Professional Documents
Culture Documents
Project Monitoring and Control PDF
Project Monitoring and Control PDF
How do we
monitor our
projects?
3
HOW do we
perform control
in our project?
Contract Execution: Overview
4
Solution to Construction
Construction in As per Program of Work
Problems & Challenges
Progress
Project Control
As per plan and
Construction in
Detect Deviations from
specification
Progress
SAFETY!
Plans and Targets
Project Monitoring
Construction in
Progress
Testing & Quality Assurance
Inspections
ON-GOING
CONSTRUCTION
Quality Control
5
Project Monitoring and Control: Overview
5
Monitoring
means keeping a track of implementation process
Involves watching the progress of a
project against time, resources and
performance schedules during the
execution of the project and identifying
lagging areas requiring timely attention
and action
nPeriodic checking of progress of works
against the targets laid down in order to
ensure timely completion of the project
Source:
http://www.slideshare.net/srengasamy/project-monitoring-evaluation-s-presentation
Project Monitoring
7
WHY DO WE MONITOR?
Actual activities don’t always go
according to plan
WHAT DO WE MONITOR?
INPUTS
Time Progress
Money Costs
Job starts
Manpower Job completion
Materials Engineering / Design changes
Equipment Variation order (VO)
Project Monitoring
9
WHEN DO WE MONITOR?
End of the project
Continuously
Regularly
Logically
While there is still time to react
As soon as possible
At task completion
At pre-planned decision points (milestones)
Project Monitoring
10
HOW DO WE MONITOR?
Through meetings with clients, parties
involved in project (Contractor,
supplier, etc.)
For schedule – Update PERT-CPM,
Charts, Update Gantt Charts
Milestones
Reports
Tests and inspections
Project Control
11
PROJECT CONTROL
Control – process and activities needed to correct
deviations from plan
Control the triple constraints
time (schedule)
planned
Total Man-hours
Cost of activity (or of project actual
to date) is higher than
expected Amt of concrete used (tons)
planned
actual
Basic indicators:
More resources or less
resources have been used
than planned
Basic indicators:
More resources or less
resources have been used
than planned
BLA
BLAH BLAH
Are monitoring and control done only during
“construction phase”?
1 Pre-Construction Phase
2 Construction Phase
3 Project Close-Out
Pre-Construction Phase
Pre-Construction Phase
Acquisition of
Budget Preparation Bidding Contract & Audit
Permits
CMPD
Construction Materials Price Data (per Region Prevailing Prices of
and District) Construction Materials
POW, APP,
ABC,
DUPA PPMP
BIDDING PROCESS
POW,
ABC,
DUPA R.A. 9184
Government Procurement
Reform Act
BID
DOCUMENTS
APP,
PPMP
Pre-Construction Phase
INPUTS OUTPUTS SYSTEMS / POLICIES
Preparation of Contract
Agreement
BID
DOCUMENTS
Contract
Agreement Data Input to CWR
Commission on Audit
CONTRACT REVIEW
NOTICE
Contract TO
Evaluation of compliance
with the requirements of
Agreement
PROCEED applicable laws, rules
and regulations
Checking the
completeness of
documentary
Pre-Construction Phase
Acquisition
NOTICE of Permits
TO
PROCEED and
Clearances
Construction Phase
ELD
ENTATION
and
TORING
Project Monitoring
Approved
Construction
35 Plans/ As-
Schedules
staked Plan
Construction
1 • Baseline for MONITORING Construction
Method
Safety &
Health
Program
Quality
Control and
Quality
Assurance
Plan
Project Monitoring
36
As-staked Construction
WHAT is As-Staked Survey and As-Staked Plan? Plan Schedules
Construction
Construction
Method Safety &
Health
Program
Quality
Control and
Quality
Assurance
Plan
Reference:
D.O. 15, Series of 2016 – Guidelines on the Processing and Approval of “As-Staked” Plan
Project Monitoring
40
As-staked Construction
Plan Schedules
Points to remember…
PERT/CPM Schedule
Construction
Construction
D.O.133 Series of 2015 Safety
Method requires&the
Health Method
adoption of Precedence Diagram
(PDM) as project scheduling technique.
