Professional Documents
Culture Documents
High Rise Const
High Rise Const
TABLE OF CONTENTS
SECTION - 1 INTRODUCTION
I. Demands & Evaluation of high rise building
High rise buildings are becoming prominent these days due to following reasons scarcity of land increasing
demand for business and residential space economic growth technological advancement innovations in
structural systems desire for aesthetics in urban setting cultural significance and prestige human aspiration
to build higher.
The first high-rise buildings were constructed in the United States in the 1880s. They arose in urban areas
where increased land prices and great population densities created a demand for buildings that rose
vertically rather than spread horizontally, thus occupying less precious land area. High-rise buildings were
made practicable by the use of steel structural frames and glass exterior sheathing.
High-rise building, also called high-rise, multistory building tall enough to require the use of a system of
mechanical vertical transportation such as elevators. The skyscraper is a very tall high-rise building
The foundations of high-rise buildings must sometimes support very heavy gravity loads, and they usually
consist of concrete piers, piles, or caissons that are sunk into the ground. Beds of solid rock are the most
desirable base, but ways have been found to distribute loads evenly even on relatively soft ground.
The most important factor in the design of high-rise buildings, however, is the building’s need to withstand
the lateral forces imposed by winds and potential earthquakes. Most high-rises have frames made of steel
or steel and concrete.
High-rise buildings are enclosed by curtain walls; these are non-load-bearing sheets of glass, masonry,
stone, or metal that are affixed to the building’s frame through a series of vertical and horizontal members
called mullions and muntins.
Because of their height and their large occupant populations, high-rises require the careful provision of life-
safety systems. Fire-prevention standards should be strict, and provisions for adequate means of egress in
case of fire, power failure, or other accident should be provided.
National Building Code (Part 4) – Fire and Life Safety all buildings 15m and above in height shall be considered
as high rise buildings
I. Demands & Evaluation of high rise building
a) Braced Frame
Lateral forces are resisted by axial actions of bracing and columns
Steel bracing members or filled-in bays
More efficient than a rigid frame
Advantages: - Girders only participate minimally in the lateral bracing Action-Floor framing design
is independent of its level in the structure. Can be repetitive up the height of the building with
obvious economy in design and fabrication.
Disadvantages: - Obstruct the internal planning and the locations of the windows and doors; for
this reason, braced bent are usually incorporated internally along wall and partition lines,
especially around elevator, stair, and service shaft. -Diagonal connections are expensive to
fabricate and erect.
Most usual form of construction for tall buildings up to 30 stories in height Column and girder
framing of reinforced concrete, or sometimes steel, is in-filled by panels of brickwork, block
work, or cast-in-place concrete. Because of the in-filled serve also as external walls or internal
partitions, the system is an economical way of stiffening and strengthening the structure. The
complex interactive behavior of the infill in the frame, and the rather random quality of
masonry, has made it difficult to predict with accuracy the stiffness and strength of an in-filled
frame.
The outrigger system is an efficient structural form that consists of a central core with outriggers,
connecting the core to the outer columns. The central core contains of either braced frames or
shear walls. When the building is loaded laterally the vertical plane rotations are resisted by the
outriggers through tension in the windward columns and compression in the leeward columns, as
in figure This is augmenting the lateral stiffness of the building and reducing the lateral deflections
as well as the moments in the core. In addition, the outriggers join the columns and makes the
building behave almost as a composite cantilever. Even the perimeter columns, those not directly
connected to the outriggers, can be used to increase the lateral resistance of the building by
connecting all the perimeter columns with a horizontal girder around the building’s facade.
Multilevel outrigger systems can provide up to five times the moment resistance of a single
outrigger system. Outrigger systems have been used for buildings up to 70 stories but the concept
should hold for even higher buildings.
SECTION – 3 EVOLUTATION OF STRUCTURE SYSTERM
I. Concrete buildings
In this section some differences between cast in-situ and precast concrete are explained as well
as different types of connections.
Concrete buildings can either be cast in-situ, composed with precast elements oar combination
of both. If the building is cast in-situ it is possible to start the activities on site in an early stage.
