LUSAKA CITY COUNCIL

ENGINEERING SERVICES DEPARTMENT


ROADS AND DRAINAGE SECTION
REF: ESD/5/3/29/BB/

COST ESTIMATES FOR ROAD CUTTING AND REINSTATEMENT


Road Name No. of cuttings

1. Great North Road 1

Client

Lusaka Water and Sewarage Company

P.O. Box 90182, Lusaka

Item Description Unit Qty Rate Amount

a Road Cutting

1 Mobilization and Demobilization LS ZMW 1,000.00


2
Cutting of edges m 18 ZMW 75.00 ZMW 1,350.00
3 Excavation of soft material in
readiness to lay cables/ pipes/
ducts m3 12 ZMW 350.00 ZMW 4,200.00
Excavation of hard material in
readiness to lay cables/ pipes/
4 ducts m3 Ls ZMW - ZMW -
5
Backfilling and compacting m3 12 ZMW 250.00 ZMW 3,000.00
6
Cement Stabilising of 150mm
thick Gravel m3 1.2 ZMW 480.00 ZMW 576.00
7 Apply MC 30 Primer m2 8 ZMW 180.00 ZMW 1,440.00
8 Bituminous surface
reinstatement with Hot Asphalt
(70mm Thick) Tons 1 ZMW 2,400.00 ZMW 2,400.00
Total Carried Forward ZMW 13,966.00

b Application Fee 1 ZMW 431.03 ZMW 431.03

SUB TOTAL: ZMW 14,397.03

VAT 16% ZMW 2,303.53

TOTAL ZMW 16,700.56

NOTE:
All excavations along the road reserve to be reinstated within 24hours
Reinstatement of the Walkway and kerbs shall be the sole responsibility of the client
Excavation of hard material in readiness to lay cables/ pipes/ ducts, should need arise is client's
responsibility.
Attach a completed "Excavation & Road Cutting Permit" form
Quote valid for 14 days
14397.03448