Second Penang Bridge PDF
Second Penang Bridge PDF
SUSTAINABLE
LEMBAGA LEBUHRAYA
DESIGN & CONSTRUCTION
MALAYSIA
8 October 2011
JAMBATAN KEDUA
SDN BHD.
Presented by: Dato’ Ir. Dr. Ismail bin Mohamed Taib
Managing Director, Jambatan Kedua Sdn Bhd
Content JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Project Introduction
Project Details
Sustainable Development
i. Social Progress
ii. Economic Activity
iii. Environmental Responsibility
Project
Introduction
NAVIGATIONAL
SPAN
0.
1+
00
0.
3+
00 0
00
PULAU
.
0.
4+
00
AMAN
0.
5+
00
0.
6+
00
7+00
0.
8+000
9+000
0.
10+
23
11
000
.
+0
+
00
22+
00
.
000
12
.
0.
.
00 +
0.
13
21+
+0
0
20+00
0.
000
19+00
14
18+00
17+00
+0
.
15+00
16+00
0.
00
0.
.
0.
0.
0.
0.
MAIN LAND
(Batu Kawan)
Project Details
P0
0.
2+
3+
00
PACKAGE 3C
0
0.
00
PULAU
.
+0 4
AMAN
0. 0
5+
00 0
.
6+
7+00
0.
8+000
(BATU KAWAN)
9+000
0.
10+
23
11
000
.
+0
+0
00
22+
.
00
12
000
.
.
.
+0
00
13
.
21+
+0
00
20+00
P292
000
.
19+00
14
18+00
17+00
+
.
00
15+00
16+00
0.
0.
0.
0.
BATU MAUNG INTERCHANGE
0.
0.
0.
PLUS TOLL
PB2X TOLL PLAZA
PLAZA
PHYSICAL PROGRESS %
(Rev 01)
COST
PAKEJ DESCRIPTION CONTRACTOR START FINISH (29 Sep 2011)
(RM MIL.)
SCH % ACT %
Structural concrete design to CP110: 1972 Structural concrete design to BS 5400: 2006
Settlement criteria for earth embankment: Settlement criteria for earth embankment:
367 mm in 5 years 50 mm in 20 years
Sustainable
Development
1. Social Progress
2. Economic Activity
3. Environmental Responsibility
Social
Sustainable
Environment Economic
1. Social Progress
i. Stakeholder communication and
involvement
ii. Occupational Safety
iii. Public Road Safety
iv. Bridge Optimization
v. Bridge Durability
• Lost time injury (LTI) achieved is 0.24 per million hours, which is very minor
with only 2 cases at 8.3 million hours. According to OSHA International
Standard, the LTI shall not be more than 5 cases in every 1 million hours.
Cont‟d
• Standard Guardrails with level TL3 is upgraded to level TL4 at strategic locations to
ensure that in the event of accident, heavy vehicles are contained.
• Motorcycle lane is separated from the main lane by NJB to protect vulnerable
motorcyclist.
NJB
Pilecap Construction
Precast Concrete Shells are used as a
formwork for the second layer casting and
permanently incorporated into the pile cap
6 pieces of Precast Concrete Shells are
required for each pilecap
Total of 3,468 nos of Precast Concrete Shell are used
Precast Concrete Shells are adopted for:
• Minimisation of temporary works (no cofferdams).
• Minimisation of insitu works
• Speed of construction
• Better surface finishing work
The Second Penang Bridge is designed to have an operational lifespan of 120 years.
For this project,
• Cathodic protection system and special coating are applied to the tubular steel piles for
protection against corrosion.
• High strength concrete with Ground Granular Blastfurnace Slag (GGBS) and Pulverised
Fuel Ash (PFA) are used for the pilecap, pier column, crosshead and SBG. This will
prevent sulphate and chloride attack that can cause corrosion to the reinforcement bar.
• Concrete cover was designed to latest Eurocode: pilecap (75 mm), pier column (65mm),
crosshead (60 mm) to protect the reinforcement bar against corrosion.
Cont‟d
• Silane coating is applied to precast concrete spun piles, pilecap and pier concrete surface to
further reduce the water and salt uptake that can cause corrosion to the embedded
reinforcing steel.
• Structural Health Monitoring System (SHMS) shall be used for preventive maintenance to
assess the state of health (e.g., damage) of the structures. It improves safety and reliability
of the bridge by detecting damage before it reaches a critical state.
Typical SHMS at a
cable-stayed bridge
Stay Cables The stay cables consists of the Parallel Strand System (PSS) made
up of parallel individually polyethylene coated seven-wire strands,
placed inside an external polyethylene stay pipe.
First Barrier
The stay cable will be provided with protection against corrosion by means of 3 barriers:
i) The first barrier is hot dip galvanising that covers the full length of the individual steel
wires.
ii) The second barrier (internal barrier) consists of High Density Polyethylene (HDPE)
sheaths around the individual strands and that the intermediate medium fills the space
between the individual sheath and the galvanized strand.
iii) The third barrier (external barrier) is the outer casing which consist of HDPE sheath
around the group of strands.
• For the anchorage components which are accessible for maintenance operation in-situ, the
corrosion protection system have a design life of 25 years. After this period of 25 years, if
necessary, the protection system will be renewed in-situ at regular intervals of 15 years
corresponding to the maintenance operations.
2. Economic Activity
i. Local construction employment
ii. Usage of Local Materials
iii.Vocational Training
iv. Regional Economic Development
Package % of Works
Package 2 30%
Package 3A 60%
Package 3B 30%
Package 3C 60%
• Except for the cable-stayed saddle and anchorage, and steel fender, all
other construction materials are obtained locally.
