Extraservis Painting Project-2019

Id Work Description Work Order Func. Location DuraciónTrabajo Comienzo


11 feb '19 25 feb '19 11 mar '19 25 mar '19 8 abr '19 22 abr '19 6 may '19 20 may '19 3 jun '19 17 jun '19 1 jul '19 15 jul '19 29 jul '19 12 ago '19 26 ago '19 9 sep '19
V M S X D J L V M S X D J L V M S X D J L V M S X D J L V M S X D J L V M S X D J L V M S X D J L V M S X D J
1 Proyecto Pintura 152 días 36,280 horas lun 18/02/19 07:00

2 C-RV-34228 - Coating repair on supports 100037926 P1-T1-UNIT 3400 8 días 400 horas lun 18/02/19 07:00 Group 5[5]
5 E. Package - L-1491 - Coating repairs 100038324 P1-T1-UNIT 1400 5 días 200 horas lun 18/02/19 07:00 Group 1[4]
10 E. Package L-1475 - Coating repair 100038577 P1-T1-UNIT 1400 7 días 210 horas lun 18/02/19 07:00 Group 4[3]
11 E. Package L-1476 - Coating repair 100038595 P1-T1-UNIT 1400 20 días 1,000 horas lun 18/02/19 07:00 Group 3[5]
13 E. Package L-1481 - Coating repair 100038599 P1-T1-UNIT 1400 8 días 320 horas lun 18/02/19 07:00 Group 6[4]
25 E. Package L-1497 - Coating repair 100038916 P1-T1-UNIT 1400 6 días 240 horas lun 18/02/19 07:00 Group 2[4]
23 E. Package L-6501 - Coating repair 100038891 P1-T1-UNIT 6500 4 días 200 horas vie 22/02/19 07:00 Group 5[5]
12 E. Package L-1493 - Coating repair 100038604 P1-T1-UNIT 1400 8 días 320 horas lun 25/02/19 07:00 Group 1[4]
20 E. Package L-1496A - Coating repair 100038601 P1-T1-UNIT 1400 4 días 160 horas mar 26/02/19 07:00 Group 2[4]
17 E. Package L-1473 - Coating repair 100038593 P1-T1-UNIT 1400 7 días 210 horas mié 27/02/19 07:00 Group 4[3]
14 E. Package L-1480 - Coating repair 100038598 P1-T1-UNIT 1400 5 días 200 horas jue 28/02/19 07:00 Group 6[4]
28 E. Package L-1495 - Coating repair 100038917 P1-T1-UNIT 1400 9 días 360 horas lun 4/03/19 07:00 Group 2[4]
32 Steel plates at roadway jetty 100039435 JETTY 30 días 1,500 horas mié 6/03/19 07:00 Group 5[5]
43 Z-3401-A FMC Obs. Corrosion ground level 100041886 JETTY 5 días 200 horas jue 7/03/19 07:00 Group 6[4]
6 Coating repair the crane 100042183 P1-T1-UNIT 1400 12 días 840 horas vie 8/03/19 07:00 Group 4[3];Group 1[4]
24 E. Package L-6602 B - Coating repair 100038893 P1-T1-UNIT 6600 7 días 280 horas jue 14/03/19 07:00 Group 6[4]
70 Area 190 Cable tray support Anchor bolts 100043009 P1-T1-UNIT 1400 8 días 400 horas jue 14/03/19 07:00 Group 5[5]
36 JX-XD-1KA450. Panel corroded. 100039117 P1-T1-UNIT 1400 3 días 120 horas vie 15/03/19 07:00 Group 2[4]
44 Z-3401-B FMC Obs. Corrosion ground level 100041887 JETTY 5 días 200 horas vie 15/03/19 07:00 Group 6[4]
7 Painting touch-up of transf. TR-1410 100038550 P1-T1-UNIT 1400 12 días 600 horas lun 18/03/19 07:00 Group 3[5]
56 L-1480 Exter. Inspect. Corrective Action 100042151 P1-T1-UNIT 1400 5 días 200 horas mié 20/03/19 07:00 Group 2[4]
45 Z-3401-C FMC Obs. Corrosion ground level 100041888 JETTY 5 días 200 horas lun 25/03/19 07:00 Group 6[4]
15 E. Package L-1478- Coating repair 100038597 P1-T1-UNIT 1400 5 días 150 horas mar 26/03/19 07:00 Group 4[3]
16 E. Package L-1477 - Coating repair 100038596 P1-T1-UNIT 1400 5 días 200 horas mar 26/03/19 07:00 Group 1[4]
57 L-1477 Exter. Inspect. Corrective Action 100042152 P1-T1-UNIT 1400 5 días 200 horas mié 27/03/19 07:00 Group 2[4]
46 Z-3401-D FMC Obs. Corrosion ground level 100041889 JETTY 5 días 200 horas mar 2/04/19 07:00 Group 6[4]
71 MR OH Crane Coating repair 100042190 P1-T1-UNIT 1400 12 días 840 horas mar 2/04/19 07:00 Group 4[3];Group 1[4]
4 E. Package - L-1471 - Coating repairs 100038321 P1-T1-UNIT 1400 4 días 200 horas mié 3/04/19 07:00 Group 3[5]
69 Hand switch support corroded - rundown 100042974 P1-T1-UNIT 1400 5 días 200 horas mié 3/04/19 07:00 Group 2[4]
