Sop For Ba-Hp Pump (r1)
Sop For Ba-Hp Pump (r1)
FOR
BA HP WATER PUMP
INTRODUCTION: HP water pump is required to conveying the ash slurry from bottom ash hopper to slurry
sump. It is obtained by 04 nos of HP water pump for 06 units. For 03 units 01 nos HP water pump is running and
another one is standby).
PRE CHECKS:
HP WATER PUMP(BA) TECHNICAL DATA:-
Make Shijiazhuang Kingda Quantity 04 Nos
Pump Industry Group
Co. Ltd
Type M100KSSH-XA Discharge Capacity 385m³/h
Discharge 1.17mpa Rotating speed r/min
Pressure
Sealing fan’s motor
Type YKK400-4 Power 250kW
Voltage 11KV Current
Rotating speed r/min
RESPONSIBILITY: Unit Control Engineer, Field Engineer and Desk Engineer.
SAFTEY PRECAUTIONS:
1. Ensure no permit to work is pending on regarding this system by checking with EE/MRSE.
OPERATING PROCEDURE -
Description RESPONSIBILITY
Sr. UCE DE FE EE
No
.
PRE- START CHECKS:
1 All permits and cross permits have been returned.
2 Power supply and control power supply available.
3 Sealing water line pressure normal.
4 Check Pump suction & discharge valve close.
1.PLANNED SHUTDOWN :
1 Insure that water tank level is low or any leakage is found in pipe line.
2 Stop the BA-HP water pump & closed the suction & discharge valve.
3 Rectify the probable problem, if any.
INTERLOCKS : Remarks
1 Water tank level is danger low.
2 Seal water pump stopped.
3 Pump suction & discharge open feedback.
ABRIVIATIONS / NOTATIONS:-
o SOP: Standard Operating Procedure
o UCE: Unit Control Engineer
o DE: Desk Engineer
o FE: Field Engineer
o DCS: Distributed Control System
o EE: Electrical Shift Engineer
o MFT: Main Fuel Trip.
o RB : Run Back
DO’s :
Prepared by: Reviewed by: Approved by:
Signature: Signature: Signature:
Name: Name: Name:
Designation: Designation: Designation:
KSK Mahanadi Power Company Ltd.
2. Ensure that Seal Water Pump is running before starting the Pump.
4. Ensure that Jet Pump Suction/Discharge valves are open before stopping the Pump.
DONT’s :