# 115KV CT LOOP CHECK_Line1

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 01YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

BAY LINE.1

CT and Associated Current Circuit

General and Technical Information


Core No. Connected Ratio Class Burden Duty Remark

1 1200/5 10P20 200VA Protection & Metering

2 1200/5 10P20 200VA Busbar Protection (87B)

Commissioning Test Checked

1 Visually check all current circuits.

2 Verify the tightness of all connections.

3 Checking of insulation resistance of each circuit and grounded only one point.

4 Checking of polarity of all cores.

Core No. Connected Ratio Grounded Remark

1 1200/5 A112

2 1200/5 X82/5

X83/5

X84/5

5 Measure overall connected loads on CT core including CT sec. winding, wiring to control cubicles, relay and

metering equipment by Ohm-meter.

Core No. A-Phase (W) B-Phase (W) C-Phase (W) Remark

1 6.25 6.21 6.24

2 2.18 2.19 2.18

4.44 4.44 4.42

4.40 4.43 4.38

# 115KV CT LOOP CHECK_Line1 Page 1 of 53


# 115KV CT LOOP CHECK_Line1

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 01YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP CHECK_Line1 Page 2 of 53


# 115KV CT LOOP CHECK_Line1

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 01YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

6 Measure load burden including wiring, relay and meter equipment by volt-amp method.

Voltage measure (V) Burden calculated (VA)


Current inject
Core No.
(A)
Phase A Phase B Phase C Phase A Phase B Phase C

1 5 0.6762 0.6704 0.6724 3.3810 3.3520 3.3620

2 5 0.6698 0.6785 0.6882 3.3490 3.3925 3.4410

0.8185 0.8048 0.8097 0.0000 0.0000 0.0000

0.7469 0.7553 0.7564 0.0000 0.0000 0.0000

7 Supply 1 A. across the sec. terminal of CT, each phase.

8 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment and fault recorder.

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

12 A f 0.0 0.0

22 B 0.1532 0.0
GIS/=E01+S0
-X610
1
32 C 0.0 0.0 0.1623

11 N 0.1642 0.1530 0.1620

1 A 0.1648 0.0 0.0

2 B 0.0 0.1633 0.0


-X83
3 C 0.0 0.0 0.1613

=E01+ 4 N 0.1617 0.1623 0.1617

LCPP1SM A 0.1648 0.0 0.0


21/21N/67N/7
B 0.0 0.1633 0.0
9
Core1 1200/5 -PM Reading
&
C 0.0 0.0 0.1613
METERING
N 0.1617 0.1623 0.1617

A 0.1640 0.0 0.0

B 0.0 0.1680 0.0


-F21.1.1 Reading
C 0.0 0.0 0.1660
=E01+
N 0.1640 0.1680 0.1660
LCPP1&LCC
P2 RELAY A 0.0820 0.2 0.2
PANEL
B 0.1 0.2016 0.3
-F21.1.2 Reading
C 0.1 0.2 0.3818

N 0.0820 0.2688 0.4482

# 115KV CT LOOP CHECK_Line1 Page 3 of 53


# 115KV CT LOOP CHECK_Line1

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 01YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP CHECK_Line1 Page 4 of 53


# 115KV CT LOOP CHECK_Line1

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 01YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

A 0.0820 0.3 0.5

B 0.1 0.3360 0.6


DFR Panel -DFR Reading
C 0.1 0.4 0.6474

N 0.0820 0.4032 0.7138

A 0.0820 0.3 0.5


21/21N/67N/7
B 0.1 0.3360 0.6
9
Core1 1200/5 HMI HMI Reading
&
C 0.1 0.4 0.6474
METERING
N 0.0820 0.4032 0.7138

0.0820 0.3 0.5

0.1 0.3360 0.6

0.1 0.4 0.6474

0.0820 0.4032 0.7138

12 A 0.4929 0.0 0.0

22 B 0.0 0.4926 0.0


GIS/=E01+S0
-X620
1
32 C 0.0 0.0 0.4850

11 N 0.4951 0.4923 0.4851

1 A - 0.0 0.0

=E01+ 2 B 0.0 0.4926 0.0


-X81
LCPP1SM 3 C 0.0 0.0 0.4850

4 N 0.4951 0.4923 0.4851

A 0.4857 0.0 0.0

B 0.0 0.4872 0.0


Core2 1200/5 -F87B1 Reading 87B
C 0.0 0.0 0.4846

N 0.4832 0.4876 0.4850


=E00+
BZP
A 0.4842 0.0 0.0

B 0.0 0.4855 0.0


-F87B2 Reading
C 0.0 0.0 0.4852

N - - -

A 0.4842 0.0 0.0

B 0.0 0.4855 0.0


DFR Panel -DFR Reading
# 115KV CT LOOP CHECK_Line1 Page 5 of 53
# 115KV CT LOOP CHECK_Line1

