Main Bridge 2-2, Total nos. of Segments: 278X2=556 (Lws & Rws) both side.

Segmental width 2.5 mtr., Segmental length=18 mtr., Segmental Height=3.80mtr.


Total nos of span MB2-2 (Lws & Rws)
10 nos of 60 mtr span
1 nos of 50 mtr span
1 nos of 45 mtr span
CYCLE TIME – SEGMENT PRECASTING

 Soffit Align and fix outside shutter panel 0.5 days


 Positioning re-bar cage & fixing cable Ducts, guide cone,
bursting rebar, 1.0 days
 Checking and inspection 0.5 days
 Fixing end forms, Inside shutter & Inspection 1.0 days
 Concreting 0.5 days
 Curing in bed (Till 25 N/mm2 strength) 2.5 days
 Removal from bed 0.5 days
Total 6.5 days
Note: (1) Outer shutter panel moved to next segment after concrete in segments
attains 10N/mm2 (Approx 1.5 days after concreting)
(2) Inside shutter panel moved to next segment (Approx 2.5 days after
concreting)
DIMENTION: Segmental width=2.5m, Segmental Length=11.0m, Segmental Height=2.5m
ARM-1 (R01) Total Nos. of Segment=254
Total Span=18 Nos., Total length= 635 meter.,
ARM-2 (R02) Total Nos. of Segment=220
Total Span=15 Nos., Total length= 550 meter.,
ARM-3 (R03) Total Nos. of Segment=246
Total Span=16 Nos., Total length= 615.387 meter.,
ARM-4 (R04) Total Nos. of Segment=104
Total Span=8 Nos., Total length= 260 meter.,
Grand Total =824 Nos.

CYCLE TIME – SEGMENT PRECASTING

 Align and fix outside shutter panel Positioning re-bar cage 1.0 days
 fixing cable Ducts Checking and inspection, guide cone,
bursting rebar 1.0 days
 Fixing end forms, Inside shutter & Inspection 0.5 days
 Concreting 0.5 days
 Curing in bed (Till 25 N/mm2 strength) 2.5 days
 Removal from bed 0.5 days
Total 6 days
Note: (1) Outer shutter panel moved to next segment after concrete in segments
attains 10N/mm2 (Approx 1.5 days after concreting)
(2) Inside shutter panel moved to next segment (Approx 2.5 days after
concreting)