MFT de Cast Cost

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

2/27/2017

COST ESTIMATION IN FOUNDRY SHOP

ESTIMATION OF COST OF CASTINGS

The total cost of manufacturing a component consists of


following elements :

TEKNIK DAN SISTEM PRODUKSI


PE4652 – Teknologi Manufaktur

1
2/27/2017

Material Cost
A. Cost of material required for casting is calculated as follows :
i. From the component drawing, calculate the volume of
material required for casting.
ii. This volume multiplied by density of material gives the
net weight of the casting.
iii. Add the weight of process scrap i.e. weight of runners,
gates and risers and other material consumed as a part
of process in getting the casting.
iv. Add the allowance for metal loss in oxidation in furnace,
in cutting the gates and runners and over runs etc.
v. Multiply the total weight by cost per unit weight of the
material used.
vi. Subtract the value of scarp return from the amount
obtained in step (iv), to get the direct material cost.

TEKNIK DAN SISTEM PRODUKSI


PE4652 – Teknologi Manufaktur

Material Cost
B. In addition to the direct material, various other materials are
used in the process of manufacture of a casting.

i. Materials required in melting the metal, i.e., coal,


limestone and other fluxes etc. The cost of these materials
is calculated by tabulating the value of material used on
per tonne basis and then apportioned on each item.
ii. Material used in core shop for making the cores, i.e., oils,
binders and refractories etc. The cost of core materials is
calculated depending upon the core size and method of
making the core. Similarly the cost of moulding sand
ingredients is also calculated. The expenditure made on
these materials is generally expressed as per kg of casting
weight and is covered under overhead costs.

TEKNIK DAN SISTEM PRODUKSI


PE4652 – Teknologi Manufaktur

2
2/27/2017

Labour Cost

Labour is involved at various stages in a foundry shop.


Broadly it is divided into two categories :

i. The cost of labour involved in making the cores,


baking of cores and moulds is based on the time
taken for making various moulds and cores.
ii. The cost of labour involved in firing the furnace,
melting and pouring of the metal. Cleaning of
castings, fettling, painting of castings etc., is generally
calculated on the basis of per kg of cast weight.

TEKNIK DAN SISTEM PRODUKSI


PE4652 – Teknologi Manufaktur

Direct Other Expenses

Direct expenses include the expenditure incurred on


patterns, core boxes, cost of using machines and other
items which can be directly identified with a particular
product.

TEKNIK DAN SISTEM PRODUKSI


PE4652 – Teknologi Manufaktur

3
2/27/2017

Overhead Expenses

The overheads consist of the salary and wages of


supervisory staff, pattern shop staff and inspection staff,
administrative expenses, water and electricity charges etc.
The overheads are generally expressed as percentage of
labour charges.

The cost of a cast component is calculated by adding the


above constituents.

TEKNIK DAN SISTEM PRODUKSI


PE4652 – Teknologi Manufaktur

Example

TEKNIK DAN SISTEM PRODUKSI


PE4652 – Teknologi Manufaktur

4
2/27/2017

Calculate the total cost of CI (Cast Iron) cap , from the


following data :

A Cost of molten iron at Rp 6000 per Kg


cupola spout
B Process scrap 17% net wt casting
C Process scrap return value Rp 1000 per Kg
D Administrative overhead Rp 400 x per kg of metal
charges poured
E Density of material used 7,2 gr/cm3

TEKNIK DAN SISTEM PRODUKSI


PE4652 – Teknologi Manufaktur

The other expenditure details are :

Shop
Labour
overhead
Time per charges
Process s (Rp)
piece (Rp) per
per hr
hr

Moulding and
F 10 min 6000 6000
pouring
Casting removal,
G 4 min 2000 6000
gate cutting etc.
Fettling and
H 6 min 2000 6000
inspection
TEKNIK DAN SISTEM PRODUKSI
PE4652 – Teknologi Manufaktur

5
2/27/2017

Solution : To calculate material cost

I Volume of the component Cm3


J Net weight of the casting IxE Kg
K Process scrap JxB Kg
L Metal required per piece J+K Kg
M Material cost/piece LXA Rp/Kg
N Process return KxC Rp
O Net material cost per piece M–N Rp

TEKNIK DAN SISTEM PRODUKSI


PE4652 – Teknologi Manufaktur

Calculate Labour Cost and Overheads


Process Time per Labour Shop
piece charges per overheads
piece (Rp) per piece
(Rp)
Moulding
10 min 10/60 x 6000 6000 x 10/60
and pouring
Casting
removal,
4 min 4/60 x 2000 6000 x 4 / 60
gate cutting
etc.
Fettling and
6 min 6/60 x 2000 6000 x 6 /60
inspection
Total P Q
TEKNIK DAN SISTEM PRODUKSI
PE4652 – Teknologi Manufaktur

6
2/27/2017

R Labour charges P
S Shop overheads Q
T Administrative overheads D
U Total cost per piece O+R+S+T

TEKNIK DAN SISTEM PRODUKSI


PE4652 – Teknologi Manufaktur

You might also like