HOANG THINH ENGINEERING CO., LTD.

266/56 To Hien Thanh St, Dist.10, Ho Chi Minh City, Vietnam


Tel.: +84 (8) 3868 0820 Fax: +84 (8) 3868 0821
www.hoangthinh.com.vn / Email: info@hoangthinh.com.vn

QUOTATION
To: PSMC From: Tạ Bá Siêu
Attn.: Mr Thành Mb.: 0908119681
Cc.: Ref.: HT-PS
Tel: Date: 13/10/2015
Fax: Page: 1
Dear Sirs,
We appreciate to your interest in our products and services and are pleased to send our offer to you as follows:

No. Description Contractor Qty Unit price (VND) Total amount (VND)
1 Increase one aggregate bin: HTEN 01 147,000,000 147,000,000
- Increase one aggregate bin
+ Storage volume is as the same as the one of existing plant
+ Discharging hopper: tole with 6mm thickness, painted
+ The wall: tole with 4 mm thickness, painted.
+ With 2 independent discharging door
+ Vibrator 270W - HTEN
+ Renew the roof and covering wall
- Extend weighing belt
+ Steel structure is the same as the one of existing belt
+ Add more rubber belt with 600mm width, 10mm thickness, EP500
- Extend aggregate weighing hopper
+ Steel structure is the same as the one of existing weighing hopper

2 Repair and supply equipment for silo: HTEN 01 72,500,000 72,500,000


- Install cone to decrease pressure and aerate for 2 silos
- Install 2 new silo dust filter V2 - WAM
- Install level indicator for 2 silos - Packer
- Control panel for filter and level indicator
3 Clean and repaint 2 cement silos and aggregate bins HTEN 01 78,000,000 78,000,000
- Clean the dust off the the surface
- Rust-proof paint for the rusted place with Alkyd paint
- Coating paint with Alkyd color paint
4 Upgrade control system HTEN 01 124,000,000 124,000,000
- Software HCS I, version 2014
- Siemens PLC S7-1200
- PT650D indicator: 3 pcs
- Relay, button, lamp
- Synoptic panel
- Reuse the existing power cabinet

Total (excluded VAT) 421,500,000


VAT10% 42,150,000
Total (included VAT) 463,650,000
In words: Vietnamese Dong Four Hundred and Sixty Three Million Six Hundred and Fifty Thousand only.
Other terms and conditions:
1 The above-mentioned price excludes other jobs outside the offer.
2 The above-mentioned price excludes the cost of replacing fault equipment. If any, the replacement cost shall be added.
3 Customer builds foundation for extended bin following HTEN's layout drawing
4 Customer supplies electric for dismantling and installation
5 Delivery time: 20 days after deposit receipt.
6 Time of repairing, painting and installing: 10 days after foundation delivery
7 Offer validity: within 30 days from the offer date.
8 Payment: shall be transferred by T/T
- 50% deposit after order confirmation
- 50% balance payment after acceptance and put into use

If you need further more information, please do not hesitate to contact us.