MASTER SCHEDULE

No. Description Duration Date 2019 2020


(Month) 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9

3 Stock Preparation
+ Civil construction 4.5
Dump tower - SP#2,3 R2
Rebar + Form work + Concrete pouring 2.5 15.08.2019 R2
Epoxy internal coating include water leakage test 1.5 30.09.2019 R2
Pulping water tower - SP#2,3 R2
Rebar + Form work + Concrete pouring 2.5 15.08.2019 R2
Epoxy internal coating include water leakage test 1 15.09.2019 R2
Dump tower - SP#1 R2
Rebar + Form work + Concrete pouring 3.5 15.09.2019 R2
Epoxy internal coating include water leakage test 1.5 30.10.2019 R2
Pulping water tower - SP#1 R2
Rebar + Form work + Concrete pouring 3.5 15.09.2019 R2
Epoxy internal coating include water leakage test 1.5 30.10.2019 R2
Disc Filter building - SP#2,3 1.5 13.07.2019 13 R2
Conveyor - SP#2,3 Done R2
Conveyor - SP#1 2.5 07.08.2019 7 R2
Screen & Cleaner machine foundation (SP2,3 Building) 2 30.07.2019 R2
Screen & Cleaner machine foundation (SP1 Building) inclu 3 30.08.2019
Screen & Cleaner machine building (Drum pulper Building) R2
1st Floor 0.5 30.08.2019 R2
2nd Floor 2.5 15.08.2019 R2
Compactor & Reject handling 2 30.08.2019 R2
MCC Room building R2
1st Floor (for Transformer) 2.5 15.08.2019 R2