Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

7 September 2010

Technical eNewsletter
Change-over to low sulphur fuel – a practical example to consider

From feedback recently received from one of our surveyors, we give an example of a change-over from
high sulphur to low sulphur fuel operation that did not work as intended.

More stringent requirements for low sulphur The situation described by the surveyor was 3. There was previous contamination in MGO
fuel (LSF) operation came into force on the following: (Marine Gas Oil) tanks and tanks were not
1 January 2010 (EU ports) and the require- During surveys by DNV for the issuance of cleaned prior to bunkering LSMGO.
ments concerning operation in European statements in connection with change-over from 4. The fuel was mixed in the tank (with probably
and Californian waters will stepwise become MGO to low sulphur MGO while entering/ too large a volume of mixing) and there had
stricter. The Revised MARPOL Annex VI operating in EU/CARBS areas, it was found been poor flushing of lines prior to starting
including maximum sulphur limit require- that when the actual fuel in use was tested, the mixing.
ments (1.00% by mass) for Emission Control sulphur content exceeded the statutory maximum 5. The change-over was based on a pure volume
Area entered into force on 1 July 2010. sulphur limit, even though the Master and offic- exchange and no mixing volume based on the
The amending directive 2005/33/EC, ers in charge were under the impression that the consumption rate/sulphur content differential
which requires a max sulphur content of fuel change-over had been completed satisfactorily. had been considered. They believe it is difficult
fuel in use of 0.1% at berth in EU ports, In discussions with the client, their prelimi- to estimate the volume of deposits on the pip-
entered into force on 1 January 2010. We nary investigation revealed the following: ing walls and how fast this coating releases
may therefore expect an increased focus 1. The sulphur content of the previous oil in use sulphur.
on sulphur content of fuel in use, from was 1.00%. 6. Some of the fuel was actually slightly off
Port State Control (PSC) officers and 2. The vessel was trading in a SOx Emission specification. This was discovered after testing
harbour authorities in EU, during this Control Area at the time. by DNV Petroleum Services (DNVPS).
autumn and onwards.

1|2
Technical eNewsletter 7 September 2010
Change-over to low sulphur fuel – a practical example to consider

Possible explanation (mixing) in the MGO tanks and/or an insuf- Recent PSC detentions
ficient change-over time.
When dealing with change-over proce- In the last week of August, two vessels were
The contamination detail of complient
dures, it is imperative to realise that many detained in a European port due to too
low sulphur MGO is important and inter-
fuel supply systems are closed-loop systems high sulphur contents in the fuel. For one
esting. A little mixing with HFO or MGO
in which the fuel is continuously circulated. of the vessels, fuel samples were taken from
(with higher sulphur content) can affect
When changing over from HFO (Heavy circulating fuel line of main engine at the
the entire operation leading to non-compli-
Fuel Oil) service tanks to LSF service tanks, booster pump, showing a sulphur content
ant fuel in use.
there will be no immediate change of sup- of 1,68%. Most probably this vessel was
It is highly recommended that sufficient
ply to the consumers (engines, boilers), following an “old” change-over procedure,
time be allowed for the fuel change-over
only a dilution of the fuel circulating in the that did not account for the max 1,00% sul-
before entering an area in which limitations
supply system. phur contents requirements, applicable in
to the sulphur content apply.
Consequently, the change-over time will ECA from 1 July 2010. This was considered
This can be verified by testing fuel qual-
be governed by the fuel oil consumption. evidence that the environmental protection
ity vs. time during change-over. Depending
Due to the relatively large quantities of fuel policy of the company is not fully imple-
outcome it may be necessary to install/
circulating, the time needed to complete mented and the vessel was requested to
retrofit separate service tanks and pipelines
the change-over can be relatively long. update the change-over procedure before
for HFO and MGO to auxiliary engines and
With only the main engine running, the departure. The other vessel had 1,17%
boilers to achieve a satisfactory change-over
blending-in ratio may be in the region of measured in the daytank even if the bunker
time and result.
1% per two minutes, and with only one delivery note stated 0,95%.
In the case discussed some of the low
auxiliary boiler or one auxiliary engine in The analysis of the sulphur contents is
sulphur MGO was delivered with sulphur
operation the ratio can be much lower. usually done in an independent laboratory
content exceeding 0.10% when tested
Experience has shown that in some cases and takes about one hour to perform. How-
by DNV Petroleum Services. One should
fuel change-over is not complete even after ever, it is understood that one normally gets
be aware of that some European Union
48 hours. As a result, the sulphur content an answer the day after (24h), due to prac-
Member States may conclude that a tested
of the fuel consumed may be in excess of tical arrangements (transport of samples
sulphur result between 0.11% and 0.14%
the applicable sulphur content limits. etc.). We are not aware of any “hand-held”
is above the maximum 0.1% by mass (one
Furthermore, but maybe not illustrated analysis-kit that is used directly on board.
decimal) limit stipulated in EU Directive
in the case discussed, time should be
2005/33/EC.
allowed to maintain the temperature gradi-
ent recommended by the engine manu-
During an audit to verify that the safety Support and references
management system effectively ensures DNV Petroleum Services can assist in
facturer, e.g. 2˚C/minute, in a controlled
compliance with rules and regulations, an developing and documenting ship-specific
manner. This will in many cases be neces-
ISM Code auditor will normally focus on change-over procedures in order to demon-
sary in order to avoid a thermal shock to
any new relevant regulations entering into strate compliance with regulation 14 of
the system, e.g. seizure of fuel injection
force. The choice of which regulations to MARPOL Annex VI. See www.dnv.com
pumps, and/or other operational problems
verify will be at the auditor’s discretion. The 32-page DNV booklet “MARPOL
that may occur due to low viscosity and/or
ISM verification in relation to MARPOL Annex VI - Technical and Operational
rapid temperature changes.
Annex VI and Sulphur Emission Control Implications” addresses SOx emissions in
Areas (SECAs) is relevant for several of the one of the chapters.
Lessons learned ISM Code requirements. See www.dnv.com
In this case, the surveyor suggested taking The fuel change-over procedure is the
a sample of the LSMGO by the boiler’s operational responsibility of the owner and
burner inlet, which showed a sulphur con- the DNV surveyor is not normally involved
tent of 0.22% rather than the 0.08% stated in any verification of such a procedure (in
in the BDN (Bunker Delivery Note) for the case discussed above, DNV issued an
the LSMGO. This indicated contamination independent statement of witnessing at the
owner’s request).

For more information, please contact:

DNV Classification Support DNV Petroleum Services


GSCNO894@dnv.com DNVPS.Oslo@dnv.com
Machinery and Systems

1|2

You might also like