Description Unit Quantity Rate Amount Remark: Footing 20,664.00

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ANALYSIS TO CALCULATE THE RATIO OF WORKS

Considering Pour 01
DESCRIPTION UNIT QUANTITY RATE AMOUNT REMARK
Footing Nos 6 3,444.00 20,664.00
Rebar MT 0.3 6,000.00 1,800.00
For 6 Nos of Footing
Formwork Sft 48 15.50 744.00
Concreting Cum 3 300 900.00
Column Nos 6 3,195.00 19,170.00
Rebar MT 0.2 6000.00 1,200.00
For 6 Nos of column
Formwork Sft 90 15.50 1,395.00
Concreting Cum 2 300.00 600.00
Retaining wall 56,450.00
Rebar MT 3.5 6000.00 21,000.00 For 60' Lenth and 15'
from Footing near DG
Formwork Sft 1900 15.50 29,450.00
Room
Concreting Cum 20 300.00 6,000.00
Slab 2,40,850.00
Rebar MT 22 6000.00 1,32,000.00
Formwork Sft 4400 15.50 68,200.00
Concreting Cum 135.5 300.00 40,650.00

TOTAL SUM OF ALL WORK RATIO OF


% OF WORK RATE PER WORK REMARK
ACTIVITY RATE WORK
Footing 20,664.00 6.13 6% 4.81
Column 19,170.00 5.69 6% 4.46
Retaining wall 56,450.00 16.74 17% 13.14
Slab 2,40,850.00 71.44 71% 56.08
TOTAL AMOUNT @ POUR 01 3,37,134.00 100.00 100% 78.50