Conference Center Project

WBS: 1.1.4.3

Work Package: Place equipment

Package Owner: Brett Dolnichio

Owner Org: IT

Participants: IT staff, IT vendor resources

Description:
Place network equipment and servers on racks as specified in the vendor’s installation instructions
document.

Place computers and audiovisual equipment in meeting rooms as specified in the vendor’s room
configuration document.

Completion State:
All equipment has been put in place in the conference center as specified in the vendor’s documents.

Reference Docs:
ConferenceCenter_Installation_Diagram.pdf
ConferenceCenter_Room_Configuration.pdf