Name of work: Demolition of Old Estate office, MMD, Printing press, NASA office(TCS shed 2) IIT Bombay.

Sr. no. Discription of Item No. Length Width Depth Qty. Unit
Estate office
a Dismantling work
1 Removing doors and windows
doors 11 11 Nos
windows 37 37 Nos
48 Nos
2 Removing collapsible gate 2 1.16 2.19 5.08 m2
3 Removing partition/ false ceiling 1 6.15 3.67 22.57 m2
1 4.53 3.67 16.63 m2
1 2.50 3.67 9.18 m2
1 4.16 3.67 15.27 m2
1 3.21 1.22 3.92 m2
1 3.65 1.22 4.45 m2
2 1.70 1.2 4.08 m2
1 2.44 1.2 2.93 m2
1 3.64 1.2 4.37 m2
1 2.40 1.2 2.88 m2
1 1.69 1.2 2.03 m2
1 2.44 1.2 2.93 m2
1 2.66 3.67 9.76 m2
1 3.19 3.67 11.71 m2
1 2.08 0.7 1.46 m2
Less door -4 0.90 2.12 -7.63 m2
false ceiling 1 10.05 31.72 318.79 m2
425.30 m2
4 Removing cupboard 2 7.70 15.40 Rmt
1 5.20 5.20 Rmt
1 12.23 12.23 Rmt
2 10.05 20.10 Rmt
52.93 Rmt
5 Removing AC sheets 2 6.40 32.00 409.60 m2
external 1 3.00 9.80 29.40 m2
1 10.60 4.26 45.16 m2
1 31.72 3.70 117.36 m2
601.52 m2
6 Dismantling structural steel
truss ISA 60x6 40 6.40 5.390 1379.84 kg
40 6.00 5.390 1293.60 kg
20 1.50 5.390 161.70 kg
20 0.85 5.390 91.63 kg
20 0.45 5.390 48.51 kg
Purlins 10 32.00 5.390 1724.80 kg
Gusset plate 10mm thick 40 0.30 0.30 78.500 282.60 kg
280 0.30 0.30 78.500 1978.20 kg
ms pipe 3" 1 9.80 6.460 63.31 kg
4 3.00 6.460 77.52 kg
1 6.00 6.460 38.76 kg
1 4.00 6.460 25.84 kg
1 10.60 6.460 68.48 kg
1 11.80 6.460 76.23 kg
1 12.90 6.460 83.33 kg
7 2.50 6.460 113.05 kg
ISMB 100 11 3.70 11.500 468.05 kg
Purlins ISMC 75 3 31.72 7.140 679.44 kg
8654.89 kg
7 Dismantling brick wall
side walls 20 3.67 0.23 2.830 47.78 m3
internal walls 1 7.70 0.15 2.600 3.00 m3
3 3.37 0.15 2.600 3.94 m3
3 4.68 0.15 3.670 7.73 m3
1 3.17 0.15 3.670 1.75 m3
4 10.05 3.67 0.150 22.13 m3
1 9.70 3.67 0.150 5.34 m3
9 2.40 0.23 0.470 2.33 m3
1 2.40 3.67 0.150 1.32 m3
Less windows -21 1.32 1.32 0.230 -8.42 m3
-16 2.70 0.95 0.230 -9.44 m3
-1 0.72 0.78 0.150 -0.08 m3
-1 2.08 0.7 0.150 -0.22 m3
Less doors -8 1.00 2.20 0.150 -2.64 m3
outer supports 4 3.50 0.60 0.640 5.38 m3
2 1.00 3.50 0.640 4.48 m3
outer corriodor columns 11 0.26 0.34 2.450 2.38 m3
86.76 m3
8 Dismantling RCC 4 14.70 0.47 0.075 2.07 m3
corridor slab 1 31.72 0.15 3.230 15.37 m3
17.44 m3
9 Dismantling UCR
columns 22 0.70 0.38 4.300 25.16 m3
1 10.05 0.38 4.300 16.42 m3
0.5 10.05 2.14 0.380 4.09 m3
2 32.00 0.6 0.380 14.59 m3
1 38.33 0.38 0.600 8.74 m3
1 2.07 0.38 0.600 0.47 m3
69.47 m3
10 Dismantling PCC
floor 1 32.00 10.50 0.100 33.60 m3
extended portion 1 10.50 0.90 0.100 0.95 m3
1 38.33 2.83 0.100 10.85 m3
45.39 m3
11 Removing soling
floor 1 32.00 10.50 0.230 77.28 m3
extended portion 1 10.50 0.90 0.230 2.17 m3
79.45 m3
12 Disposing debrises
Brickwall 86.76 m3
RCC 15.54 m3
PCC 45.39 m3
147.69 m3
b Recovery
1 Aluminium
Partitions at starting three bays 6 3.05 0.942 17.24 kg
2 2.15 0.940 4.04 kg
8 3.67 0.940 27.60 kg
Glazing clips 8 2.58 0.097 2.00 kg
16 3.84 0.097 5.96 kg
16 4.14 0.097 6.43 kg
middle partition 5 3.67 0.940 17.25 kg
5 4.53 0.940 21.29 kg
Glazing clips 16 3.94 0.097 6.11 kg
16 4.26 0.097 6.61 kg
doors 4 0.95 1.600 6.08 kg
2 0.95 1.139 2.16 kg
4 2.00 1.139 9.11 kg
fixed glass 1 2.84 0.940 2.67 kg
Glazing clips 2 2.84 0.097 0.55 kg
Drawing office partition 8 3.67 0.940 27.60 kg
3 2.49 0.940 7.02 kg
1 1.59 0.940 1.49 kg
5 4.16 0.940 19.55 kg
Glazing clips 8 3.16 0.097 2.45 kg
4 1.40 0.097 0.54 kg
16 3.63 0.097 5.63 kg
8 4.06 0.097 3.15 kg
8 4.34 0.097 3.37 kg
half height partition 2 3.21 0.940 6.03 kg
6 1.22 0.940 6.88 kg
glazing clips 4 3.21 0.097 1.25 kg
16 1.22 0.097 1.89 kg
2 3.65 0.940 6.86 kg
4 1.22 0.940 4.59 kg
Glazing clips 4 3.65 0.097 1.42 kg
12 1.22 0.097 1.42 kg
shutter alu. sections 1 39.68 0.414 16.43 kg
tender section partition 0.00 kg
low height partition 26 1.22 0.940 29.82 kg
4 1.69 0.940 6.35 kg
4 2.44 0.940 9.17 kg
2 3.64 0.940 6.84 kg
2 2.40 0.940 4.51 kg
2 1.69 0.940 3.18 kg
Glazing clips 8 3.99 0.097 3.10 kg
18 4.73 0.097 8.26 kg
4 2.35 0.097 0.91 kg
4 3.98 0.097 1.54 kg
Wall hung compartment 0.00 kg
two track sliding 4 3.66 0.659 9.65 kg
bearing bottom 8 1.85 0.417 6.17 kg
top shutter member 8 1.85 0.475 7.03 kg
interlocking member 8 0.92 0.558 4.11 kg
openeable shutter 0.00 kg
shutter frame 4 3.66 0.849 12.43 kg
shutter alu. sections 8 2.62 0.414 8.68 kg
Tender section cupboard 32 1.12 0.414 14.84 kg
DR room 5 3.19 0.940 14.99 kg
9 3.67 0.940 31.05 kg
3 2.60 0.940 7.33 kg
1 1.70 0.940 1.60 kg
Glazing clips 24 3.30 0.097 7.68 kg
8 3.86 0.097 3.00 kg
6 3.50 0.097 2.04 kg
6 3.22 0.097 1.87 kg
4 3.70 0.097 1.44 kg
4 3.96 0.097 1.54 kg
top vetilator in tender section 6 2.77 0.781 12.98 kg
12 0.92 0.781 8.62 kg
3 0.50 0.781 1.17 kg
shutters 9 3.12 0.526 14.77 kg
9 3.00 0.724 19.55 kg
Glazing clips 9 3.00 0.286 7.72 kg
526.62 kg
2 Structural steel work
As per item no.7-dismantling work 8654.69 kg
Add for cupboard frames
at drawing section ISA 50x6 16 1.26 4.500 90.72 kg
10 1.23 4.500 55.35 kg
10 0.60 4.500 27.00 kg
SE cabin 32 1.28 4.500 184.32 kg
20 1.00 4.500 90.00 kg
20 0.60 4.500 54.00 kg
4 1.64 4.500 29.52 kg
2 1.00 4.500 9.00 kg
6 0.60 4.500 16.20 kg
Tender section 8 10.05 4.500 361.80 kg
36 0.93 4.500 150.66 kg
36 0.60 4.500 97.20 kg
Grills 12 2.70 0.92 15.000 447.12 kg
2 1.56 3.00 20.000 187.20 kg
4 3.00 0.46 20.000 110.40 kg
4 1.56 0.46 20.000 57.41 kg
Collapsible gate 100.00 kg
window gaurd bars 176 1.42 0.880 219.93 kg
ventilator guard bars 45 2.80 0.880 110.88 kg
11053.40 kg
3 Reinforcement
Approximate qty of steel consider 70 kg/m3 1 17.44 70.00 1220.80 kg
4 Wood
door frame 9 5.29 0.10 0.075 0.36 m3
window frame 21 6.58 0.06 0.095 0.79 m3
42 2.76 0.06 0.035 0.22 m3
42 1.48 0.06 0.035 0.13 m3
top ventilators 16 10.05 0.06 0.100 0.96 m3
frame 64 2.80 0.05 0.040 0.36 m3
ceiling frame 40 10.05 0.08 0.100 3.02 m3
9 32.00 0.10 0.080 2.30 m3
8.14 m3
750 kg/m3 6105.44 kg
5 Plywood, flush door kg/m2orm3
flush doors 9 0.95 2.10 17.00 305.24 kg
Plywood 18mm 6 5.07 0.60 7.560 137.99 kg
3 6.50 0.60 7.560 88.45 kg
18 0.40 0.91 7.560 49.53 kg
581.21 kg
6 Glass
windows 42 0.49 0.64 12.470 164.24 kg
winddows 42 0.49 0.25 12.470 64.16 kg
partitions 1 5.90 2.30 12.470 169.22 kg
partitions 1 0.66 0.66 12.470 5.41 kg
partitions 1 6.25 2.30 12.470 179.26 kg
partitions 1 2.00 0.64 12.470 15.96 kg
partitions 1 5.39 2.300 12.470 154.59 kg
752.84 kg

