Main Bridge 2-2, Total Nos. of Segments: 278X2 556 (Lws & RWS) Both Side
Main Bridge 2-2, Total Nos. of Segments: 278X2 556 (Lws & RWS) Both Side
Align and fix outside shutter panel Positioning re-bar cage 1.0 days
fixing cable Ducts Checking and inspection, guide cone,
bursting rebar 1.0 days
Fixing end forms, Inside shutter & Inspection 0.5 days
Concreting 0.5 days
Curing in bed (Till 25 N/mm2 strength) 2.5 days
Removal from bed 0.5 days
Total 6 days
Note: (1) Outer shutter panel moved to next segment after concrete in segments
attains 10N/mm2 (Approx 1.5 days after concreting)
(2) Inside shutter panel moved to next segment (Approx 2.5 days after
concreting)