Bubble Deck Structure Solutions

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 194

VIETCONS EDUCATION www.vietcons.

org

Appendices

A. Appendix A Brochure UK

B. Appendix B Geometry for Standard Deck sizes

C. Appendix C Eurocodes 2 – Practical Use

D. Appendix D Comments to Eurocodes 2

E. Appendix E Shear according to Eurocodes 2

F. Appendix F BubbleDeck Standard Details

G. Appendix G Examples

H. Appendix H Brochure UK – Site Installation


VIETCONS EDUCATION www.vietcons.org

Appendix A Brochure UK
VIETCONS EDUCATION
CI/SfB
www.vietcons.org
(23) Eq4
Part 1 September 2008

BubbleDeck
Structure Solutions
R

U N I T E D K I N G D O M

Product
Introduction

The Original Voided Flat Slabs


with BubbleDeck
VIETCONS EDUCATION www.vietcons.org

What i s t h e BubbleDeck® S y s t e m ?

Reinforcing mesh, top


Recycled plastic hollow ‘Bubble’ void former
Reinforcing mesh, bottom – cast into optional
concrete filigree ‘biscuit’ permanent formwork

Advantages
Design Freedom
Reduced
Dead Weight
Longer Spans
Green and
Sustainable
Fast
Construction

Want to know more?


BubbleDeck Technical Manual

BubbleDeck Design Guide

Interactive CD ROM with


BubbleDeck slab calculator

are also available


upon request
R

VIETCONS EDUCATION www.vietcons.org

U N I T E D K I N G D O M

The engineering solution that radically


improves building design and performance
while reducing the overall cost.
BubbleDeck is a revolutionary method of virtually eliminating concrete from the middle of a floor slab not performing any
structural function, thereby dramatically reducing structural dead weight. BubbleDeck is based on a new patented technique
- the direct way of linking air and steel. Void formers in the middle of a flat slab eliminates 35% of a slabs self-weight
removing constraints of high dead loads and short spans.

Incorporation of recycled plastic bubbles as void formers permits 50% longer spans between
columns. Combination of this with a flat slab construction approach spanning in two
directions – the slab is connected directly to insitu concrete columns without any beams -
produces a wide range of cost and construction benefits including:-

• Design Freedom – flexible layout easily adapts to irregular & curved plan layouts.
• Reduced Dead Weight – 35% removed allowing smaller foundation sizes.
• Longer spans between columns – up to 50% further than traditional structures.
• Downstand Beams eliminated – quicker & cheaper erection of walls and services.
• Load bearing walls eliminated – facilitating MMC with lightweight building envelopes.
• Reduced concrete usage – 1 kg recycled plastic replaces 100 kg of concrete.
• Environmentally Green and Sustainable – reduced energy & carbon emissions.

The overall floor area is divided down into a series of planned individual elements, either 3 or
BubbleDeck’s 2.4 metres wide dependant upon site access, which are manufactured off-site using MMC
height saving
allowed 2
techniques. These elements comprise the top and bottom reinforcement mesh, sized to suit
floors to be the specific project, joined together with vertical lattice girders with the bubble void formers
added trapped between the top and bottom mesh reinforcement to fix their optimum position. This
during
is termed a ‘bubble-reinforcement’ sandwich which is then cast into bottom layer of pre-cast
construction
concrete, encasing the bottom mesh reinforcement, to provide permanent formwork
within part of the overall finished slab depth.

On site the individual elements are then ‘stitched’ together with loose reinforcement simply
laid centrally across the joints between elements. Splice bars are inserted loose above the pre-cast concrete layer between
the bubbles and purpose made mesh sheets tied across the top reinforcement mesh to join the elements together. After the
site finishing concrete is poured and cured this technique provides structural continuity across the whole floor slab – the
joints between elements are then redundant without any structural effect – to create a seamless floor slab.

BubbleDeck has proved to be highly successful in Europe since its invention ten years ago. In Denmark and Holland over 1
million square metres of floors have been constructed in the last seven years using the BubbleDeck system in all types of
multi-storey buildings.