Program
Quality
Control and
Quality
Assurance
Plan
Project Monitoring
42
As-staked Construction
Plan Schedules
ACTUAL ACCOMPLISHMENT AS OF
OCTOBER 15, 2015
V Finishing Works 2,321,922.75 3.90%
4.34%
# # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #
Control and
VIII Plumbing/Sanitary Works 1,111,365.74 1.87% # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #
X Mechanical Works
TOTAL AMOUNT (IN FIGURE)
3,507,043.74
59,518,878.45
5.89%
100.00%
Quality # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #
0.00%
0.00%
0.00%
0.00%
0.00%
0.31%
0.31%
0.01%
0.33%
0.00%
0.33%
0.00%
0.33%
0.00%
0.33%
0.00%
0.33%
0.00%
0.33%
0.00%
0.33%
0.00%
0.33%
4.42%
4.75%
Assurance
5.10%
9.85%
12.34%
22.18%
18.20%
40.38%
26.77%
67.15%
21.92%
89.07%
10.71%
99.78%
0.22%
100.00
WeeklyActual Periodic Accomplishment 0.00% 0.00% 0.00% 1.38% 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 2.02% 0.70%
Plan
WeeklyActual Cumulative Accomplishment 0.00% 0.00% 0.00% 1.38% 1.62% 1.62% 1.62% 1.62% 1.62% 1.62% 3.64% 4.34%
Quality
Control and
Quality
Assurance
PlanPlan
Project Monitoring
44
As-staked Construction
Plan Schedules
The contractor shall take all reasonable
precautions to maintain the health and
safety of his personnel based on the
Construction Safety and Health Program
(CSHP). Construction Construction
Method Safety &
Health
Program
WHAT is a CSHP?
Quality
• Refers to a set of detailed rules to cover the Control and
processes and practices that shall be utilized in a
specific construction project site in conformity with the Quality
Occupational Safety and Health Standards (OSHS). Assurance
Plan
Project Monitoring
45
As-staked Construction
Plan Schedules
WHEN to prepare and apply for approval?
Construction
Construction
Safety &
Method
Health
Program
Quality
Required to be submitted
Control
by the contractor for the and
perfection of contract
Quality
Assurance
Plan
Project Monitoring
50
As-staked Construction
Plan Schedules
Construction Construction
Method Safety &
Health
Program
Quality
Control and
Quality
Assurance
Plan
Project Monitoring
51
2 • On-Site Inspections
HOW to conduct on-site
WHO will conduct? inspections?
Project
Status
Reports
Project Monitoring
53
Project
Site Monitoring
Instruction Charts
Status
Reference: Reports
D.O. 216, Series of 2000 – Project Records
Project Monitoring
54
Project
CONSTRUCTION LOGBOOK
* 1ST Page
- Name of Project/Location
Minutes of
the
Project
Documentation
Weather
Chart
Meetings
- Name of Contractor
- Contractual Data
- Names of DPWH PE/ME/PI
- Name of contractor’s PE/ME/Site Site
Instruction
Engrs. Monitoring
Charts
- List of Contractor’s committed equipment Status
and
manpower Reports
085
PROJECT: Strengthening/Retrofitting of Premier Guest House, Gate 4, Malacanan Cpd., San Miguel, Manila
DATE: August 04, 2012 (Saturday)
WEATHER: AM – Fair
PM – Fair
• Sample Content of Project Logbook
MANPOWER:
55 1-Project Manager 4- Carpenter 1-Safety Officer 2-Plumbers
1-Project Engineer 2-Steelman 12-Laborers 1-Time Keeper Project
1-General Foreman 4-Mason 1-Warehouse Man Construc-
1-Project Accountant 2-Electrician 1-Site Engineer/Safety Officer tion
EQUIPMENT: Logbook
1- Bar bending machine 1 - Bar Cutter 1- Pumpcrete Correspon- Materials
CONSTRUCTION ACTIVITIES: dence Logbook
1. Installation of formworks for roof deck & beams @ GL K-R/2-3.
2. Installation of rebars for roof deck & beams @ GL K-R/2-3
3. Concrete pouring for roof deck slab & beams @ GL K-R/2-3,
columns L-R / 3 and Corbel 3/L, M, N, O, P, Q & R
4. Chipping of existing floor and wall tiles at ground floor Grid line D4-6 to E4-6.
5. Installation of electrical conduits at Kitchen. Minutes of
6. Installation of sanitary/plumbing conduits along GL 5-6 at ground floor. Project Weather
the
Documentation Chart
7. Hauling of waste materials for disposal. Meetings
REMARKS:
1. Concrete pouring:
Supplier : Summit Sigma
Volume : 31.0 cu.m.
