Concrete works unit qty

grd. Flr. Slab cu.m 3 0.03


2nd flr. Slab cu.m 3
beam cu.m 1.6 0.54 0.9
roof beam cu.m 1.6
wall footing cu.m 2.83 1.32
footing cu.m 0.986
others 0.12
column 0.54

Plastering
2 face sq.m 254 33.6 1.6 48 43.2 18.56

Chb laying sq.m 202.58 21 223.58 2906.54

Gravel bedding cu.m 3.6 0.242 3 0.3 0.48

Tile setting

item of works
excavation works/filling &compaction 6500
soil poisoning 500
gravel bedding & compaction 1000
tileworks 4500
2 cr 4000
kitchen 1600
vinyl works 2500
chb laying 30000
concreting 20000
roofing 6500
truss and steel works 6500
electrical works 15000
carpentry works 15000
plastering 40000
painting 15000
plumbing works 10000
reinforcement works 8500
finishes/moulding 8500
grill works 3500
installation of windows 3500
collection of debris/garbage/gen. cleaning 2500
total labor cost 205,100.00
material
total cement sand gravel cement sand
3.03 30.3 4.0905 8.181 77,660.93 40,146.00
3 30 3.9 8.1
3.04 30.4 3.952 8.208
1.6 16 2.08 4.32
4.15 41.5 5.395 11.205
0.986 9.86 1.2818 2.6622
0.12 1.2 0.156 0.324
0.54 5.4 0.702 1.458

2 4.2 405.16 115.76 25.00416

223.58 96.88467 20.34578

10.622 10.622

11 2.31

total 388.3047 69.21724 55.0802


total material cost
gravel
33,048.12 150,855.05