Printing press
a Dismantling work
1 Removing doors and windows
doors 6 6 Nos
windows 24 24 Nos
Top vetilators 15 15 Nos
45 Nos
2 Removing collapsible gate/rolling shutter 1 1.20 2.20 2.64 m2
3 Removing partition/ceiling 1 4.70 2.60 12.22 m2
1 4.26 2.56 10.91 m2
2 5.23 2.56 26.78 m2
1 4.50 2.56 11.52 m2
1 3.03 3.67 11.12 m2
1 3.65 1.22 4.45 m2
1 11.00 2.56 28.16 m2
2 2.50 2.43 12.15 m2
door portions 5 0.95 1.00 4.75 m2
False ceiling 1 10.05 31.72 318.79 m2
1 4.70 10.05 47.24 m2
1 5.23 3.60 18.83 m2
506.91 m2
4 Removing AC sheets 2 6.40 32.00 409.60 m2
5 Dismantling structural steel
truss ISA 60x6 40 6.40 5.390 1379.84 kg
40 6.00 5.390 1293.60 kg
20 1.50 5.390 161.70 kg
20 0.85 5.390 91.63 kg
20 0.45 5.390 48.51 kg
Purlins 10 32.00 5.390 1724.80 kg
Gusset plate 10mm thick 40 0.30 0.30 78.500 282.60 kg
280 0.30 0.30 78.500 1978.20 kg
6960.88 kg
6 Dismantling brick wall
side walls 20 3.67 0.23 2.83 47.78 m3
2 10.00 2.43 0.23 11.18 m3
5 10.05 3.67 0.15 27.66 m3
cabin walls 1 11.00 1.00 0.15 1.65 m3
1 4.26 1.00 0.15 0.64 m3
1 5.23 1.00 0.15 0.78 m3
1 4.50 1.00 0.15 0.68 m3
1 5.23 1.00 0.15 0.78 m3
less windows -24 1.31 1.31 0.23 -9.47 m3
doors -4 1.60 2.15 0.15 -2.06 m3
-4 1.18 2.10 0.23 -2.28 m3
Top ventilators -10 2.77 0.95 0.230 -6.05 m3
-5 2.40 0.45 0.230 -1.24 m3
less door bottom portions for cabin -5 0.95 1.00 0.150 -0.71 m3
69.33 m3
7 Dismantling RCC 1 10.00 3.00 0.150 4.50 m3
columns 6 0.30 0.30 2.450 1.32 m3
5.82 m3
8 Dismantling UCR
columns 22 0.70 0.38 4.300 25.16 m3
1 10.05 0.38 4.300 16.42 m3
0.5 10.05 2.14 0.380 4.09 m3
2 32.00 0.6 0.380 14.59 m3
60.26 m3
9 Dismantling PCC
floor 1 32.00 10.50 0.100 33.60 m3
extended portion 1 10.50 2.50 0.100 2.63 m3
36.23 m3
10 Removing soling
floor 1 32.00 10.50 0.230 77.28 m3
extended portion 1 10.00 2.50 0.230 5.75 m3
83.03 m3
11 Disposing debrises
Brickwall 69.33 m3
RCC 5.82 m3
PCC 36.23 m3
111.38 m3
B Recovery
1 Aluminium
Partitions at manager cabin 6 2.73 0.942 15.43 kg
4 4.70 0.942 17.71 kg
Glazing clips 8 2.72 0.097 2.11 kg
2 1.80 0.097 0.35 kg
6 4.42 0.097 2.57 kg
2 3.50 0.097 0.68 kg
6 3.76 0.097 2.19 kg
2 2.92 0.097 0.57 kg
door 2 0.90 1.600 2.88 kg
1 0.90 1.139 1.03 kg
2 2.23 1.139 5.08 kg
Glazing clips 4 4.15 0.097 1.61 kg
inside partition 3 4.50 0.942 12.72 kg
1 3.67 0.942 3.46 kg
5 2.67 0.942 12.58 kg
Glazing clips 10 3.55 0.097 3.44 kg
10 2.95 0.097 2.86 kg
8 3.85 0.097 2.99 kg
door 12 0.89 1.600 17.09 kg
6 0.89 1.139 6.08 kg
12 2.10 1.139 28.70 kg
Glazing clips 24 3.38 0.097 7.87 kg
middle partition 6 2.67 0.942 15.09 kg
4 5.23 0.942 19.71 kg
Glazing clips 10 3.65 0.097 3.54 kg
10 3.05 0.097 2.96 kg
10 3.85 0.097 3.73 kg
2nd partition 3 4.50 0.942 12.72 kg
1 3.67 0.942 3.46 kg
5 2.67 0.942 12.58 kg
Glazing clips 10 3.55 0.097 3.44 kg
10 2.95 0.097 2.86 kg
8 3.85 0.097 2.99 kg
door 12 0.89 1.600 17.09 kg
6 0.89 1.139 6.08 kg
12 2.10 1.139 28.70 kg
Glazing clips 12 3.38 0.097 3.93 kg
middle partition 6 2.67 0.942 15.09 kg
4 5.23 0.942 19.71 kg
Glazing clips 10 3.65 0.097 3.54 kg
10 3.05 0.097 2.96 kg
10 3.85 0.097 3.73 kg
3rd room partition 4 3.67 0.942 13.83 kg
3 3.00 0.942 8.48 kg
2 2.05 0.942 3.86 kg
Glazing clips 4 3.23 0.097 1.25 kg
8 3.39 0.097 2.63 kg
4 3.53 0.097 1.37 kg
4 3.79 0.097 1.47 kg
south side rooms 6 3.67 0.942 20.74 kg
4 2.81 0.942 10.59 kg
6 2.76 0.942 15.60 kg
4 3.15 0.942 11.87 kg
door 6 0.91 1.600 8.74 kg
3 0.91 1.139 3.11 kg
6 2.10 1.139 14.35 kg
Glazing clips 18 3.35 0.097 5.85 kg
18 2.75 0.097 4.80 kg
12 3.65 0.097 4.25 kg
door glazing clips 12 3.38 0.097 3.93 kg
backside room - partition 8 2.43 0.942 18.31 kg
4 2.50 0.942 9.42 kg
8 0.77 0.942 5.80 kg
door 4 0.95 0.719 2.73 kg
4 2.04 0.537 4.38 kg
Glazing clips 8 2.00 0.097 1.55 kg
16 1.55 0.097 2.41 kg
4 5.72 0.097 2.22 kg
Aluminium windows 4 5.28 0.526 11.11 kg
8 3.74 0.724 21.66 kg
4 1.26 0.764 3.85 kg
sliding window 2 2.46 0.933 4.59 kg
2 1.20 0.933 2.24 kg
shutters 6 0.80 0.417 2.00 kg
4 1.20 0.469 2.25 kg
2 1.20 0.417 1.00 kg
False ceiling 8 10.05 0.350 28.14 kg
17 4.70 0.350 27.97 kg
8 3.60 0.350 10.08 kg
6 4.50 0.350 9.45 kg
back side windows 25 0.45 0.945 10.63 kg
10 2.40 0.945 22.68 kg
Glazing clips 20 1.85 0.097 3.59 kg
678.69 kg
2 Structural steel work
As per item no.7-dismantling work 6960.88 kg
Rolling shutter 70.00 kg
window gaurd bars 28 1.30 0.880 32.03 kg
ventilator guard bars 45 2.80 0.880 110.88 kg
add for weld mesh 16 5.00 80.00 kg
grill 1 3.60 2.40 20.00 172.80 kg
7426.59 kg
3 Reinforcement
Approximate qty of steel consider 70 kg/m3 1 5.82 70.00 407.40 kg
4 Wood
door frame 3 5.40 0.10 0.075 0.12 m3
1 5.90 0.10 0.075 0.04 m3
1 6.50 0.10 0.075 0.05 m3
back side panelled door 8 0.55 0.13 0.030 0.02 m3
4 0.55 0.20 0.030 0.01 m3
8 2.18 0.20 0.030 0.10 m3
top ventilators 10 10.05 0.06 0.100 0.60 m3
frame 40 2.80 0.05 0.040 0.22 m3
ceiling frame 40 10.05 0.08 0.100 3.02 m3
9 32.00 0.10 0.080 2.30 m3
6.50 m3
750 kg/m3 4871.63 kg
5 Plywood, flush door kg/m2orm3
flush doors 1 1.40 2.05 17.00 48.79 kg
3 1.03 2.03 17.00 106.64 kg
155.43 kg
6 Glass
windows 36 0.49 0.64 12.470 140.78 kg
windows 36 0.49 0.25 12.470 54.99 kg
Top ventilators 40 0.60 0.78 12.470 233.44 kg
sliding window 1 2.25 1.10 12.470 30.86 kg
partitions 1 2.48 4.30 12.470 132.98 kg
partitions 2 0.80 3.29 12.470 65.64 kg
2 4.18 2.35 12.470 244.99 kg
middle partition 2 4.85 2.35 12.470 284.25 kg
1 2.75 3.29 12.470 112.82 kg
south side rooms 1 10.00 2.51 14.470 363.20 kg
backside room 1 2.25 2.18 14.470 70.98 kg
top fixed glass 20 0.51 0.32 14.470 47.82 kg
1782.75 kg