BubbleDeck® is a simple solution that eliminates non-working


dead load in floors while fully retaining strength.
page 2
VIETCONS EDUCATION www.vietcons.org

Simple site installation


( Ty p e A - Fi l i g r e e E l e m e n t s )
• Temporary Support – Propping on parallel beams at 1.8
to 2.4 metre spacing
• Placing Elements – Semi pre-cast elements mechanically
lifted into position
• Joint Reinforcement – Insert loose bottom splice bars
BubbleDeck®
and tie top mesh across joints between elements is a two-way
• Shear Reinforcement – Insert loose bars across columns spanning hollow
• Edge reinforcement – Insert edge bars and hairpins deck in which
around slab perimeter recycled plastic
• Perimeter shuttering – Fix shuttering to bottom pre-cast
bubbles serve the
purpose of
concrete layer & tie to top mesh reinforcement
eliminating
• Soffite shuttering – Prop plywood across tolerance joints non-structural
between element bays and between elements & columns concrete
• Preparation – Seal joints between elements, clean and
moisten bottom pre-cast concrete layer
• Concreting – Pour, vibrate and float 10mm max.
aggregate in-situ concrete
• Temporary works – Remove, typically after 3 – 5 days,
according to specific site advice
• Finishing – no further work required, the slab is complete
unless requirement for exposed soffite

page 3
R

VIETCONS EDUCATION www.vietcons.org

Bubbledeck® slab versions U N I T E D K I N G D O M

The appropriate BubbleDeck slab version is bespoke engineered to suit building configuration, span length between supports,
applied loadings and vertical alignment of supports. Indicative spans are given as a guide to what can be achieved. Established from
full calculation FE analysis these are based on 20mm concrete cover to bottom rebar (1 hour fire resistance); live load 3+1 kN/m2,
dead load 1.5 kN/m2 and lightweight external envelope maximum 6 kN/m line load. Completed slab mass and Site Concrete
Quantity based on 3 x 9 metre pre-cast elements with 35 kg/m2 total reinforcement.
Version Slab Bubbles Span Cantilever Span Completed Site Concrete
Thickness (Multiple bays) Maximum Length (Single bay rows) Slab Mass Quantity
mm mm metres metres metres kN/m 2 m 3/m 2
BD230 230 Ø 180 5 – 8.1 2.8 5 – 6.5 4.26 0.112
BD280 280 Ø 225 7 – 10.1 3.3 6 – 7.8 5.11 0.146
BD340 340 Ø 270 9 – 12.5 4.0 7 – 9.5 6.22 0.191
BD390 390 Ø 315 11 – 14.4 4.7 9 – 10.9 6.92 0.219
BD450 450 Ø 360 13 – 16.4 5.4 10 – 12.5 7.95 0.252
BD510* 510 Ø 410 15 – 18.8 6.1 11 – 13.9 9.09 0.298
BD600* 600 Ø 500 16 – 21.0 7.2 12 – 15.0 10.30 0.348 * New 2006

Element
BubbleDeck slab
types configurations:
Agrément
BubbleDeck can be supplied in 3 types of
certification
manufactured elements: pending, outside
scope of KOMO
Type A – Filigree Elements, where the bottom of the bubble- technical
reinforcement sandwich includes a 70mm thick pre-cast concrete certificate.
layer acting as permanent formwork within part of the finished slab
depth replacing the need for soffite shuttering. The elements are
placed on temporary propping, loose joint, shear & edge
reinforcement added, perimeter and tolerance joints shuttered and then the remaining
slab depth concreted.

Most commonly specified being suitable for the majority of new-build projects. Requires fixed or
mobile crane to lift into position due to weight of manufactured
elements as delivered to site.

Type B – Reinforcement Modules


comprising pre-fabricated ‘bubble-
reinforcement’ sandwich elements.
The modules are placed on
traditional site formwork, loose joint,
shear & edge reinforcement added and then
concreted in 2 stages to the full slab depth.
Suitable for suspended ground floor slabs and alteration /
refurbishment projects, particularly where site access is
extremely restricted. Can be manually lifted into position.

