The document outlines scope of work for cranes across multiple areas of an ammonia plant, urea plant, utility and power house, and PH & S. It includes tasks such as replacing catalysts, inspecting and repairing safety valves, overhauling pumps, punch killing jobs, dismantling and refitting control valves and man holes, inspecting distributors and beds, replacing lines, and replacing gear boxes on various conveyors.
The document outlines scope of work for cranes across multiple areas of an ammonia plant, urea plant, utility and power house, and PH & S. It includes tasks such as replacing catalysts, inspecting and repairing safety valves, overhauling pumps, punch killing jobs, dismantling and refitting control valves and man holes, inspecting distributors and beds, replacing lines, and replacing gear boxes on various conveyors.
The document outlines scope of work for cranes across multiple areas of an ammonia plant, urea plant, utility and power house, and PH & S. It includes tasks such as replacing catalysts, inspecting and repairing safety valves, overhauling pumps, punch killing jobs, dismantling and refitting control valves and man holes, inspecting distributors and beds, replacing lines, and replacing gear boxes on various conveyors.
2. Glands packing of SX, SH and SL valves. 3. Replacement of Methanator catalyst. 4. CO2 line replacement up to CO2 compressor suction drum. 5. CO2 Absorber (A-101-E), Inspection of distributors, beds height & demister cleaning. 6. CO2 Stripper (A-102-E), Inspection of distributors, beds height & demister cleaning. 7. Inspection of Safety Valves (list will be provided later). 8. A-101-JC Surface condenser.(End plates removal). 9. Punch killing jobs (list will be provided later).
Urea Plant
1. Inspection & Repair of Safety Valves.
2. Overhauling of High pressure pumps. 3. Shifting of water Jetting Machine. 4. Punch Killing jobs. 5. Dismantling & refitting of Stripper Top Man Hole. 6. Dismantling & refitting of control valves.
Utility & Power House
1. Dismantling & refitting of safety valves at Boiler No 1.
2. Repair of walls / doors of superheater of boiler No 3. 3. Punch Killing Jobs (List will be provided later). 4. Cooling water steam turbine CGT 3301 a/b/c general checking & Inspection. 5. Checking of safety valves of superheater and steam drum of Boiler No 3. 6. Overhauling of pump CGA 3302 A/B . 7. General overhauling of motor of IGG Unit. 8. Repair / overhauling / cleaning of cooling water return line main valves (02 Nos.). 9. To rectify the seat leakage of Boiler feed water control valve. 10. Cleaning of Nitrogen cooler.
PH & S
1. Replacement of gear box of SJD-101 Conveyor.
2. Replacement of gear box of SJD-102 Conveyor. 3. Replacement of gear box of SJD-103 Conveyor. 4. Replacement of gear box of SJD-106 Conveyor. 5. Replacement of gear box of SJD-107 Conveyor. 6. Replacement of gear box of SJD-108 Conveyor. 7. Replacement of gear box of SJD-109 Conveyor. 8. Replacement of gear box of SJD-110 Conveyor. 9. Replacement of drive / driven pulleys of Conveyors if required.