Time Started : 11:00AM
time Completed: 4:40PM Site Monitoring
VISITORS: Instruction Charts
1. ____________________________ - _____________________
2. ____________________________ - _____________________
Status
PREPARED BY: NOTED BY: Reports
_____________________________ _________________________
DPWH-Project Inspector DPWH-Project Engineer
Project Monitoring
56
Project
MATERIALS LOGBOOK
* 1ST Page
- Name of Project/Location
Minutes of
the
Project
Documentation
Weather
Chart
Meetings
- Name of Contractor
- Contractual Data
- Names of DPWH
QC Personnel Site
Instruction
Monitoring
Charts
- Name of contractor’s Status
QC Personnel Reports
068
PROJECT: Strengthening/Retrofitting of Premier Guest House, Gate 4, Malacanan Cpd., San Miguel, Manila
DATE: August 04, 2012 (Saturday)
WEATHER: AM – Fair • Sample Content of Materials Logbook
PM – Fair
CONSTRUCTION
57 ACTIVITIES:
1. Installation of formworks for roof deck & beams @ GL K-R/2-3.
2. Installation of rebars for roof deck & beams @ GL K-R/2-3 Project
Construc-
3. Concrete pouring for roof deck slab & beams @ GL K-R/2-3, columns L-R/3 and Corbel 3/L, M, N, O, P, & Q
tion
4. Chipping of existing floor and wall tiles at ground floor Grid line D4-6 to E4-6. Logbook
5. Installation of electrical conduits at Kitchen.
6. Installation of sanitary/plumbing conduits along GL 5-6 at ground floor. Correspon- Materials
dence Logbook
7. Hauling of waste materials for disposal. (1-truck load)
QUALITY CONTROL ACTIVITIES:
1. Inspection of materials used – electrical and sanitary conduits conform with spec’s/plans.
2. Sampling of Concrete:
Slump Test – 6.5” Cylinder - 6 samples, ID: PGH-Deck Slab
GL K-R/2-3
Minutes of
08-04-12 A, B, C, D, E, F Project Weather
the
REMARKS: Documentation Chart
Meetings
1. Concrete pouring:
Supplier : Summit Sigma
Volume : 31.0 cu.m.
Time Started : 11:00AM
Time Completed : 4:40PM
2. 1 transit mixer load (6 cu.m.) was rejected due to failed slump test (9.5”)
3. Reminded the contractor’s ME to observe proper curing of the newly concreted structures and cylinderSite
samples.
Monitoring
Instruction Charts
VISITORS:
1. ____________________________ - _____________________
2. ____________________________ - _____________________ Status
PREPARED BY: NOTED BY: Reports
______________________________ _________________________
DPWH-Materials Engineer DPWH-Project Engineer
Project Monitoring
58
Project
Minutes of
Project Weather
the
Documentation Chart
Meetings
Site Monitoring
Instruction Charts
Status
Reports
59
Project
Construc-
tion
Logbook
Correspon- Materials
dence Logbook
Minutes of
Project Weather
the
Documentation Chart
Meetings
Site Monitoring
• Sample Accomplished Weather Chart
Instruction Charts
Status
EDDIE R. VILLANUEVA Reports
DPWH-Project Inspector DPWH-Project Engineer
Project Monitoring
60
Project
Minutes of
Project Weather
the
Documentation Chart
Meetings
Site Monitoring
Instruction Charts
Status
Reports
Project Monitoring
61
Project
Minutes of
Project Weather
the
Documentation Chart
Meetings
Site Monitoring
Instruction Charts
Status
Reports
Department of Public Works and Highways
BUREAU OF CONSTRUCTION
DESIGN AND BUILD OF FOUR (4) STOREY ENGINEERING AND SCIENCE RESEARCH CENTER
PUP Mabini Campus, Sta. Mesa, Manila
TOTAL - 43
PROJECT UPDATE:
1.) The project is on-going.
Accomp (% WT)
Relative
ITEM NO. DESCRIPTION Qty. Unit Amount THIS
Weight PREVIOUS TO DATE
WEEK
A. ARCHITECTURAL AND ENGINEERING DESIGN SERVICES 1.00 lot 4,600,000.00 6.07% 6.07% 6.07%
I. GENERAL REQUIREMENTS
Accomplishment a. Mobilization/Demobilization
b. Temporary Facilities
1.00 lot
8.00 months
99,993.60
626,304.00
0.13%
0.83%
0.11%
0.83%
0.11%
0.83%
d. General Scaffolding and Shoring Works (Rental) 2,191.86 sq.m. 1,706,779.46 2.25%
II. EARTHWORKS
a. Excavation 1,212.56 cu.m 977,809.19 1.29% 1.29% 1.29%
a.2 Footing Tie Beam 22.67 cu.m 162,092.31 0.21% 0.21% 0.21%
64
SCHEDULE UPDATING
THIRD FLOOR
I Concrete Works 6,839,884.70 11.49% # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #
ACTUAL ACCOMPLISHMENT AS OF
OCTOBER 15, 2015
V Finishing Works 2,321,922.75 3.90%
4.34%
# # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #
Weekly Target Cumulative Accomplishment 0.00% 0.00% 0.00% 0.31% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 4.75% 9.85% 22.18% 40.38% 67.15% 89.07% 99.78% 100.00
WeeklyActual Periodic Accomplishment 0.00% 0.00% 0.00% 1.38% 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 2.02% 0.70%
WeeklyActual Cumulative Accomplishment 0.00% 0.00% 0.00% 1.38% 1.62% 1.62% 1.62% 1.62% 1.62% 1.62% 3.64% 4.34%
65
Project Monitoring
66
3 • Project Documentation:
• Site Instruction Project
