible to
and during normal working hours. The fin at peak times. This is highly advantageous in a operating independently. The advantage of this create a large ground floor atrium below the
pattern on these façades comprises mainly courtyard. The importance of this space for
shallow fins to maximise natural lighting and Amorepacific goes beyond the functional brief,
views. On the south-east and south-west Family A, Fin type 1 (40%), 2 (40%), 3 (20%) which was to provide secure access for staff
façades controlling solar gain and glare is Family B, Fin type 1 (33%), 2 (33%), 3 (33%)
and visitors. It is also the setting for the public
more critical. Here, deeper fins provide a entrance hall used by people visiting the
higher degree of solar shading to significantly Family C, Fin type 1 (20%), 2 (40%), 3 (40%)
building’s amenity spaces. These include the
Family D, Fin type 2 (33%), 3 (33%), 4 (33%) art museum, tea room, auditorium, childcare
centre, product testing areas, retail spaces,
restaurants and cafés. The atrium also creates a
Size 1 Size 2 Size 3 Size 4 pedestrian link to the adjacent Yongsan Park.
Big series
The early design envisaged an artificially lit
200
250

of fins
350
450

facing
outwards
space. Arup worked with the architect to bring
9: The fin pattern, with various fin sizes used, natural light into the expansive space. This
gives the building its unique look, while also Small
200
250

series of
350

managing daylighting requirements and solar


450

fins facing
heat gain into the
courtyard
10: The fins around the façade are of various sizes 150 115 80 65
Distance
in order to manage solar gain and glare (mm)
13: The award-winning headquarters provides
450 450 450
depending on the façade orientation views over Seoul and links with the nearby park
10. 13.