Core2 1200/5 87B

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 01YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -


DFR Panel -DFR Reading
C 0.0 0.0 0.4852

N - - -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP CHECK_Line1 Page 6 of 53


# 115KV CT LOOP CHECK_Line2

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 04YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

BAY LINE.2

CT and Associated Current Circuit

General and Technical Information


Core No. Connected Ratio Class Burden Duty Remark

1 1200/5 10P20 200VA Protection & Metering

2 1200/5 10P20 200VA Busbar Protection (87B)

Commissioning Test Checked

1 Visually check all current circuits.

2 Verify the tightness of all connections.

3 Checking of insulation resistance of each circuit and grounded only one point.

4 Checking of polarity of all cores.

Core No. Connected Ratio Grounded Remark

1 1200/5 A112

2 1200/5 X82/5

X83/5

X84/5

5 Measure overall connected loads on CT core including CT sec. winding, wiring to control cubicles, relay and

metering equipment by Ohm-meter.

Core No. A-Phase (W) B-Phase (W) C-Phase (W) Remark

1 6.25 6.21 6.24

2 2.18 2.19 2.18

4.44 4.44 4.42

4.40 4.43 4.38

# 115KV CT LOOP CHECK_Line2 Page 7 of 53


# 115KV CT LOOP CHECK_Line2

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 04YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP CHECK_Line2 Page 8 of 53


# 115KV CT LOOP CHECK_Line2

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 04YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

6 Measure load burden including wiring, relay and meter equipment by volt-amp method.

Voltage measure (V) Burden calculated (VA)


Current inject
Core No.
(A)
Phase A Phase B Phase C Phase A Phase B Phase C

1 5 0.6762 0.6704 0.6724 3.3810 3.3520 3.3620

2 5 0.6698 0.6785 0.6882 3.3490 3.3925 3.4410

0.8185 0.8048 0.8097 0.0000 0.0000 0.0000

0.7469 0.7553 0.7564 0.0000 0.0000 0.0000

7 Supply 1 A. across the sec. terminal of CT, each phase.

8 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment and fault recorder.

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

12 A f 0.0 0.0

22 B 0.1532 0.0
GIS/=E04+S0
-X610
1
32 C 0.0 0.0 0.1623

11 N 0.1642 0.1530 0.1620

1 A 0.1648 0.0 0.0

2 B 0.0 0.1633 0.0


-X83
3 C 0.0 0.0 0.1613

=E04+ 4 N 0.1617 0.1623 0.1617

LCPP2SM A 0.1648 0.0 0.0


21/21N/67N/7
B 0.0 0.1633 0.0
9
Core1 1200/5 -PM Reading
&
C 0.0 0.0 0.1613
METERING
N 0.1617 0.1623 0.1617

A 0.1640 0.0 0.0

B 0.0 0.1680 0.0


-F21.2.1 Reading
C 0.0 0.0 0.1660
=E04+
N 0.1640 0.1680 0.1660
LCPP1&LCC
P2 RELAY A 0.0820 0.2 0.2
PANEL
B 0.1 0.2016 0.3
-F21.2.2 Reading
C 0.1 0.2 0.3818

N 0.0820 0.2688 0.4482

# 115KV CT LOOP CHECK_Line2 Page 9 of 53


# 115KV CT LOOP CHECK_Line2

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 04YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

# 115KV CT LOOP CHECK_Line2 Page 10 of 53


# 115KV CT LOOP CHECK_Line2

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 04YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

A 0.0820 0.3 0.5

B 0.1 0.3360 0.6


DFR Panel -DFR Reading
C 0.1 0.4 0.6474

N 0.0820 0.4032 0.7138

A 0.0820 0.3 0.5


21/21N/67N/7
B 0.1 0.3360 0.6
9
Core1 1200/5 HMI HMI Reading
&
C 0.1 0.4 0.6474
METERING
N 0.0820 0.4032 0.7138

