Professional Documents
Culture Documents
Rev - 06 - Ms - Installation of Electric Galvanized Conduits
Rev - 06 - Ms - Installation of Electric Galvanized Conduits
FOR
INSTALLATION OF ELECTRIC GALVANIZED CONDUITS
TABLE OF CONTENTS
3. LOCATION OF ACTIVITY
6. OPERATION
7. INSTALLATION
8. FIXATION
9. RESPONSIBILITIES
16. DISTRIBUTION
1. INTRODUCTION AND SCOPE
This method of statement specify the detailed requirements and
procedures for the installation of Galvanized Conduits for
the exposed surface installation requirement for MEP services of
buildings.
Division: Installation
3. LOCATION OF ACTIVITY
Mechanical Room / Exposed Area.
6. OPERATION
Material: Material used will be as approved by the Engineer. The sizes
and routes routing will be as per the approved Shop Drawings.
7. INSTALLATION
No conduit smaller than 20mm in diameter or larger than 32mm
diameter shall be used.
o Straight run - 10 m.
Conduits shall not be run closer than 0.15m to any steam or hot
water pipes and shall be run underneath such pipes rather than
over them. It should not also be run closer than 0.05m to any
telephone, bell or other signaling circuit.
8. FIXATION
When conduits are run on shuttering, prior to the laying of
concrete insist, additional security must be provided near to
every box and at intervals of not more than 1.2 meters by the
introduction of short lengths of steel wire, of not less than 2mm
diameter twisted around the conduit and reinforcing steel. The
conduits shall be adequately fixed to prevent excessive
movement and damage during the pouring and setting of
concrete and shall be protected from mechanical damage.
Check there is no damage before screed/concrete is poured.
Unless otherwise indicated, to cast in conduits shall not be less
than 30mm. Cores to plaster over conduits shall not be less than
5mm. Galvanized or cadmium plated screws shall be used in all
cases where galvanized conduit is installed.
9. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
1. Painting Brush
2. Measuring tape
3. Cutting plier
4. Threading Machine
6. Bending Machine
7. Pipe Wrench
8. Drilling Machine
9. Round files
16. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer