Professional Documents
Culture Documents
Arup Journal Issue 1 2019
Arup Journal Issue 1 2019
Arup Journal Issue 1 2019
Strengthening
connections
The Hong Kong-Zhuhai-Macao Bridge (HZMB) is the world’s
longest sea crossing. It promotes connectivity in a fast-growing
region, significantly cutting journey times in the Greater Bay Area
Authors Naeem Hussain, Steve Kite, Samuel Kwan, David Pegg, James Sze, Peter
Thompson, Fergal Whyte, Philip Wong, Ngai Yeung
On 23 October 2018, Chinese President Along the way, the firm had to be mindful of
Xi Jinping opened the world’s longest sea the scheme’s impact on the surrounding
crossing, the 55km Hong Kong-Zhuhai- environment and wildlife, the effect of
Macao Bridge. Until then, travelling extreme weather conditions on the
between Hong Kong and Macao/Zhuhai programme and design, and the logistical
involved either a one-hour ferry ride challenges of coordinating and completing
(sometimes through bad weather such a large and ambitious scheme – the
conditions) or a four-hour detour over the HZMB took nine years to construct.
Humen Bridge, a crossing to the north of
the Pearl River Delta. With the opening of Developing a Greater Bay Area
the HZMB, it is now possible to make the The HZMB is part of a broader effort by
journey by car in a mere 40 minutes. the Chinese government to improve
connections between 11 cities on the
Arup performed a range of roles on the Pearl River Delta: Hong Kong, Macao,
project, including creating and developing Guangzhou, Shenzhen, Zhuhai, Foshan,
the concept and preliminary design for the
main bridge and tunnel, and proposing
environmentally friendly reclamation
solutions for artificial island construction.
Arup also worked on roads, tunnels,
viaducts and other associated infrastructure. 1: The 55km HZMB took nine years to construct
1.
2: It was necessary to construct a 6.7km tunnel to 4: Xxxxxx xxxxxxxxxx xxxxxxxx xxxxxxxxxxxxx 4: The HZMB project has significantly cut travel
allow unobstructed navigation channels (Lingding xxxxxxx xxxxxx xxxxxxxx xxxxx xxxxxx xxxxxxx times in the Greater Bay Area
and Tonggu channels) 5: Xxxxxx xxxxxxxxxx xxxxxxxx xxxxxxxxxxxxx 5: The Jiuzhou Bridge is a cable-stayed bridge
3: An S-curved alignment was used adjacent to xxxxxxx xxxxxx xxxxxxxx xxxxx xxxxxx xxxxxxx with central sail-like towers and a central single
Hong Kong’s Airport Island to avoid constraints 6: Xxxxxx xxxxxxxxxx xxxxxxxx xxxxxxxxxxxxx cable plane
relating to the airport runway and the Government xxxxxxx xxxxxx xxxxxxxx xxxxx xxxxxx xxxxxxx
Flying Service Headquarters
Alluvium ˜105m
Band drains
9.
11. 12.
9: The Hong Kong Link Of the 725 piles used for this section of the When carrying out the box jacking, tunnel form to connect to the existing Lung The northern section is 5km in length and
Road was a complex project, 65 are on land (with a diameter of the team came up against extremely Mun Road in Tuen Mun and the future Tuen includes a sub-sea twin-bore tunnel between
part of the project, due 2.8m) and the remaining 660 are at sea, and hard bedrock that had to be excavated Mun Western Bypass. the BCF and landfall at Tuen Mun. Typically
to the geography of have diameters of 2.3m, 2.5m or 2.8m. The manually, as blasting was not an option 14m in diameter and reaching depths of up
the area and various
piles range from 7m to 107m in length. for the section underneath the railway. Arup was one of the designers for the to 60m below ground level, each tunnel
design constraints
An additional smaller tunnel was contractor of the southern section of the accommodates two lanes of traffic. They
10: To avoid any Part of the link road is tunnelled, minimising excavated inside the main tunnel, using TMCLKL, which comprises about 9km of were originally designed to connect with
construction footprint
the visual impact for local residents. It runs round-the-clock construction, to increase elevated viaducts. The southern section traditional cut-and-cover launch and
in an area of
archaeological interest
through Scenic Hill, under both the Airport the rock excavation faces and accelerate between Lantau Island and the BCF artificial reception shafts at either end within the
at Sha Lo Wan Express railway and the Airport Road. the overall rock excavation. This was island travels over 2km of water. The section newly formed reclamations. However, to
Headland, a special Different construction methods were used done at the same time as the box jacking that travels over land passes over existing speed up construction, the contractor’s
segment lifting frame for different sections of the tunnel. Drill and on the other side, so the work could railway lines at skewed angles, requiring design team modified the tunnel design at
was used to install the blast was utilised at Scenic Hill where the progress as efficiently as possible. spans of up to 100m. The viaduct structures the northern landfall by shifting the launch
bridge deck segments rock was particularly hard; mining were designed as prestressed concrete shaft 400m further north. This replaced the
techniques were used underneath Airport TMCLKL girders, which were constructed using the deepest section of cut-and-cover structure by
Road where the flow of traffic to the airport A new road was also required to precast segmental method. The southern extending the bored tunnel, significantly
needed to be maintained during tunnelling; accommodate the anticipated rise in traffic connection viaduct was designed with a reducing the amount of excavation and
whole tunnel box jacking – a controlled between Lantau Island and the North-West seagull theme: the supporting piers over the lateral support works required at this
shallow underground excavation process New Territories, a region of new towns and water are shaped like the maritime birds, location. The exit tunnel, which included an
that causes minimal disruption – was used development in Hong Kong, which will also with the span lengths gradually increasing additional climbing lane, was formed using
under the railway where there were railway serve as an alternative route to the airport. from the Lantau shore towards the Hong the world’s largest tunnel boring machine
tracks with stringent settlement requirements The proposal was for this link road to start Kong BCF to imitate seagulls flying over (TBM), which is 17.6m in diameter. To
to be adhered to; and an open cut-and-cover at the North Lantau Highway at Tai Ho, the sea. The longest span is 200m where create a large enough shaft to launch the
method was used in the new reclamation before running through the Hong Kong the viaduct spans the Tung Chung TBM (which required clear headroom of
area where there were fewer constraints. BCF. The road then travels northwards in navigation channel. 20m), Arup designed a bespoke caterpillar
10.
13: Arup developed the caterpillar diaphragm wall to combine these BCFs into a single board – created a working environment that With Hong Kong a well-known financial
cofferdam, creating sufficient unobstructed space artificial island of approximately 220ha. supported shared thinking, knowledge centre, Macao a major tourist destination,
to launch the world’s largest TBM In 2009, Arup won the detailed design exchange and critical review, leading to a and abundant development opportunities in
14: The 70ha Macao BCF is located on an consultancy to design the BCF’s design that was best tailored to the client the Pearl River Delta and the Greater Bay
artificial island infrastructure after developing the functional and the region’s needs. Area, the whole area is experiencing
layout of the 70ha Macao BCF. Arup considerable growth. The HZMB will
was responsible for designing the facility’s Increased connectivity encourage the connection of people and
viaducts, underpasses, roadworks, utility The HZMB provides the shortest link developments in this area. Being an
tunnel, drainage and sewerage, and between Hong Kong, Macao and the impressive structure in its own right, the
functional buildings. Arup also undertook western Pearl River Delta region. The bridge is also a tourist attraction, providing
the detailed design for the link road connection between Hong Kong, Macao magnificent views. It is hoped that this
diaphragm wall cofferdam – the first of its connecting the BCF to the new artificial and Zhuhai has been greatly improved, ambitious project will be the catalyst
kind used in Hong Kong. This cofferdam island, referred to as Reclamation A, significantly cutting the time it takes for for further growth and integration in the
comprised a series of circular interconnected which is located at the east of people and cargo to travel across the bay. area for years to come.
cells that formed an unobstructed strut-free Macao Peninsula.
excavation area by making use of hoop
stresses within the diaphragm walls to Management
maintain lateral stability. A project of this scale presented major Authors de Infra-estruturas, Macao SAR Government;
challenges when it came to management Naeem Hussain was the bridge design leader Hong Kong-Zhuhai-Macao Bridge Authority;
The twin-bored tunnels are connected by and logistics. Arup appointed a core for the HZMB main bridge. He is Arup’s global Gammon Construction Limited; Dragages-
cross-passages at 100m intervals that serve management team to focus on issues bridge design leader and an Arup Fellow. He is Bouygues Joint Venture
as a means of escape and allow access such as risk management, design a Director in the Hong Kong office.
between the tunnels during an emergency. coordination, cost control, planning Arup team
The original design had the mechanical and reviews, handling vast amounts of Steve Kite is Arup’s East Asia region highways Faux Abad, Andrew Armstrong, Sean Arnold,
electrical (M&E) equipment required for documents, interfaces and resources, business leader. He is an Associate Director in Che-Hung Au, Lukasz Bies, Eric Chan, George
the Hong Kong office. Chan, Ivan Chan, Ken Chan, Simon Chan,
tunnel operation located in every alternate and conducting quality assurance.
