Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

GENERAL CONSTRUCTION NOTES

GENERAL NOTES NOTES ON CONCRETE MIXES & PLACING


1. ALL CONCRETE SHALL DEVELOP A MIN. COMPRESSIVE STRENGTH AT THE END OF TWENTY EIGHT 3. IF SLABS ARE REINFORCED BOTH WAYS BARS ALONG THE SHORTER SPAN SHALL BE PLACED
1.0 STANDARDS AND REFERENCES BELOW THOSE ALONG THE LONG SPAN AT THE CENTER AND OVER THE LONGER SPAN FOR
(28) DAYS W/ CORRESPONDING MAXIMUM SIZE AGGREGATE & SLUMP AS FOLLOWS.
THE FOLLOWING SHALL GOVERN THE DESIGN FABRICATION AND CONSTRUCTION OF THE PROJECT. REINFORCING BARS NEAR THE SUPPORTS. THE SPACING OF THE BARS AT THE COLUMN STRIPS
1.1 NATIONAL STRUCTURAL CODE OF THE PHILIPPINES (N.S.C.P 2015) VOL.1, SEVENTH EDITION. MAX. SIZE OF SHALL NOT BE MORE THAN ONE AND A HALF (1 21 ) SLAB THICKNESS.
LOCATION 28 DAYS STRENGTH AGGREGATE MAX SLUMP
2.0 DESIGN CRITERIA ALL OTHERS, INCLUDING 20mm 100mm 4. TEMPERATURE BARS FOR SLAB SHALL BE GENERALLY PLACED NEAR THE FACE IN TENSION AND
4000 PSI(27.6 MPa)
2.1 LOADINGS SHALL NOT BE LESS THAN 0.0025 X GROSS-SECTIONAL AREA (Ag) OF THE SLAB.

CONF.REINF.
SUSPENDED SLABS JOINT HOOP SPACE @ "2Sh" WHEN
COLUMNS 4000 PSI(27.6 MPa) 20mm 100mm (SEE SCHEDULE BELOW)
A. DEAD LOAD THERE ARE BEAMS HAVING WIDTH OF
BEAMS 4000 PSI(27.6 MPa) 20mm 100mm

D JOINTREINF. D PER SCHEDULE D JOINT REINF. D


CONCRETE 23.56kNm 3 AT LEAST ONE-HALF THE COLUMN
SLABONFILL 2500 PSI(17.5 MPa) 20mm 100mm SCHEDULE OF MINIMUM SLAB REINFORCEMENT WIDTH & DEPTHS NOT LESS THAN
STEEL 76.93kNm 3 THREE QUARTERS OF THE DEEPEST
150mmTHK.CHBWALL 2.73kPa 2. MAINTAIN MINIMUM CONCRETE COVER FOR REINFORCING STEEL AS FOLLOWS. MINIMUMTEMPERATUREBARS BEAM THAT FRAME INTO FOUR

CONF.REINF.
100mmTHK.CHBWALL 2.11kPa SUSPENDED SLABS 20mm 100mm 10mmØ @250mm EACH WAY SIDES OF THE COLUMN. ALL OTHER
B. LIVE LOAD SLAB ON GRADE 40mm 125mm 10mmØ @250mm EACH WAY CONDITIONS USE HOOPS @ "Sh" CENTERS.

Sh
WALLS ABOVE THE GRADE 25mm
ROOF 1.00kPa 150mm 10mmØ @250mm EACH WAY
BEAM STIRRUPS AND COLUMN TIES 40mm

COLUMN TIES AS
CLASSROOMS 1.90kPa 175mm 10mmØ @250mm EACH WAY
WHERE CONCRETE IS EXPOSED TO FOR COL. BAR SPLICES SEE TABLE
TOILETS 1.90kPa 200mm 10mmØ @250mm EACH WAY
CORRIDORS ABOVE, STAIRS 3.80kPa EARTH BUT POURED AGAINST FORMS 50mm OF MIN. LAP SPLICE LENGTH OF
WHERE CONCRETE IS DEPOSITED COLUMN REINFORCEMENT
CORRIDORS ON GROUND 4.80kPa 75mm 5. UNLESS OTHERWISE NOTED IN THE PLANS ALL BEDDED SLABS SHALL BE REINFORCED WITH 10mmØ
DIRECTLY AGAINST EARTH
AT 250mm O.C. EACH WAY TO CENTER OF SLAB AND CONSTRUCTION JOINTS FOR SAME SHALL

CONF.REINF.
C. WIND LOAD
BUILDING CATEGORY = 1 (ESSENTIAL FACILITIES) NOT BE LESS THAN 3.65 METER APART.