0.0820 0.3 0.5

0.1 0.3360 0.6

0.1 0.4 0.6474

0.0820 0.4032 0.7138

12 A 0.4929 0.0 0.0

22 B 0.0 0.4926 0.0


GIS/=E04+S0
-X620
1
32 C 0.0 0.0 0.4850

11 N 0.4951 0.4923 0.4851

1 A - 0.0 0.0

=E04+ 2 B 0.0 0.4926 0.0


-X81
LCPP1SM 3 C 0.0 0.0 0.4850

4 N 0.4951 0.4923 0.4851

A 0.4857 0.0 0.0

B 0.0 0.4872 0.0


Core2 1200/5 -F87B1 Reading 87B
C 0.0 0.0 0.4846

N 0.4832 0.4876 0.4850


=E00+
BZP
A 0.4842 0.0 0.0

B 0.0 0.4855 0.0


-F87B2 Reading
C 0.0 0.0 0.4852

# 115KV CT LOOP CHECK_Line2 Page 11 of 53


# 115KV CT LOOP CHECK_Line2

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.


Core2 1200/5 FIELD INSPECTION AND TEST REPORT 87B

115 KV CT LOOP TEST


=E00+
SUBSTATION BZP TAI
: PATTAYA LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 04YC-01


-F87B2 Reading
CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

N - - -

A 0.4842 0.0 0.0

B 0.0 0.4855 0.0


DFR Panel -DFR Reading
C 0.0 0.0 0.4852

N - - -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP CHECK_Line2 Page 12 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA NUA LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

BAY TR2

CT and Associated Current Circuit

General and Technical Information


Core No. Connected Ratio Class Burden Duty Remark

1 1800/1 5P 20 20VA Busbar Protection (87B)

2 1800/1 0.5 20VA Metering


3 1800/1 5P 20 20VA Protection Main 2

4 1800/1 5P 20 20VA Protection Main 1

Commissioning Test Checked

1 Visually check all current circuits.

2 Verify the tightness of all connections.

3 Checking of insulation resistance of each circuit and grounded only one point.

4 Checking of polarity of all cores.

Core No. Connected Ratio Grounded Remark

1 1800/1 A112

2 1800/1 X82/5

3 1800/1 X83/5

4 1800/1 X84/5

5 Measure overall connected loads on CT core including CT sec. winding, wiring to control cubicles, relay and

metering equipment by Ohm-meter.

Core No. A-Phase (W) B-Phase (W) C-Phase (W) Remark

1 6.25 6.21 6.24

2 2.18 2.19 2.18

3 4.44 4.44 4.42

4 4.40 4.43 4.38

L2 EX Page 13 of 53
PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA NUA LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

L2 EX Page 14 of 53
PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA NUA LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

6 Measure load burden including wiring, relay and meter equipment by volt-amp method.

Voltage measure (V) Burden calculated (VA)


Current inject
Core No.
(A)
Phase A Phase B Phase C Phase A Phase B Phase C

1 1 0.6762 0.6704 0.6724 0.6762 0.6704 0.6724

2 1 0.6698 0.6785 0.6882 0.6698 0.6785 0.6882

3 1 0.8185 0.8048 0.8097 0.8185 0.8048 0.8097

4 1 0.7469 0.7553 0.7564 0.7469 0.7553 0.7564

7 Supply 1 A. across the sec. terminal of CT, each phase.

8 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment and fault recorder.

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

1 A f 0.0 0.0

5 B 0.1532 0.0
GIS/=E04+S0
-X301
1
9 C 0.0 0.0 0.1623

13 N 0.1642 0.1530 0.1620

1 A 0.1648 0.0 0.0

=E04+ 2 B 0.0 0.1633 0.0


-X81
LCPP2SM 3 C 0.0 0.0 0.1613

4 N 0.1617 0.1623 0.1617

A 0.1648 0.0 0.0

=E04+ B 0.0 0.1633 0.0


Core1 1800/1 -SM1 Reading 87B1/87B2
LCPP2SM C 0.0 0.0 0.1613

N 0.1617 0.1623 0.1617

10 A 0.1640 0.0 0.0

=E04+ 11 B 0.0 0.1680 0.0


-X81
LCPP2SM 12 C 0.0 0.0 0.1660

13 N 0.1640 0.1680 0.1660

A 0.0820 0.2 0.2

=E04+ B 0.1 0.2016 0.3


-SM2 Reading
LCPP2SM C 0.1 0.2 0.3818

N 0.0820 0.2688 0.4482

L2 EX Page 15 of 53
PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA NUA LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

