Professional Documents
Culture Documents
S 'Umist,: K. UK UK UK
S 'Umist,: K. UK UK UK
S 'Umist,: K. UK UK UK
'UMIST, UK
qational Grid Company, UK
Power Technology, UK
397
comprishg a portfolio of reactive support contracts to dispatch, a reactive capacity layout ( QE ,Q; ,QK ,Qf)),
be purchased, the settings of preventive controls as well
-j
as the preventive generation active power dispatch for including proposed settings of preventive controls ( k e )
each loading condition, is made. for each loading condition.
The feasibility of the proposal is evaluated at the Slave This single state OPF problem can be formulated with
level (second stage). For each contingent state at each the objective function as follows:
load condition (demand level), this assessment carried
out using an advanced non-linear programming based
optimal power flow (OPF). Objective:
398
Nodal violated v,oltage constraints for non voltage
controlled buses: lar load level). Vectors - refer to the sensitivity
au e
=(Pt,Qi,,Ep 1 ( 20)
coefficients of the reactive power output with respect to
av; the control variables. Note that constraints in Equation
Vmin 5 V p ) +-(Ue - u y ) s Vmax (21) (22) are the linear approximations of the constraints in
h e Equation (8).
Reactive power constraints for voltage controlled
buses: After selecting the states with most severely violated
- Q F , e -Q! 'Q,e j(0) + constraints from each individual load level, the con-
straints in Equation (21)-(23) are formed. These con-
straints are brought back from decision evaluation to the
decision making sub-problem, whch improves the
decision to satisfy all constraints. The improved deci-
MVA constraints (demand level and system state
specific): sions (QE ,Q,",QF , Q! and k e ) are then fed to the
decision evaluation sub-problems, the feasibility check-
ers.
Active power re-dispatch constraints MODELLING GENERATOR LOADING CAPA-
Pe -P: - 1 p +De = O ( 24) BILITY CHART
NG
C(Pi,!-PIT]() =o ( 25)
i =1
idack
ue represent the vectors of control variables to be op- Figure 2 Generator loading capability chart
timised and comprises of vectors of active power dis-
patch, reactive injections at non-voltage control buses Figure 2 illustrates the piece wise linear approximation
of the generator loading capability chart. The chart is
(QJ
gx
) and positions of preventive controls for each broken down into several linear segments. If the number
loading condition. of breakpoints is n, than number of segments n-1. P, to
P, denote the possible range of active power production.
Constraints (2 1) are formed for each load level from the Outside that range, generator may not be stable or could
states with most severely violated voltages, indicated by E
be overloaded.Q,",,I QEl andQEn I Qr,nrepresent
the presence of new reactive reinforcement. Vi repre- the maximum reactive power generation I absorption
sents the vectors of voltages at voltage optimised buses when generator produces active power at minimum and
with subscript j and .! being referred to the severely maximum level respectively. Increasing the number of
segments will make the approximation closer to the real
av{
violated system state and load level. -refers to the one. However, the optimisation problem becomes more
he complex and more difficult to solve since the number of
vectors of sensitivity coefficients of the bus voltage integer variables increases. In practice, a trapezoidal
magnitudes at demand level .!in j-th system state to the form may be sufficient.
control variables.
Constraints (29 - 37) are added into the decision-
making problem to include generation loading capabil-
Constraints in Equation (22) are formed for the voltage-
ity chart constraint.
controlled buses for each load level. Vectors of reactive
power outputs ( C& ) at voltage-controlled buses (sub-
Pe -a:P1 -a:P2 - .........-a;€', =P~(y'-l) (29)
script j refer to the state with most severely violated
reactive constraint, while l? corresponds to the particu- a:,! -.:a:,, -.:a:,, ---afQF,n <Q;,~(Y' -1) (30)
399
nificant impact on the voltage and local reactive power
requirements.
h4xQcapabilityatbus 28
. h'0xOcapabilityatbus 31
400
Table 2 Loading conditions and their duration for each investment required by optimising control variables in
case preventive and/or corrective modes. The coupled man-
I Duration(h) 1 agement of active and reactive power for voltage con-
trol strategy, showed by minimising the cost of voltage
dnven out of merit generation and allocation of VAr
support contract and investment are presented. Genera-
tor loading capability chart was modelled and discussed.
This tool can optimise reactive support of the system
across a number of demand levels taking into account
some credible contingencies. Case studies performed
show that the developed SA-SCOPF is applicable to
Table 3 Reactive capability layout and out of merit large-scale power systems.
generation reauired for each case
QPE QNE QPP QNP OMG ACKNOWLEDGEMENTS
(MVAr) (MVAr) (MVAr) (MVAr) (MW)
Case 1 19904 534 832 32 0 The authors gratefully acknowledge the support from
EPSRC (GRW37489) and the valuable inputs from
(case 3 I 1693 11 521 404 24 126d National Grid Company and Power Gen.
Columns “QPE” and “QNE” present the reactive gen-
eration and absorption capability from existing VAR REFERENCES
providers (generators) respectively. Column “QPF’” and [l] Strbac, G. et al, 1997,”Co-ordination of investment deci-
“QNP” consist the reactive generation and absorption sions and controls in reactive power planning”, Paper
capability from new reactive sources suggested to be 342-05, CIGRE symposium on Open access, Tours,
installed. While column “ O M G gives of the amount of France, 8- 12 June.
out of merit generation required to be dispatched to [2] Pudjianto,D. et al, 2001, “Optimal Reactive Power
enforce the satisfaction of voltage constraint. allocation using Sensitivity Analysis Based Security
Constrained OPF (SA-SCOPF)” , IPECOl, May,
Table 3 shows that when the duration of the peak de- Singapore
mand period (51,028 MW) is long, engaging out of [3] Chebbo, A.M. et al, 1995,”Combined Active and Reac-
merit generation is an expensive option. Installation of tive Dispatch, Parts I and II”, IEE Proceedings, Part C,
new VAR support (864 MVAr) combined with reactive Vol. 142, No.4, July, pp 393 - 405.
capability committed from generators (19909 MVAr) is [4] J..Kubokawa et al, 1998,”An Interior Point nonlinear
the preferred option. programming for Optimal Power Flow with a novel data
structure”, IEEE Tarns.on Power Systems, Vo1.13, No.3,
August, pp. 870-877.
However, when the duration of the peak reduces to
157h, some 364 MW out-of-merit generation is dis- [5] V.H. Quintana et. al, 2000, “Interior Point methods and
patched, while the capacity of new VARs installed their applications to Power Systems: A classification of
publications and Software codes”, IEEE Tams. on Power
reduces from 832MVAr (lagging) and 32 MVAr (lead- Systems, Vol. 15, No. 1, February, pp. 170-176.
ing) to 638 MVAr (lagging) and 23 MVAr (leading)
[6] National Grid Company plc., Seven Years Statement,
respectively. Also amount of reactive capability pur-
2000.
chased from the generators reduces from 19,909 MVAr
(lagging) and 534 MVAr (leading) to 18,713 MVAr
(lagging) and 439 MVAr (leading).
CONCLUSION
401