Precalculation Gedung Kuliah Teknik Elektro Ruang Kuliah Teknik Listrik

PT. KIL (KUTILANG INDO LAMP)

Price /
Kode Price / unit Waktu Waktu pekerja Upah / Upah pekerja
NO. Material Unit Quantity material
material (Rp) / unit (jam) jam (Rp)
(Rp)
1. Saklar Seri Pcs DMC 2 25.000 50.000 0.3 0.6 8500 5.100
2. Elbow Buah DMC 5 500 2.500 0.15 0.75 8500 6.375
3. Kotak Hubung Pcs DMC 6 15.000 90.000 0.3 1.8 8500 15.300
4. Kotak Kontak Pcs DMC 2 25.000 50.000 0.35 0.7 8500 5.950
5. Pipa PVC 5/8 Pcs DM 12 33.000 396.000 0.8 9.6 8500 81.600
6. Isolasi Pcs DM 5 15.000 75.000 0.25 1.25 8500 10.625
NYA 4 mm2 25
7. M DM 50 4.000 200.000 0.05 8500 212.500
(merah)
8. NYA 4 mm2 (biru) M DM 50 4.000 200.000 0.05 25 8500 212.500
NYA 4 mm2 25 212.500
9. M DM 50 4.000 200.000 0.05 8500
(Hijau-Kuning)
10. MCB 20 A Pcs DMC 4 220.000 880.000 0.2 0.8 8500 6.800
Armatur TL 3
11. Pcs DMC 6 170.000 1.020.000 0.5 8500 25.500
2x40W
12. Lampu TL 40W Pcs DMC 12 70.000 840.000 0.75 9 8500 76.500
13. Klem buah DM 100 550 55.000 0.05 5 8500 42.500
Jumlah 6.858.500 Jumlah 920.125
RANCANGAN ANGGARAN BIAYA PEMASANGAN INSTALASI LISTRIK
PT. KIL (KUTILANG INDO LAMP)
Kode Price / unit Harga
NO. Material Unit Quantity
material (Rp) Tender (Rp)
1. Saklar Seri Pcs DMC 2 53.060 106.120
2. Elbow Buah DMC 5 6.912 34.560
3. Kotak Hubung Pcs DMC 6 39.180 235.080
4. Kotak Kontak Pcs DMC 2 54.164 108.328
5. Pipa PVC 5/8 Pcs DM 12 196.560 2.358.720
6. Isolasi Pcs DM 5 35.312 176.560
NYA 4 mm2
7. M DM 50 29.250 1.462.500
(merah)
8. NYA 4 mm2 (biru) M DM 50 29.250 1.462.500
NYA 4 mm2
9. M DM 50 29.250 1.462.500
(Hijau-Kuning)
10. MCB 20 A Pcs DMC 4 442.720 1.770.880
Armatur TL 365.500
11. Pcs DMC 6 2.193.000
2x40W
12. Lampu TL 40W Pcs DMC 12 254.750 3.057.000
13. Klem buah DM 100 5.350 535.000
Jumlah 14.962.748