L2 EX Page 16 of 53
PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA NUA LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

A 0.0820 0.3 0.5

B 0.1 0.3360 0.6


DFR Panel -DFR Reading
C 0.1 0.4 0.6474

N 0.0820 0.4032 0.7138

A 0.0820 0.3 0.5

B 0.1 0.3360 0.6


=E00+
Core1 1800/1 -F87B1 Reading 87B1/87B2
BZP
C 0.1 0.4 0.6474

N 0.0820 0.4032 0.7138

A 0.0820 0.3 0.5

B 0.1 0.3360 0.6


=E00+
-F87B2 Reading
BZP
C 0.1 0.4 0.6474

N 0.0820 0.4032 0.7138

1 A 0.4929 0.0 0.0

5 B 0.0 0.4926 0.0


GIS/=E04+S0
-X402
1
9 C 0.0 0.0 0.4850

13 N 0.4951 0.4923 0.4851

1 A - 0.0 0.0

2 B 0.0 0.4926 0.0


-X82
3 C 0.0 0.0 0.4850

4 N 0.4951 0.4923 0.4851


Core2 1800/1 Metering
CT1+ A 0.4857 0.0 0.0

=E04+ CT2+ B 0.0 0.4872 0.0


-PM
LCPP2SM CT3+ C 0.0 0.0 0.4846

- N 0.4832 0.4876 0.4850

10 A 0.4842 0.0 0.0

11 B 0.0 0.4855 0.0


-X82
12 C 0.0 0.0 0.4852

13 N - - -

L2 EX Page 17 of 53
PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA NUA LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

L2 EX Page 18 of 53
PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA NUA LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

A 0.4819 0.0 0.0

B 0.0 0.4850 0.0


-SM1 Reading
C 0.0 0.0 0.4852

A 0.4819 0.0 0.0

=E04+ B 0.0 0.4850 0.0


Core 2 1800/1 -SM2 Reading Metering
LCPP2SM C 0.0 0.0 0.4852

A 0.4819 0.0 0.0

B 0.0 0.4850 0.0


-HMI Reading
C 0.0 0.0 0.4852

1 A

5 B
GIS/=E04+S0
-X303
1
9 C

13 N

1 A

2 B
-X83
3 C

4. N
21/21N/67/67
Core3 1800/1
N/50BF/79
A

=E04+ B
-SM2 Reading
LCPP2SM C

B
-HMI Reading
C

L2 EX Page 19 of 53
PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA NUA LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

L2 EX Page 20 of 53
PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA NUA LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

Distance B
=E04+
Reading
LCPP2
No.2 C

N
21/21N/67/67
Core3 1800/1
N/50BF/79
A

B
DFR Panel -DFR Reading
C

1 A

5 B
GIS/=E04+S0
-X304
1
9 C

13 N

1 A

2 B
-X84
3 C

4. N

=E04+ B
21/21N/67/67
Core4 1800/1 -SM1 Reading
N/50BF/79
LCPP2SM C

B
-HMI Reading
C

Distance B
=E04+
Reading
LCPP2
No.1 C

L2 EX Page 21 of 53
PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA NUA LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

L2 EX Page 22 of 53
PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA NUA LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

B
21/21N/67/67
Core4 1800/1 DFR Panel -DFR Reading
N/50BF/79
C

10 Supply 1 A. across the Sec. terminal of CT phase AB , BC, CA at 0° to 180°, and ABC at 0° to -120° to 120°
Device. Measure Secondary measement (A) Correct
Core no. Location
No. Terminal No. Phase Phase A-B Phase B-C Phase C-A Phase ABC Core

1 A OK

5 B
GIS/=E04+S0
1 -X301
1
9 C

13 N

1 A OK

5 B
GIS/=E04+S0
2 -X402
1
9 C

13 N

1 A OK

5 B
GIS/=E04+S0
3 -X303
1
9 C

13 N

1 A OK

5 B
GIS/=E04+S0
4 -X304
1
9 C

13 N

L2 EX Page 23 of 53
PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA NUA LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