Li-Ling Chen, Fergus Cheng, Justin Cheung,
cross-passage. This would have resulted in Kayla Cheung, James Chim, Franki Chiu, Issac
Samuel Kwan was the Project Manager for the
two different cross-passage sizes, one with It was crucial to have a project and design TMCLKL southern viaduct section and the Choi, Timo Chow, Harry Clements, James
a larger diameter to facilitate the equipment review before every milestone, to make sure deputy Project Manager for the Hong Kong Link Collins, Derrick Dai, Mark Darlow, Ian Davis,
13.
rooms and the escape passage. To simplify everything was on the right track. A review Road. He is an Associate Director in the Hong Mark de Melo, Alex de Oliveira, Mo Ezzat, Corey
construction, Arup modified the design to panel was set up and the budgets were Kong office. Fan, Alfred Fong, Mike Ford, Henry Fung,
relocate the M&E equipment. By making assessed and refined to achieve the most Matthieu Galland, Nilda Galvez, Stephen Hope,
use of the void space created by the circular cost-effective solutions. Arup’s highly David Pegg was the Project Director for the Min Huang, Miro Huang, Erica Hui, Naeem
tunnel form, the equipment was placed collaborative approach – bringing a broad TMCLKL southern viaduct section and is a Hussain, David Ingram, Chris Jackson, Piers
within a service gallery in the carriageway range of disciplines and stakeholders on Director in the Hong Kong office. James, Sze James, Jesper Jensen, Duncan
Johnston, Gerald Kam, Micheál Killeen, Steve
inside the main tunnel with M&E islands
James Sze led the infrastructure team on the Kite, Samuel Kwan, Irene Lai, Isis Lai, Jack
every 200m. This allowed all the cross- Lam, Kaitlin Langdon, Michael Lau, Conor
detailed design for the man-made island for the
passage sizes to be the same smaller size, Hong Kong BCF. He is a Director in the Hong Lavery, Sam Law, Kitty Lee, Koon-Yu Leung,
facilitating easier operation and Arup technical services: Kong office. Terence Leung, Brian Li, Yingyan Li, Jeffrey Lo,
maintenance by providing a separate service Hong Kong Kin-Wang Lo, Ken Lu, Danny Lui, Lin-Fat Mak,
corridor for maintenance purposes only. Hong Kong BCF Reclamation: Feasibility Peter Thompson was the Project Manager for Laura Merry, Chryso Metta, Amanda Mo, Polly
Study, Overall Planning, Environmental the twin-bore tunnel section of the TMCLKL. He Mok, Alex Morris, Fokker Ng, Sandra Ng,
A mini-TBM was used to construct Impact Assessment, Preliminary and Detailed is a Director in the Hong Kong office. Declan O’Shea, Josh Palmer, David Pegg, Sue
the cross-passages, rather than mined Design, Construction Contract Procurement Poo, Jacek Przysiezny, Victoria Richardson,
construction with ground freezing and Supervision Fergal Whyte was the Project Director for the Emily Roberts, Rob Ryan, Denis Shapley, Victor
Hong Kong BCF: Feasibility Study, Overall HZMB main bridge and the Hong Kong BCF, Shea, Dora Shum, Michelle Shun, Gopal
(traditionally used for sub-sea tunnels).
Planning, Environmental Impact Assessment, and the Project Manager for the Hong Kong Srinivasan, Raymond Sy Guan, James Sze,
This method reduced construction risk, Sherry Tang, Peter Thompson, Tom Tong,
Preliminary Design Link Road. He is a Director in the Hong Kong
improved efficiency and significantly cut Hong Kong Link Road: Feasibility Study, office and a member of the Arup Group Board. Eric Tsang, Iris Tse, Alessandra Villa, Mark
construction time. This was the first project Overall Planning, Environmental Impact Wallace, William Wei, Fergal Whyte, Heather
in Hong Kong to use a mini-TBM for Assessment, Preliminary and Reference Philip Wong was the Project Director for the Wilson, Christopher Wong, Desmond Wong,
cross-passage construction. Design, Design & Build Contract Macao Link Road and the Project Manager Josephine Wong, Philip Wong, Tim Wong,
Procurement and Supervision for the Macao BCF. He is a Director in the Alastair Woodland, Christian Wrede, Ngai
Macao BCF and link road TMCLKL: Feasibility Study, Detailed Design Macao office. Yeung, Damon Yung, Cesar Zamora, Heng
In 2006, Arup was appointed by the Macao Zang, Ying Zhou.
government to undertake a feasibility study Zhuhai Ngai Yeung worked on the HZMB main
for the Macao BCF and the associated link HZMB Main Bridge Preliminary Design bridge and is an Associate Director in the Image credits
Hong Kong office. 1-3, 5, 12: Marcel Lam Photography
roads to the city. The original scheme had 4, 6-9, 11: Arup
Macao
proposed two separate BCFs for Macao Macao BCF infrastructure: Overall Planning, Project credits 10: Dragages-China Harbour-VSL JV
and Zhuhai, on two artificial islands. Arup Preliminary and Detailed Design Clients Highways Department, Hong Kong SAR 13: Dragages-Bouygues JV
rationalised this complex plan, following Macao Link Road: Detailed Design Government; Gabinete para o Desenvolvimento 14: CHEC
the decision by the Chinese government
14.
Located in a prime section of Copenhagen’s cantilevers, long spans, unaligned grids and Arup provided structural, building services and
harbour area, BLOX is a six-storey mixed- double height volumes. The building was façade engineering; sustainability consultancy
use building that is part of an exciting officially opened by the Queen of Denmark services; ICT and AV; vertical transport;
waterfront regeneration in the city. The in May 2018. security; and daylighting, from inception to
27,000m2 venue is the new home for the detailed design. The firm produced design 2.
Danish Architecture Center (DAC) and Working in close collaboration with the solutions for and provided input on topics
BLOXHUB, a new creative workspace Office for Metropolitan Architecture including energy efficiency, carbon neutrality,
initiative for companies, research (OMA), Arup’s engineering expertise helped materials and embodied carbon. Arup also Its location, locked in by the harbour and within the building. The staggered pattern number of one- and two-storey deep trusses
institutions and organisations involved shape a complex regeneration project that sought to address socioeconomic issues. canal, with a busy arterial road bisecting the that forms the building’s terraced landscape with depths varying from 2.4m to 8.4m. These
in sustainable urban development. overcame the constraints that challenged the site, presented considerable challenges for shape, the road through the building and the create large column-free spaces within the
viability of the site for development. BLOX Site development development. Most recently, the site included deep basement car park all put considerable building and also bridge over the road.
The building features an auditorium, spans over and under the busy Christians Philanthropic association Realdania invested a 350-space street-level car park and a small constraints on where columns could be
exhibition spaces, cafés and offices, as well as Brygge ring road, with the site perimeter in BLOX to help regenerate this section of the children’s playground. located and how loads could be transferred The structural frame comprises steel beams
22 apartments across the top floors, and framed on two sides by the city’s harbour waterfront and strengthen the connection down to the foundations. and columns with precast concrete floor
recreational indoor and outdoor areas. These wall and the Frederiksholms canal. Located between the inner city and the harbour. Structural frame planks. The structural floor plate depth is
differing spaces are arranged as a series of close to a series of historic buildings, the Originally, the site was home to the royal Arup worked closely with OMA to With a conventional grid structure not feasible typically 400mm, with the beams located
stacked cubes that form a terraced landscape, ground works in particular had to be dealt brewery, Kongens Bryghus. The buildings rationalise the structural layout so that it because of the overlapping volumes and within the depth of the planks to reduce the
requiring a structural scheme with significant with sensitively. were demolished after a fire in the 1960s. would support the series of stacked volumes column-free spaces required, Arup developed overall floor volume. The planks in the offices
a scheme comprising an interconnected were grouted together without the need for a
system of transfer structures. By using a structural screed topping.
number of interventions such as downstand
beams, trusses and hangers, an initial 48 truss Due to the complex interface between the
solution was developed. With a working trusses, Arup’s structural team devised a
scheme in place, the challenge was to reduce construction sequence in collaboration with
the number of trusses to ensure construction the main contractor, Züblin. To determine the
viability and improve efficiency. stresses that would build up in the steel frame
during its assembly, Arup created a digital
Through further detailed design and model of the construction sequence.
rationalisation, the grid was re-aligned and the
trusses optimised, with Arup’s final scheme an With the transfer structures and complicated
interconnecting framework of 18 steel trusses load paths, it was crucial that deflections were
that typically span 30m. They include a controlled as stresses became locked in while
1. 3. 4.
Bridging over and under the road 9: BIM model of the exhibition hall showing the
One of the key elements to developing the site layout of the trusses
was to design a scheme that could span over 10: The exhibition hall being set up for an event
and under the ring road, allowing pedestrians
11: The precast concrete floor in the hall has a
access to the harbour without having to cross reinforced concrete structural topping. This assists with
a road that is used by more than 25,000 acoustics as well as the floor’s dynamic performance
vehicles a day. 11.
12: BLOX is made • appropriate intake and exhaust locations 15: Arup used its Sustainable Project Appraisal
up of a series of and separations to ensure effective Routine (SPeAR) to track sustainability throughout
stacked volumes ventilation (a particular challenge the project
13: 3D rendering of given the proximity to the road); 16: BLOX has helped to transform a previously
vibration analysis • a high performance building envelope; neglected section of Copenhagen’s waterfront
for events in the • low water consumption; and 17: ‘Ove Arup and the Philosophy of Total
exhibition hall • improved local amenities and activation Design’ exhibition
14: BIM model of public spaces.
of the building
services BLOX is close to public transport, adding to Ove Arup exhibition
its sustainability credentials. The mixed-use
development promotes social integration, as From October 2018 to February 2019, the
the publicly accessible pedestrian route Danish Architecture Center hosted an
running through the building creates a new exhibition on Ove Arup that celebrated the
link between the city and the harbour. pioneering work and ongoing legacy of the
Anglo-Danish engineer and designer.