NASA & SOUL lab


a Dismantling work
1 Removing doors and windows
nasa office
doors 1 1 Nos
windows 6 6 Nos
ventilators 2 2 Nos
soul lab 0 Nos
doors 10 10 Nos
windows 7 7 Nos
ventilators 6 6 Nos
32 Nos
2 Removing partition 1 3.24 3.12 10.11 m2
2 2.91 2.5 14.55 m2
2 4.60 2.5 23.00 m2
less doors -2 0.97 2.1 -4.07 m2
-1 1.73 2.12 -3.67 m2
2 10.03 12.46 249.95 m2
289.86 m2
3 dismantling platform 1 14.91 14.91 Rmt
4 Removing AC sheet
NASA 2 6.40 6.23 79.74 m2
soul lab 2 6.40 12.46 159.49 m2
239.23 m2
5 Dismantling structural steel
truss ISA 60x6 20 6.40 5.390 689.92 kg
20 6.00 5.390 646.80 kg
10 1.50 5.390 80.85 kg
10 0.85 5.390 45.82 kg
10 0.45 5.390 24.26 kg
Purlins 10 20.00 5.390 1078.00 kg
Gusset plate 10mm thick 48 0.30 0.30 78.500 339.12 kg
2904.76 kg
6 Dismantling brick wall
side walls 12 3.67 0.23 2.830 28.67 m3
internal walls 1 10.03 0.15 3.670 5.52 m3
1 3.40 0.15 3.670 1.87 m3
1 2.83 0.15 3.670 1.56 m3
1 0.95 0.15 3.670 0.52 m3
4 10.05 3.67 0.150 22.13 m3
Less windows -7 1.32 1.32 0.230 -2.81 m3
-8 2.70 0.95 0.230 -4.72 m3
-1 0.75 1.2 0.150 -0.14 m3
-1 0.75 0.7 0.150 -0.08 m3
Less doors -5 1.00 2.12 0.150 -1.59 m3
-2 0.96 2.10 0.230 -0.93 m3
-2 1.08 2.12 0.230 -1.05 m3
48.96 m3
7 Dismantling UCR
columns 14 0.70 0.38 4.300 16.01 m3
wall 1 10.05 0.38 4.300 16.42 m3
0.5 10.05 2.14 0.380 4.09 m3
2 18.88 0.6 0.380 8.61 m3
1 10.05 0.38 0.600 2.29 m3
47.42 m3
8 Dismantling PCC
floor 1 18.88 10.50 0.100 19.82 m3
9 Removing soling
floor 1 18.88 10.50 0.230 45.60 m3
10 Disposing debrises
Brickwall 48.96 m3
PCC 19.82 m3
68.78 m3
B Recovery
1 Aluminium
Partitions at SOUL 6 3.24 0.942 18.31 kg
3 0.76 0.942 2.13 kg
Glazing clips 14 3.59 0.097 4.88 kg
inside partition 4 2.91 0.942 10.96 kg
8 2.50 0.942 18.84 kg
2 1.94 0.942 3.65 kg
Glazing clips 12 2.74 0.097 3.19 kg
16 4.04 0.097 6.27 kg
door 4 0.97 1.139 4.42 kg
4 2.10 1.139 9.57 kg
2 0.92 1.139 2.10 kg
Glazing clips 4 4.04 0.097 1.57 kg
middle partitions 8 4.60 0.942 34.67 kg
10 2.50 0.942 23.55 kg
Glazing clips 20 3.96 0.097 7.68 kg
Two doors 4 2.12 1.600 13.57 kg
4 1.05 1.139 4.78 kg
2 0.95 1.139 2.16 kg
Glazing clips 4 5.64 0.097 2.19 kg
False ceiling 10 4.60 0.350 16.10 kg
16 2.91 0.350 16.30 kg
206.89 kg
2 Structural steel work
As per item no.7-dismantling work 4269.41 kg
window gaurd bars 28 1.30 0.880 32.03 kg
ventilator guard bars 45 2.80 0.880 110.88 kg
add for weld mesh 16 5.00 80.00 kg
grill 2 3.60 2.40 20.00 345.60 kg
4837.92 kg
3 Wood
door frame 2 5.40 0.10 0.075 0.08 m3
4 4.50 0.10 0.075 0.14 m3
2 5.25 0.10 0.075 0.08 m3
back side panelled door 4 0.55 0.13 0.030 0.01 m3
2 0.55 0.20 0.030 0.01 m3
4 2.18 0.20 0.030 0.05 m3
top ventilators 10 10.05 0.06 0.100 0.60 m3
frame 40 2.80 0.05 0.040 0.22 m3
1.19 m3
750 kg/m3 891.94 kg
4 Plywood, flush door kg/m2orm3
flush doors 2 1.05 2.14 17.00 76.40 kg
2 0.96 2.10 17.00 68.54 kg
1 0.87 2.12 17.00 31.35 kg
176.30 kg
5 Glass
windows 26 0.49 0.64 12.470 101.68 kg
windows 26 0.49 0.25 12.470 39.72 kg
Top ventilators 24 0.60 0.78 12.470 140.06 kg
sliding door 1 1.05 1.10 12.470 14.40 kg
partitions 6 0.75 1.04 12.470 58.36 kg
partitions 5 4.00 0.97 12.470 241.92 kg
2 4.18 2.35 12.470 244.99 kg
6 1.15 0.83 12.470 71.42 kg
8 1.15 0.83 12.470 95.22 kg
1007.76 kg

