Site Mobilisation Site Setting Out Site Clearance

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID Task Name Duration Month 2 Month 3

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7


1 Adopt innovative approach where solar system 30 days
becomes primary energy source for piped water supply
system in Ikyogen, Adagom and Ukende settlements

2 Site Mobilisation 2 days

3 Site Setting out 2 days

4 Site clearance 1 day

5 Geopysical Survey 3 days

6 Drilling of Borehole 7 days

7 Supply and Installation of pressure UPVC casing 1 day

8 Flushing and development of borehole 1 day

9 Borehole pump test 1 day

10 Physical, bacteriological and chemical analyses 2 days

11 Overhead Tank (Reservoire) Installation 4 days

12 Pump Installations 2 days

13 Solar Power Installation 3 days

14 Pipe Connections and Reticulations 3 days

15 Fence 5 days

16 Site cleaning 1 day

17 Site Hand Over 1 day