Sh
3. CONCRETE SHALL BE DEPOSITED IN ITS FINAL POSITION WITHOUT SEGREGATION. RE-HANDLING
OR PLACING SHALL BE DONE PREFERABLY WITH BUGGIES, BUCKETS OR WHEEL BARROWS, 6. PROVIDE EXTRA REINFORCEMENTS FOR CORNER SLAB (TWO ADJACENT DISCONTINUES EDGES) NOTE:
OPTION 1
NO CHUTES WILL BE ALLOWED EXCEPT TO TRANSFER CONCRETE FROM HOPPERS TO BUIGGIES, AS SHOWN BELOW. ALL CONCRETE REINF. DETAIL SHOULD
EXPOSURE CAT. D (FLAT UNOBSTRUCTED AREAS AND/OR NEAR BODIES OF WATER) WHEEL BARROWS OR BUCKETS IN WHICH CASE THEY SHALL NOT EXCEED SIX (6) METERS BE DONE IN ACCORDANCE WITH ACI
7. CONCRETE SLAB REINFORCEMENT SHALL BE PROPERLY SUPPORTED WITH 10mm STEEL CHAIR DETAILING MANUAL (LATEST EDITION)
WIND VELOCITY V = 340 KPH

CONF.REINF.
IN AGGREGATE LENGTH. OR APPROVED EQUIVALENT SPACED AT 1.0 METER ON CENTER BOTH WAYS.
P = qh (GCpf) - (GCpi) (DESIGN WIND PRESSURE)
4. NO DEPOSITING OF CONCRETE SHALL BE ALLOWED WITHOUT THE USE OF VIBRATORS UNLESS
WHERE: qh = VELOCITY PRESSURE (kPa)
AUTHORIZED IN WRITING BY DESIGNER AND ONLY FOR UNUSUAL CONDITIONS WHERE VIBRATIONS
GCpf = EXTERNAL PRESSURE COFFECIENT Ø12x1000 LONG AT
ARE EXTREMELY DIFFICULT TO ACCOMPLISH. MID-DEPTH OF SLAB
GCpf = INTERNAL PRESSURE COFFECIENT
5. ALL ANCHOR BOLTS, DOWELS, AND OTHER INSERTS SHALL BE PROPERLY POSITIONED & SECURED TYPICALCOLUMNELEV.SHOWING
D. SEISMIC LOAD IN PLACE PRIOR TO PLACING OF CONCRETE. DOWN INTO EDGE BEAM. EXTENDED AT EACH CORNER DOWELSANDTIESSPACING
4-Ø 12@1800 LONG TOP BARS BEND 1-Ø12 TOP &
Cvl W (DESIGN BASE SHEAR) 6. ALL CONCRETE SHALL BE KEPT MOST FOR A MINIMUM OF SEVEN CONSECUTIVE DAYS IMMEDIATELY BARS MIN. OF1,200 (4'-0") INTO BARS. BOTT.BARS
V= AFTER POURING BY THE USE OF WET BURLAP, FOG SPRAYING, CURING COMPOUNDS OR OTHER
RT
APPROVED METHODS. 4-Ø12 BOTT. BARS
Vmax= 2.50CaI W

400
Vmin= 0.11CalW
RT 7. STRIPPING OF FORMS AND SHORES: LAP SPLICE LENGTH:
Vmin= 0.80ZNvI W (ZONE4) FOUNDATION 24 HOURS AT ANY LEVEL NO MORE THAN
R

0
ALTERNATE BARS SHOULD BE

60
SUSPENDED SLAB EXCEPT WHEN 8 DAYS 0 SLAB 38mm
WHERE: W = TOTAL DEAD LOAD 60 OPENING CLEAR SPLICED. MIN .DISTANCE BET.
ADDITIONAL LOADS ARE IMPOSED
T = NATURAL PERIOD = Ct(h) WALLS 21 DAYS TWO ADJACENT BARS SPLICES
SHALL BE 600mm.
WHERE: C = NUMERICAL COEFFICIENT