Type C – Finished Planks, delivered to the building site as complete


pre-cast factory made slab elements with the full concrete thickness. These
span in one direction only and require the inclusion of supporting beams or walls
within the structure.
page 4
VIETCONS EDUCATION www.vietcons.org

Selected BubbleDeck® projects


Le Coie Housing
The largest BubbleDeck structure so far erected in Great Britain was These are only a few of many projects with
completed 6 weeks ahead of programme. The structure comprises 7,800m2 of BubbleDeck floors.
BubbleDeck floor slabs between 3 and 6 stories high supported on in-situ
For many others and new projects see our
reinforced concrete columns. Over £400,000 of savings were realised as a
WEB site: www. BubbleDeck-UK.com
direct result of incorporating BubbleDeck into this project, amounting to a
3% saving off the TOTAL project cost.

The Main Contractor subsequently found the BubbleDeck system


benefits continue throughout the whole construction process with
faster and cheaper erection of external & internal walls plus fast
and easy installation of services below the flat soffites.

Chris Dunne, Project Architect, commented:- “Our original


solution for Le Coie was a steel frame with Bison floor planks &
structural concrete topping in the 5 to 6 storey areas, with load
bearing blockwork supporting a composite metal deck in the lower sections.

The BubbleDeck technique not only saved a considerable sum but simplified
the buildings structure, removing my co-ordination headache of getting
services around or through beams required with a traditional solution.We
were also able to eliminate all load bearing walls down the middle of each
flat, required to support the short spans of composite metal decks, giving
more internal space and fantastic flexibility.

I will definitely consider BubbleDeck


for use on my future projects.”

page 5
R
VIETCONS EDUCATION www.vietcons.org

U N I T E D K I N G D O M

Media City
This 32.000 m2 building was
constructed with great
transparency, revealing a huge
open atrium. This atrium is the fulcrum and heart of the
building. The spaces are formed in soft, organic

BubbleDeck® shapes that allow light to spill onto every


single workplace in the building.
BubbleDeck is
the ONLY officially To achieve these wide, open, internal
spaces a BubbleDeck structure of
certified voided flat
post – tensioned 450mm deep
slab system having floor plates, achieving 16 metre
been granted Kiwa spans between columns was
N.V. KOMO Certificate selected - dramatically reducing
K22722, recognised structure dead weight and
in the Building enabling long spans. The flexibility
Regulations as of BubbleDeck also facilitated
equivalent to construction of the soft flowing,
an Agrément organic shapes forming the floors around
Certificate. the central atrium.

Millennium Tower
Originally designed with hollow core planks, late in the
design stage it was determined that BubbleDeck would
realise considerable cost and time savings. Adopting
BubbleDeck also reduced the structural floor zone City Hall and Offices
depth due to omission of beams, lowering the BubbleDeck’s superior cantilevering ability
overall building’s height. achieved 3.3 metre cantilevers from a
Another consideration was the lack of storage 280mm deep slab with 7.5 metre internal
space on the building site which is located close to spans between columns. The building
major arterial roads and streets. The floors were on provides a City Hall and financial centre
average erected, cast and completed in half the for Danske Bank containing 4,000 m2
time - 4 days instead of 8 days – it would have floor area. The slender slab without any
taken to construct with hollow core planks. Half beams secures maximum light from the
way through constructing the structure it was facades, which is enhanced by an internal
decided to add another 2 floors which was made atrium. This project won “Building of the
possible within the overall height of the original building Year 2004” award for offices and
due to BubbleDeck reducing structural floor depth. commercial buildings.
page 6
VIETCONS EDUCATION www.vietcons.org

