Site Mobilisation and Demobilisation Site Layout: Renovation of 6 Blocks of Classrooms (Block G, H, I, J, K & L)
Site Mobilisation and Demobilisation Site Layout: Renovation of 6 Blocks of Classrooms (Block G, H, I, J, K & L)
W1 W2 W3 W4 W5 W6 W7
1 RENOVATION OF 6 BLOCKS OF CLASSROOMS (BLOCK G, H, I, J, 34 days
K & L)
2 SITE MOBILISATION AND DEMOBILISATION 4 days
3 SITE LAYOUT 5 days
4 BLOCK G - RENOVATION OF DOUBLE CLASSROOM BUILDING WITH 17 days
OFFICE
5 DEMOLITION AND ALTERATION WORKS 3 days
6 CONCRETE WORKS 3 days
7 ROOFING, CARPENTRY AND JOINERY 2 days
8 METAL WORKS 3 days
9 ELECTRICAL INSTALLATIONS 1 day
10 TEACHING BOARDS 1 day
11 FINISHES 7 days
12 PAINTING AND DECORATION 3 days
13 BLOCK H - RENOVATION OF DOUBLE CLASSROOM 17 days
BUILDING WITH OFFICE
14 DEMOLITION AND ALTERATION WORKS 3 days
15 CONCRETE WORKS 3 days
16 ROOFING, CARPENTRY AND JOINERY 2 days
17 METAL WORKS 3 days
18 ELECTRICAL INSTALLATIONS 1 day
19 TEACHING BOARDS 1 day
20 FINISHES 7 days
21 PAINTING AND DECORATION 3 days
22 BLOCK I - RENOVATION OF DOUBLE CLASSROOM BUILDING 17 days
Page 1