400
BEAMS 14 DAYS

CONF.REINF.TIESLAT.TIES H(CLEARHEIGHTOFCOL.)
h = BUILDING HEIGHT 21 DAYS L
COLUMNS
I = IMPORTANCE FACTOR = 1.50

WITHIN CENTER
IN TWO WAY SLAB EXTEND

HALF OF "H"
R= NUMERICAL FACTOR = 8.50 8. THE CONTRACTOR SHALL SUBMITT HIS SCHEDULE OF POURING AND THE LOCATION OF THE BARS UP TO BEAM SUPPORT

60
CONSTRUCTION JOINTS TO THE STRUCTURAL ENGINEER AT LEAST (4) DAYS PRIOR TO THE

0
SEISMIC COEFFICIENT Cv = 0.44Nv 0.25L
POURING FOR APPROVAL. OMIT TRIMMER BARS WHERE
Ca = 0.64Nv OPENING IS FRAMED BY BEAM TOP BARS @ SUPPORT (CONT.)
NEAR SOURCE FACTOR (5km) Nv = 1.6 9. THE CONTRACTOR SHALL FURNISH AND MAINTAIN ADEQUATE FORMS AND SHORING UNTIL THE TYPICAL CORNER SLAB DETAIL REQ'D. BOTT. BARS @ SUPPORT
Na = 1.2 CONCRETE MEMBERS HAVE ATTAINED THEIR WORKING CONDITION AND STRENGTH. TYPICAL SLAB