MMD OFFICE
a Dismantling work
1 Removing doors and windows
doors 14 14 Nos
windows 34 34 Nos
ventilators 13 13 Nos
61 Nos
2 Removing collapsible gate/rolling shutter 1 2.72 2.37 6.45 m2
1 1.46 2.42 3.53 m2
1 3.00 2.45 7.35 m2
17.33 m2
3 Removing partition 1 6.30 3.67 23.12 m2
1 3.66 3.67 13.43 m2
1 10.05 3.67 36.88 m2
1 3.66 3.15 11.53 m2
1 44.48 10.05 447.02 m2
531.99 m2
4 Removing AC sheets 2 44.80 6.40 573.44 m2
573.44 m2
5 Dismantling structural steel
truss ISA 60x6 48 6.40 5.390 1655.81 kg
48 6.00 5.390 1552.32 kg
24 1.50 5.390 194.04 kg
24 0.85 5.390 109.96 kg
24 0.45 5.390 58.21 kg
Purlins 10 44.80 5.390 2414.72 kg
Gusset plate 10mm thick 48 0.30 0.30 78.500 339.12 kg
336 0.30 0.30 78.500 2373.84 kg
8698.02 kg
6 Dismantling brick wall
side walls 28 3.67 0.23 2.830 66.89 m3
1 10.05 3.67 0.150 5.53 m3
1 6.30 3.67 0.150 3.47 m3
1 3.34 3.67 0.150 1.84 m3
1 6.00 3.67 0.150 3.30 m3
Less windows -34 1.32 1.32 0.230 -13.63 m3
-13 2.70 0.95 0.230 -7.67 m3
-1 1.22 1.25 0.150 -0.23 m3
Less doors -8 0.90 2.00 0.150 -2.16 m3
-4 1.10 2.10 0.230 -2.13 m3
-2 2.72 2.37 0.230 -2.97 m3
52.25 m3
7 Dismantling RCC 2 2.20 1.00 0.180 0.79 m3
1 3.15 1.00 0.180 0.57 m3
1 5.30 0.38 0.160 0.32 m3
1.68 m3
8 Dismantling UCR
columns 28 0.70 0.38 4.300 32.03 m3
1 10.05 0.38 4.300 16.42 m3
0.5 10.05 2.14 0.380 4.09 m3
1 3.42 5.00 0.380 6.50 m3
2 44.48 0.38 0.900 30.42 m3
1 10.05 0.9 0.380 3.44 m3
92.89 m3
9 Dismantling PCC
floor 1 44.48 10.50 0.100 46.70 m3
46.70 m3
10 Removing soling
floor 1 44.48 10.50 0.230 107.42 m3
107.42 m3
11 Disposing debrises
Brickwall 52.79 m3
RCC 1.68 m3
PCC 46.70 m3
101.17 m3
b Recovery
1 Aluminium
fixed window 1 4.88 0.942 4.60 kg
door 1 4.95 1.200 5.94 kg
10.54 kg
2 Structural steel work
As per item no.7-dismantling work 8698.02 kg
Collapsible gate/rolling shutter 135.00 kg
window gaurd bars 374 1.42 0.880 467.35 kg
ventilator guard bars 65 2.80 0.880 160.16 kg
ceiling grid 16mm dia. Bar 24 3.34 1.580 126.65 kg
33 2.42 1.580 126.18 kg
9713.36 kg
3 Reinforcement
Approximate qty of steel consider 70 kg/m3 1 1.68 70.00 117.60 kg
4 Wood
door frame 7 5.10 0.10 0.075 0.27 m3
4 5.28 0.10 0.075 0.16 m3
window frame 34 6.58 0.06 0.095 1.28 m3
68 2.76 0.06 0.035 0.36 m3
68 1.48 0.06 0.035 0.21 m3
top ventilators 13 10.05 0.06 0.100 0.78 m3
frame 52 2.80 0.05 0.040 0.29 m3
ceiling frame 56 10.05 0.08 0.100 4.22 m3
9 44.48 0.10 0.080 3.20 m3
10.77 m3
750 kg/m3 8079.48 kg
5 Plywood, flush door kg/m2orm3
flush doors 9 0.95 2.10 17.00 305.24 kg
4 1.08 2.10 17.00 154.22 kg
Plywood 18mm 2 6.30 3.67 7.560 349.59 kg
2 10.05 3.67 7.560 557.68 kg
2 3.66 3.67 7.560 203.09 kg
1569.82 kg
6 Glass
windows 68 0.49 0.64 12.470 265.92 kg
winddows 68 0.49 0.25 12.470 103.88 kg
ventilators 52 0.60 0.78 12.470 303.47 kg
1 1.10 1.10 12.470 15.09 kg
688.35 kg

Connecting corriodors
a Dismantling work
1 Removing AC sheets
Corridor infront of printing press 1 44.40 3.70 164.28 m2
infront of toilet 1 19.02 3.70 70.37 m2
1 3.00 3.70 11.10 m2
1 28.35 3.70 104.90 m2
350.65 m2
2 Dismantling structural steel
ISMB 100 15 3.70 11.500 638.25 kg
9 3.70 11.500 382.95 kg
10 3.70 11.500 425.50 kg
Purlins ISMC 75 3 44.40 7.140 951.05 kg
3 19.02 7.140 407.41 kg
3 28.35 7.140 607.26 kg
3 3.00 7.140 64.26 kg
3476.67 kg
3 Dismantling brick wall
outer corriodor columns 34 0.26 0.34 2.450 7.36 m3
4 Dismantling RCC
corridor slab 1 44.40 0.15 3.230 21.51 m3
1 19.02 0.15 3.230 9.22 m3
1 3.00 0.15 3.230 1.45 m3
1 28.35 0.15 3.230 13.74 m3
45.92 m3
5 Dismantling UCR 1 44.40 0.38 0.450 7.59 m3
2 2.07 0.38 0.450 0.71 m3
1 19.02 0.38 0.900 6.50 m3
1 10.02 0.38 0.900 3.43 m3
1 28.35 0.38 0.900 9.70 m3
1 2.07 0.38 0.900 0.71 m3
2 3.00 0.38 0.600 1.37 m3
30.00 m3
6 Dismantling PCC 1 44.40 2.83 0.100 12.57 m3
1 19.02 2.33 0.100 4.43 m3
1 28.35 2.33 0.100 6.61 m3
1 3.00 2.33 0.100 0.70 m3
24.30 m3
7 Removing soling 1 44.40 2.83 0.230 28.90 m3
1 19.02 2.33 0.230 10.19 m3
1 28.35 2.33 0.230 15.19 m3
1 3.00 2.33 0.230 1.61 m3
55.89 m3
8 Disposing debrises
Brickwall 7.36 m3
RCC 45.92 m3
PCC 24.30 m3
77.58 m3
b Recovery
1 Structural steel work
As per item no.2-dismantling work 3476.67 kg
2 Reinforcement
Approximate qty of steel consider 70 kg/m3 1 45.92 70.00 3214.40 kg

Toilet block
a Dismantling work
1 Removing doors and windows
doors 8 8 Nos
windows 9 9 Nos
17 Nos
2 Dismantling brick wall 2 7.31 0.23 2.500 8.41 m3
1 5.18 0.23 2.500 2.98 m3
4 1.20 0.15 2.100 1.51 m3
1 6.36 0.15 2.100 2.00 m3
1 3.00 0.15 2.500 1.13 m3
1 1.50 0.15 2.500 0.56 m3
16.59 m3
3 Removing wash hand basin/urinal 6 6 Nos
4 Removing G.I pipe line 1 12.00 12.00 Rmt
5 Dismantling RCC 1 7.31 5.18 0.150 5.68 m3
5.68 m3
6 Dismantling UCR 1 5.18 0.38 2.500 4.92 m3
1 3.98 0.38 2.500 3.78 m3
for foundation 2 5.18 0.38 0.600 2.36 m3
2 7.31 0.38 0.600 3.33 m3
14.40 m3
7 Dismantling PCC
floor 1 5.18 7.31 0.100 3.79 m3
3.79 m3
8 Removing soling
floor 1 5.18 7.31 0.230 8.71 m3
8.71 m3
9 Disposing debrises
Brickwall 16.59 m3
RCC 5.68 m3
PCC 3.79 m3
26.06 m3
b Recovery
1 Aluminium
Ventilators 8 3.00 0.850 20.40 kg
louvered 16 0.100 1.60 kg
22.00 kg
2 Reinforcement
Approximate qty of steel consider 70 kg/m3 1 5.68 70.00 397.60 kg
3 Plywood, flush door kg/m2orm3
FRP door 8 0.75 2.10 8.00 100.80 kg
4 G.I pipe line 1 12.00 1.930 23.16 kg

Store room
A Dismantling work
1 Removing doors and windows
doors 1 1 Nos
windows 10 10 Nos
11 Nos
2 Dismantling brick wall 2 8.30 0.4 3.350 22.24 m3
2 4.55 0.4 3.350 12.19 m3
1 5.35 0.4 0.950 2.03 m3
36.47 m3
for foundation 2 8.30 0.40 0.600 3.98 m3
2 4.55 0.40 0.600 2.18 m3
6.17 m3
3 Dismantling RCC 5 1.20 0.6 0.100 0.36 m3

3 Dismantling M.S door 1 2.20 1.500 3.30 m2


3.30 m2

4 Removing MS sheets 1 2.96 8.50 25.13 m2


5 Dismantling structural steel
ISMC 75 6 8.50 6.800 346.80 kg
MS Angle 50X50X5 12 2.96 3.800 134.98 kg
MS pipe 65 dia 4 3.65 5.840 85.26 kg
2 8.50 5.840 99.28 kg
4 1.30 5.840 30.37 kg
MS Angle 40X40X4 40 0.60 2.400 57.60 kg
20 1.20 2.400 57.60 kg
811.89 kg

