Esitimation & Costing: S.No Description Code No'S Needed Block Work
Esitimation & Costing: S.No Description Code No'S Needed Block Work
BLOCK WORK
Block Masonary in CM(1:6) prop using 1ST grade autoclaved aerated concrete block having a compressive Stren
Kg/cm3, thermal conductivity 0.132 - 0.151 for 800 Kg/m3, Dry Density 750 - 800 Kg/m3 including cost and con
material and water to work site and all operational, incidental labour charges such as mixing mortor, constructin
charges, curing etc complete for finished item of work 0.10 m / 0.20m thick wall.
BRICK WORK
Brick Masonary in CM(1:6) prop using 2nd class brick having a crushing strength not less than 35 Kg/ Sqcm inclu
conveyance of material and water to work site and all operational, incidental labour charges such as mixing mort
constructing masonary, lift charges, curing etc complete for finished item of work 0.22 M thick brick walls
PARAPET WALL 1
WATCH MANS CABIN
GROUND FLOOR 0.10M THICK WALL 1 1
2 1
3 4
4 4
5 1
6 2
7 1
8 1
9 1
10 1
11 1
12 1
ESITIMATION & COSTING
LENGTH BREADTH DEPTH QUANTITY/ NO UNITS TOTAL QUANTITY
RS 2225.39 / CU.M
CU.M
CU.M
CU.M
CU.M
CU.M
CU.M
CU.M
CU.M
CU.M
CU.M
CU.M
CU.M
CU.M
CU.M
CU.M
CU.M
S.NO DESCRIPTION / RAW MATERIAL NO'S DIMENSIONS UNITS
ACC BLOCK 1 0.22M X 0.10M X 0.075M 1 BLOCK
BRICK BLOCK 1 0.19M X 0.09M X 0.09M 1 BLOCK
GRADE / QUALITY AMOUNT/UNIT
1ST GRADE RS 45/-
2ND CLASS RS 22/-
RATE ANALYSIS
0.00
S. No Quantity Descrpition of item Rate
1 2 3 4
Block Masonary in CM(1:6) prop using 1ST grade
autoclaved aerated concrete block having a compressive
Strength OF 30 - 35 Kg/cm3, thermal conductivity 0.132 -
0.151 for 800 Kg/m3, Dry Density 750 - 800 Kg/m3
including cost and conveyance of material and water to
work site and all operational, incidental labour charges such
as mixing mortor, constructing masonary, lift charges, curing
etc complete for finished item of work 0.10 m / 0.20m thick
wall.
8 9
50.00 3000.00
1 cum 334.90
1 cum 32.90
1 No 69.72
1 No 143.08
1 No 81.20
1 No 243.60
134.40
4039.80
161.60
0.00
4201.40
50 Nos 1100.00
1 cum 334.90
1 cum 32.90
1 No 69.72
1 No 143.08
1 No 81.20
1 No 243.60
134.40
2139.80
85.59
0.00
2225.39
1 cum 50.50
1 cum
1 cum 10
1 cum 20.00
18.94
99.44
3.98
5.00
108.42
RATE ANALYSIS
0.00
S. No Quantity Descrpition of item Rate Per
1 2 3 4 8
1 Earth work excavation for pile foundations and raft
footing including all operational, incidental, labour
charges such as shoring, sheeting, planking
shuttering etc comlete for finished item of work as
per SS 302 & 303
Amount
50.50
10
20.00
18.94
99.44
3.98
5.00
108.42
ESITIMATION & COST
S.NO DESCRIPTION CODE NO'S NEEDED LENGTH
EARTH WORK EXCAVATION
Earth work excavation for pile foundations and raft footing
including all operational, incidental, labour charges such
as shoring, sheeting, planking shuttering etc comlete for
finished item of work as per SS 302 & 303
RS 108.42 /-
34.20 M 1.50M 1703.06 CU.M 1703.06 CU.M
0.60M 24.1 27.3 CU.M 4313.4 CU.M
3 1.5 22.5 CU.M 22.5 CU.M
5 3 75 CU.M 75 CU.M
6113.96 CU.M
662875.50/-