8 Painting touch-up of transf. TR-1420 100038549 P1-T1-UNIT 1400 12 días 600 horas mar 9/04/19 07:00 Group 3[5]
76 Paint touch up Manbasket 100040969 Paint Shop 4 días 160 horas mié 10/04/19 07:00 Group 2[4]
73 Coating repair on PR/MR Stack 100042624 P1-T1-UNIT 1400 52 días 4,160 horas mar 16/04/19 07:00 Group 2[4];Group 6[4]
18 E. Package L-1470 - Coating repair 100038592 P1-T1-UNIT 1400 6 días 180 horas jue 18/04/19 07:00 Group 4[3]
26 E. Package L-6701 - Coating repair 100038925 P1-T1-UNIT 6700 6 días 240 horas jue 18/04/19 07:00 Group 1[4]
37 E. Package L-6603 B - Coating repair 100041662 P1-T1-UNIT 6600 15 días 750 horas jue 25/04/19 07:00 Group 3[5]
72 Coating repair by touch up paint a crane 100042189 P1-T1-UNIT 3400 10 días 700 horas vie 26/04/19 07:00 Group 4[3];Group 1[4]
49 INSPECT AND REPAIR STRUCT. SURPLUS TEN100040340 OSBL 24 días 1,200 horas lun 29/04/19 07:00 Group 5[5]
3 Coating refurbishment at HVAC A-7001 100038320 P1-T1-UNIT 4000 20 días 1,400 horas vie 10/05/19 07:00 Group 4[3];Group 1[4]
38 E. Package L-6603 A - Coating repair 100041663 P1-T1-UNIT 6600 15 días 750 horas jue 16/05/19 07:00 Group 3[5]
34 Tagging LNG Storage Tanks T-3401/3402 100039362 P1-T1-UNIT 3400 15 días 600 horas mié 22/05/19 07:00 Group 6[4]
35 Emerg Air compress K-6601C coating rep. 100040655 P1-T1-UNIT 6600 5 días 200 horas mié 22/05/19 07:00 Group 2[4]
30 E. Package L-6604B - Coating repair 100038924 P1-T1-UNIT 6600 5 días 200 horas mié 29/05/19 07:00 Group 2[4]
75 Paint Caisson, passivate shaft P-6302-B 100042844 JETTY 24 días 1,200 horas vie 31/05/19 07:00 Group 5[5]
67 L-3401 BOG Anchor bolts/Concrete slabs 100042944 P1-T1-UNIT 3400 12 días 600 horas mar 4/06/19 07:00 Group 5[5]
42 Moderate damage-Repair Coating 100041873 JETTY 5 días 200 horas mié 5/06/19 07:00 Group 2[4]
63 Coating refurbishment Hot Lines-310 Area 100042322 P1-T1-UNIT 3100 27 días 1,350 horas jue 6/06/19 07:00 Group 3[5]
47 Paint touch-up of roof structure at J8 100041904 OSBL 20 días 1,400 horas vie 7/06/19 07:00 Group 4[3];Group 1[4]
74 Paint cabinets OSBL Power Distrib SG TF 100042677 OSBL 18 días 1,260 horas vie 5/07/19 07:00 Group 4[3];Group 1[4]
53 Finding on Breakwater Southside Jetty 100042169 JETTY 6 días 300 horas lun 15/07/19 07:00 Group 3[5]
51 coating and fibaroll on beam 330 area 100041856 P1-T1-UNIT 3100 4 días 200 horas mar 16/07/19 07:00 Group 3[5]
48 Painting touch-up of transf. TR-3401 A 100038548 P1-T1-UNIT 3400 7 días 280 horas jue 18/07/19 07:00 Group 2[4]
55 L-1302 Exter. Inspect. Corrective Action 100042150 P1-T1-UNIT 1300 8 días 320 horas jue 18/07/19 07:00 Group 6[4]
29 E. Package L-6303 - Coating repair 100038993 P1-T1-UNIT 6300 10 días 400 horas lun 22/07/19 07:00 Group 2[4]
68 Painting touch-up of transf. TRE-1003 100038544 P1-T1-UNIT 1000 6 días 300 horas lun 22/07/19 07:00 Group 5[5]
54 Finding on Breakwater Norhtside Jetty 100042168 JETTY 6 días 300 horas mié 24/07/19 07:00 Group 3[5]
9 Painting touch-up of transf. TR-3401 B 100038547 P1-T1-UNIT 3400 7 días 280 horas mar 30/07/19 07:00 Group 2[4]
58 L-3402 Exter. Inspect. Corrective Action 100042154 P1-T1-UNIT 3400 6 días 240 horas mar 30/07/19 07:00 Group 6[4]
66 Severe corrosion of 115-NI-67216-01 100042469 P1-T1-UNIT 1100 4 días 200 horas mar 30/07/19 07:00 Group 5[5]
50 Painting touch-up of the FW piping 100042330 JETTY 6 días 240 horas mié 31/07/19 07:00 Group 1[4]
52 Moderate damage-Repair Coating 100041871 JETTY 4 días 120 horas mié 31/07/19 07:00 Group 4[3]
31 Ventillation grill corroded U-7024A/B 100039373 P1-T1-UNIT 4000 8 días 320 horas jue 1/08/19 07:00 Group 1[4]