Construc-
tion
Logbook
Correspon- Materials
dence Logbook
Minutes of
Project Weather
the
Documentation Chart
Meetings
Site Monitoring
Instruction Charts
Status
Reports
• Sample Issued Site Instruction
67
Project
Construc-
tion
Logbook
Correspon- Materials
dence Logbook
Minutes of
Project Weather
the
Documentation Chart
Meetings
Site Monitoring
Instruction Charts
Status
Reports
Project Monitoring
68
3 • Project Documentation:
• Minutes of the Meetings Project
Construc-
tion
Logbook
Correspon- Materials
dence Logbook
Minutes of
Project Weather
the
Documentation Chart
Meetings
Site Monitoring
Instruction Charts
Status
Reports
Project Monitoring
69
3 • Project Documentation:
• Minutes of the Meetings Project
Construc-
tion
Logbook
Correspon- Materials
dence Logbook
Minutes of
Project Weather
the
Documentation Chart
Meetings
Site Monitoring
Instruction Charts
Status
Reports
Project Monitoring
70
3 • Project Documentation:
• Minutes of the Meetings Project
Construc-
tion
Logbook
Correspon- Materials
dence Logbook
Minutes of
Project Weather
the
Documentation Chart
Meetings
Site Monitoring
Instruction Charts
Status
Reports
Project Monitoring
71
3 • Project Documentation:
• Correspondence Project
Construc-
tion
Logbook
Correspon- Materials
dence Logbook
Minutes of
Project Weather
the
Documentation Chart
Meetings
Site Monitoring
Instruction Charts
Status
Reports
Project Monitoring
72
4 • Reporting system using Project and Contract
Management Application (PCMA
Project Monitoring
• Reporting system using Project and
4
73
Contract Management Application
(PCMA
Wherein updating of
accomplishment is per item of
work
Project Monitoring
• Reporting system using Project and
4
75
Contract Management Application
(PCMA
Project Control
Slippage
For Contractor shall be given a warning and is required
(-) 5% slippage to submit “catch-up program” on a fortnightly
83 – (two weeks) basis to eliminate the slippage.
(‘’Early The contractor shall be instructed to
Warning’’ specify the additional input resources - money,
• Calibrated Actions on
2
Stage) manpower, materials, equipment,
• Calibrated Actions on
2 Negative Slippage
86
6
Project
Close-Out WHO will issue?
87
Head of Implementing Office
WHEN to issue?
88
Project
Quality Check Completion
89
6
Project
Close-Out WHO will issue?
90
Head of Implementing Office
WHEN to issue?
91
6
Project Close-Out
92
• Buildings of types 4 and 5 as classified under • Buildings of types 1, 2, and 3 as classified under the
the National Building Code of the Philippines and National Building Code of the Philippines,
other structures made of steel, iron, or concrete concrete/asphalt roads, concrete river control,
which comply with relevant structural codes drainage, irrigation line canals, river landing, deep
(e.g., DPWH Standard Specifications) , such as wells, rock causeway, pedestrian overpass, and other
but not limited to, steel/concrete bridges, similar semi-permanent structures;
flyovers, aircraft movement areas, ports, dams,
tunnels, filtration and treatment plants, Other Structures:
sewerage systems, power plants, transmission
and communication towers, railway system and 2 years
other similar permanent structures;
• Bailey and wooden bridges, shallow wells,
spring Developments, and other similar
structures.
6
Project Close-Out
93
Contractor
Third Parties
• where structural defects/failures arise due to the fault attributable to
the improper construction, use of inferior quality/sub-standard
materials, and any violation of the contract plans and specifications;
• where structural defects/failures are caused by work
undertaken by them such as leaking pipes, diggings or
Consultants excavations, underground cables and electrical wires,
underground tunnel, mining shaft and the likes, in which case
the applicable warranty to such structure should be levied to
• where structural defects/failures arise due to faulty and/or third parties for their construction or restoration works;
inadequate design and specifications as well as construction
supervision;
Users
IO's Representatives/ PM/ CM
• where the structural defects/failures are due to his/their willful • where structural defects/failures are due to abuse/misuse by
intervention in altering the designs and specifications, negligence or the end user of the constructed facility and/or non-
omission in not approving or acting on proposed changes to noted compliance by a user with the technical design limits and/or
defects or deficiencies in design and specifications, and use of intended purpose of the same.
substandard construction materials in the project;
6
Project Close-Out
94
marshmallow) WINS!