Vocational Training
The route will become major passage for the movement of goods
to Penang ports and the international airport in which will
facilitate economic activity and also promote regional tourism
industry.
3. Environmental
Responsibility
i. High Environmental Standards
ii. Minimal Impact on water flow
iii. Green Building Technology
iv. Reducing the Impact of Dredging
v. Flora and Fauna Monitoring
vi. Habitat Creation
The IEM, HTETD’s 20th Annual General Meeting – 8 October 2011
Sustainable Bridge Design and Construction
Environmental Responsibility JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
DREDGING AND
DISPOSAL OF
EIA & EMP EIA & EMP EIA & EMP EIA & EMP EIA & EMP
SPOIL MATERIAL
DR. Nik & R-SYNC Tech. YES Enviro CSK CSK
Associates Sdn Environmental
Resources Services Murni Murni
Bhd. Science
Sdn. Bhd. Sdn. Bhd. Services Services
The IEM, HTETD’s 20 th Annual General Meeting – 8 October 2011
Sustainable Bridge Design and Construction
Environmental Responsibility JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Segmental
Box Girder
Precast Shell
The IEM, HTETD’s 20th Annual General Meeting – 8 October 2011
Sustainable Bridge Design and Construction
Environmental Responsibility JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Substructure
Total pilecap : 4 nos
Pilecap size (P25 & P26): 48.1m x 17.5m x 6m
Pilecap size (P24 & P27): 42.7m x 10.6m x 4m
Steel Fender System
The steel fender system was adopted due to its environmental friendliness, cost
saving and shorter construction period.
iii) Low impact on the environment iii) Occupy larger water area restricting
and existing hydrological condition flow tidal
due to its relatively small size
• The design is based on requirements of 80% of IBS and 80% of Green Building Index.
• The landscaping and the exterior look of the Toll Plaza are designed in such a way that
the trespassing light is eliminated by plants and shaded area.
• Rain water from the roof of the building is harvested to supplement the conventional
water supply. The natural light is maximized for the intermediate floors to minimize the
usage of electricity. High efficiency windows and insulation in walls, ceilings and floors
are used for the benefit of better temperature control.
NAVIGATIONAL SPAN
1+
PROPOSED
00 0
TRUMPET
2+
.
3+
00
00
INTERCHANGE
0.
0.
PULAU
4+
00
AT Km 154 NSE
0.
AMAN
5+
00 0
PROPOSED
.
6+
00
PENANG SECOND
7+00
0.
8+000
9+000
10+
23
TOLL PLAZA PLUS TOLL
11
000
.
+0
JTTY
+0
22+
00
.
0 00
12
.
.
.
RSA
00
0.
Pulau Kendi
13
21+
+0
00
20+00
000
.
19+00
1
18+00
4+
17+00
.
0
15+00
16+00
0
00
.
0.
.
0.
0.
0.
LEGEND
CL
Viaducts
Sea Water
Level
R- Sync Technical Resources Sdn Bhd is appointed as the EMA Consultant for the
monitoring of dredging and offshore disposal of spoils during construction phase.
Equipment used:
o Garmin GPS Receiver ( Model GPSMAP 76 CSx)
Disposal
The IEM, HTETD’s 20th Annual General Meeting – 8 October 2011 Area
Sustainable Bridge Design and Construction
Environmental Responsibility JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Location of Cage
Culture Farms
• Monitored at 1m below
surface
• Readings were collected
every minute for at least
10 minutes
Previous Study
Current Study
Dissolved Oxygen
(mg/L) levels at Study
Area
• Generally, most parameters were recorded within suitable range for marine
environment and fisheries purposes
The IEM, HTETD’s 20th Annual General Meeting – 8 October 2011
Sustainable Bridge Design and Construction
Environmental Responsibility JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Contractor /
Role Signature Project
Consultant
CHEC Construction Main contractor • The Donghai Bridge, China
(M) Sdn Bhd for Main 25.5km length over water cable-stayed bridge,
- subsidiary of China Navigation span the second longest cross sea bridge in the
Harbour and substructure world.
Engineering for approach span. • The Sutong Bridge, China
Company Ltd Cable stayed bridge with the longest main span
(CHEC) (1088m) in the world.
Highway Planning & Designer for CHEC • The Sutong Bridge, China
Design Institute, Construction (M) • The Hangzhou Gulf Bridge, China
China Sdn Bhd The world‟s longest sea-crossing bridge (36km)
• The Xihoumen Bridge, China
The world‟s second largest span suspension
bridge (1650m)
Contractor /
Role Signature Project
Consultant
ARUP Jururunding • Independent • Stonecutter Bridge, Hong Kong
Sdn Bhd Checking Engineer Cable stayed bridge with the second longest main span
- Technical support for Package 1& 2 (1018m) in the world
from ARUP Hong • Supervision • Forth Replacement Crossing, Scotland, UK
Kong Consultant for A 2.7 km cable-stayed bridge with three single column
Package 3 towers, wind shielding and a single deck carrying two
general lanes of traffic and hard shoulders in each
direction
Thank You
For Your Kind Attention
* JKSB acknowledges the assistance of CHEC & UEMB for the preparation of this
presentation.
Casting of T-beam is in
progress
Construction activities at
CH18480
The IEM, HTETD’s 20th Annual General Meeting – 8 October 2011
Sustainable Bridge Design and Construction
Site Photographs – Package 3B JAMBATAN KEDUA SDN. BHD. (824573-U)
Wholly owned by Minister of Finance, Incorporated
Pile Embankment
works at CH20900
Relocation of Pylon is
completed
The IEM, HTETD’s 20 Annual General Meeting – 8 October 2011