Targets Discussion with Anuj Sir

Projects Target
Present Coming
Awarded
Denso Detail design drgs sent for client's 1st review 16.01.2018

Internal & External Pipe rack prepare (24.01.2018) 23.01.2018

Denso Fire BA drgs updated by consultant, submitted 09.02.2018

Denso Site visit mech meeting 01.02.2018

Detail Drgs Update & Utility space planning

Internal & External Pipe rack drawings update 24.02.2018

Topre Client Comments received on 11.01.2018 & explained


by client on 15.01.2018.
Topre 22.01.2018
To be incorporated with updated Arch.
(Client meeting on 24.01.2018)
Client comments updated & submitted 29.01.2018
Moresco Detail Design first set submitted 27.01.2018
Internal Pipe Rack (25.01.2018) 27.01.2018
DAIDO Detail design first set submitted 31.01.2018
Drawings updation as per updated Arch layout 12.02.2018
NGK Yamazaki San coming to HO 02.02.2018
Yamazaki san Comp room & P&ID comments updated 05.02.2018
Meeting for handover to Nozawa San 09.02.2018
All utility planning (CA, CW, WFD) as per revised client's
updated data 05.03.2018
Submission for Nozawa San Review

NGK Client visiting office 06.03.2018

NGK All drawings submission


(Updated arch not yet received) 10.03.2018

Sumitomo Tyre CA room & Piping layout submission 31.01.2018


ASTI Preparation of Estimation drgs (WFD, Fire, HVAC) 15.02.2018
Review of site documents & prepare major equipments
TDS 10.02.2018
notes.
Keihin Neemrana Nozawa San comments updation & Submission 14.02.2018
Nozawa San comments on HVAC, Chilled water system
update (received on 28.02.2018)
TPR Contract drawings submission 28.02.2018
Yamaha Estimation drgs submission 28.02.2018
Expected

Date: 02-Apr-2018
Designer Loading (Target)
First half Second Half
Kamal Enkey wheel LPG Layout update (2 hrs)
Srichand NGK Fire BA drawing change and print (4 hrs)
Pramod First Half Leave.
Amandeep Denso HVAC (3 hrs)

Date: 03-Apr-2018
Designer Loading (Target)
First half Second Half
Kamal Denso Site
Srichand Denso Site
Pramod NGK Comment reply sheet type, NGK Ren 1 & Ren 2 Contract drawings
Amandeep Denso Site

Date: 04-Apr-2018
Designer Loading (Target)
First half Second Half
Kamal Enkay wheel Water P&ID (3 hrs)
Srichand Denso Fire BA internal comments (3 hrs)
Pramod HCIL Emmission lab Drgs (6 hrs)
Amandeep Unplanned leave

Date: 10-Apr-2018
Designer Loading (Target)
First half Second Half
Kamal Denso- Fire Tank - positive suction option
Srichand Denso Piping set comments update
Pramod Denso HVAC Comments update
Amandeep Denso HVAC Comments update(2 hrs) 'Denso Piping set comments update

Date: 11-Apr-2018
Designer Loading (Target)
First half Second Half
Kamal NGK HVAC Comments update (Under Anuj Sir)
Srichand Denso Piping set comments update
Pramod Denso HVAC Comments update
Amandeep Denso Piping set comments update (Half day), 'Denso HVAC comments update (Half day)

Date: 12-Apr-2018
Designer Loading (Target)
First half Second Half
Kamal NGK Piping Comments update (Under Anuj Sir), Denso HVAC
Srichand Denso Piping set comments update, NGK Fire BA drg (sprinklers add)
Pramod Denso HVAC Comments update (Mehta sir comments)
Amandeep Denso Piping set comments update (mehta sir comments)

Date: 13-Apr-2018
Designer Loading (Target)
First half Second Half
Kamal Denso HVAC Comments update (2nd half)
Srichand Planned 'Leave
Pramod Denso HVAC Comments update (2nd half)
Amandeep Denso Piping set comments update (2nd half)

Date: 14-Apr-2018
Designer Loading (Target)
First half Second Half
Kamal Denso-Anuj sir HVAC Comments update (1st half), Prints
Srichand Planned 'Leave
Pramod Denso-Anuj sir Piping Comments update (1st half), Prints
Amandeep Denso-Anuj sir Piping Comments update (1st half), Prints
Planned Leaves (if any)
Pramod 16-Apr-2018, 2nd half