Solid deck comparisons


A BubbleDeck slab has the same applied load carrying capacity with As an example for BD280 slab version, with 1 hour fire
only 50% of the concrete required for a solid concrete slab, or with resistance, d is 260mm so 39xd indicates a maximum 10.14
the same slab thickness has twice the load carrying capacity using metre continuously supported (multiple bay) span; 30xd
65% of the concrete required by a solid concrete slab. indicates a maximum 7.8 metre simply supported (single bay)
span, and 12.5xd indicates a maximum 3.25 metre cantilever is
Schematic design basic principle potentially feasible. This basic principle has been verified for
As a general guide for project scoping purposes the maximum achievable dead loadings up to 4.5 Kn/m2 following full calculations on
spans for each BubbleDeck slab depth is usually determined by deflection many projects as a generally reliable indication.We can refine
limitations. This criteria is controlled by the ratio of span / effective depth this approximate indication by full calculation and we would be
(L/d) stipulated in BS8110 and modified by applying a factor of 1.5, pleased to give you advice on a specific project.
permitted by BS8110 to take account of BubbleDeck’s dramatically lower
dead weight than traditional solid flat slabs. Post tensioning
When mega spans are required
L/d 30 for simply supported floors (single spans)
(above 15 metres) we can provide
L/d 39 for continuously supported floors (multiple spans)
a Post–Tensioned (PT)
L/d 12.5 for cantilevers.
BubbleDeck solution. The above
The effective depth of a BubbleDeck slab is the overall depth less standard deflection limits can be
20mm concrete cover (achieving 1 hour fire resistance) from the bottom increased by up to 30% with
mesh reinforcement to underside of the slab. Where 90 minute fire post-tensioned BubbleDeck
resistance is required deduct 25mm off overall slab depth, or for 120 slabs.
minute fire resistance deduct 30mm off overall slab depth. In the case of
spanning onto columns without beams use the longest dimensions
between columns, where the slab will span onto walls or beams use the
shortest span dimension.

page 7
R

VIETCONS EDUCATION www.vietcons.org

Solid slab BubbleDeck® BubbleDeck®


same thickness same capacity U N I T E D K I N G D O M
Carrying capacity
Slab Dead load

Relative values in % of solid slab


Carrying capacity
Dead load
25
75
50
50
25
40 Green credentials
Dead load / Carrying capacity 3:1 1:1 1.5:1
By virtually eliminating concrete in the middle of a slab BubbleDeck
Absolute values in % of solid slab makes a significant contribution to reducing environmental impact.
Carrying capacity 100 200 100
Slab dead load 100 65 50 Guidance from the ODPM requires the direct environmental effects of buildings
Utility value of 300 200 to be considered, including usage of natural resources and emissions resulting
concrete increased
from construction. Not only is concrete usage reduced by up to 50% within a
A BubbleDeck has twice the capacity with 65% concrete and
buildings structure but knock-on benefits can be realised through reduced
the same capacity with 50% concrete compared to
a solid slab. foundation sizes. BubbleDeck can make a big contribution towards achieving
BREEAM targets.
BubbleDeck®
Every 5,000 m2 of BubbleDeck floor slab can save:-
floors make a
• 1,000 m3 site concrete.
substantial • 166 ready mix lorry trips.
contribution to • 1,798 Tonnes of foundation loads – or 19 less piles.
reducing carbon • 1,745 GJ energy used in concrete production & haulage.
emissions arising • 278 Tonnes of CO2 – green house gases – emissions.
from construction.

Consider the benefits


Data based on typical 4,500 m2 Office Building with 7.5 x 7.5 metre multiple
spans between in-situ or precast concrete columns.
Slab Site Concrete Site Concrete Total Slab Embodied CO 2
Depth Volume Quantity Dead Load Energy Emissions
(mm) m3 / m2 m3 (Tonnes) (Giga Joules) (Tonnes)
Solid Slab 310 0.31 1,395 3,376 3,278 522
BubbleDeck 230 0.11 495 1,758 1,707 272
BD SAVES 80 0.20 900 1,618 1,571 250
Assumptions:
1) Lightweight external envelope (curtain walling or equal).
2) Typical office live load 2.5 kN/m2 + 1.5 kN/m2 for lightweight partitions, computer floor, finishes & services.
3) Overall stability braced by stair / lift core shear walls in both cases BubbleDeck transfers lateral loads to cores.
4) Energy from materials transport – cement 50 miles, aggregate 10 miles (to ready mix plant) and concrete 5
miles (to site).