L2 EX Page 24 of 53
PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 02YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

BAY TR.1

CT and Associated Current Circuit

General and Technical Information


Core No. Connected Ratio Class Burden Duty Remark

1 1200/1 10P 20 200VA Protection

2 1200/1 10P 20 200VA Busbar Protection (87B)


TRANSFORMER 1200/1 10P 20 200VA Protection & Metering

Commissioning Test Checked

1 Visually check all current circuits.

2 Verify the tightness of all connections.

3 Checking of insulation resistance of each circuit and grounded only one point.

4 Checking of polarity of all cores.

Core No. Connected Ratio Grounded Remark

1 1200/5 A112

2 1200/5 X82/5

TRANSFORMER 1200/5 X83/5

X84/5

5 Measure overall connected loads on CT core including CT sec. winding, wiring to control cubicles, relay and

metering equipment by Ohm-meter.

Core No. A-Phase (Ω) B-Phase (Ω) C-Phase (Ω) Remark

1 6.25 6.21 6.24

2 2.18 2.19 2.18

TRANSFORMER 4.44 4.44 4.42

4.40 4.43 4.38

# 115KV CT LOOP CHECK_TR.1 Page 25 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 02YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP CHECK_TR.1 Page 26 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 02YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

6 Measure load burden including wiring, relay and meter equipment by volt-amp method.

Voltage measure (V) Burden calculated (VA)


Current inject
Core No.
(A)
Phase A Phase B Phase C Phase A Phase B Phase C

1 5 0.6762 0.6704 0.6724 3.3810 3.3520 3.3620

2 5 0.6698 0.6785 0.6882 3.3490 3.3925 3.4410

TRANSFORMER 5 0.8185 0.8048 0.8097 4.0925 4.0240 4.0485

0.7469 0.7553 0.7564 0.0000 0.0000 0.0000

7 Supply 1 A. across the sec. terminal of CT, each phase.

8 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment and fault recorder.

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

11 A

21 B
GIS/=E02+S0
-X610
1
31 C

12 N

1 A

=E02+ 2 B
-X84
TCPP1SM 3 C

4 N

=E02+ B
Core1 1200/5 TCPP1 -F87T Reading 87T
Relay C

B
DFR Panel -DFR Reading
C

# 115KV CT LOOP CHECK_TR.1 Page 27 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 02YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP CHECK_TR.1 Page 28 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 02YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

11 A

21 B
GIS/=E02+S0
X620
1
22 C

12 N

15 A

=E02+ 16 B
Core2 1200/5 X82 87B
TCPP1SM 17 C

18 N

B
=E00+
-F87B1 Reading
BZP
C

B
=E00+
-F87B2 Reading
BZP
C

B
DFR Panel -DFR Reading
C

N
Core2 1200/5 87B

# 115KV CT LOOP CHECK_TR.1 Page 29 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 02YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP CHECK_TR.1 Page 30 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 02YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

131 A

133 B
TR.1 X2
135 C

201 N

15 A
50/50N,51/51
TRANSFORMER 16 B
N
-X82
50BF&METE
1200/5 17 C
RING
=E02+ 18 N

TCPP1SM A

B
-PM Reading
C

B
HMI -HMI Reading
C

B
DFR Panel -DFR Reading
C

TRANSFORME N 50/50N,51/51
R N,50BF&MET
12000/5 A ERING

=E02+ B
TCPP1 -F51.1 Reading
Relay C

B
-BCU Reading
C

# 115KV CT LOOP CHECK_TR.1 Page 31 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 02YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP CHECK_TR.1 Page 32 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 05YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

BAY TR2

CT and Associated Current Circuit

General and Technical Information


Core No. Connected Ratio Class Burden Duty Remark

1 1200/1 10P 20 200VA Protection

2 1200/1 10P 20 200VA Busbar Protection (87B)


TRANSFORMER 1200/1 10P 20 200VA Protection & Metering

Commissioning Test Checked

1 Visually check all current circuits.

2 Verify the tightness of all connections.

3 Checking of insulation resistance of each circuit and grounded only one point.

4 Checking of polarity of all cores.

Core No. Connected Ratio Grounded Remark

1 1200/5 A112

2 1200/5 X82/5

TRANSFORMER 1200/5 X83/5

X84/5

5 Measure overall connected loads on CT core including CT sec. winding, wiring to control cubicles, relay and

metering equipment by Ohm-meter.

