Mid-Tupper Pipelines
Construction Schedule
Appendix 5
2
ID Task Name Duration -1 1 2 3 4 5 6 7
1 Receive NEB Permit 0 days
2 Construction 26 days
3 Mobilization 2 days
4 Clearing & Logging 4 days
5 ROW Preparation 4 days
6 Pipeline Construction 10 days
7 Pressure Testing 3 days
8 Tie-Ins 2 days
9 Clean-up 5 days
10 Demobilization 1 day