BubbleDeck structures are also Sustainable with the system allowing frame re-use for future
purposes. The envelope and all internal work can be removed from a BubbleDeck building
and the original frame simply refitted for a new purpose. The two way spanning nature of
BubbleDeck slabs allows any internal layout to be reconfigured to new uses within the
original design load parameters.

page 8
VIETCONS EDUCATION www.vietcons.org

B U B B L E D E C K

Service options
We provide two alternative Service Options covering provision of design, detailing, drawing production,
element manuifacture and supply of all components to site completely ready for construction:-

Option A – Full Floor Design by BubbleDeck (BD)


1. Initial Enquiry & consultation / advice / meetings (FOC).
2. Schematic design of Deck Type and advice on appropriate solution (FOC).
3. Quotation for Detail Design, Drawing Production, Element Manufacture & Supply, based on estimated amount of reinforcement
required per m2 (FOC).
4. Acceptance of Quotation and order / payment for Detail Engineering Design,
Calculations and Drawing Production.
5. Detail Engineering Design and Calculations of BubbleDeck floors by
Bubbledeck, Detail Design of all other elements (foundations,
columns, external envelope & roof) by Clients Agents or others. The
6. Production of Manufacturing and Site Installation drawings
by Bubbledeck, including pre-cast elements ready for
manufacture and all required loose reinforcement. BubbleDeck ®

7. Preparation of Design & Calculation report


by Bubbledeck. Provision of Design Report and
Manufacturing / Site Installation Drawings to Clients
system is based
Agents for their Building Control submission.
8. Acceptance and sign-off by Clients Agents of upon the patented
BubbleDeck Design Report and Manufacturing / Site
Installation Drawings.
9. Preparation of loose site reinforcement bar bending integration
schedules issued to Main Contractor / Site Installer
for supply to site by others.
10. Adjusted Quotation, based on final amount of reinforcement per m2.
technique - the
11. Acceptance of Adjusted Quotation & Order for prefabricated BubbleDeck Element
manufacture, production & supply to site. direct way of
12. Advice to Clients Main Contractor & Agents on Site Installation & Construction.
13. Manufacture of prefabricated BubbleDeck Elements & supply to Site.
14. Advice to Main Contractor during Site Installation & Construction. linking air and
15. Site Inspections of Erection, Loose Reinforcement installation and sign off by
BubbleDeck prior to final concrete pour.
Option A under-written by Bubbledeck's Professional Indemnity / Product Liability Insurance Policies and
steel.
Collateral Warranty issued following settlement of BubbleDeck Account.

Option B –Structure & BubbleDeck Floor Design by Clients Agents


1. Initial Enquiry & consultation / advice / meetings (FOC).
2. Advice on Deck Type, appropriate solution, element layout and design (FOC).
3. Quotation for Element Production & Supply, based on Clients Agents estimated reinforcement per m2 (FOC).
4. Detail Design of BubbleDeck floors and all other elements (foundations, columns, external envelope & roof)
by Clients Agents or others.
5. Submission of Detail Design by Clients Agents to BubbleDeck for review & comment.
6. Production of Manufacturing drawings by BubbleDeck, production of Site Installation drawings by Clients Agents
including all required loose site reinforcement.
8. Preparation by Clients Agents of Design & Calculation report and submission with Manufacturing / Site Installation Drawings by
Clients Agents to Building Control for approval.
7. Submission of Design & Calculation report and Site Installation drawings to BubbleDeck for review & comment.
8. Preparation by Clients Agents of loose site reinforcement bar bending schedules for supply to site by others.
9. Adjusted Quotation, based on final amount of reinforcement per m2 in prefabricated BubbleDeck elements.
10. Acceptance of Adjusted Quotation & Order for prefabricated BubbleDeck Element manufacture, production & supply to site.
11. Advice to Clients Main Contractor & Agents on Site Installation & Construction.
12. Manufacture of prefabricated BubbleDeck Elements & supply to Site.
13. Site Inspections of Erection, Loose Reinforcement installation and signoff by Clients Agents prior to final concrete pour.
Option B under-written by BD's Product Liability Policy and Product Guarantee.