3 Dismantling PCC
floor 1 7.50 4.50 0.100 3.38 m3
1 8.30 1.20 0.100 1.00 m3
4.37 m3
4 Removing soling
floor 1 7.50 4.50 0.350 11.81 m3
1 8.30 1.20 0.600 5.98 m3
17.79 m3
5 Disposing debrises
Brickwall 42.64 m3
RCC 0.36 m3
PCC 4.37 m3
17.79 m3
65.16 m3
B Recovery
2 Reinforcement
Approximate qty of steel consider 70 kg/m3 1 0.36 70.00 25.20 kg
3 MS DOOR kg/m2orm3
angle 25*25*3 1 13.30 1.10 14.63 kg
Plate 1 1.50 2.20 0.02 51.80 kg
66.43
4 Structural steel 1 12.00 1.930 23.16 kg
ISMC 75 6 8.50 6.800 346.80 kg
MS Angle 50X50X5 12 2.96 3.800 134.98 kg
MS pipe 65 dia 4 3.65 5.840 85.26 kg
2 8.50 5.840 99.28 kg
4 1.30 5.840 30.37 kg
MS Angle 40X40X4 40 0.60 2.400 57.60 kg
20 1.20 2.400 57.60 kg
811.89 kg
24 Exposing 8.00 m2
25 P/A Bond coat 8.00 kg
26 P/A PMM 1 8.00 0.02 2275.000 364.00 kg
27 P/A Internal plaster
Removing plaster 8.00 m2
wall 1 0.90 1.40 1.26 m2
2 0.30 2.10 1.26 m2
1 0.30 1.10 0.33 m2
10.85 m2
Say 11.00 m2
28 P/A Birla putty 11.00 m2
29 P/A Sand face plaster 1 0.90 1.40 1.26 m2
2 0.30 2.10 1.26 m2
1 0.30 1.10 0.33 m2
2.85 m2
Say 3.00 m2
30 P/F mosquito mesh 2 0.60 1.40 1.68 m2
Say 2.00 m2
31 P/A Primer
for G1/4 2 9.00 3.10 55.80 m2
1 4.50 3.10 13.95 m2
ceiling 1 7.00 7.00 49.00 m2
room no.110A 2 4.50 3.90 35.10 m2
2 3.00 3.90 23.40 m2
1 3.50 4.50 15.75 m2
1 5.00 2.50 12.50 m2
205.50 m2
Say 206.00 m2
32 P/A Plastic paint
for G1/4 2 9.00 3.10 55.80 m2
1 4.50 3.10 13.95 m2
ceiling 1 7.00 7.00 49.00 m2
room no.110A 2 4.50 3.90 35.10 m2
2 3.00 3.90 23.40 m2
1 3.50 4.50 15.75 m2
193.00 m2
33 P/A OBD 1 5.00 2.50 12.50 m2
Say 13.00 m2
34 P/A Exterior primer and paint 3.00 m2
35 P/A Rain coat 1 8.50 9.00 76.50 m2
Say 77.00 m2
100
100
INDIAN INSTITUTE OF TECHNOLOGY
IIT POWAI, MUMBAI- 400 076.
EO/A/WORKSHOP/WKS- /17-18 Estate Office
Name of work : Demolition of Old Estate office, MMD, Printing press, NASA office(TCS shed 2) IIT Bombay.
SR.
Description of work Qty Unit Rate Details of basis Amount
NO.
A) Old Estate office
CPWD 2016,
Removing door shutters and window shutters of any size item
1 and type with fittings (if available) and taking out the 48.00 Nos 261.40 no.15.12.2+35.2 12547.20
same outside IIT Campus etc. complete. 9% cost index-
12% GST
Removing rolling shutters, collpsible gate etc. with fittings
2 5.08 m2 141.00 Rate Analysis 716.28
and taking out the same outside IIT Campus etc. complete.
Removing teak wood or aluminium paneled / partly glazed CPWD 2016,
or veneer / plywood partitions, any type of ceiling item
carefully without damaging the frame or panels and taking
3 out the same outside IIT Campus etc. complete. 425.30 m2 29.35 no.15.57+35.29 12482.56
% cost index-
12% GST
Removing existing cupboard from its position, stacking
4 dismantled material at site and taking away the same 52.93 Rmt 71.00 Rate Analysis 3758.03
outside campus etc. completed as directed.

CPWD 2016,
Removing galvanised iron or asbestos cement sheet roof item
covering and taking out the same outside IIT Campus,
5 scaffolding etc. complete. (5% cost will be deducted from
601.52 m2 84.68 no.15.28.1+35.2 50934.94
Item of work if material taken outside campus) 9% cost index-
12% GST
CPWD 2016,
Dismantling steel work in built up sections in angles, tees, item
flats and channels including all gusset plates, bolts, nuts,
6 cutting rivets, welding etc. including dismembering and
8654.89 kg 2.90 no.15.18+35.29 25091.14
stacking within 50 meters lead etc. completed as directed. % cost index-
12% GST
Dismantling burnt brick masonry (in cement mortar) with CPWD 2016,
plaster including sorting out serviceable bricks and item
lowering down debrises, stacking the same and debris
7 separately upto a distance of 50 meters or spreading the 86.76 m3 1018.00 no.15.7.4+35.29 88321.68
debris as directed. % cost index-
12% GST
Dismantling R.C.C. work including breaking concrete by CPWD 2016,
chiselling, wedging etc., cutting the reinforcement, item
8 17.44 m3 1757.02 no.15.3+35.29% 30642.40
lowering down debrises, stacking the debris upto a cost index-12%
distance of 50 metres or spreading as directed. GST
Pulling down stone masonry in cement mortar with plaster CPWD 2016,
/ pointing without dust nuisance including sorting out the item
9 69.47 m3 1214.83 no.15.9.2+35.29 84394.36
stone chips and debris separately and stacking upto % cost index-
distance of 1000 metres as directed. 12% GST
Dismantling plain cement concrete work including CPWD 2016,
breaking concrete by chiselling, wedging etc., and item
10 45.39 m3 743.07 no.15.2.2+35.29 33727.95
stacking the debris upto a distance of 50 metres or % cost index-
spreading as directed. 12% GST
Removing soling without dust nuisance including sorting
11 out the stone chips and debris separately and stacking upto 79.45 m3 170.00 Rate Analysis 13506.50
distance of 50 metres as directed.
Disposing debris, loose stones, boulders, concrete pieces
broken etc. collected and stacked as directed including
loading in trucks, transporting out of IIT Campus
including obtaining approval from Government/ private CPWD 2016,
land owners for disposing off on to their approved item
12 147.69 m3 145.62 no.15.60+35.29 21506.31
location. The contractor will be solely responsible for
% cost index-
disposing debrises out of campus and the debris are to be 12% GST
removed from site within 72 hours from stacking (30%
voids will be deducted from actual measurement for
debris, loose stones, boulders, concrete pieces).
A Total dismantling amount Rs. 377629.35
RECOVERY
1 structural and Reinforcement Steel 12274.20 kg 20.00 Market Rate 245483.95
2 Aluminum sheets, sections etc. 526.62 kg 100.00 Market Rate 52662.48
3 wood 6105.44 kg 25.00 Market Rate 152636.00
4 Plywood, door shutters 581.21 kg 6.00 Market Rate 3487.26
5 Glass 752.84 kg 6.00 Market Rate 4517.04
B Total recovery amount Rs. 458786.73
Amount to be recover from contractor by IIT Total B-A 81157.38
B Printing press
CPWD 2016,
Removing door shutters and window shutters of any size item
1 and type with fittings (if available) and taking out the 45.00 Nos 261.40 no.15.12.2+35.2 11763.00
same outside IIT Campus etc. complete. 9% cost index-
12% GST
Removing rolling shutters, collpsible gate etc. with fittings
2 2.64 m2 141.00 Rate Analysis 372.24
and taking out the same outside IIT Campus etc. complete.
Removing teak wood or aluminium paneled / partly glazed CPWD 2016,
or veneer / plywood partitions, any type of ceiling item
carefully without damaging the frame or panels and taking
3 out the same outside IIT Campus etc. complete. 506.91 m2 29.35 no.15.57+35.29 14877.81
% cost index-
12% GST
CPWD 2016,
Removing galvanised iron or asbestos cement sheet roof item
covering and taking out the same outside IIT Campus,
4 scaffolding etc. complete. (5% cost will be deducted from
409.60 m2 84.68 no.15.28.1+35.2 34683.72
Item of work if material taken outside campus) 9% cost index-
12% GST
CPWD 2016,
Dismantling steel work in built up sections in angles, tees, item
flats and channels including all gusset plates, bolts, nuts,
5 cutting rivets, welding etc. including dismembering and
6960.88 kg 2.90 no.15.18+35.29 20180.09
stacking within 50 meters lead etc. completed as directed. % cost index-
12% GST
Dismantling burnt brick masonry (in cement mortar) with CPWD 2016,
plaster including sorting out serviceable bricks and item
lowering down debrises, stacking the same and debris
6 separately upto a distance of 50 meters or spreading the 69.33 m3 1018.00 no.15.7.4+35.29 70577.94
debris as directed. % cost index-
12% GST
Dismantling R.C.C. work including breaking concrete by CPWD 2016,
chiselling, wedging etc., cutting the reinforcement, item
7 5.82 m3 1757.02 no.15.3+35.29% 10225.85
lowering down debrises, stacking the debris upto a cost index-12%
distance of 50 metres or spreading as directed. GST
Pulling down stone masonry in cement mortar with plaster CPWD 2016,
/ pointing without dust nuisance including sorting out the item
8 60.26 m3 1214.83 no.15.9.2+35.29 73205.76
stone chips and debris separately and stacking upto % cost index-
distance of 1000 metres as directed. 12% GST
Dismantling plain cement concrete work including CPWD 2016,
breaking concrete by chiselling, wedging etc., and item
9 36.23 m3 743.07 no.15.2.2+35.29 26921.43
stacking the debris upto a distance of 50 metres or % cost index-
spreading as directed. 12% GST
Removing soling without dust nuisance including sorting
10 out the stone chips and debris separately and stacking upto 83.03 m3 170.00 Rate Analysis 14115.10
distance of 50 metres as directed.
Disposing debris, loose stones, boulders, concrete pieces
broken etc. collected and stacked as directed including
loading in trucks, transporting out of IIT Campus
including obtaining approval from Government/ private CPWD 2016,
land owners for disposing off on to their approved item
11 111.38 m3 145.62 no.15.60+35.29 16218.93
location. The contractor will be solely responsible for
% cost index-
disposing debrises out of campus and the debris are to be 12% GST
removed from site within 72 hours from stacking (30%
voids will be deducted from actual measurement for
debris, loose stones, boulders, concrete pieces).
A Total dismantling amount Rs. 293141.85
Recovary
1 structural and Reinforcement Steel 7833.99 kg 20.00 Market Rate 156679.84
2 Aluminum sheets, sections etc. 678.69 kg 100.00 Market Rate 67868.62
3 wood 4871.63 kg 25.00 Market Rate 121790.63
4 Plywood, door shutters 155.43 kg 6.00 Market Rate 932.56
5 Glass 1782.75 kg 6.00 Market Rate 10696.51
B Total recovery amount Rs. 357968.15
Amount to be recover from contractor by IIT Total B-A 64826.30
c NASA and SOUL lab
CPWD 2016,
Removing door shutters and window shutters of any size item
1 and type with fittings (if available) and taking out the 32.00 Nos 261.40 no.15.12.2+35.2 8364.80
same outside IIT Campus etc. complete. 9% cost index-
12% GST
Removing teak wood or aluminium paneled / partly glazed CPWD 2016,
or veneer / plywood partitions, any type of ceiling item
carefully without damaging the frame or panels and taking
2 out the same outside IIT Campus etc. complete. 289.86 m2 29.35 no.15.57+35.29 8507.39
% cost index-
12% GST
Dismantling existing platform and stacking dismantled
3 material at site and taking away the same outside campus 14.91 Rmt 42.00 Rate Analysis 626.22
etc. completed as directed.