Preparation for scaffolding and molding can start as soon as the contract is assigned to the
contractor and the design of the building starts. This is not possible when constructing with
precast elements as all decisions regarding dimensions, shapes and so forth has to be taken long
before the activities on site can start. When using precast elements, it is of importance to
industrialize the manufacturing. This implies manufacturing in covered factories, use of
automatic tools and thoroughly plan the production process. There are some important
differences regarding cast in-situ and precast buildings. When a building is cast in-situ the
elements are created in molds on site and are constantly checked to have the correct height. But
when a building is constructed with precast elements the elements are created in a factory
where the factory worker is fully dependent on the drawing. If for example a column has the
wrong height on the drawing, no one will correct this in the factory and an incorrect column will
be created causing problems on site.
SECTION – 4 CONSTRUCTION METHODS AND TECHNIQUES
a) SLIP FORM
PROCEDURE:
• Assembly can only start once the foundations are in place and the wall starter is in correct
alignment.
• Slip form shuttering is aligned with the help of yokes.
• Horizontal crossbeams connect these yokes.
• Hydraulic jacks are attached to these crossbeams for simultaneous upward movement.
• Height of the slip form ranges from 1.1 to 1.5 meters.
• Yokes and crossbeams also used to support the working platform.
• Structure should be rigid and shape maintained at all times.
• Make sure there is no lag or else it prevents the structure from free upward movement
• It is also possible to reduce wall thicknesses.
b) JUMP FORM
Generally, jump form systems comprise the formwork and working platforms for
cleaning/fixing of the formwork, steel fixing and concreting.
Jump form, often described as climbing form. It is suitable for construction of multi-floor
vertical concrete elements in high-rise structures, such as shear walls, core walls, lift
shafts, stair shafts and bridge pylons.
It is a highly productive system designed to increase speed and efficiency while
minimizing labor and time.
PROCESS EFFICIENCY-
Fast construction can be achieved by careful planning of the construction process. Crane
availability is critical for normal jump form.
Self-climbing formwork cuts down the requirement for crane time considerably. By allowing
the crane to be used for other construction work this may reduce the total number of cranes
needed on site.
The formwork is independently supported, so the shear walls and core walls can be
completed ahead of the rest of the main building structure. This can help to provide stability
to the main structure during its construction and can have the beneficial effect of taking the
jump from core off the project critical path.
SAFETY.
Working platforms, guard rails, and ladders are built into the completed units of market-
leading formwork systems. Complete wind-shield protection on platform edges is also
possible.
Self-climbing formwork systems are provided with integral free-fall braking devices. The
completed formwork assembly is robust and provides a stable working platform.
The reduced use of scaffolding and temporary work platforms results in less congestion on
site.
The setting rate of concrete in those parts of the structure supporting the form is critical in
determining the rate at which construction can safely proceed.
The repetitive nature of the work means that site operatives can quickly become familiar
with health and safety aspects of their job. Formwork suppliers provide materials and
resources to help train the labor force.
Climbing formwork is a special type formwork for vertical concrete structures that rises
with the building process. While relatively complicated and costly, it can be an effective
solution for buildings that are either very repetitive in form (such as towers or
skyscrapers) or that require a seamless wall structure (using gliding formwork, a special
type of climbing formwork).
Various types of climbing formwork exist, which are either relocated from time to time, or
can even move on their own (usually on hydraulic jacks, required for self-climbing and
gliding formworks). Types of climbing form
Type of Climbing formwork
Climbing formwork (self-climbing): In this type of the structure elevates itself with
the help of mechanic leverage equipment (usually hydraulic). To do this, it is usually
fixed to sacrificial cones or rails emplaced in the previously cast concrete.
Gliding formwork: This type of formwork is similar to the climbing type above.
However, the climbing process is continuous instead of intermittent, and is usually
only interrupted for a very short time (for example to fix the mounting mechanisms
to new anchoring points). The advantage is that it will produce seamless structures,
but it requires a continuous, uninterrupted process throughout, with serious
potential quality and stability problems if the pour has to be stopped
f) TUNNEL FORM
Tunnel form is used to form repetitive cellular structures, and is widely recognised as a
modern innovation that enables the construction of horizontal and vertical elements
(walls and floors) together.
Significant productivity benefits have been achieved by using tunnel form to construct
cellular buildings such as hotels, low- and high-rise housing, hostels, student
accommodation, prison and barracks accommodation.