U N I T E D K I N G D O M
W E B : w w w. B u b b l e D e c k - U K . c o m
page 9
VIETCONS EDUCATION www.vietcons.org

Appendix B Geometry for Standard Deck sizes


BubbleDeck Slab
Cross section of joint
BD 230 Type A 230 mm BubbleDeck
X
Y Y 1:5

Rebars longitudal: black marking


Rebars directional: white marking

200 200 200 100 100 200


20 20
75 125 75 125 75 125 75 42.5 42.5 75 125 75 125

100 100 100 100 100 100 100 30 30 100 100 100 100

Y5
Y5
VIETCONS EDUCATION

Girder 152
Girder 152

Y8
Y8
25

125 75 125 75 125 75 125 125 75 125 75


17.5 17.5
100 100 100 100 100 100 100 30 30 100 100 100 100
20 20
www.vietcons.org

BubbleDeck International
Dotted “bars” ONLY indication of distance between directional rebars
Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org
BubbleDeck Slab Cross section and mesh
230 mm BubbleDeck
BD 230 Type A X
1:20
Y Y

Measures in mm

Top mesh

100
100
100
100
100
100
100
100
100
30

75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75
42.5 42.5

2960

Cross section

Girder 152
Girder 152

D = 180

3000

Bottom mesh

100
100
100
100
100
100
100
100
100
30

125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125
17.5 17.5

2960
BubbleDeck Slab
Cross section of joint
BD 230 Type B 230 mm BubbleDeck
X
Y Y 1:5

Rebars longitudal: black marking


Rebars directional: white marking

200 200 200 100 100 200

75 125 75 125 75 125 75 75 67.5 67.5 75 75 125 75 125

100 100 100 100 100 100 100 100 30 30 100 100 100 100 100
20 20

Y5
Y5
VIETCONS EDUCATION

Girder 152
Girder 152

Y8

Y8
25

125 75 125 75 125 75 125 75 42.5 42.5 75 125 75 125 75

100 100 100 100 100 100 100 100 30 30 100 100 100 100 100
20 20
www.vietcons.org

BubbleDeck International
Dotted “bars” ONLY indication of distance between directional rebars
Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org
BubbleDeck Slab Cross section and mesh
230 mm BubbleDeck
BD 230 Type B X
1:20
Y Y

Measures in mm

Top mesh

100
100
100
100
100
100
100
100
100
30

75 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 75
87.5 87.5

2960

Cross section

Girder 150-155
Girder 150-155

D = 180

3000

Bottom mesh

100
100
100
100
100
100
100
100
100
30

75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75 125 75
42.5 42.5

2960
BubbleDeck Slab
Cross section of joint
BD 285 Type A 285 mm BubbleDeck
X
Y Y 1:5

Rebars longitudal: black marking


Rebars directional: white/grey marking

250 250 125 125 250

150 100 150 100 150 100 55 55 100 150


20 20
100 150 100 150 100 150 30 30 150 100

Y6

Y6
VIETCONS EDUCATION

Girder 195-200
Girder 195-200

Y08
25

Y08

150 100 150 100 150 30 30 150 100

20 20
100 150 100 150 100 55 55 100 150
www.vietcons.org

BubbleDeck International
Dotted “bars” ONLY indication of distance between directional rebars
Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org
BubbleDeck Slab Cross section and mesh
285 mm BubbleDeck
BD 285 Type A X
1:20
Y Y

Measures in mm

Top mesh

150

100

150

100

150

100

150
30

55 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 55

2960

Cross section
Girder 195-200

Girder 195-200
D = 225

3000

Bottom mesh

100

150

100

150

100

150

100
55

30 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 30

2960
BubbleDeck Slab
Cross section of joint
BD 285 Type B 285 mm BubbleDeck
X
Y Y 1:5

Rebars longitudal: black marking


Rebars directional: white marking

250 250 125 125 250

150 100 150 100 150 100 150 30 30 150 100 150
20 20
100 150 100 150 100 150 100 55 55 100 150 100