The mechanical services required careful
design to manage the variety of uses for 15. 16. The exhibition, ‘Ove Arup and the
the different spaces within the building. Philosophy of Total Design’, was first
The layout is predominantly office space shown at the Victoria and Albert (V&A)
around the building’s perimeter, with the insulated façade. The performance of Transformation Museum, London, in 2016 and provided
large DAC exhibition space, auditorium the façade required careful consideration BLOX has transformed this section of an overview of Ove Arup’s vision of ‘Total
and conference facilities located at the in order to achieve the correct level of Copenhagen’s waterfront into an inviting Design’. The exhibition revealed Arup’s
centre of the building. The ground floor light transmission into the building to space for people to visit. In addition to collaborative approach to problem-solving
includes a gym, restaurant and some retail meet required lighting levels under providing the new pedestrian link between in the built environment by harnessing
spaces. Along with the basement car park, Danish regulations, while also maintaining the city and the harbour, a new urban the creativity and technical prowess
12. each of these areas have different drivers the appropriate U-value (thermal) and playground offers a safe space for play of engineers, architects, urban
and requirements from a comfort and G-value (solar gain). Eight façade during the day, turning into a stage or planners, designers, consultants and
occupancy level. configurations were assessed across amphitheatre seating in the evening. technical specialists.
criteria including energy, daylight, cost, The building draws in visitors and is a
Plant and building services maintenance and aesthetics to determine landmark publicly orientated mixed-use The exhibition featured archival materials
The mixed-use nature of the building, and the the preferred option. building in the Danish capital. from iconic projects such as the Sydney
constraints of the road, meant that locating Opera House and the Centre Pompidou in
plant and developing the building services Paris. Also displayed were digital exhibits
distribution strategies were critical to overall featuring simulations and augmented
space planning and developing an efficient reality that captured some of the most
Authors Duncan, Russell Fraser, Lesley Gale, Kieran Giblin,
floor plate. Plant areas were located in Michael Bradbury was the Project Manager and Andrew Grant, Duncan Gray, Ning He, John innovative infrastructure projects Arup has
various parts of the building. The basement lead building services engineer. He is an Heath, Stuart Hitchcock, Ed Hoare, Christina contributed to in recent times. They
has the main connections to the district Associate Director in the London office. Hsieh, Dan Ingall, Craig Irvine, Ben Jones, Ben included a specially commissioned
heating and cooling, along with ventilation Kaggwa, Adri Kerciku, Vivien Kwan, Amy Leitch, immersive installation about the Øresund
plant that serves the basement and the Chris Carroll was the Project Director. He is a Ben Lewis, Roland Li, Alexandra Lindesay- Bridge and a recreated Arup SoundLab®
13. restaurant areas. Additional plant is located Director in the London office. Bethune, Di Liu, Ian Lockwood, Georgina presenting a range of acoustic studies,
under the auditorium, with smaller plant areas Lockwood, Paul Lynch, Mani Manivannan, Adam including of the BLOX building and
Project credits Martin, Nina McCallion, Ben Moss, Sheyda Okke,
serving the offices and apartments. Copenhagen city.
Client Realdania Julian Olley, Jean Parker, Dean Payne, David
Architect OMA Penn, Stuart Pennington, Clare Perkins, Dan
With quite a deep plan for the building, Pook, Tony Pullen, Rob Quail, Nihal Rajapakse,
Local architect CF Muller
chilled ceilings were used in the majority Vincenzo Reale, Tony Ricchetti, Amelia Rushford,
Traffic, environmental issues, fire, risk
of areas for cooling, with fresh air provided analyses and local engineer of record COWI Anokhee Shah, Amy Shen, Jamie Shewan, Tania
through the floor (along with distribution Contractor Züblin Smith, Julian Sutherland, Mark Thomas, Mutlu
for power and data). Chilled beams were Structural, building services and façade Ucuncu, Nick Unsworth, Manja Van De Worp,
used around the perimeter to provide engineering, and sustainability consultancy John Verniers, James Whelan, Robin Wilkinson,
additional cooling at the façade. services, ICT and AV, vertical transport, Giovanni Zemella.
security, daylighting Arup:
The main exhibition space uses Yasmin Alam, Francis Archer, Marcus Arvidsson, Image credits
displacement vents to distribute air, with Bibi Banjo, Jonathan Ben-Ami, Daniel Bergsagel, 1, 10, 16: Rasmus Hjortshøj
Michael Bingham, Kimberley Blackburn, Philip 2: Søren Svendsen
sidewall displacement vents used in the
Bogan, Michael Bradbury, Alexis Brown, Emma 3, 4, 8, 9, 13-15: Arup
auditorium. The restaurant and apartments 5-7: BLOX/Dragør Luftfoto
Brunton-Reed, Giorgio Buffoni, Chris Burgess,
have their own dedicated systems. Tony Campbell, Stuart Carey, Chris Carroll, Andrea 11, 12: Delfino Sisto Legnani and Marco
Charlson, Mark Chen, Anna Coppel, Dominic Cappelletti/OMA
Detailed thermal analysis was key to Coyle, James Dare, Rica Dela Cruz, Andrew 17: Camilla Hylleberg
17.
achieving a naturally ventilated and highly
14.
Factory frame
The factory halls are based on a single- services the roof can support. The bracing optimised all the truss members. The wind
storey braced frame, supporting multi-span is kept at the perimeter, which allows for the analysis carried out on the roof took into
mono-pitched roofs, with trusses designed subdivision of bays and means the assembly account the roof’s specific geometry and
for multi-bay continuity. The north-lights lines can be reconfigured if required in peak wind direction for the site, allowing
are formed using steelwork trusses that future. Arup developed a loading manual for uplift loads on the roof to be reduced by up
span 30m. In the machine hall, the grid is Jaguar Land Rover that sets out the design to 70% for the majority of the surface
30m by 15m, with a 30m by 30m grid load locations and magnitudes. area. These design processes resulted in
in the assembly halls. This arrangement significant savings, minimising the
facilitates the production areas currently In designing the roof trusses, Arup took steelwork roof tonnage. At 28kg/m2, the
required by the client, giving clear spans the structural analysis output and, using roof weight is light for a 30m-span roof
without compromising the quantity of automated member utilisation checks, that supports the quantity of services
3.
energy consumption and providing located 3m above floor level. To reduce amount of work required to be carried out
significant carbon savings. airborne contamination within the machine at height.
and assembly halls, the supply air is filtered
This Colourcoat Renew SC cladding system, through class F9 filters – the level below a Energy monitoring
developed by Tata Steel and the University cleanroom environment. Arup developed an energy management
of Swansea’s Innovation Centre, heats 5m3/s system in conjunction with Jaguar Land
of supply air, producing carbon savings of A gas-fired heating system, rather than Rover to allow the client to monitor building
1 tonne per 5m of solar collector. The a more traditional water-based system, energy consumption and energy used in each
Machine Hall (30m x 15m Grid) Assembly Hall (30m x 30m Grid)
system has also been used on the third phase was used to serve the production halls. process of engine production. The system
Building Access – Main Halls Building Access – Main Halls of the project. A water-based system would have had design included the communication
the potential for significant heat and infrastructure for the process equipment to
Dynamometers pumping losses due to the length of the support Industry 4.0 implementation, as well
As part of the engine testing regime, a pipe runs required for a facility of this size. as the metering and monitoring mechanisms
sample of engines produced at the factory The gas heating system overcame this for all the building utilities. Arup’s Building
are tested using dynamometers. Arup issue, particularly as the gas distribution Performance and Systems team were
worked with Jaguar Land Rover to design system was already required to serve commissioned after handover to carry out
the system that takes the energy generated process equipment. monitoring of the energy performance in the
during testing and feeds it back into the operational building and collate feedback
building’s energy distribution system. Where possible, high-level services were from users. This work identified
supplied using modular technology. Arup’s opportunities to reduce further electricity
Heating and cooling detailed design allowed for modules to be and gas consumption.
The machine hall is heated from an all-air manufactured off-site to facilitate a quick
system with the heating diffusers located 3m and safe installation on-site. This method Digital design
above the factory floor. Six AHUs supply allowed for factory inspections prior to The structural steel frame design was highly
85m3/s of air to the space. This volume of delivery on-site, and also reduced the automated. Optimisation of design input to
Clear Way Finding & Access Strategy Daylighting & Roof Design air is required to maintain a 20°C
Building Access – Offices & Staff Support Facilities Natural Light & Dynamic Roof Form temperature in the machine hall, and also to
provide make-up air to supplement the
6. extract system that removes the oil mist
created during the engine manufacturing
process. Fresh air, with 0.25 air changes per
required for this highly automated Renewable energy hour, is also fed into the machine hall for
manufacturing facility. Total design As part of an initial energy study, Arup staff comfort levels. During the winter
identified the potential for significant carbon months, the manufacturing equipment in the
Staff support areas Arup applied its total design philosophy savings by using a roof-mounted PV array machine hall provides heat to the space,
The connecting staff support buildings are to deliver technically creative and and solar thermal installation on the façade. with gas-fired AHUs providing top-up heat
bright, naturally ventilated two-storey sustainable solutions at speed. as required. In the summer, vents in the
spaces. Arup designed the bulk of the heavy Innovation, collaboration and worker More than 21,000 PV panels were installed north-light windows can be opened to expel
plant – servicing the factory halls – to be wellbeing is at the heart of the success on the south-facing areas of the roof. These hot air, helping to reduce extract energy.