Core No. A-Phase (Ω) B-Phase (Ω) C-Phase (Ω) Remark

1 6.25 6.21 6.24

2 2.18 2.19 2.18

TRANSFORMER 4.44 4.44 4.42

4.40 4.43 4.38

# 115KV CT LOOP CHECK_TR.2 Page 33 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 05YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP CHECK_TR.2 Page 34 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 05YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

6 Measure load burden including wiring, relay and meter equipment by volt-amp method.

Voltage measure (V) Burden calculated (VA)


Current inject
Core No.
(A)
Phase A Phase B Phase C Phase A Phase B Phase C

1 5 0.6762 0.6704 0.6724 3.3810 3.3520 3.3620

2 5 0.6698 0.6785 0.6882 3.3490 3.3925 3.4410

TRANSFORMER 5 0.8185 0.8048 0.8097 4.0925 4.0240 4.0485

0.7469 0.7553 0.7564 0.0000 0.0000 0.0000

7 Supply 1 A. across the sec. terminal of CT, each phase.

8 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment and fault recorder.

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

11 A

21 B
GIS/=E05+S0
-X610
1
31 C

12 N

1 A

=E05+ 2 B
-X84
TCPP2SM 3 C

4 N

=E05+ B
Core1 1200/5 TCPP2 -F87T Reading 87T
Relay C

B
DFR Panel -DFR Reading
C

# 115KV CT LOOP CHECK_TR.2 Page 35 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 05YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP CHECK_TR.2 Page 36 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 05YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

11 A

21 B
GIS/=E05+S0
X620
1
22 C

12 N

15 A

=E05+ 16 B
Core2 1200/5 X82 87B
TCPP2SM 17 C

18 N

B
=E00+
-F87B1 Reading
BZP
C

B
=E00+
-F87B2 Reading
BZP
C

B
DFR Panel -DFR Reading
C

N
Core2 1200/5 87B

# 115KV CT LOOP CHECK_TR.2 Page 37 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 05YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP CHECK_TR.2 Page 38 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 05YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

131 A

133 B
TR.2 X2
135 C

201 N

15 A
50/50N,51/51
TRANSFORMER 16 B
N
-X82
50BF&METE
1200/5 17 C
RING
=E05+ 18 N

TCPP2SM A

B
-PM Reading
C

B
HMI -HMI Reading
C

B
DFR Panel -DFR Reading
C

TRANSFORME N 50/50N,51/51
R N,50BF&MET
12000/5 A ERING

=E05+ B
TCPP2 -F51.1 Reading
Relay C

B
-BCU Reading
C

# 115KV CT LOOP CHECK_TR.2 Page 39 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 05YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP CHECK_TR.2 Page 40 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


22 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 22 kV Switchgear

CONTRACT NO. : จ.281/2560 DEVICE NO. : T1L1,L2,L3

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

BAY TR2

CT and Associated Current Circuit

General and Technical Information


Core No. Connected Ratio Class Burden Duty Remark

1 1200/5 1M5 10VA Metering


2 1200/5 10P 20 40VA Protection & Arc
3 1200/5 10P 20 40VA Transformer Diff (87T)

Commissioning Test Checked

1 Visually check all current circuits.

2 Verify the tightness of all connections.

3 Checking of insulation resistance of each circuit and grounded only one point.

4 Checking of polarity of all cores.

Core No. Connected Ratio Grounded Remark

1 1200/5

2 1200/5

3 1200/5

5 Measure overall connected loads on CT core including CT sec. winding, wiring to control cubicles, relay and

metering equipment by Ohm-meter.

Core No. A-Phase (Ω) B-Phase (Ω) C-Phase (Ω) Remark

3 4.44 4.44 4.42

# 22KV CT LOOP CHECK_Incoming1 Page 41 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


22 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 22 kV Switchgear

CONTRACT NO. : จ.281/2560 DEVICE NO. : T1L1,L2,L3

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 22KV CT LOOP CHECK_Incoming1 Page 42 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


22 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 22 kV Switchgear

CONTRACT NO. : จ.281/2560 DEVICE NO. : T1L1,L2,L3

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

6 Measure load burden including wiring, relay and meter equipment by volt-amp method.

Voltage measure (V) Burden calculated (VA)


Current inject
Core No.
(A)
Phase A Phase B Phase C Phase A Phase B Phase C

1 5

2 5

3 5 0.8185 0.8048 0.8097 4.0925 4.0240 4.0485

7 Supply 1 A. across the sec. terminal of CT, each phase.

8 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment and fault recorder.