Name of the Resources: Group1, Group2, Group3, Group4, Group5, Group6. Página 1
Extraservis Painting Project-2019
Id Work Description Work Order Func. Location DuraciónTrabajo Comienzo
11 feb '19 25 feb '19 11 mar '19 25 mar '19 8 abr '19 22 abr '19 6 may '19 20 may '19 3 jun '19 17 jun '19 1 jul '19 15 jul '19 29 jul '19 12 ago '19 26 ago '19 9 sep '19
V M S X D J L V M S X D J L V M S X D J L V M S X D J L V M S X D J L V M S X D J L V M S X D J L V M S X D J
62 Latex coating of V-3401 Fireproofing 100042323 P1-T1-UNIT 3400 4 días 120 horas jue 1/08/19 07:00 Group 4[3]
39 P-4101-A platform support recoat 100041799 P1-T1-UNIT 1100 17 días 850 horas lun 5/08/19 07:00 Group 5[5]
64 Coating repair of 190-NG-10016-01/02 100042376 P1-T1-UNIT 1400 7 días 350 horas mar 6/08/19 07:00 Group 3[5]
59 L-3412 Exter. Inspect. Corrective Action 100042155 P1-T1-UNIT 3400 6 días 240 horas mié 7/08/19 07:00 Group 6[4]
41 Moderate damage - repair coating 100041874 P1-T1-UNIT 3400 4 días 120 horas jue 8/08/19 07:00 Group 4[3]
40 Moderate damage-Repair coating 100041875 P1-T1-UNIT 3400 3 días 90 horas mié 14/08/19 07:00 Group 4[3]
60 L-3401 Exter. Inspect. Corrective Action 100042153 P1-T1-UNIT 3400 5 días 200 horas jue 15/08/19 07:00 Group 6[4]
65 Coating Insulation Repairs - E-1405 100042403 P1-T1-UNIT 1400 9 días 450 horas jue 15/08/19 07:00 Group 3[5]
27 E. Package L-7105 - Coating repair 100038927 P1-T1-UNIT 3400 6 días 240 horas mar 20/08/19 07:00 Group 1[4]
19 E. Package L-3411 - Coating repair 100038585 P1-T1-UNIT 3400 11 días 440 horas mié 21/08/19 07:00 Group 2[4];Group 4[3]
33 Foundation of CPI L-7105 coating repair 100040651 P1-T1-UNIT 3400 9 días 360 horas jue 22/08/19 07:00 Group 6[4]
22 E. Package 3421- Coating repair 100038613 P1-T1-UNIT 3400 10 días 510 horas mié 28/08/19 07:00 Group 1[4];Group
61 L-4004 Exter. Inspect. Corrective Action 100042156 P1-T1-UNIT 4000 15 días 750 horas mié 28/08/19 07:00 Group 3[5
21 E. Package 3422 - Coating repair 100038612 P1-T1-UNIT 3400 8 días 560 horas jue 5/09/19 07:00 Group 2[4]
77 Fin de Proyecto Pintura - Extraservis 0 días 0 horas mar 17/09/19 18:00 mar 17 se

Name of the Resources: Group1, Group2, Group3, Group4, Group5, Group6. Página 2