located at the first floor and on the roof. This of this facility, which has won provide over 5.3MW of power – equivalent
gives easy access to plant for maintenance numerous awards. to 30% of the facility’s energy requirements The assembly halls are heated and cooled
and avoids the need to put heavy plant on – and reduce the factory’s carbon footprint using a displacement ventilation system,
the long-span roof trusses. The structure 2018 by at least 2,400 tonnes per year. Further with five AHUs supplying 71m3/s of air. To
supporting the plant consists of precast Structural Steel Design Awards: power is supplied via a ground-mounted PV maximise the facility’s future flexibility and
hollowcore concrete slabs. The exposed Winner, Project of The Year array, added as part of the most recent phase adaptability in relocating process plant and
thermal mass of the concrete slab soffit World Architecture Awards: of works. Solar thermal panels also provide layouts, the displacement terminals are
helps with moderating temperatures in the Shortlisted, Production Energy and heating for domestic hot water.
office areas, further reducing energy costs. Recycling Category
Solar cladding
Arup’s architectural design of the staff 2017 The factory features a transpired solar
support areas provides a working CIBSE Building Performance Awards: collector cladding system, which is used to
environment that brings people together by Winner, Project of the Year preheat the supply air to the staff changing
providing visual transparency and social Royal Institute of British Architects facility. Used on the south-facing façade of
spaces. These areas have natural light and Awards: Winner, West Midlands the staff support building, the outer steel
ventilation, with glazing providing Sustainable Award and Regional Award layer of the system is a dark perforated
transparency between the office areas and profiled steel sheet. It is separated from the
factory floors. Automated dimming controls 2014 inner insulated layer by an air cavity. Solar 6: Arup, in conjunction with the client, developed
for the lighting system reduce the need for Royal Institution of Chartered energy warms the perforated steel skin and an overall facility layout that focused on efficiency
artificial light, creating further energy Surveyors National Awards: the air in the cavity, and a fan at high level and future building flexibility
savings, with LED lights specified in the Regeneration Project of the Year draws the warm air out. This preheated air 7: The assembly hall has a 30m x 30m
most recent development phase. feeds the AHUs in these areas, reducing structural grid
7.
9.
Authors Architecture, transport planning, environmental, Liebana, Mark Lusher, Sean Macintosh, Colin
Mark Bartlett was the lead electrical engineer and landscaping, and access advice (Phase 1 and Magner, Alice Malaiperuman, Rajiv Malik, Natalia
the Project Manager for the third phase of the 2); civil, structural, geotechnical, security, Mambrilla, Mei-Yee Man Oram, Ann Marie Aguilar,
development. He is an Associate Director in Arup’s sustainability, fire and building services Barbara Marino, Tony Martin, Curtis Martyn, Paul
Midlands Campus in the UK. engineering (for all three phases) Arup: Matthews, Alex May, Andrew McAleer, Rachael
Muhammad Abdullah, Jorge Albert, Mehdi McAteer, Chris McCarthy, Gary McCarthy, Laura
James Finestone was the Project Director for the Alhaddad, Steve Allen, Simon Anson, Dimitri Mino, Jessica Monk, Philip Monypenny, Mostafa
first phase of the development. He is Arup’s Argyros, Nohman Awan, Yiannis Baltagiannis, Andy Moradalizadeh, Adina Nimas, Julia Novitchenko,
Europe region leader for architecture and is based Barnes, Daniel Barnes, Greg Barnes, Mark Bartlett, Carlos Nunes Baptista, James O’Hanlon, Johnny
in the Milan office. Gill Blackburn, Mark Bowen, Richard Boyd, Tom Ojeil, Nick Olson, Petra O’Sullivan, Constance
Brooks, Gemma Broughton, Alexis Brown, Alex Pang, Yesol Park, Yona Park, Andy Payne, Tom
Philip Hives was the lead mechanical engineer and Bunn, Kevin P Burke, Josh Chapman, Sean Pearce, Anett Pengelly, Oliver Pengelly, Ryan Perry,
Project Manager for the second phase of the Chapman, Wayne Charles, Sam Collett, Carl Chris Powell, Jan Pratt, Sean Preece, Georgie
8. development. He is an Associate Director in Arup’s Collins, Jose Pedro Conceicao Dos Santos, Tiago Price, Danny Quartermaine, Mario Querol, Jon
Midlands Campus in the UK. Contins Teixeira, John Corbett, Tian Coulsting, Rhodes James, Colin Roberts, Paul Robinson,
Arron Croft, Dominic Cropper, Sebastian Alberto Rossi, Luca Rossi, Dave Runaghan, Anand
Sean Macintosh is a Senior Architect in the Cumpatescu, Hal Currey, Hazel Dalton, James Sagoo, Tanvir Saini, Neil Scott, Andrew Sherratt,
London office. Davies, Sean Davies, Steven Davies, Matthew Michael Shuster, Lee Smith, Tim Snelson, Joaquin
the analysis models was driven from carried out BIM management services data tagging of equipment and services
Davis, Jo Dicken, Natalia Duffy, John Edgar, Ed Soria Diaz, Chris Stanford, Michael Stevens,
spreadsheets, to minimise the risk of manual on behalf of the main contractor, for use post-occupancy. This ensured Elbourne, Karim Elgendy, Steve Fancourt, David Calvin Stewart, Susanne Stolper, David Storer,
Timothy Snelson was the lead structural engineer
input errors. Subsequent results from the Interserve. The subcontractors’ work the client’s facilities management team and Project Manager for the first phase of the Farmer, Ben Fenech, James Finestone, Kate Craig Stott, Eric Sturel, Mike Summers, Steven
analysis were post-processed through was coordinated throughout the delivery could utilise all the design information development. He is an Associate Director in the Fletcher, Bob Flynn, Helen Foti, Sally Friswell, Swan, Martin Tarnowski, Thomas Taverner, Scott
spreadsheets for utilisation checks. Designing of the project, and also with the fit-out embedded within the model. London office. Carolyn Gallehawke, Amparo Galvan Nieto, Thirtle, Xing Tong, Bernard Travers, Sara Turnbull,
in this digital environment allowed changes requirements of the highly specialised Andrew Gardiner, Stephen George, Marten Ryan Turner, Tijl Uijtenhaak, Dora Vagiou, Michael
to be incorporated into the design as the client robotics used for engine manufacturing As the manufacturing process changed David Storer was the Project Director for the second Gessen, Andrew Gibbon, Daniel Goodreid, Jack Wadsworth, Julie-Anne Walker, Killian Walsh, John
updated their manufacturing requirements (which were designed by PowerTrain during the design phase, the digital and third phases of the development. He is a Director Goulding, Aidan Griffin, Paul Grosvenor, Craig Walton, James Watts, Marcos Watts, Chris Webb,
during the design process. The structural for Jaguar Land Rover). The design design elements were used to take in those based in Arup’s Midlands Campus in the UK. Harkness, Mike Haydon, Christopher Hayward, Luke Webster, Mel West, David Wheatley, Joe
model was produced directly from the model was integrated with the process changes to minimise the potential of any Andy Heath, Cameron Heggie, George Hemsley, Wheelwright, Deborah White, Sam Williams, John
Project credits John Higginson, Philip Hives, Thomas Howes, Woodman, Darren Wright, Mat Wright, Evangelos
analysis model and exported to Tekla and equipment model. This allowed delay. For example, when another 30m bay
Client Jaguar Land Rover Ltd Callum Hulme, Alan Jefcoat, Ian Jenkins, Joao Zacharis, Akhtar Zaman, Dima Zogheib.
software for production of the fabrication coordination of process machinery and was added to the building, the automated Jesus, Ben Johnson, Matt Jones, Elida
Project manager Stace
drawings, thereby saving the steelwork services, along with the building services work flow enabled the design checks to be Quantity surveyor (AECOM – formerly Davis Karaivanova, Abdullah Khan, Michael Kinney, Image credits
fabricator significant modelling time. and structural frame. The fully integrated carried out quickly. The models were Langdon) Maciej Krezolek-Shrewsbury, Martin 1, 7: Jaguar Land Rover
model was issued as part of the completed updated to reuse already manufactured steel, Main contractor Interserve Construction Ltd Kuzmanov, Jason Kwong, Samantha L Godden, 2, 3, 8, 9: Simon Kennedy
The complete building was modelled project’s operation and maintenance and the new bay was inserted as the (Phase 1 and 2); Vinci (Phase 3) Oliver Lawrie, David Lee, Matt Lewis, Alvar 4, 5, 6: Arup
in BIM. At construction stage, Arup manual and included specification and penultimate bay.
A dramatic refresh of
Seattle’s Space Needle
The use of cutting-edge techniques in the renovation of Seattle’s most iconic
structure has readied it for the next 50 years of its life, and means that the original
concept for the Space Needle has finally been achieved
Authors Peter Alspach, Clayton Binkley, David Okada, Kristen Strobel, Cress Wakefield
A landmark on the Seattle skyline, the The general contractor, Hoffman team. Arup provided on-call support to the 2.
Space Needle was built for the 1962 World’s Construction, worked around the clock on a contractor that at times included three-shift
Fair and stands 605ft (184m) above the city. tight schedule that avoided the peak tourist support for the 24-hour construction period.