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

549 A

552 B
-X1
555 C

558 N

22 A

24 B
-TT4
26 C

28 N
22kV
Core3 1200/5 87T
Incoming .1
A

B
-DFR Reading
C

# 22KV CT LOOP CHECK_Incoming1 Page 43 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


22 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 22 kV Switchgear

CONTRACT NO. : จ.281/2560 DEVICE NO. : T1L1,L2,L3

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 22KV CT LOOP CHECK_Incoming1 Page 44 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


22 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 22 kV Switchgear

CONTRACT NO. : จ.281/2560 DEVICE NO. : T1L1,L2,L3

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

BAY TR2

CT and Associated Current Circuit

General and Technical Information


Core No. Connected Ratio Class Burden Duty Remark

1 1200/5 1M5 10VA Metering


2 1200/5 10P 20 40VA Protection & Arc
3 1200/5 10P 20 40VA Transformer Diff (87T)

Commissioning Test Checked

1 Visually check all current circuits.

2 Verify the tightness of all connections.

3 Checking of insulation resistance of each circuit and grounded only one point.

4 Checking of polarity of all cores.

Core No. Connected Ratio Grounded Remark

1 1200/5

2 1200/5

3 1200/5

5 Measure overall connected loads on CT core including CT sec. winding, wiring to control cubicles, relay and

metering equipment by Ohm-meter.

Core No. A-Phase (Ω) B-Phase (Ω) C-Phase (Ω) Remark

3 4.44 4.44 4.42

# 22KV CT LOOP CHECK_Incoming2 Page 45 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


22 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 22 kV Switchgear

CONTRACT NO. : จ.281/2560 DEVICE NO. : T1L1,L2,L3

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 22KV CT LOOP CHECK_Incoming2 Page 46 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


22 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 22 kV Switchgear

CONTRACT NO. : จ.281/2560 DEVICE NO. : T1L1,L2,L3

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

6 Measure load burden including wiring, relay and meter equipment by volt-amp method.

Voltage measure (V) Burden calculated (VA)


Current inject
Core No.
(A)
Phase A Phase B Phase C Phase A Phase B Phase C

1 5

2 5

3 5 0.8185 0.8048 0.8097 4.0925 4.0240 4.0485

7 Supply 1 A. across the sec. terminal of CT, each phase.

8 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment and fault recorder.

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

549 A

552 B
-X1
555 C

558 N

22 A

24 B
-TT4
26 C

28 N
22kV
Core3 1200/5 87T
Incoming .2
A

B
-DFR Reading
C

# 22KV CT LOOP CHECK_Incoming2 Page 47 of 53


PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


22 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 22 kV Switchgear

CONTRACT NO. : จ.281/2560 DEVICE NO. : T1L1,L2,L3

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 22KV CT LOOP CHECK_Incoming2 Page 48 of 53


# 115KV CT LOOP BZP&BCCP1

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

BAY TR2

CT and Associated Current Circuit

General and Technical Information


Core No. Connected Ratio Class Burden Duty Remark

1 1200/5 10P20 200VA Busbar Protection (87B)

2 1200/5 10P20 200VA Busbar Protection (87B)

Commissioning Test Checked

1 Visually check all current circuits.

2 Verify the tightness of all connections.

3 Checking of insulation resistance of each circuit and grounded only one point.

4 Checking of polarity of all cores.

Core No. Connected Ratio Grounded Remark

1 1200/5 A112

2 1200/5 X82/5

X83/5

X84/5

5 Measure overall connected loads on CT core including CT sec. winding, wiring to control cubicles, relay and

metering equipment by Ohm-meter.