Y6
Y6
VIETCONS EDUCATION

Girder 195-200
Girder 195-200

Y10

Y10
25

150 100 150 100 150 100 55 55 100 150 100

20 20
100 150 100 150 100 150 30 30 150 100 150
www.vietcons.org

BubbleDeck International
Dotted “bars” ONLY indication of distance between directional rebars
Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org
BubbleDeck Slab Cross section and mesh
285 mm BubbleDeck
BD 285 Type B X
1:20
Y Y

Measures in mm

Top mesh

150

100

150

100

150

100

150

100
55

80 100 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 100 80

2960

Cross section
Girder 195-200

Girder 195-200
D = 225

3000

Bottom mesh

100

150

100

150

100

150

100

150
30

55 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 150 100 55

2960
BubbleDeck Slab
Lattice Girder
BD 285 : Lattice Girder 285 mm BubbleDeck
Y
X X 1:5

Rebars longitudal: white/grey marking


Rebars directional: black marking

250 250 250 250

Y08
VIETCONS EDUCATION

Y08
Girder 195-200

Y08

25
250 250 250 125
www.vietcons.org

BubbleDeck International
Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
BubbleDeck Slab
Cross section of joint
BD 340 Type A 340 mm BubbleDeck
X
Y Y 1:5

Rebars longitudal: black marking


Rebars directional: white marking

300 150 150 300

Y6 Y6

100 100 100 100 100 100 100 100 80 20 80 100 100 100 100

150 150 150 150 150 150 55 20 55 150 150 150


VIETCONS EDUCATION

girder 230 - 235


girder 230 - 235

Y12

Y12

25
200 100 200 100 200 30 30 200 100 200

150 150 150 150 150 55 55 150 150 150


20 20
www.vietcons.org

BubbleDeck International
Dotted “bars” ONLY indication of distance between directional rebars
Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org
BubbleDeck Slab Cross section and mesh
340 mm BubbleDeck
BD 340 Type A X
1:20
Y Y

Measures in mm

Top mesh

150

150

150

150

150

150

150
55

80 100 100 100 100 100 100 100 100 100 100 100 100 100 100
100 100 100 100 100 100 100 100 100 100 100 100 100 100 80

2960

Cross section

Girder 230-235
Girder 230-235

D = 270

3000

Bottom mesh

150

150

150

150

150

150

150
55

30 200 100 200 100 200 100 200 100 200 100 200 100 200 100 200 100 200 100 200 30

2960
BubbleDeck Slab
Cross section of joint
BD 340 Type B 340 mm BubbleDeck
X
Y Y 1:5

Rebars longitudal: black marking


Rebars directional: white marking

300 150 150 300

Y6 Y6

100 100 100 100 100 100 100 100 50 80 20 80 50 100 100 100 100

150 150 150 150 150 150 55 20 55 150 150 150


VIETCONS EDUCATION

girder 230 - 235


girder 230 - 235

Y12

Y12

25
25

200 100 200 100 200 100 80 80 100 200 100

150 150 150 150 150 150 55 55 150 150 150


20 20
www.vietcons.org

BubbleDeck International
Dotted “bars” ONLY indication of distance between directional rebars
Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org
BubbleDeck Slab Cross section and mesh
340 mm BubbleDeck
BD 340 Type B X
1:20
Y Y

Measures in mm

Top mesh

150

150

150

150

150

150

150
55

50 100 100 100 100 100 100 100 100 100 100 100 100 100 50
80 100 100 100 100 100 100 100 100 100 100 100 100 100 100 80

2960

Cross section

Girder 230-235
Girder 230-235

D = 270

3000

Bottom mesh

150

150

150

150

150

150

150
55

30 100 200 100 200 100 200 100 200 100 200 100 200 100 200 100 200 100 200 100 30