CPWD 2016,
Removing galvanised iron or asbestos cement sheet roof item
covering and taking out the same outside IIT Campus,
4 scaffolding etc. complete. (5% cost will be deducted from
239.23 m2 84.68 no.15.28.1+35.2 20257.29
Item of work if material taken outside campus) 9% cost index-
12% GST
CPWD 2016,
Dismantling steel work in built up sections in angles, tees, item
flats and channels including all gusset plates, bolts, nuts,
5 cutting rivets, welding etc. including dismembering and
2904.26 kg 2.90 no.15.18+35.29 8419.66
stacking within 50 meters lead etc. completed as directed. % cost index-
12% GST
Dismantling burnt brick masonry (in cement mortar) with CPWD 2016,
plaster including sorting out serviceable bricks and item
lowering down debrises, stacking the same and debris
6 separately upto a distance of 50 meters or spreading the 48.96 m3 1018.00 no.15.7.4+35.29 49841.28
debris as directed. % cost index-
12% GST
Pulling down stone masonry in cement mortar with plaster CPWD 2016,
/ pointing without dust nuisance including sorting out the item
7 47.42 m3 1214.83 no.15.9.2+35.29 57607.32
stone chips and debris separately and stacking upto % cost index-
distance of 1000 metres as directed. 12% GST
Dismantling plain cement concrete work including CPWD 2016,
breaking concrete by chiselling, wedging etc., and item
8 19.82 m3 743.07 no.15.2.2+35.29 14727.65
stacking the debris upto a distance of 50 metres or % cost index-
spreading as directed. 12% GST
Removing soling without dust nuisance including sorting
9 out the stone chips and debris separately and stacking upto 45.60 m3 170.00 Rate Analysis 7752.00
distance of 50 metres as directed.
Disposing debris, loose stones, boulders, concrete pieces
broken etc. collected and stacked as directed including
loading in trucks, transporting out of IIT Campus
including obtaining approval from Government/ private CPWD 2016,
land owners for disposing off on to their approved item
10 68.78 m3 145.62 no.15.60+35.29 10015.60
location. The contractor will be solely responsible for
% cost index-
disposing debrises out of campus and the debris are to be 12% GST
removed from site within 72 hours from stacking (30%
voids will be deducted from actual measurement for
debris, loose stones, boulders, concrete pieces).
A Total dismantling amount Rs. 186119.21
RECOVERY
1 structural and Reinforcement Steel 4837.92 kg 20.00 Market Rate 96758.44
2 Aluminum sheets, sections etc. 206.89 kg 100.00 Market Rate 20688.90
3 wood 891.94 kg 25.00 Market Rate 22298.44
4 Plywood, door shutters 176.30 kg 6.00 Market Rate 1057.78
5 Glass 1007.76 kg 6.00 Market Rate 6046.55
B Total recovery amount Rs. 146850.11
Amount to be recover from contractor by IIT Total B-A -39269.10
d MMD dept.
CPWD 2016,
Removing door shutters and window shutters of any size item
1 and type with fittings (if available) and taking out the 61.00 Nos 261.40 no.15.12.2+35.2 15945.40
same outside IIT Campus etc. complete. 9% cost index-
12% GST
Removing rolling shutters, collpsible gate etc. with fittings
2 17.33 m2 141.00 Rate Analysis 2443.53
and taking out the same outside IIT Campus etc. complete.
Removing teak wood or aluminium paneled / partly glazed CPWD 2016,
or veneer / plywood partitions, any type of ceiling item
carefully without damaging the frame or panels and taking
3 out the same outside IIT Campus etc. complete. 531.99 m2 29.35 no.15.57+35.29 15613.91
% cost index-
12% GST
CPWD 2016,
Removing galvanised iron or asbestos cement sheet roof item
covering and taking out the same outside IIT Campus,
4 scaffolding etc. complete. (5% cost will be deducted from
573.44 m2 84.68 no.15.28.1+35.2 48557.20
Item of work if material taken outside campus) 9% cost index-
12% GST
CPWD 2016,
Dismantling steel work in built up sections in angles, tees, item
flats and channels including all gusset plates, bolts, nuts,
5 cutting rivets, welding etc. including dismembering and
8698.02 kg 2.90 no.15.18+35.29 25216.18
stacking within 50 meters lead etc. completed as directed. % cost index-
12% GST
Dismantling burnt brick masonry (in cement mortar) with CPWD 2016,
plaster including sorting out serviceable bricks and item
lowering down debrises, stacking the same and debris
6 separately upto a distance of 50 meters or spreading the 52.25 m3 1018.00 no.15.7.4+35.29 53190.50
debris as directed. % cost index-
12% GST
Dismantling R.C.C. work including breaking concrete by CPWD 2016,
chiselling, wedging etc., cutting the reinforcement, item
7 1.68 m3 1757.02 no.15.3+35.29% 2951.79
lowering down debrises, stacking the debris upto a cost index-12%
distance of 50 metres or spreading as directed. GST
Pulling down stone masonry in cement mortar with plaster CPWD 2016,
/ pointing without dust nuisance including sorting out the item
8 92.89 m3 1214.83 no.15.9.2+35.29 112845.72
stone chips and debris separately and stacking upto % cost index-
distance of 1000 metres as directed. 12% GST
Dismantling plain cement concrete work including CPWD 2016,
breaking concrete by chiselling, wedging etc., and item
9 46.70 m3 743.07 no.15.2.2+35.29 34701.37
stacking the debris upto a distance of 50 metres or % cost index-
spreading as directed. 12% GST
Removing soling without dust nuisance including sorting
10 out the stone chips and debris separately and stacking upto 107.42 m3 170.00 Rate Analysis 18261.40
distance of 50 metres as directed.
Disposing debris, loose stones, boulders, concrete pieces
broken etc. collected and stacked as directed including
loading in trucks, transporting out of IIT Campus
including obtaining approval from Government/ private CPWD 2016,
land owners for disposing off on to their approved item
11 101.17 m3 145.62 no.15.60+35.29 14732.17
location. The contractor will be solely responsible for
% cost index-
disposing debrises out of campus and the debris are to be 12% GST
removed from site within 72 hours from stacking (30%
voids will be deducted from actual measurement for
debris, loose stones, boulders, concrete pieces).
A Total dismantling amount Rs. 344459.17
RECOVERY
1 structural and Reinforcement Steel 9830.96 kg 20.00 Market Rate 196619.24
2 Aluminum sheets, sections etc. 10.54 kg 100.00 Market Rate 1054.00
3 wood 8079.48 kg 25.00 Market Rate 201987.00
4 Plywood, door shutters 1569.82 kg 6.00 Market Rate 9418.92
5 Glass 688.35 kg 6.00 Market Rate 4130.10
B Total recovery amount Rs. 413209.26
Amount to be recover from contractor by IIT Total B-A 68750.09