Core No. A-Phase (W) B-Phase (W) C-Phase (W) Remark

1 6.25 6.21 6.24

2 2.18 2.19 2.18

4.44 4.44 4.42

4.40 4.43 4.38

# 115KV CT LOOP BZP&BCCP1 Page 49 of 53


# 115KV CT LOOP BZP&BCCP1

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

6 Measure load burden including wiring, relay and meter equipment by volt-amp method.

Voltage measure (V) Burden calculated (VA)


Current inject
Core No.
(A)
Phase A Phase B Phase C Phase A Phase B Phase C

1 5 0.6762 0.6704 0.6724 3.3810 3.3520 3.3620

2 5 0.6698 0.6785 0.6882 3.3490 3.3925 3.4410

0.8185 0.8048 0.8097 0.0000 0.0000 0.0000

0.7469 0.7553 0.7564 0.0000 0.0000 0.0000

7 Supply 1 A. across the sec. terminal of CT, each phase.

8 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment and fault recorder.

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

12 A f 0.0 0.0

22 B 0.1532 0.0
GIS/=E01+S0
-X610
1
32 C 0.0 0.0 0.1623

11 N 0.1642 0.1530 0.1620

1 A 0.1648 0.0 0.0

2 B 0.0 0.1633 0.0


-X81
3 C 0.0 0.0 0.1613

=E01+ 4 N 0.1617 0.1623 0.1617

BCPP1SM

Core1 1200/5 87B

A 0.1640 0.0 0.0


=E03+
# 115KV CT LOOP BZP&BCCP1
BZP&BCCP1 -F87B1 Reading Page 50 of 53
RELAY
# 115KV CT LOOP BZP&BCCP1

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
Core1 1200/5 87B
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -


=E03+
B 0.0 0.1680 0.0
BZP&BCCP1 -F87B1 Reading
RELAY C 0.0 0.0 0.1660
PANEL
N 0.1640 0.1680 0.1660

A 0.0820 0.2 0.2

B 0.1 0.2016 0.3


DFR Panel -DFR Reading
C 0.1 0.2 0.3818

N 0.0820 0.2688 0.4482

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

# 115KV CT LOOP BZP&BCCP1 Page 51 of 53


# 115KV CT LOOP BZP&BCCP1

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.

FIELD INSPECTION AND TEST REPORT


115 KV CT LOOP TEST
SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

9 Reading the measured values of all sec. current output at all loads e.g. relays, meter equipment.
Core Device. Measure (A) Correct
Location
No. No. Terminal No. Phase Phase A Phase B Phase C Core

12 A 0.0820 0.3 0.5

22 B 0.1 0.3360 0.6


GIS/=E01+S0
X620
1
32 C 0.1 0.4 0.6474

11 N 0.0820 0.4032 0.7138

1 A 0.1648 0.0 0.0

=E01+ 2 B 0.0 0.1633 0.0


Core2 1200/5 -X82 87B
BCPP1SM 3 C 0.0 0.0 0.1613

4 N 0.1617 0.1623 0.1617

A
=E03+
B
BZP&BCCP1 BCU Reading
RELAY C
PANEL
N

A 0.1640 0.0 0.0


=E03+
B 0.0 0.1680 0.0
BZP&BCCP1 -F87B2 Reading
RELAY C 0.0 0.0 0.1660
PANEL
N 0.1640 0.1680 0.1660

A 0.0820 0.2 0.2

B 0.1 0.2016 0.3


DFR Panel -DFR Reading
C 0.1 0.2 0.3818

N 0.0820 0.2688 0.4482

Core2 1200/5 87B

# 115KV CT LOOP BZP&BCCP1 Page 52 of 53


# 115KV CT LOOP BZP&BCCP1

PEA. SUBSTATION CONSTRUCTION DIVISION. COMPANY

200 Ngam Wong Wan Road, Chatuchak, Bangkok 10900 Thailand.


Core2 1200/5 FIELD INSPECTION AND TEST REPORT 87B

115 KV CT LOOP TEST


SUBSTATION : PATTAYA TAI LOCATION : 115 kV GIS

CONTRACT NO. : จ.281/2560 DEVICE NO. : 03YC-01

CONTRACTOR : ITALTHAI ENGINEERING CO.,LTD. SERIAL NO. : -

RESPONSIBILITY TESTED BY CONFIRMED BY WITNESSED BY APPROVED BY

COMPANY ITALTHAI ENGINEERING CO.,LTD. ITALTHAI ENGINEERING CO.,LTD. PROVINCIAL ELECTRICITY AUTHORITY

NAME Mr. Rattapong Chaitawong Mr.Kitsana Phanthuna Mr. Nirin Techadisai

SIGNATURE

DATE 19/8/2016 19/8/2016 19/8/2016

# 115KV CT LOOP BZP&BCCP1 Page 53 of 53