Professional Documents
Culture Documents
Case 5
Case 5
As per the case, 20 units of T178 are required to produce Z101. As annual demand of Z101 is 40 units,
the annual demand of T178 = 20*40 = 800 units
The process flow and the appropriate cost breakup is also given which is displayed below:
Assumption: It is assumed that the parts/processes mentioned in the table above are required to make
T178. This is not clearly mentioned in the case.
The decision to be taken is to manufacture it in-house or outsource it to Supper Suppliers. The costs
associated with both the scenarios is analysed below:
a. In-House Manufacturing
Cost of each item = $150.1
Fixed cost = 20% of total produced
Assumptions made: No uncertainty, Zero breakdowns, Zero quality losses, Zero production losses, JIT
manufacturing, Zero safety / buffer stock.
Assumptions made: 10% of total volume taken as buffer stock to compensate for quality losses,
breakdown losses and production losses
Using the concept of Economic Order Quantity (EOQ) to calculate the optimum order quantity:
Therefore total cost = Purchase Cost + Inventory Cost = (108.2*800) + (0.2*108.2)*75/2 + 800*75/75
= $ 88172
Recommendation:
Using these 2 options, it is better to outsource the parts rather than to make it In-House. It will
give a savings of $70334.
There is a 3rd option that is mentioned below. It is a little unorthodox but some organizations
do practice it under certain circumstances.
c. Mixed model
The mixed model entails using the best of both worlds (in-house and outsource) depending on the cost
of each part (T67, T75, T69, T77, T70) required to make T178. There are some major assumptions being
made here as the data provided to consider this option is not available.
Assumptions:
Under these assumptions, the parts that need to made in-house and those need to be outsourced are as
follows:
Using the concept of Economic Order Quantity (EOQ) to calculate the optimum order quantity:
Therefore total cost = Purchase Cost + Inventory Cost = (102.4*800) + (0.2*102.4)*77/2 + 800*75/77
= $ 83487
Conclusion: As can be seen, if al the assumptions provided can be met, the lowest cost comes out to be
the 3rd option of a mixed model.