It is the globally recognised symbol of Seattle season. The Atmos stayed open to the public
and attracts more than 1.3 million visitors throughout. This 11-month period required 520ft level
per year. The Space Needle Corporation constant communication and collaboration The work at the 520ft level included installing
engaged architectural firm Olson Kundig to between the owner, contractor and design new stairs, an accessible lift and increased
help them create a new vision that would interior glazing, as well as the replacement of
preserve the building’s historic exterior while the exterior safety barriers at the external deck
revolutionising the guest experience and with glass vertical barriers featuring integrated
clarifying the original conceptual design glass ‘Skyriser’ benches. One of the primary
vision. Arup collaborated closely with the
Space Needle goals of this work was to restore the
architects on the renovation, designing a renovation facts transparency envisioned in the conceptual
3.
seismic retrofit, accessibility upgrade and sketches for the original design, while making
modernisation of building services. The firm 605 Height of the Space Needle, in feet all public areas step-free and fully accessible
provided structural, mechanical, electrical for the first time.
and plumbing engineering, as well as 1,300,000 Visitors to the Space Needle
building physics and fire consulting. each year The quest for transparency extended beyond 1. Existing Truss
5. 6. 7. 10. 11.
5: Repairs were made to parts of the existing maintaining public access to the observation allowed the damaged tubes to be cut away and Arup created a detailed finite element model they be cleanly detailed and as small as no longer an option, as the cavity below
structure that were found to have corrosion damage deck throughout construction. new sections welded in place without any of the canoe beams to determine their lateral possible, to minimise any visual obstruction. the rotating floor was now visible.
6 & 7: The knee-high walls were replaced with additional shoring. The modification also torsional buckling capacity and ability to
glazing to optimise views When standing on the observation deck, the included architectural detailing to improve resist the increased weight of the rotating floor Providing thermal comfort across the range The air distribution approach was refined to
8: Arup carried out detailed flexural buckling guests’ view to ground level is through the drainage and prevent future water intrusion. with reduced out-of-plane bracing. Several of possible operating conditions was the incorporate separate linear supply diffusers
analysis of the canoe beams signature ring of louvers, also known as the retrofits were installed to strengthen the focus of Arup’s mechanical design in this for heating at the perimeter windows, cooling
9: Construction sequence for installation of the halo, that gives the Atmos its distinctive flying 500ft level existing canoe beams, with welds added to the space and required careful consideration supply diffusers toward the interior and a
Oculus Stair opening saucer shape. During construction, significant The 500ft level was redeveloped into a flexible bottom flange to allow the structure to support due to the increase in the glazed surface return airflow path at the centre of the
corrosion, water infiltration and freeze/thaw space that can serve as either an observation clamps for rope-access maintenance loading. area at this level. The original heating, structure. All air distribution elements
damage was discovered in the rectangular deck or dining area. The original (opaque) ventilation and air conditioning system are coordinated with the sculpted ceiling
tube sections of the halo structure that make rotating floor at this level was replaced with The The existing strap bracing diaphragm below the provided heating at window sills from fan contour. Arup’s building physics team used
up the last panel of the radial trusses Loupe – a new glazed floor and soffit that rotating floor was replaced with stainless steel coil units located in the cavity below the computational fluid dynamic (CFD) analysis
supporting the observation level. With the allows views through the structure to the ground tension rods. As these rods are visible below the rotating floor and cooling via large round to optimise the design and ensure a
building opened up and these zones accessible 500ft below. The new design also includes taller glass floor, it was architecturally important that ceiling diffusers. Underfloor services were comfortable guest experience.
via scaffolding, Arup was able to conduct a windows and updated architectural finishes.
full survey of all trusses. The team designed a Steel plate shear walls have replaced the
retrofit scheme including a temporary support existing concrete wall to improve seismic
structure that relied on adjacent trusses and performance and allow penetrations that 10: The glazed area was increased by 200%,
8. increase circulation and improve access. providing visitors with magnificent
unobstructed views
The structure of the building at this level 11: CFD analysis of air distribution at the
consists of a 66ft diameter box-section ring 500ft level
beam that rests on top of the main tower legs. 12: 3D model showing the complex
Inboard of the ring beam, six radial box beams interaction of building services in the Atmos
connect the ring beam and legs to the central
core of the tower. Outboard of the ring beam,
48 tapered radial built-up beams, dubbed
1.1.Existing
Existing 1. Existing
1. Existing
Framing1.
Framing Existing
Framing
Framing Framing 2.2.Demo
Demo 2. Demo
2. Demo
Slab
Slab 2. Demo
Slab Slab Slab 3.3.Shore
Shore 3. Shore
3. Beams
Shore
Beams 3. Shore
BeamsBeamsBeams 4.4.Install
Install 4. Install
4. Beams
Install
Beams 4.
Beams
and
andInstall
Beams ‘canoe
and andbeams’ for their shape, cantilever out
andBeams
and
andDemo
Demo and Demo
and Demo and Demo Core Core Core
CoreConnections
Connections
Core Connections to support the rotating floor.
Connections
Connections
Services upgrade
A comprehensive building services upgrade was
required due to the age of the building as well
as the extent of interventions across all the
levels in the Atmos. The main service level is
between the 520ft and 500ft levels, with plant
located between the radial trusses supported off
14. 15. the storey-deep ring girder.
These stairs are highly trafficked, as most 16 & 17: Stair top connection
visitors arrive on the 520ft level and walk down detail – shown under normal and
the staircase to exit via the elevator lobby on the seismic loading
500ft level. With the staircase such an important
circulation path, Arup paid particular attention
to its dynamic response across a range of
loading conditions. The finished stair looks light
but feels solid underfoot.
Century Project
The redevelopment was dubbed the ‘Century
Project’ and was just that – a comprehensive
renovation that looks back to the structure’s
historic vision and first half century of
operations to set the stage for the next 50 years
and beyond. Final phases of the project will
include updating the elevators, repainting and
a roll out of a new dining experience at the
500ft level on The Loupe.
Authors
Peter Alspach was the Project Director. He
is a Principal in the Seattle office.
34
BRENT DELTA PLATFORM LIFT | NORTH SEA, UK
1.
2: Underdeck and GBS legs of Brent Delta strengthening works required post-cut, prior 6: Section through
3 & 4: 3D non-linear finite element model of to the removal of the topside of the platform Loading Plate
the concrete ring
transition piece, strengthening and concrete shaft from its supporting structure. 650x650x65 beam showing the
80
800 Steel Ring Beam connection details of
5: Shear restraint inspection at the manufacturer 160mm deep L800x500x70x40
Topside removal design development existing Transition
the steel ring beam
(S460)
Arup began the project with a workshop, Piece 40 760
7: Shell’s Brent
which resulted in over 30 design proposals. Delta platform in
70
Using a qualitative assessment, these the Brent field prior
to topside removal
Arup supported the decommissioning of were then rationalised down to the five Grout
500
the platform by designing the strengthening most viable solutions. Following scoping
250
430
required to enable cutting the three calculations and after agreeing relevant
supporting concrete legs to allow the selection criteria with the client, Arup used
100
separation of the topside from its supporting a trade-off matrix to select the preferred 300 M20 Grade 8.8
3: Part of the bridge travels over the existing federal 7: The Rawang Bypass reduces peak time
trunk road. In order not to disrupt traffic, a cantilever journeys to Kuala Lumpur by 90 minutes
method of construction was used at this point
4: Box girder construction was used for the bridge
section above the federal trunk road
5: Typical bridge deck cross-section at pier location
6: To avoid extensive earthworks and minimise
deforestation, the high-level bridge deck was
constructed using a movable scaffolding system
Foundation and pier construction
Having determined a more sustainable route
for the bridge, it was important that the
Department and NGOs such as the World
construction process also had a minimal
Wildlife Fund (WWF).
impact on the area by avoiding extensive
earthworks and deforestation. For the
Arup devised an elegant solution to the
construction of the pier foundations, Arup
problem: an elevated bridge structure over
devised a method that avoided using heavy
the outer fringes of the forest, moving the
3. machinery on site, reducing disturbance to 7.
route initially suggested by the Public Works
the forest’s ecosystem. With the mountainous
Department down to the foothills of the
terrain, it would have been difficult to
In 2005, the state government designated the revisit the concept design and review the forest. This ensured that the bypass would However, the 51st to the 53rd spans required breathtaking views over the forest, the
manoeuvre large machinery on site. This
forest as an official heritage site, meaning no road alignment. For Arup, the challenge was be located at the edge of the heritage area, a different construction method. With the bridge has received resounding public
would have required removing trees and
major development that could affect the to redesign this vital bypass to minimise reducing the need for forest clearance. bridge at this point travelling over the approbation and the approval of
levelling the ground, with this latter activity
reserve’s ecology was allowed. deforestation, ensuring little impact on the existing federal trunk road near Templer Park organisations concerned with protecting
having the potential to cause soil erosion.
environment during the construction phase This amended route required the road at a skewed angle, an MSS could not be used wildlife and preserving the environment.