Refixing the old removed aluminium frame partition with


existing glass / particle boards etc. with new screws, nails,
5 rubber gasket, beading and other required fittings 16.00 m2 404.00 Rate Analysis 6464.00
including cutting making good the partition including
scaffolding etc. all complete as directed.
Supplying, fabricating and fixing in position aluminum
anodized openable door shutter using aluminum standard
door section 80mm x 40mm (not less than 1.139kg/mtr)
for verticals and middle, 100mm x 40mm (not less than
1.60kg/mtr) for top & bottom members, providing and
fixing 80mm wide and 16 gauge aluminium louvered over
40mm x 16 gauge aluminium plate for top portion and
4mm thick both side colour and designer aluminium
6 3.00 m2 5030.00 Rate Analysis 15090.00
composite sheet of approved make and approved colour
for bottom portion using 3 nos stainless steel hinges 4"
long for each shutter, 10" long SS handles 2 nos. for each
shutter, lock, stainless steel tower bolt 8" long 1 no for
each shutter, providing and fixing stainless steel mosquito
mesh for top portion with require fixtures etc. all complete
as directed. (All aluminium sections should be 15 micron
anodized/ powder coated)
Providing and fixing in position three track aluminium
sliding windows using sections of size 92 mm x 45mm x
1.05 mm (1.659kg/mtr) thick for bottom, sections of size
92 mm x 31mm x 1.30 mm (0.933kg/mtr) thick for sides
and top. The shutter comprising of bottom and top
member of size 40 mm x18 mm x 1.25 mm (0.417kg/mtr)
thick , interlocking section of size 40 mm x 18 mm x 1.10
mm (0.469kg/mtr) thick and handle section of size 40mm
x 18 mm x 1.25 mm (0.417kg/mtr) thick including
7 6.00 m2 4646.00 Rate Analysis 27876.00
providing and fixing 5mm thk. glass in the shutter using
rubber gasket, providing and fixing another shutter fixed
with stainless steel mosquito proof mesh in window with
require fittings such as approved quality minimum two
nos.PVC rollers for each shutter, necessary locks, handles,
PVC lining and other required fittings, provision for fixing
A.C. units (if required) etc. complete as directed by
Engineer in charge.( Note: All aluminium sections and
fitting are 15 micron anodized/ powder coated).
Providing second class burnt brick masonry with IS
approved quality well burnt bricks having crushing CPWD 2016,
strength of 35 kg. / square cm. and maximum water
item
8 0.20 m3 6813.06 no.6.3.1+35.29 1362.61
absorption of 20% in cement mortar 1:6 in superstructure
% cost index-
including striking joints, racking out joints, watering and
12% GST
scaffolding complete.
Providing and fixing 20mm thick cement bonded wood
particle board (bison panel) for chajja, ceiling, staircase at
any floor, providing suitable hole for fixing nuts and bolts
9 7.50 m2 1352.00 Rate Analysis 10140.00
including making suitable groove on walls, making vata at
joint, P/F sheet in proper slope including double
scaffolding wherever required complete as directed.
Providing and fabricating structural steel works in rolled
sections like joists, channels, angles, tees, hollow sections
CPWD 2016,
and any other required sections etc. as per detailed designs item
10 & drawings for supports, rafters, purlins, railing, staircase 145.000 kg 70.60 no.10.1+35.29% 10237.00
and any other work including fixing in position with cost index-12%
connecting plates, braces and welding, riveting, bolting as
GST
necessary including painting, scaffolding etc. complete.
Providing and fixing mild steel grill work for window,
ventilator, partition weighing 15 kg per sqm as per
drawing including necessary welding and painting with
11 21.00 m2 1395.00 Rate Analysis 29295.00
one coat ( one coat of red lid oil paint and two coats of oil
paint of approved shade) of anti-corrosive paint etc.
complete.
Add for extra weight or deduct for less weight over item
no.11 for fabricating such as cutting, shaping, riveting etc.
12 mild steel for grill works including welding and painting 147.00 kg 98.00 Rate Analysis 14406.00
with one coat of red lid oil paint and two coats of oil paint
of approved shade.
Providing and laying colour veined granite slabs 18 to
20mm thick of approved quality colour and veins over CPWD 2016,
table, pasting the slab using approved quality resin, filling item
13 10.00 m2 4048.98 no.8.2.2.1+35.29 40489.80
joints with white cement to match colour of slab, P/F teak % cost index-
wood molding of required size around stone, polishing to 12% GST
slab and molding etc complete.
Providing and fixing Kadappa stone slab for platform of
approved type and design 20 to 30mm thick in cement
14 6.00 m2 1232.00 Rate Analysis 7392.00
mortar 1:4 including providing and fixing border patti on
front edge, filling joints, curing, cleaning etc. complete.
Providing and fixing white glazed earthenware sink
having approximate size 600mm x 400mm x 200mm
15 1 Nos 8144.00 Rate Analysis 8144.00
including waste coupling, PVC pipe upto trap, testing etc.
complete.
Providing and fixing 12mm dia heavy duty brass
16 chromium plated three way taps with all fittings etc all 1 Nos 1505.00 Rate Analysis 1505.00
complete as directed.
Providing and laying I.S.I. approved 15mm dia. heavy
type galvanized iron pipes having weight as per IS
specification to walls, ceilings, floors etc. with screwed
CPWD 2016,
sockets, back nuts, elbows, tees, reducers, enlargers, item
17 plugs, clamps etc. including necessary drilling in holes in 5.00 Rmt 225.16 no.18.10.1+35.2 1125.80
walls / slabs etc. and remaking good the demolished 9% cost index-
portion to restore the same in original condition neatly and 12% GST
applying primer and two coats of oil painting including
necessary scaffolding etc. or as directed etc. complete.
Providing and fixing ISI approved 50mm dia. HDPE pipes
manufactured by NOCIL / PIL of various diameters with
wall thickness of 2.60 mm to 10.00mm for taking drain
water with all required fittings such as bend, tee, elbows
etc. with proper line and gradient connecting all joints
18 with fusion butt welding by using hot plate, keeping hole 2.00 Rmt 604.00 Rate Analysis 1208.00
in wall / pardi etc. filling the patches, with cement
concrete 1:1½:3, clamping the pipes on wall / column etc.
with the use of scaffolding, testing the line, providing
inspection joints with and caps etc. all complete as
directed.
Providing & Fixing of Dune microlook R.H 99% NRC
ceiling system consisting of 600x600mm size grid with
fleece laying in tiles of pre-coated galvanized steel in
0.4/0.5 mm thickness in required colour with 15mm wide
19 50.00 m2 1363.00 Rate Analysis 68150.00
T - section silhoute flanges of required colour having
rotary stitching on the main Runner including P/F
1200mm &600mm cross Tees as per manufacturer
specifications.
Providing, fabricating and fixing loft cupboard having
approximate depth 450mm using 18mm thick commercial
plywood for shutter, shelves, top, side, bottom and center
support, 8mm thick plywood for backside, P/F 1mm thick
design sunmika for exposed sides and 0.80mm thick white
20 1.50 m2 9246.00 Rate Analysis 13869.00
sunmika for unexposed sides and back side including all
necessary fittings and fixtures such as lipping, self closing
hinges of (ebco or equivalent make), screw, nails and
other required fittings and fixtures etc. complete as
directed.
Providing and fixing openable shutter made up of 18mm
thick marine plywood of approved make, P/F 1mm thick
designer sunmika on expose side and edges of shutters and
frame, P/F 0.80mm thick white sunmika on unexposed
21 side and frame, P/F stainless steel hinges 2 nos. for each 3.00 m2 4052.00 Rate Analysis 12156.00
shutter, 1no handle(S.S) for each shutter, ball cage etc.
with screws in line and level, P/F wooden frame of
required size for frame rectification of all damages etc.
complete as directed.
Providing and fixing drawers of having approximate size
depth 600 mm x width 400mm x 200mm height using
12mm thick commertial plywood for all sides and for
22 fixing drawer, P/F 0.80mm thick white sunmika for all 3 Nos 3925.00 Rate Analysis 11775.00
sides with fittings and fixtures such as telescopic sliding
channels, handle and other require fixtures etc. completed
as directed.
Carefully removing internal or external plaster in patches
or any length without damaging structure brickwork in
the vicinity by using electric cutting tools including CPWD 2016,
cutting a groove first to demarcate exact area of damage item
23 8.00 m2 27.06 no.15.56+35.29 216.48
taken place stacking the debrises with in 50 meter,
% cost index-
cleaning the site etc. complete. including covering the 12% GST
furniture, floor, windows and partitions with plastic sheets
while chipping with double scaffolding.
Note:-
a) No extra payment shall be made for extra thickness
removed.
b)  Proper tools to be used for removal of concrete and it
should be seen by contractor no damage on the other side /
near by area will be taken place and if required other
portions are to be checked by the contractors with respect
to the damage before commencement of the work.
c) The area in vertical plane shall be measured.
Chipping the RCC surface and cleaning the rusted
reinforcement and exposed surface by wire brush
mechanical device or any other establish method and
applying rust removing solution of approved make and
quality with cotton waste swab to reinforcement and
24 allowing to dry the same for 24 hours, brushing of loose 8.00 m2 105.00 Rate Analysis 840.00
partial and applying 1st coat of rust preventing coating of
polymer and cement slurry in 1:1.5 proportion with soft
brush without adding water including applying another
coat of rust preventing after 4 hours allowing Air curing
for 48 hours etc. including scaffolding etc. complete.
Providing and applying an effective bond coat of Polymer
(SBR) approved by IITB and cement in the proportion of
1:1 by using brush in multiples coats as required to
accommodate the whole thickness of polymer modified
mortar wherever required including scaffolding wherever
required on the surface of old concrete / repaired concrete
25 Polymer (SBR) of approved manufacturer should have the 8.00 kg 346.00 Rate Analysis 2768.00
following properties: · Suspended solid particles should
not be less than 40% · Specific gravity should not be more
than 1.01 · PH should not be less than 8.5 Note: The
actual consumption of polymer shall be measured for
payment on weight basis. Challans of authorized dealer
will be verified.
Providing and Placing in position Readymix Polymer
mortar manufacture by Dr.Fixit, Sunanda, Roff or M.C.
Bouchmey, Chembond and adding water in the proportion
of 1:0.14( Polymer morter:water) at any floor over the
prepared RCC surfaces in layers as directed (thickness of
each layer shall not exceed 10 to 15mm ) including
26 364.00 kg 72.00 Rate Analysis 26208.00
mixing the polymer mortar with water using forced action
mixer including double scaffolding wherever required
mild curing will be done with water for 3 days etc
complete.( payment will be paid for the actual quantity of
polymer mortar PX used on weight basis.Challans of
authorized dealer will be verified)
Providing internal cement plaster 12mm thick in single CPWD 2016,
coats in cement mortar 1:4 without neeru finish to item
27 11.00 m2 208.91 no.13.1.1+35.29 2298.01
concrete or brick surfaces in all positions with the use of % cost index-
step ladder and curing complete 12% GST
Providing and applying white cement based Birla make
wall care putty of averarge thickness 1mm, over plaster/ CPWD 2016,
item
concrete surface in proper line / level to prepare surface
28 11.00 m2 105.51 no.13.80+35.29 1160.61
even and smooth for including preparing the wall surface
% cost index-
for the application of wall care putty etc. complete as
12% GST
directed.
Providing sand face plaster externally using approved
screened sand in all positions including base coat of
15mm thick in cement mortar 1:4 using water proofing
compound at the rate of 1kg per cement bag and curing
29 the same for not less than two days and keeping the 3.00 m2 545.38 Rate Analysis 1636.14
surface of base coat rough to receive the sand faced
treatment not to exceed 8mm thick in cement mortar 1:4,
finishing the surface by taking out grains and curing for
14 days, scaffolding etc. complete.
Providing and fixing in position shutter in sliding window
using aluminium section for bottom and top member of
size 40 mm x18 mm x 1.25 mm (0.417kg/mtr) thick ,
interlocking section of size 40 mm x 18 mm x 1.10 mm
(0.469kg/mtr) thick and handle section of size 40mm x 18
mm x 1.25 mm (0.417kg/mtr) thick including providing
30 and fixing mosquito proof mesh in the shutter using 2.00 m2 2202.00 Rate Analysis 4404.00
approved quality minimum two nos.PVC rollers,
necessary locks, handles and other required fittings,
making shutter removable as and when require etc.
complete as directed by Engineer in charge.( Note: All
aluminium sections and fitting are 15 micron anodized/
powder coated).
Providing and applying one coat of seal cement primer CPWD 2016,
IITB approved brand, cleaning the surface with the use of item
31 stepladder including scrapping the surface, filling the 206.00 m2 44.63 no.13.43+35.29 9193.78
holes, covering the floor, windows, instruments during % cost index-
painting etc. complete. 12% GST
Providing and applying roller finish Acrylic plastic
emulsion paint of of IITB approved manufacturer and of CPWD 2016,
desired colour and shade to old / new ceiling & wall item
32 surfaces in two coats with the use of stepladder, preparing 193.00 m2 66.74 no.14.53.1+35.2 12880.82
and levelling the surfaces with Acrylic palty, as per 9% cost index-
manufactures specification (excluding priming coat) 12% GST
complete.
Providing and applying Acrylic oil bound distemper of
IITB approved manufacturer and of desired colour and CPWD 2016,
shade to old / new surfaces in two or more coats including item
33 scaffolding, preparing the surfaces (excluding priming 13.00 m2 36.00 no.14.63.1+35.2 468.00
coat), covering the floor, windows, instruments during 9% cost index-
painting complete. 12% GST

