Generator bus-ducts high temperatures issue still not resolved for Unit-1. Suitable modifications to
be done by M/s. BHEL to reduce the temperatures. Prior action may be taken for Unit-2 generator
2 bus ducts to avoid the reoccurrence of the same issue.
6 Air leakages in Unit-1 IPBD from inspection covers, welding joints and in seal off bushings
Completion of pending works in AHP, CHP, Unit-1 IPBD, Unit 1 SPBD, Unit 2 SPBD (recorded in a
7 joint inspection report and was submitted vide mail dated 13.02.2018)