Finding a solution and after handover. structure to be raised significantly above the Rather than using piled foundations, which due to the large 114m span between piers. In Arup’s strategy for the construction meant
Although the road was an essential part ground to match the vertical alignment of require large drilling equipment, light addition, as an MSS is an underslung system, that deforestation and earthworks were
of improving Malaysia’s transport Finalising the design took almost a year the other sections of the road. The final machinery was used to dig caisson foundations. steel frames hung below the bridge had the minimised. Passing high amid the treetops,
infrastructure, the risk was that any and involved an intense process of engaging design included a 2.7km elevated structure The construction works could therefore be potential to interfere with the headroom of the elevated bridge respects the ecosystem
construction work would require extensive with the Malaysian central government and supported by piers that are up to 58m tall. spread over a smaller area than would otherwise vehicles travelling on the road below. A more below, as well as easing congestion in the
deforestation, resulting in an unacceptable other interested parties. Through meetings, This makes it the longest and highest bridge be necessary. This method required only a conventional balance cantilever method of adjacent town, cutting peak journey time
impact on the natural environment. The presentations and public hearings, Arup in Malaysia, with vehicles on this section of narrow 50m corridor for the construction of the construction was used at this location, with through this area by 90 minutes. In
Malaysian Public Works Department, which gathered input from public representatives, the road almost level with the treetops of the foundations and bridge piers. The foundations the remainder of the spans built using completing the project, Arup has designed a
commissioned the project, requested Arup local authorities, the country’s Forestry surrounding forest. range between 1.7m and 6m in diameter, and traditional inverted-T post-tensioned beams. piece of infrastructure suitable for the needs
were dug using jack hammers and hydraulic of Malaysia’s ambitious, fast-growing
rock breakers. The piers were built using Arup’s design allowed the project to progress economy, without causing damage to the
slipform construction, allowing each pier to be as quickly and efficiently as possible, ensured country’s ancient natural heritage.
constructed quickly, safely and accurately. minimal disturbance to the forest’s ecological
system and permitted access for animals to
Movable scaffolding system travel below the bridge during construction
With the need to avoid extensive earthworks and following completion of the works.
and deforestation fundamental to the choice Author
of construction method, a movable Collaboration Wan Anuar bin Wan Endut was the Project
scaffolding system (MSS) was adopted to Teamwork was key to the project’s Director and is the Managing Director for
Arup in Malaysia.
construct the high-level bridge deck. The successful completion. A project office was
MSS provided a quick, reliable and set up near the site, allowing Arup to work Project credits
economical solution for construction of the under the same roof with the client, the Client Malaysian Public Works Department
4. elevated bridge. This was the first time this contractor and other team members. (Jabatan Kerja Raya). Thanks to Haji Abd.
method was used in Malaysia. Rahman bin A. Aziz as Superintending
Monthly meetings took place on site, where Officer’s Representative
With an MMS, a hydraulically operated giant external stakeholders were also invited, Bridge engineering, infrastructure and
steel gantry, formwork and platform slides including utilities companies, representatives geotechnical design, electrical
from pier to pier, enabling the beams and of the local council, Forestry Department engineering and construction supervision
concrete slabs to be constructed from the top officials and, when there were particular Arup: Wan Anuar bin Wan Endut, Wong Chee
of the piers. Once each section is completed, issues to address, NGOs. This meant that all Thong, Ng Say Gim, Muhd Khairul Asyraf bin
Abd Rani, Mohd Nazri bin Mat Daud,
the formwork is released and pushed to the concerned parties were kept abreast of the
Adlie bin Mohd Ali, Muhd Bazli bin Omar,
next pier, meaning that workers, equipment project’s progress. Azeri bin Ahmad.
and materials have minimal impact at ground
level. In total, 50 sections of 40m span were Safeguarding Malaysia’s natural heritage Image credits
constructed using this method. Two 600-tonne The Rawang Bypass opened to great All images: Arup
gantries were used for the installation. acclaim in November 2017. For its
5. 6.
Lowering Leeds city centre flood risk The first phase of the Leeds Flood
Alleviation Scheme was completed at the
With the rejection of this original scheme,
there was a risk that the flood alleviation
end of 2017. The works have significantly initiative would be removed completely from
reduced the risk of floods that have the the list of national infrastructure spending
The Leeds Flood Alleviation Scheme is one of the largest flood defence potential to cause devastating physical priorities. For Arup, whose Leeds office is
projects in the UK and the first in the country to use movable weirs and economic damage to the heart of located on the River Aire, getting involved in
the city. developing a new scheme was an
Authors Michael Nichols and David Wilkes opportunity to propose a more sustainable
Previously, 3,500 residences and 500 solution. The firm, working together with
commercial city centre properties were at high Leeds City Council, developed an alternative
risk, as were key access routes to the train proposal more in keeping with the city’s
station area, data and telecommunications character and landscape. Arup focused on
infrastructure, electricity sub-stations and reducing obstructions that were causing
more than 300 acres of developable land. water levels to rise, meaning the length,
visual impact and cost of the riverside
In 2015, Storm Eva hit the city, with the defences could be significantly reduced.
resulting flooding causing an estimated
£37 million worth of damage. This By identifying which flood defence
highlighted the importance of completing measures would provide the most immediate
the flood alleviation measures as quickly benefits and developing the project in stages,
as possible. The first phase of the scheme Arup believed it could make substantial
provides protection to the city without improvements on a smaller budget, adding
compromising the character of the more sophisticated measures when further
waterfront, with careful interventions funding was secured – an attractive proposal
maintaining the important connection during a time of economic recession.
between the city and the River Aire.
The design comprised three main elements:
Scheme development the removal of the river’s two main
In 2011, the UK government’s Department navigation weirs, replacing them with
for the Environment, Food and Rural Affairs, moving mechanical weirs that allow the
and the Treasury, rejected a proposal from a water level to be better controlled; installing
different firm for a £190 million flood scheme 10km of linear defences in the form of walls
due to the excessive cost. That scheme along 5km of the city centre waterfront,
advocated the construction of 3m high walls embankments and landscape improvements;
and embankments. While these would have and the removal of a 600m-long man-made
provided flood protection, they would have island that separated the river and canal,
also severed the physical connection between thus eliminating a bottleneck for water flow.
the city and the waterfront. Such high walls
would have had a negative effect on the café In November 2011, the Environment
and bar culture along the river, and a pleasant Agency commissioned Arup to develop the
waterfront walking and cycling route would scheme further and the project subsequently
have been lost. secured funding. With Leeds due to connect
1: Completed Crown
Point replacement
weir – part of
the Leeds Flood
Alleviation Scheme,
which provides
100-year storm
flood protection
2: Arup developed
a web-accessible
BIM model for
the scheme
1. 2.
Eel pass
identified by the UK government as an project data that was linked to the model, on site. This structure ensured there was 9.
important strategic
P2 project. such as drawings and photographs. good collaboration across the complete
11800
project team.
Digital construction and collaboration The aim was to ensure that everyone involved Aire valley was home to industries such as
Min. 8200
Arup developed a web-accessible interactive in the project had a sound understanding of Replacing the weirs carpet and cloth making, and coal mining.
Building Information Modelling (BIM) the scheme’s fundamentals and access to all The existing masonry weirs on the river
P1
model for the scheme. Through this virtual the technical information whenever needed. dated from the Victorian era, when the River These fixed weirs made the river navigable
through the city centre, forming an
important trade and passenger route linking
Min 12400
4500
Weir design to include
curved abutment plate
7.
kept the river level high enough to allow
Scour
to match pier
large barges carrying industrial cargo to
Min. 6200
Existing weir to be
demolished
Eel pass
Steel plate attached to pier
navigate the waterway. However, when the
14895
21000
pier to be demolished
P3 The previous scheme did not seek to change
Scour protection(to be designed
these weirs; however, Arup saw them as a
1602
400 400
11800
Seepage cut-off as
crucial element of the flood management
strategy. The firm proposed replacing the
Concrete base structure
needed
B
Eel pass
Existing weir to be
demolished Steel plate attached to pier
5: The water level is controlled using bottom-
14895
21000
Strap
hinged steel plates supported on inflatable
B
18.40 or lower
18.527 or lower Bladder Scour bladders. These movable weirs can be lowered in
protection
6: Arup used physical models of the weirs to test 9: Crown Point replacement weir
Seepage cut-off as
needed
Concrete base structure
flow patterns under construction
4. 6. 8.
10: In order to ensure the connection between the national flood defence schemes. The
city and the River Aire was maintained, flood- movable weirs allow a significant reduction
proof glazed units were installed along a stretch of in the height of the walls and embankments
the riverbank most used by the public within the city compared with the previously
11: Natural flood alleviation methods were also proposed scheme. Together with terracing
used, such as planting trees and landscaping, this maintains physical and
12: The Trans Pennine Trail was relocated so that visual connectivity with the waterfront.
it now crosses the river on a 70m span bridge
installed to connect the trail and the north bank of The scheme’s success has protected the city
the Aire centre from flooding – providing a 100-year
storm standard of protection up to 2069,
taking into account climate change – and
There are many high-quality public areas ensured that the development of Leeds
along the River Aire, so a priority was to South Bank can progress with confidence.
preserve these and the relationship between This project has the potential to create
people and the water. As the movable weirs 35,000 jobs and 4,000 homes, and will
reduce the flood water level in the city house the terminus of HS2.
centre, this means that the walls could be
much lower than the previously proposed Arup’s scheme has enhanced the area’s
3m height. Arup’s design ensured the natural habitat, encouraging local wildlife to
majority of the walls were less than 1.2m flourish. The new weirs include fish and eel
high and were clad in stone and brickwork passes that allow baby salmon to come
to match their surroundings. In the areas down the river and for mature adult fish to
10. most used by the public and near residential 12. swim back up. It also provides a habitat for
areas, flood-proof glazed units were mammals such as otters and beavers. For the
In normal conditions, the gates are at a 45° temporary weir was installed upstream at installed to make sure that views of the river bottleneck. Its removal was another element rainfall and high river levels. The 275km2 first time in about 200 years, there is now a
angle, which maintains the high river level Knostrop, which allowed construction work could be maintained. A testament to the in Arup’s strategy to prevent flooding by model – one of the biggest of its kind in small otter population living in Leeds city
and allows for navigation. However, as the to be undertaken in a safer manner in project’s success was that a very active eliminating blockages rather than relying on Europe – brought together all the elements of centre. In addition, as part of the natural
waters rise, the gates can be progressively shallower water, and ensured the flood risk residents’ committee with properties along excessively high flood protection walls. To local and highway drainage and both the flood management techniques used by Arup,
lowered towards the riverbed over a to surrounding properties was not increased the river was satisfied by the result. facilitate the removal of the island, Arup current and historical water company records. over 700 trees have been planted.