Providing and applying one coat of acrylic primer and two


coats of pure Acrylic exterior paint of IITB approved
manufacturer as per manufacturers specification on old or
CPWD 2016,
new plastered surface over concrete / brickwork as per item
34 manufacturer's specification including scaffolding and 3.00 m2 116.02 no.13.46.1+35.2 348.06
cleaning the surface throughly with coir brush, watering 9% cost index-
the surface etc complete including covering the floor, 12% GST
window glass with plastic sheet and as directed by the
office.
Providing and applying exterior coating for wall including
mechanical cleaning of the external surface and treating
surface in sound, clean and free from dirt, oil and other
loose material and may be done with vacuum cleaning if
required. All surface cracks upto 5 mm width will be filled
up with Dr. Fixit Crack X paste or similar material. The
external surface will be primed with Dr. Fixit Primeseal
(or equivalent BASF/ FOSROC/ STP) diluted with
potable water in the ratio of 2:1 by volume prior to
application of Dr. Fixit Raincoat. Allow it to dry for at
least 2 to 3 hours and then apply Dr. Fixit Raincoat or
equivalent (BASF/ FOSROC/ STP) having DFT of 110
micron, elongation of > 100% as per ASTM D412-02 and
algae Fungal resistance as per SS 345-1998. Accelerated
weathering (2000 Hrs UV Exposure) as per ASTM D4587
35 77.00 m2 385.00 Rate Analysis 29645.00
No defects) in 2 coats by brush, roller or spray with
required shade steiner to give required shade to the surface
with an interval of 5 to 6hrs. Allow it to air cure for 7 days
and do not dilute Dr. Fixit Raincoat by any means. Work
includes scaffolding and cleaning the surface thoroughly,
watering the surface etc. complete including covering the
floor, window glass with plastic sheet and as directed by
this office. Work shall be guaranteed for 5 years by the
contractor on Rs. 500/- stamp paper including submitting
written guarantee. ( if any leakage occurs during the
guarantee period the agency has to cover the terrace with
tarpaulin. If the contractor fail to provide tarpaulin, Estate
office will provide and fix tarpaulin at contractor's risk
and cost. Security deposit will be released after 2 years but
1% per year)
Total Amount Rs. 5704544.44
Say Rs. 5704544.00
RATE ANALYSIS
Removing rolling shutter
For 11.50 m2
Skilled Labour 0.50 days 673.00 336.50
2 Unskilled 1.00 days 553.00 553.00
Transport 220.00
Scaffolding 9.00 m2 31.50 283.50
Tools and plants 15.00
1408.00
Add 15% C.P 0.15 211.20
1619.20
Rate for 1 m2 1619.20 / 11.50 140.80 per m2
Say Rs. 141.00 per m2
Removing cupboard
For 7.70 Rmt
1 carpenter 0.30 days 673.00 201.90
1 helper 0.30 days 553.00 165.90
Transport 100.00
Tools and plants 10.00
477.80
Add 15% C.P 0.15 71.67
549.47
Rate for 1 Rmt 549.47 / 7.70 71.36 per Rmt
Say Rs. 71.00 per Rmt
Removing soling
For 2.00 m3
Labour - 2 Unskilled for 2 hrs 4.00 hrs 69.13 276.52
Tools 20.00
296.52
Add 15% C.P. 0.15 44.48
341.00 Per m3
For 1 m3 341.00 / 2.00 170.50 Per m3
Say Rs, 170.00 Per m3
Disposing debris's outside campus
For 6.44 m3
Rent for truck by deducting 30% voids 1.00 truck 3500.00 3500.00
BMC permission/ private land owner 1.00 m3 350.00 350.00
3850.00
Add 15% C.P 0.15 577.50
4427.50
Rate for 1 m2 4427.50 / 6.44 687.50 per m3
Say Rs. 688.00 per m3
Dismantling platform
For 14.19 Rmt
2 helper 0.75 days 553.00 414.75
Transport 100.00
Tools and plants 5.00
519.75
Add 15% C.P 0.15 77.96
597.71
Rate for 1 Rmt 597.71 / 14.19 42.12 per Rmt
Say Rs. 42.00 per Rmt
1.120 11.120 10.000
1.640 9.480
2.130 8.990
1.245 9.875
1.105 10.015
2.805 8.315