The document lists common problems observed on construction sites and suggestions for addressing them. Key problems include unclear design documents, lack of drawings on site, site engineers not reading documents, and no site engineer present. Suggested solutions are to scrutinize documents for errors, always have drawings on site, read documents thoroughly, and require contractors to have a qualified site engineer. Proper documentation, communication, management, and safety practices are also recommended to address other common issues.
The document lists common problems observed on construction sites and suggestions for addressing them. Key problems include unclear design documents, lack of drawings on site, site engineers not reading documents, and no site engineer present. Suggested solutions are to scrutinize documents for errors, always have drawings on site, read documents thoroughly, and require contractors to have a qualified site engineer. Proper documentation, communication, management, and safety practices are also recommended to address other common issues.
The document lists common problems observed on construction sites and suggestions for addressing them. Key problems include unclear design documents, lack of drawings on site, site engineers not reading documents, and no site engineer present. Suggested solutions are to scrutinize documents for errors, always have drawings on site, read documents thoroughly, and require contractors to have a qualified site engineer. Proper documentation, communication, management, and safety practices are also recommended to address other common issues.
Problems What can be done Design, drawings, Documents should undergo specifications not scrutiny by equally clear, not complete competent persons (human errors are natural) No drawings at site Always carry drawings, you cannot remember everything Site engineers do • Read, read & read to not read the understand what you are documents supposed to do • Ask the seniors, architects, designers if you do not understand Most common problems observed and what can be done Problems What can be done No site • Contractor is responsible for engineer at site day to day supervision • Make it mandatory in the contract document to post a qualified site engineer • Government engineers check on contractor’s engineer and monitor important quality aspects Most common problems observed and what can be done Problems What can be done Even physical Checking of size, shape, parameters of works slope, length, breath, depth, and materials not weight, volume, diameter, checked etc..etc.. is possible….please do it !!!
Everything is not Make best use of the
possible to be engineering knowledge. detailed in the Above all, use common sense documents to solve practical problems Most common problems observed and what can be done Problems What can be done Poorly or no Records are important for records maintained many reasons, for accountability, for future reference, for improvement, keep proper records
Inadequate Conduct regular meetings to
communication review progress, to resolve with the contractor problems, to understand each other better Most common problems observed and what can be done Problems What can be done Poor or no management • Site management is at the work site (safety equally important for for the workers & general safety & public public) convenience • Need little extra efforts to guide the contractor’s site engineers & workers on storage of materials, equipment, tools & cleaning up of site after a day’s work