two-hour period, removing the barrier to during construction. designed the diversion of the Trans Pennine It created a detailed picture of Leeds and its
flows and greatly improving water Eliminating another barrier Trail (used by walkers, cyclists and horse flooding hotspots. This means that measures By improving river accessibility and
conveyance. This reduces high-flow water Linear defences in the city centre The final element of this phase of the flood riders across the Pennines). The trail was can be designed in the future to tackle spot securing the future of local leisure and
levels by 2m at the weir locations and by The second element of the scheme was to alleviation scheme was the removal and relocated by creating a new 1km walkway surface water flooding in Leeds, which has a business establishments, Arup’s flood
approximately 1m in the city centre. build flood defences on each river bank to relocation of a man-made island at on the left bank of the river that included high river flow and intense local rainfall alleviation scheme has also added to local
protect a 5km section of the city centre, as Knostrop, which separated the river and the measures to encourage wildlife and plantlife (1,025mm per year over 152 days). employment in the city. It has created 150
Mechanical weirs are used in other countries the water level could still rise above the Calder and Hebble canal along a 600m and improved public wayfinding and direct jobs and will safeguard 22,000 more
– in the US and Canada, for example – but original riverbank during a flood event. stretch. This eliminated a water flow interpretation of the environment. The cutting edge over the next ten years, supporting further
typically to control the flow of water into The implementation of this £50 million growth and regeneration of the Leeds
hydroelectric plants. Arup’s scheme in Leeds, The trail needed to cross the Aire, so a scheme puts Leeds at the cutting edge of regional economy.
using weirs developed by Dryhoff, is the first locally manufactured bridge was installed
time movable weirs have been used as part of at the weir location connecting the diverted
a flood alleviation scheme in the UK. trail with the north bank of the river.
Weighing approximately 150 tonnes and Authors Dean, Paul Dickens, Mike Dobson, Stephanie
Michael Nichols was the Project Manager and is Dye, Mike Farrer, Nick Ferro, Paige Garside,
Configuring the system’s layout and spanning approximately 70m, the bridge Libby Gibson, Arlene Goode, Llew Hancock,
an Associate Director in the Leeds office.
installation correctly was crucial. As part of was designed by Arup, Knight Architects David Hardy, Milly Hennayake, Dean Hogg,
the design process, Arup used both digital and the BAM Nuttall/Mott MacDonald David Wilkes was the Project Director. He is an James Holloway, Sophie Hornsby, Jon
and physical models of the weirs to test the joint venture. Associate Director in the Leeds office and is Horrocks, Lan Huang, Andera John, Michael
various flow patterns ahead of construction. Arup’s Global Flood Resilience Leader. Jones, Christian Junge-Filipek, Jenny Lightfoot,
Some 180,000 tonnes of material was Jou Lin Ng, Amy Martin, Mark Matthews, Will
In addition, the 3D digital model helped excavated during the re-shaping and Project credits McBain, Michael Nichols, Alex Nicholson,
plan the weir construction sequence. The re-grading of the river. This was reused Client Leeds City Council Daniel Patten, Matthew Peacock, Miguel Piedra
model was also used to create a video that on a local development site and also for Contractor BAM Nuttall Lara, Novlet Pitter, Ruairi Revell, Felicia
Civil, water, geotechnical, mechanical, Rhodes, Victoria Robinson, Marcus Shepherd,
showed how the weirs worked, illustrating the diversion of the Trans Pennine Trail,
electrical, structural engineering services in Paul Simkins, Paul Smith, Hannah Smith, Alex
the process to the wider public. resulting in a saving of £6 million. Smith, Veronika Stoyanova, Martyn Tattersall,
addition to hydraulic design, commercial
management, environmental impact Trevor Taylor, Lee Wallace, Jen Whelan, David
Arup worked with the design and build Integrated urban drainage model assessment Arup: Daniel Aspden, Chris Baker, Wilkes, Sam Wright.
contractor to design the system, which had In addition to minimising flood risk from the Luke Ballantyne, Niall Bourke, Adam
to meet strict requirements for control of river, Arup created a digital model to identify Broadhead, Eric Buffin, Olly Carlton, Oliver Image credits
flood risk and needed to maintain navigation the risk of residual surface water flooding Clarke, Paul Davies, Richard Deakin, Alan All images: Arup
during construction. For example, a issues, looking at the combination of heavy
11.
combining shading and ventilation with 7: A 70mm deep reflecting pool covers the atrium
permanent access for cleaning and glazing in the courtyard
maintenance. This is a bespoke composite 8: Solar gain is controlled primarily by vertical fins
system in which every component has been that form a brise-soleil. The access walkways also
designed from first principles. The system provide additional solar shading
contributes to the look, feel and operation of
the headquarters. Within the building, Arup
and DCA designed many systems that were
specifically developed for the project, and
even patented the modular LED luminaire
system used throughout the building.
reduce solar gains and, consequently, reduce the large façade openings, the down-wash 11: BIM model of the building services showing the
the energy consumed by the building’s impact at entrances and, crucially, to be able cores positioned at the four corners of the building
cooling systems. to refine the structural robustness of the 12: The building’s arrangement around a central space
exposed parts of the fins. The fins have allows natural daylight to flood into the courtyard, which
There was little codified guidance for pinstripe surface protrusions along their is landscaped with various natural elements
designing such large elements. Typically, wind vertical axis that become visible only when
loads are anticipated to be greatest at the near the building. While these make a strong
corners and edges of a building, where wind visual contribution – purely rounded shapes
speed accelerates. However, the configuration can be difficult to process visually – Arup
of the brise-soleil affects these predictions: the introduced the 3mm linear protrusions to
presence of the fins provides resistance to the encourage vortex shedding. Micro turbulence
wind and the repeating pattern of fins could created by wind passing over the stripes
provide sheltering effects near the corners. reduces deflection and vibration effects as well
Surrounding buildings create additional as improving robustness.
turbulence, which can result in significantly
increased wind loads at the building’s corners. Arup integrated the structural and the shading
performance needs in determining the fin
In order to optimise the fins’ design, Arup patterns, recommending appropriate sizes and
conducted a series of wind tunnel tests of the weights of fins for different locations around
brise-soleil at different scales to determine the the building. For example, shallow fins were
9.
response to wind effects. dominant in locations with lower wind
pressure and deeper fins were prioritised at the
The fins’ size meant they could not be corners of the building.
distinctive appearance both during the day and modelled at normal wind tunnel testing scales
at night, this system maximises transparency, of 1:400–1:300. Arup’s wind specialists Walkways
controls daylight and provides views out across developed a customised approach to testing. A typical challenge for external shading, which
Seoul. It also assists with managing the solar Preliminary small-scale, whole-building is exposed to the elements, can be the
heat gain within the building. testing in South Korea was followed up by difficulty of maintenance and cleaning. For 11. 12.
1:70 scale fin tests in Europe’s largest Amorepacific’s headquarters, the layer of
Arup performed daylighting and structural atmospheric boundary layer wind tunnel in vertical fins is separated from the building’s
testing to optimise the geometry and pattern of Milan, Italy. The design of the fin section was glazing by a series of grillages at each floor external moving parts, greatly simplifying its culture where work arrival and departure times ‘twin lift’ system, with hall-call control, over
the fins. The system comprises approximately further refined to an aerofoil shape with level that serve the triple function of horizontal maintenance requirements. and lunch times are commonly punctual, often a conventional ‘double deck’ system is an
1,150 aluminium fins in four sizes – 450mm, tapering edges, with additional testing carried shading, fin support and access walkways. leading to lengthy waiting times. increase in capacity and reduction in waiting
350mm, 250mm and 200mm deep. Although out at this stage of the design. These allow the outside of the windows to be Vertical transport time, as well as a reduction in energy
these have a uniform appearance, the fins are cleaned easily and give access to the fins and The latest advances in lift technology have been The central courtyard arrangement precludes consumption. This application is the largest
grouped in patterns that vary around the This combination of tests enabled Arup to motorised ventilation louvers for inspection used in order to provide a high level of service the use of a central lift and staircore. Instead, of its kind in the region.
building, tuned for orientation, based on predict the behaviour of wind at the edges of and maintenance. The external shading has no and reduce waiting times, thereby facilitating cores are positioned at the four corners of the
sun-path solar exposure. For example, on the rapid mobility around the building while floor plates and comprise five passenger lift Courtyard, atrium and glazed floor
north-east and north-west façades, direct solar minimising the lift core sizes. Waiting times are shafts, and one service and one firefighting lift. By locating the stair and lift cores in the
exposure is minimal during summer months nine seconds in normal service and 15 seconds Each passenger lift shaft contains two lift cars corners of the building, it became possible to
and during normal working hours. The fin at peak times. This is highly advantageous in a operating independently. The advantage of this create a large ground floor atrium below the
pattern on these façades comprises mainly courtyard. The importance of this space for
shallow fins to maximise natural lighting and Amorepacific goes beyond the functional brief,
views. On the south-east and south-west Family A, Fin type 1 (40%), 2 (40%), 3 (20%) which was to provide secure access for staff
façades controlling solar gain and glare is Family B, Fin type 1 (33%), 2 (33%), 3 (33%)
and visitors. It is also the setting for the public
more critical. Here, deeper fins provide a entrance hall used by people visiting the
higher degree of solar shading to significantly Family C, Fin type 1 (20%), 2 (40%), 3 (40%)
building’s amenity spaces. These include the
Family D, Fin type 2 (33%), 3 (33%), 4 (33%) art museum, tea room, auditorium, childcare
centre, product testing areas, retail spaces,
restaurants and cafés. The atrium also creates a
Size 1 Size 2 Size 3 Size 4 pedestrian link to the adjacent Yongsan Park.