JT. REINF.
Z = SEISMIC ZONE = 0.40 (ZONE 4) OPENING DET.
S = SOIL TYPE = D
NOTES ON FOOTINGS
2.2 DESIGN STRESSES 1. FOOTINGS ARE DESIGNED FOR AN ALLOWANCE SOIL BEARING PRESSURE OF 96 KPa(2000 psf).
A. CONCRETE COMPRESSIVE STRENGTH @ 28 DAYS: CONTRACTOR SHALL REPORT TO THE ENGINEER, IN WRITING, THE ACTUAL SOIL CONDITIONS NOTES ON COLUMNS 0.165L SPLICE BOTTOM BARS
AT MIDSPAN
a. FOOTINGS, COLUMNS, BEAMS AND SLABS f'c = 27.6 MPa(4,000 psi) UNCOVERED AND CONFIRM ACTUAL BEARING CAPACITY OF SOIL BEFORE DEPOSITING CONCRETE. 1. PROVIDE EXTRA SETS OF TIES AT 100 O.C. FOR TIED COLUMN REINFORCEMENT ABOVE 0.22L EXTRA TOP BARS
b. SLAB ON FILL f'c = 17.5 MPa(2,500 psi) 2. FOOTING SHALL REST AT LEAST 1500mm BELOW NATURAL GRADE LINE UNLESS OTHERWISE AND BELOW BEAM-COLUMN CONNECTIONS FOR A DISTANCE FROM FACE OF CONNECTION @ SUPPORT
C. SLAB f'c = 27.6 MPa(4,000 psi) INDICATED IN PLANS. NO FOOTING SHALL REST ON FILL EQUAL TO GREATER OF THE OVERALL THICKNESS OF COLUMN, 16 TIMES THE CLEAR HEIGHT OF
3. MINIMUM CONCRETE PROTECTION FOR REINFORCEMENT SHALL BE 75mm CLEAR FOR CONCRETE COLUMN OR 450mm.
B. REINFORCING STEEL BARS
a. FOR BARS 16mm AND GREATER (INTERMEDIATE GRADE DEFORMED BAR) fy = 414 MPa(60,000 psi) DEPOSITED THE GROUND AND 50mm FOR CONCRETE DEPOSITED AGAINST A FORM WORK.
b. FOR BARS LESS THAN 16mm (STRUCTURAL GRADE DEFORMED BAR) fy = 275 MPa(40,000 psi) 4. IN CASES WHERE THE SOIL CONDITION IS SUCH THAT THE MINIMUM ALLOWABLE SOIL PRESSURE
2. COLUMN TIES SHALL BE PROTECTED EVERY WHERE BY A COVERING OF CONCRETE CAST
MONOLITHICALLY WITH THE CORE WITH A MINIMUM THICKNESS OF 40mm AND NOT LESS
TYP. DETAIL OF COL. LAP SPLICE
OF 96 KPa(2000 psf) CANNOT BE ATTAINED AT A PRACTICAL DEPTHS THE USE OF MICROPILES,
C. STRUCTURAL STEEL ASTM-A36 BORED PILES, OR DRIVEN PILES MAY BE ADOPTED IN LIEU OF STANDARD ISOLATED FOOTINGS. THAN 40 TIMES THE MAXIMUM SIZE OF COARSE AGGREGATE IN MILLIMETERS. & EXT. GIRDER TO COL. CONNECT.
FOR TRUSSES, BRACING ,& STRUTS fy = 248 MPa(36,000 psi) 3. WHERE COLUMNS CHANGE IN SIZE, VERTICAL REINFORCEMENT SHALL BE OFF SET AT A
D. PURLINS SLOPE MONOLITHICALLY WITH THE CORE WITH MINIMUM THICKNESS OF 40mm AND
COLD FORMED LIGHT fy = 248 MPa(36,000 psi) NOTES ON REINFORCEMENT
E. MASONRY UNIT (CHB) NOT LESS THAN 40 TIMES THE MAXIMUM SIZE COARSE AGGREGATE IN MILLIMETERS
1. UNLESS OTHERWISE NOTED IN PLANS, THE YIELD STRENGTH OF REINFORCING BARS SHALL BE: 4. UNLESS OTHERWISE INDICATED IN THE PLANS, LAP SPLICES FOR VERTICAL COLUMN NOTES ON BEAMS AND GIRDERS
NON-LOADING BEARING CHB WALLS fm' = 3.45 MPa(500 psi) fy = 414 MPa(60,000 psi)
A. FOOTINGS, FOOTING BEAMS AND GIRDERS REINFORCEMENT SHALL BE MADE WITHIN THE CENTER HALF OF COLUMN HEIGHT, AND
F. WELDS E - 60XX ELECTRODE fy = 414 MPa(60,000 psi) 1. UNLESS, OTHERWISE NOTED IN PLANS, CAMBER ALL BEAMS AND GIRDER AT
a. Ft = 96.60MPa(14,000 psi) B. COLUMNS AND SHEAR WALLS THE SPLICE LENGTH SHALL BE LESS THAN 40 BAR DIAMETERS. WELDING OR APPROVED
G. STRUCTURAL BOLTS ASTM-A307 fy = 414 MPa(60,000 psi) LEAST 6mmØ FOR EVERY 4.50m OF SPAN, EXCEPT CANTILEVERS FOR WHICH
b. Fv=69.00 MPa(10,000 psi) C. BEAMS AND GIRDER MECHANICAL DEVICES MAYBE USED PROVIDED THAT NOT MORE THAN ALTERNATE BARS
3.0 IN THE INTERPRETATION OF THE DRAWING, INDICATED DIMENSIONS SHALL GOVERN. D. NON-LOAD BEARING WALL PARTITIONS, BEDDED SLABS, FLOOR & ROOF SLABS, THE CAMBER SHALL BE AS NOTED IN PLANS OR AS ORDERED BY THE ENGINEER
PARAPETS, CATCH BASIN, SIDEWALK fy = 275 MPa(40,000 psi) ARE WELDED OR MECHANICALLY SPLICED AT ANY LEVEL AND THE VERTICAL DISTANCES
DISTANCES AND SIZES SHALL NOT BE SCALED FOR CONSTRUCTION PURPOSES BETWEEN THESE WELDS OR SPLICES OF ADJACENT BARS IS NOT LESS THAN 600mm. BUT IN NO CASE LESS THAN 20mm FOR EVERY 3.0M OF FREE SPAN.
2. ALL REINFORCING BARS SIZE 10mm OR LARGER SHALL BE DEFORMED IN ACCORDANCE WITH THE ASTM A-706
4.0 IN REFERENCES TO OTHER DRAWINGS, SEE ARCHITECTURAL DRAWINGS FOR DEPRESSIONS IN FLOOR 2. TYPICAL BARS BENDING AND CUTTING DETAILS FOR BEAMS SHALL BE AS
BARS SMALLER THAN 10mm MAY BE PLAIN.
SLABS, OPENINGS IN THE WALLS AND SLABS,INTERIOR PARTITIONS, LOCATIONS OF DRAINS ETC. 3. SPLICES SHALL BE SECURELY WIRED TOGETHER & SHALL LAP OR EXTEND IN ACCORDANCE w/ TABLE B SHOWN IN FIG.B-1
5.0 IN CASE OF DISCREPANCIES AS TO THE LAYOUT, DIMENSIONS AND ELEVATIONS BETWEEN THE (TABLE OF LAP SPLICE & ANCHORAGE LENGTH) UNLESS OTHERWISE SHOWN ON DRAWINGS, SPLICES SHALL BE H
STRUCTURAL PLANS AND ARCHITECTURAL DRAWINGS, THE CONTRACTORS SHALL NOTIFY BOTH THE STAGGERED WHEN EVER POSSIBLE.
STRUCTURAL ENGINEER AND ARCHITECT. CROSS-TIE
NOTES ON CONCRETE SLABS