54 1/2019 | The Arup Journal 55


AMOREPACIFIC HEADQUARTERS | SEOUL, SOUTH KOREA

14: Arup and DCA various light atmospheres and a high level of
created a luminaire future adaptability.
system that uses a
single luminaire Taking a conscious low material wastage, high
body shape that can recyclability approach, DCA and Arup created a
be adapted for
modular, re-usable and adaptable luminaire
various applications
system that provides a huge variety of lighting
15: The courtyard performances. The system uses a single
provides a natural link
luminaire body shape with interchangeable
between the inner
building and the outer
optical lenses for different applications
environment throughout the building. This is an innovative
and sustainable departure from the conventional
approach to lighting flexibility, which relies on
different luminaire products and manufacturers
14. for different settings. The emitting surface of the
optical lenses is covered with microlenses of
was achieved by creating a glazed ceiling for system that is also aesthetically pleasing. The different shape, producing wide, medium, oval
the atrium, with a deep clear-span structure panels are located in areas where people or narrow light distributions. The unique optical
supporting the courtyard floor and the congregate and have conversations. Corridor system combines reflection inside the lens with 16. 17.
reflecting pool. The solution provides daylight ceilings are treated with sound-absorbing panels refraction at the underside of the lens, and offers
to the ground floor and, looking up from comprising a 50mm mineral wool core covered 12 different light distribution performances in up
below, provides a view of the sky, giving a with a 70% perforated metal sheet, recessed to 30 possible combinations. Available as systems. It won the 2018 Tall Building of the Arup’s total design approach, working 16: Reflected ceiling plan showing sound-
connection with the outside. within the concrete coffers of the exposed recessed, surface-mounted, adjustable and Year at the Dezeen Awards. in close collaboration with DCA, local absorbing panel distribution in the atrium
structural soffit. The outcome minimises high pendant versions, the system provides the consultants and the client, has resulted 17: DCA, with Arup, designed a variable acoustic
A precise integration of structure and services noise levels and disturbance, and so facilitates optimal light for any desired lighting atmosphere The design team has created a building that in an innovative building incorporating system for the auditorium
defines the character of the atrium. Lighting, comfortable conversation among small groups. and room use, and forms a decorative element embraces the climatic and cultural characteristics inventive façade, lighting, ventilation
diffusers and sound absorption are integrated that compliments the architecture. of Seoul. The work spaces are naturally and lift systems. The result is a flexible
with the structure so that the exposed concrete In the auditorium adjacent to the atrium, Arup ventilated and provide extensive levels of and healthy working environment for
soffit requires no additional ceiling treatment. designed a variable acoustic system to allow Every component is replaceable and the lights daylight and good views across the city. staff and visitors.
Despite its busy public nature and hard the venue to be used for amplified and can be modified for any changes in the building’s
surfaces – with natural stone floors and unamplified scenarios (i.e. music and speech) use without compromising the appearance of the
concrete columns, walls and ceilings – Arup’s by deploying two layers of acoustic curtains ceiling. Patented by the design team, the lighting
acoustic designers created a controlled and diffusers on the auditorium side walls. system, manufactured by Italian company Authors vertical transport, acoustics, Joachim Guesgen, Charlotte Heesbeen,
environment while maintaining its live nature. Viabizzuno, is commercially available. Francesca Coppa is a senior acoustic engineer building physics, security Arup Cameron Heggie, Carsten Hein, Karen
in the London office. Henderson, Felipe Herrera, Eva Hinkers, Daniel
Lighting
Local team Hof, Duncan Hough, Anna Janda, Adam
Acoustic panels are discretely integrated with Amorepacific currently operates 28 Museum Architect HAEAHN Architecture Jaworski, Lidia Johnson, Jimmy Jonsson, Lisa
Eva Hinkers was the Project Director. She is the
the raw finish of the space to create an effective brands under one roof, creating the need for Designed to international museum standards, Chair of Arup’s Europe Region Board and is Interior architect Kesson Kaluzni, Berthold Keck, Matthew King, Chris
the Amorepacific Museum of Art focuses on based in the Düsseldorf office. Structure CSSE Kinnaird, Christiane Kleinke, Fabian Knauber,
traditional and contemporary Korean art and Building services HIMEC; SUKWOO Mike Kong, Paul Lander, Diana Lassalle, Paula
crafts. Careful integration of structure and Julian Olley led the design of the vertical Façade engineering Withus Longato, Maria Lynch, Vasilis Maroulas, André
services has created a gallery space that is transportation. He is a Director in the Vertical transport KEC Martins, Jacek Marzec, Joana Mendo, Ross
re-configurable to allow one main exhibition London office. LEED Cosentini Mills, Andreas Muenz, Duc Nguyen, Julian Olley,
or a combination of smaller exhibitions. Fire engineering KF UBIS Ender Ozkan, Stefan Petersen, Warner Post,
Alexander Rotsch is an Associate Director in the Lighting Huel Hugh Quail, Gregory Quinn, Lena Raizberg, Dirk
Berlin office and Arup’s Europe region lighting Acoustics Chungbuk National University Regenspurger, Hagen Rock, Melanie Rosenthal,
Arup advised on providing a dedicated art
skill leader. Sustainable design EEC Alexander Rotsch, Nina Rutz, Ronny Schiemann,
handling truck-lift at street level to transport Geotechnical consultant CG ENC Amanda Schilling, Henning Schlechtriem,
vehicles to the basement level secure art Nigel Tonks is a Director and the leader of Barbara Schmelz, Jens Schmidt, Oliver
handling area for the museum. This greatly Arup’s Buildings Group in London. Arup team Schwabe, Dave Seager, Amy Shen, Andrew
simplified vehicle movements near the building Rachid Abu-Hassan, Andres Acosta, Mikal Sherratt, Patrick Simon, Jolyon Smith, James
and freed up a greater site area for landscaping Frank Walter led the façade design. He is an Ahmed, Claudia Albornoz, Andrew Allsop, Andy Smith, Jamie Stern-Gottfried, Glen Swinney,
and planting. Associate in the Berlin office. Bailey, Stefan Behring, Corinne Benedek, Ed Carolin Tietgen, Magdalena Tomaszewska, Nigel
Blower, Trevor Bone, Phil Borowiec, Ian Tonks, Laurie Turnbull, Brian Twohig, Martin
Award-winning Project credits Braithwaite, Wojciech Cepok, Christopher Unger, Nick Unsworth, Stephan Vogt, Frank
Amorepacific’s headquarters are innovative, Client Amorepacific Corporation Clifford, Francesca Coppa, Marc Crompton, Walter, Colin Winant, Maciej Wlecial, Jan Wurm,
Architect David Chipperfield Architects Berlin John Dakin, Lizzie Davies, Jim Deegan, Luca Andrew Yeoh, Gertraud Zwiens.
highly sustainable and distinctive. The
General contractor Hyundai Engineering & Dellatorre, Michal Dengusiak, Tarun Devlia,
building has been awarded the KIRA Korean Alexander Diaz, Lars Dobberstein, Aidan Doyle, Image credits
Construction
Architecture premier prize and won the 2019 Structural, building services, Emily Dufner, Andrew Duncan, Pablo Efferenn, 1: Namsun Lee
Council on Tall Buildings and Urban Habitat geotechnical, façade, wind, Ulrike Elbers, Adam Foxwell, Matthias Frechen, 2, 8, 10, 13: David Chipperfield Architects
Award of Excellence for the Best Tall fire engineering services, Paul Freund, Hannah Geissler, Alex 3, 4, 7, 9, 11, 16: Arup
Building (100-199m), as well as the MEP lighting, sustainability, LEED, Goldsbrough, Nicolo Guariento, Rene Guenther, 5, 6, 12, 14, 15, 17: Noshe
Engineering Award for the building services
15.

56 1/2019 | The Arup Journal 57


1 2 3

4 5 6

7 8

1. Hong Kong-Zhuhai-Macao Bridge, Greater China: Marcel Lam Photography; 2. Leeds Flood Alleviation Scheme, UK: Arup; 3. Seattle Space Needle, USA: Olson
Kundig; 4. Rawang Bypass, Kanching Forest Reserve, Malaysia: Arup; 5. BLOX, Copenhagen, Denmark: Rasmus Hjortshøj; 6. Amorepacific Headquarters, Seoul, South
Korea: Noshe; 7. Brent Delta Platform Lift, North Sea, UK: Allseas; 8. Jaguar Land Rover Engine Manufacturing Centre, Wolverhampton, UK: Simon Kennedy.
Front cover image: Hong Kong-Zhuhai-Macao Bridge, Greater China: Marcel Lam Photography.

The Arup Journal Printed by Geoff Neal Group


Vol.54 No.1 (1/2019) Produced on FSC paper
Editor: Macdara Ferris and printed with vegetable-
Designer: Wardour based inks.
Email: arup.journal@arup.com

Published by Arup
13 Fitzroy Street
London W1T 4BQ, UK.
Tel: +44 (0)20 7636 1531
All articles ©Arup 2019

www.arup.com

You might also like