Big series
The early design envisaged an artificially lit
200
250
of fins
350
450
facing
outwards
space. Arup worked with the architect to bring
9: The fin pattern, with various fin sizes used, natural light into the expansive space. This
gives the building its unique look, while also Small
200
250
series of
350
fins facing
heat gain into the
courtyard
10: The fins around the façade are of various sizes 150 115 80 65
Distance
in order to manage solar gain and glare (mm)
13: The award-winning headquarters provides
450 450 450
depending on the façade orientation views over Seoul and links with the nearby park
10. 13.
14: Arup and DCA various light atmospheres and a high level of
created a luminaire future adaptability.
system that uses a
single luminaire Taking a conscious low material wastage, high
body shape that can recyclability approach, DCA and Arup created a
be adapted for
modular, re-usable and adaptable luminaire
various applications
system that provides a huge variety of lighting
15: The courtyard performances. The system uses a single
provides a natural link
luminaire body shape with interchangeable
between the inner
building and the outer
optical lenses for different applications
environment throughout the building. This is an innovative
and sustainable departure from the conventional
approach to lighting flexibility, which relies on
different luminaire products and manufacturers
14. for different settings. The emitting surface of the
optical lenses is covered with microlenses of
was achieved by creating a glazed ceiling for system that is also aesthetically pleasing. The different shape, producing wide, medium, oval
the atrium, with a deep clear-span structure panels are located in areas where people or narrow light distributions. The unique optical
supporting the courtyard floor and the congregate and have conversations. Corridor system combines reflection inside the lens with 16. 17.
reflecting pool. The solution provides daylight ceilings are treated with sound-absorbing panels refraction at the underside of the lens, and offers
to the ground floor and, looking up from comprising a 50mm mineral wool core covered 12 different light distribution performances in up
below, provides a view of the sky, giving a with a 70% perforated metal sheet, recessed to 30 possible combinations. Available as systems. It won the 2018 Tall Building of the Arup’s total design approach, working 16: Reflected ceiling plan showing sound-
connection with the outside. within the concrete coffers of the exposed recessed, surface-mounted, adjustable and Year at the Dezeen Awards. in close collaboration with DCA, local absorbing panel distribution in the atrium
structural soffit. The outcome minimises high pendant versions, the system provides the consultants and the client, has resulted 17: DCA, with Arup, designed a variable acoustic
A precise integration of structure and services noise levels and disturbance, and so facilitates optimal light for any desired lighting atmosphere The design team has created a building that in an innovative building incorporating system for the auditorium
defines the character of the atrium. Lighting, comfortable conversation among small groups. and room use, and forms a decorative element embraces the climatic and cultural characteristics inventive façade, lighting, ventilation
diffusers and sound absorption are integrated that compliments the architecture. of Seoul. The work spaces are naturally and lift systems. The result is a flexible
with the structure so that the exposed concrete In the auditorium adjacent to the atrium, Arup ventilated and provide extensive levels of and healthy working environment for
soffit requires no additional ceiling treatment. designed a variable acoustic system to allow Every component is replaceable and the lights daylight and good views across the city. staff and visitors.
Despite its busy public nature and hard the venue to be used for amplified and can be modified for any changes in the building’s
surfaces – with natural stone floors and unamplified scenarios (i.e. music and speech) use without compromising the appearance of the
concrete columns, walls and ceilings – Arup’s by deploying two layers of acoustic curtains ceiling. Patented by the design team, the lighting
acoustic designers created a controlled and diffusers on the auditorium side walls. system, manufactured by Italian company Authors vertical transport, acoustics, Joachim Guesgen, Charlotte Heesbeen,
environment while maintaining its live nature. Viabizzuno, is commercially available. Francesca Coppa is a senior acoustic engineer building physics, security Arup Cameron Heggie, Carsten Hein, Karen
in the London office. Henderson, Felipe Herrera, Eva Hinkers, Daniel
Lighting
Local team Hof, Duncan Hough, Anna Janda, Adam
Acoustic panels are discretely integrated with Amorepacific currently operates 28 Museum Architect HAEAHN Architecture Jaworski, Lidia Johnson, Jimmy Jonsson, Lisa
Eva Hinkers was the Project Director. She is the
the raw finish of the space to create an effective brands under one roof, creating the need for Designed to international museum standards, Chair of Arup’s Europe Region Board and is Interior architect Kesson Kaluzni, Berthold Keck, Matthew King, Chris
the Amorepacific Museum of Art focuses on based in the Düsseldorf office. Structure CSSE Kinnaird, Christiane Kleinke, Fabian Knauber,
traditional and contemporary Korean art and Building services HIMEC; SUKWOO Mike Kong, Paul Lander, Diana Lassalle, Paula
crafts. Careful integration of structure and Julian Olley led the design of the vertical Façade engineering Withus Longato, Maria Lynch, Vasilis Maroulas, André
services has created a gallery space that is transportation. He is a Director in the Vertical transport KEC Martins, Jacek Marzec, Joana Mendo, Ross
re-configurable to allow one main exhibition London office. LEED Cosentini Mills, Andreas Muenz, Duc Nguyen, Julian Olley,
or a combination of smaller exhibitions. Fire engineering KF UBIS Ender Ozkan, Stefan Petersen, Warner Post,
Alexander Rotsch is an Associate Director in the Lighting Huel Hugh Quail, Gregory Quinn, Lena Raizberg, Dirk
Berlin office and Arup’s Europe region lighting Acoustics Chungbuk National University Regenspurger, Hagen Rock, Melanie Rosenthal,
Arup advised on providing a dedicated art
skill leader. Sustainable design EEC Alexander Rotsch, Nina Rutz, Ronny Schiemann,
handling truck-lift at street level to transport Geotechnical consultant CG ENC Amanda Schilling, Henning Schlechtriem,
vehicles to the basement level secure art Nigel Tonks is a Director and the leader of Barbara Schmelz, Jens Schmidt, Oliver
handling area for the museum. This greatly Arup’s Buildings Group in London. Arup team Schwabe, Dave Seager, Amy Shen, Andrew
simplified vehicle movements near the building Rachid Abu-Hassan, Andres Acosta, Mikal Sherratt, Patrick Simon, Jolyon Smith, James
and freed up a greater site area for landscaping Frank Walter led the façade design. He is an Ahmed, Claudia Albornoz, Andrew Allsop, Andy Smith, Jamie Stern-Gottfried, Glen Swinney,
and planting. Associate in the Berlin office. Bailey, Stefan Behring, Corinne Benedek, Ed Carolin Tietgen, Magdalena Tomaszewska, Nigel
Blower, Trevor Bone, Phil Borowiec, Ian Tonks, Laurie Turnbull, Brian Twohig, Martin
Award-winning Project credits Braithwaite, Wojciech Cepok, Christopher Unger, Nick Unsworth, Stephan Vogt, Frank
Amorepacific’s headquarters are innovative, Client Amorepacific Corporation Clifford, Francesca Coppa, Marc Crompton, Walter, Colin Winant, Maciej Wlecial, Jan Wurm,
Architect David Chipperfield Architects Berlin John Dakin, Lizzie Davies, Jim Deegan, Luca Andrew Yeoh, Gertraud Zwiens.
highly sustainable and distinctive. The
General contractor Hyundai Engineering & Dellatorre, Michal Dengusiak, Tarun Devlia,
building has been awarded the KIRA Korean Alexander Diaz, Lars Dobberstein, Aidan Doyle, Image credits
Construction
Architecture premier prize and won the 2019 Structural, building services, Emily Dufner, Andrew Duncan, Pablo Efferenn, 1: Namsun Lee
Council on Tall Buildings and Urban Habitat geotechnical, façade, wind, Ulrike Elbers, Adam Foxwell, Matthias Frechen, 2, 8, 10, 13: David Chipperfield Architects
Award of Excellence for the Best Tall fire engineering services, Paul Freund, Hannah Geissler, Alex 3, 4, 7, 9, 11, 16: Arup
Building (100-199m), as well as the MEP lighting, sustainability, LEED, Goldsbrough, Nicolo Guariento, Rene Guenther, 5, 6, 12, 14, 15, 17: Noshe
Engineering Award for the building services
15.
4 5 6
7 8
1. Hong Kong-Zhuhai-Macao Bridge, Greater China: Marcel Lam Photography; 2. Leeds Flood Alleviation Scheme, UK: Arup; 3. Seattle Space Needle, USA: Olson
Kundig; 4. Rawang Bypass, Kanching Forest Reserve, Malaysia: Arup; 5. BLOX, Copenhagen, Denmark: Rasmus Hjortshøj; 6. Amorepacific Headquarters, Seoul, South
Korea: Noshe; 7. Brent Delta Platform Lift, North Sea, UK: Allseas; 8. Jaguar Land Rover Engine Manufacturing Centre, Wolverhampton, UK: Simon Kennedy.
Front cover image: Hong Kong-Zhuhai-Macao Bridge, Greater China: Marcel Lam Photography.
Published by Arup
13 Fitzroy Street
London W1T 4BQ, UK.
Tel: +44 (0)20 7636 1531
All articles ©Arup 2019
www.arup.com