350mm.MAX.
6.0 ALL CONCRETE WORKS AND CONCRETE REINFORCEMENTS SHALL BE DONE IN ACCORDANCE WITH THE L1 L2
ACI.318-14M BUILDING CODE REQUIREMENT AND ALL STRUCTURAL STEEL WORKS ACCORDING WITH THE 1. ALL SLAB REINFORCEMENTS SHALL BE 20mm CLEAR MINIMUM FROM BOTTOM AND FROM THE TOP OF SLAB. L1 3
1
L13 L23 L23
AISC-05 IN SO FAR AS THEY DO NOT CONFLICT WITH THE LOCAL BUILDING CODE REQUIREMENT. 2. UNLESS OTHERWISE SHOWN, REINFORCEMENT IN CONTINUOUS ELEVATED SLAB SHALL BE CUT AS FOLLOWS:

10

H
dm
7.0 ACI REFERS TO AMERICAN CONCRETE INSTITUTE, AISC REFERS TO AMERICAN INSTITUTE OF STEEL

in.
CONSTRUCTION AND ASTM REFERS TO AMERICAN SOCIETY FOR TESTING MATERIALS.
BENTBAR
8.0 CONSTURCTION NOTES AND TYPICAL DETAILS APPLY TO ALL DRAWINGS UNLESS OTHERWISE SHOWN OR
NOTED. MODIFY TYPICAL DETAILS AS DIRECTED TO MEET SPECIAL CONDITIONS. L1 L2 1
L1 5 L15 L25 L25
L14 L14 L24 TOPBARS
9.0 SHOP DRAWING WITH ERECTION AND PLACING DIAGRAMS OF ALL STRUCTURAL STEELS, MISCELLANEOUS TOPBAR 2 Ø 12mm SIDE BARS WEBBARS
IRON, PRE-CAST CONCRETE, ETC. SHALL BE SUBMITTED FOR ENGINEERS APPROVAL BEFORE FABRICATION. BOTTOMBARS
10. CONTRACTOR SHAL LNOTE AND PROVIDE ALL MISCELLANEOUS CURBS,SILLS, STOOLS EQUIPMENT AND
MECHANICAL BASES THAT ARE REQUIRED BYTHEARCHITECTURAL, ELECTRICAL AND MECHANICAL DRAWINGS.
FIGUREB-1
11. ALL RESULTS OF THE MATERIAL TESTING FOR CONCRETE, REINFORCING BARS & STRUCTURAL STEEL MUST
BOTTOMBAR
BE NOTED & APPROVED BY THE MATERIALS ENGINEER OR STRUCTURAL DESIGNER.

NO. DATE REVISIONS/COMMENTS SHEET CONTENTS : SHEET NO. :


JOB NO. :
CHRISTIAN G. GODINO PROPOSED 2 STOREY RESIDENTIAL GENERAL CONSTRUCTION NOTES
DATE : -
STRCUTURAL ANALYSIS AND CONSTRUCTION
CIVIL ENGINEER WITH DECK RESIDENCE MR. AND MRS. CARLITO MENESES SCALE :
BORONGAN CITY, EASTERN SAMAR CADD BY :
MOBILE #:09263791625
EMAIL: chrisgodino@yahoo.com 0117452 9186683 LOCATION :
BRGY. 02, POBLACION, MAYDOLONG, EASTERN SAMAR
PROJECT OWNER CHECKED BY : S-1
MAY 2019 BORONGAN CITY DATE :

You might also like