Professional Documents
Culture Documents
Survey Jomsom Airport
Survey Jomsom Airport
- Chainage survey
- Survey monumentation
- Baseline survey
- Benchmark survey Centre line survey
- Cross-section survey
- Topography survey
Methodological procedures used in various surveys are briefly given in the following sections.
• Cast in-situ concrete posts, 10 cm square. With an iron bolt flushed with concrete on the top.
• Concrete iron nails driven on engraved points in stable rocks.
• Paint marks with iron nails driven at centre on other permanent structures (e.g. building,
parapet of culverts etc.) available at site.
These monuments were established at safer place, easily visible and away from potential
disturbance due to construction activities. The monuments also severed as the baseline station for
horizontal ground control. At intermediate location additional temporary benchmarks (TBMs) and
transverse points (TPs) were fixed, to facilitate survey work. The description card of permanent
BMs is given in Appendix – A of the report.
The survey details were sufficient to prepare topomaps in 1:500 scales for whole area including
portion of Kali Gandaki for river training sites.
L-Scetion X-Section
1:500 H 1:200 H
1:100V 1:100 V
Main items of the inventory of existing physical facilities pertaining to each project airport are
summarized in the following sections, whereas the detail of inventory survey is presented in
Appendix-2 of the report. Likewise, existing problems and proposed measures for relevant
physical facilities are dealt in detail in corresponding chapters.
• Terminal Building
• Drainage
• River Training
4.2.2 Drainage
It included existing internal and external drainage at this airport:
• Interior Drainage
Visual Survey
Soil Investigation
• Test Pits
• Laboratory tests
No systematic condition survey was deemed necessary, as existing surface is not paved and
would require upgrading to hard surface for which necessary ground details were covered by
centerline cross-section and topography surveys. Likewise, drainage condition survey was
separately undertaken as part of airport inventory survey.
5.2.2 Soil Investigation
The soil investigation of runway, side strips and apron was carried out to:
• Test Pitting
• In- situ Tests
• Laboratory Tests
In the case of runway, test pits were excavated along the centre line and alternately in row to
determine horizontal and vertical variation in subgrade soil across the width. Spacing of test pits
was dependent on soil variation, whereas the depth was guided by position of groundwater table
and type of materials.
Test pit logs were prepared along with visual classification of soil by USCS and record of depth to
soil freezing/frost penetration and position of groundwater table. Representative samples of
subgrade materials were collected from test tips for laboratory test. The test pits were properly
backfiled after in- situ tests and sampling.
In total 18 number of test pits were excavated with 14 on runway and 4. at apron. Location and
elevation of test pits were taken by topography survey.
5.2.2.2 In-Situ-Tests
The following type of in-situ tests were performed in runway, side strips and apron area:
The subgrade in apron area falls under category II. Because of heterogeneous nature, the
subgrade strength is found to vary widely. CBR tests on gravelly materials are difficult to interpret.
Labotary CBR tests on gravel often yield CBR results, which are too high due to the confining
effects of the mold. The assignment of CBR values to gravelly subgrade materials may be based
on judgement and experience.
Subgrade in Category I consist of heterogeneous mixture of sand, gravel, cobbles and boulders
derived from side hill/terrace cuts and laid in random sub layering in existing formation. Whereas
subgrade in category II consist of soil from hill terrace cultivation overlaid by coarser materials of
varying proportion. But the materials in the sublayers were not found as coarse as in category I.
In category II, the subgrade consists of soil partly from terrace cultivation and partly sandy gravels
of kali8 Gandaki river terrace deposit. Because of thin overlaying of other materials, original soil
belongingto terrace cultivation are exposed at shalloe depth or even on surface at few places
especially on central portion of runway between ch 0+630 and ch 0+660 and on lift side strip
between ch 0+660 and ch+0+739 ane on right side strip between ch 0+630 and ch 0+739. The soil
originating from cultivation consist of sand, silts and clay (TP-16, TP -18).Due to higner pro portion
of sand and non-plastic fines, these soil are found to have low dry strength.
With consideration of variable nature and composition of subgrade and new fill materials required
to raise the existing formation at many areas for geometric improvement CBR strength of 9
percent is a is assigned as the design CBR value for pavement design at this airport.
DRAINAGE DESIGN
11.1 GENERAL
This chapter deals with hydraulic revive and assessment of drainage condition, design of surface
and sub-surface drains, cross drainage structures including drainage outlet.
• Stone masonry lined runway side drain along north-weatern and with steep untended
outfall to Kali Gandaki River.
• RCC slab culvert of inadequate size across runway at ch 0+357.5 without proper outlet.
Problems related to existing drainage system are many such as deformed existing side drains,
lakeness of proper drains, flow of strom water from outside (i.e. Jomsom bazaar) inadequacy
of drain outfalls, etc.
Because of topography and existing layout of airport and adjouning Jomsom bazaar, the
airport drainage system is influenced by drainage from outside. Due to slope of topography
towards the airport, drainage from Jomsom bazzar area tend to flow to the airport. Thus the
airport drains have become outlet of drains from Jomsom bazzat and strom run-off from hills at
the backside. Moreover sewage from houses are seen discharge directly into the airport
drains.
It is unlikely that existing situation will change in future. Therefore the drainage planning for
airport required consideration for both interior and exterior drainage as one system.
− Flood of 25 year's return period for cross-drains (i.e. culverts) and drainage outlets.
The discharge capacity for all type of drains has been computed using Manning's formula with
manning Roughness coefficient as 0.018.
The culvert is designed by assuming that 80% of the sectional area is filled with water.
• Drains
11.6.1 Drains
Two types of drains have been designed for the airport on the basis of location and level of
discharge. These include
− Rectangular drain
− Trapezoidal drain
The drains will be of stone masonry using following types of construction:
Rectangular drains of cement masonry in MM5
Trapezoidal drains of dry stone lining with MM7.5 cement pointing on sides and MM5 cement
masonry lining on bed.
All drains will be open except drains D-5, D-7 and D-24 which will be covered type with RCC
precast slab covers.
Incase of trapezoidal drain the thickness of lining are 200mm on sides and 250 mm on bed. Whist
rectangular drains will have uniform thickness of 250mm on sides and base except drain D-5
under track/road crossing, which will be 450mm on sides and 400 mm at base including 200mm
thick stone soling.
Type and size of drains are given in Table 11.1. Similarly, typical details of different drains are
shown in Figure 11.2.
11.6.2 Drop Structures
Drop structures have been provided in design to adjust large elevation difference due to
topography variation. These are simple stone masonry structures with inclined face to enable
smooth transition of flow. Incase of large drops base have been strengthened with plum concrete.
Whereas for small drops bed is protected with masonry lining.
Drops structures provided in airport drainage system are listed in table …
11.6.3 Culverts
As discussed earlier cross-drainage of airport drainage system are provided by existing culvert
C1and proposed culvert C2 across runway and a taxiway culvert.
The culverts are designated as slab culverts with stone masonry abutments and precast or cast in-
situ slab covers, as appropriate. The bed will be protected with PCC layer over stone soling.
Size of existing and proposed culverts includes:
Culvert CI
Width 0.90m and height 1.00M
Culvert C2
Width 1.00m and height 1.15m
Taxiway Culvert
Width 1.50m and height 0.80m
11.6.5 Inlets/Outlets
Inlets are proposed in design for junction with drop structures and railway culverts. Existing inlet
structure at culvert C1is modified to design requirements. Outlet structures are provided for
culverts C1 and C2 to regulate/channelize flow to drainage outlet.