2960
BubbleDeck Slab
Cross section of joint
BD 390 390 mm BubbleDeck
X
Y Y 1:5

Rebars longitudal: black marking


Rebars directional: white marking

350 350 100 100 350

Y6 Y6 Y6
Y6 Y6
50 100 100 100 50 100 100 100 50 55 20 55 50 100 100 100

100 50 150 50 100 50 150 50 100 30 20 30 100 50 150 50 100


VIETCONS EDUCATION

Girder 280 - 285

Y10 Y10
Y10

25
25

25

50 50 200 50 50 50 200 50 50 55 55 50 50 200 50 50

100 50 150 50 100 50 150 50 100 30 30 100 50 150 50 100


20 20
www.vietcons.org

BubbleDeck International
Dotted “bars” ONLY indication of distance between directional rebars
Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org
BubbleDeck Slab Cross section and mesh
395 mm BubbleDeck
BD 395 X
1:20
Y Y

Measures in mm

Top mesh

50
150
50
100
50
150
50
100
50
150
50
100
30

50 100 50 100 50 100 50 100 50 100 50 100 50 100 50 100 50


55 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 55

2960

Cross section
Girder 280-285

Girder 280-285
D = 315

3000

Bottom mesh

50
150
50
100
50
150
50
100
50
150
50
100
30

50 200 50 200 50 200 50 200 50 200 50 200 50 200 50 200 50


55 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 55

2960
BubbleDeck Slab
Cross section of joint
BD 450 450 mm BubbleDeck
X
Y Y 1:5

Rebars longitudal: black marking


Rebars directional: white marking
400 400 100 100

Y6
Y6 Y6
Y6
125 75 125 75 125 75 125 75 75 67.5 20 67.5 75 75 125 75

150 50 150 50 150 50 150 50 100 55 20 55 100 50 150 50

Girder 330
VIETCONS EDUCATION

Y14

Y14

25
50 200 50 100 50 200 50 100 30 30 100 50 200 50 100

50 150 50 150 50 150 50 100 55 55 100 50 150 50 150


20 20
www.vietcons.org

BubbleDeck International
Dotted “bars” ONLY indication of distance between directional rebars
Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org
BubbleDeck Slab Cross section and mesh
450 mm BubbleDeck
BD 450 X
1:20
Y Y

Measures in mm

Top mesh

50
150
50
150

50
150
50
150

50
150
50
100
55

75 125 125 125 125 125 125 125 125 125 125 125 125 125 75
67.5 75 75 75 75 75 75 75 75 75 75 75 75 75 75 67.5

2960

Cross section
Girder 330

Girder 330
D = 360

3000

Bottom mesh

50
150
50
150

50
150
50
150

50
150
50
100
55

100 200 100 200 100 200 100 200 100 200 100 200 100 200 100
30 50 50 50 50 50 50 50 50 50 50 50 50 50 50 30

2960
VIETCONS EDUCATION www.vietcons.org

Appendix C Eurocodes 2 – Practical Use


VIETCONS EDUCATION www.vietcons.org
The practical use of Eurocode 2

1 Introduction
When or before Eurocode 2 is introduced in early 2003, most engineers will need to be
assured that it can be used as a practical concrete design tool, as well as producing
economic results. If they are not assured of this, practices will continue to use BS 8110 in
preference to adopting the new code.

Necessary guidance in the form of explanatory literature, process flowcharts, spreadsheets


and other software etcetera is in preparation. This brief report will attempt to summarise the
principal design procedures required by EC2, compare them with their BS 8110
counterparts, and demonstrate that the transition to EC2 need not be a difficult process.

2 Comparisons with BS 8110

2.1 Loading
EC2 BS 8110
Worst of γG = 1.35, γQ = 1.05
Loaded spans: γG = 1.4, γQ = 1.6
and γG = 1.15, γQ = 1.5
Unloaded spans: γG = as above γG = 1.0
Loading pattern: All + adjacent + alternate spans All spans + alternate spans

For the sake of simplicity, γG = 1.35 and γQ = 1. 5 may be used for loaded spans (with γG =
1.35 on unloaded spans), although this would be very conservative. Both γG and γQ are
marginally lower than in BS 8110, but for unloaded spans γG is higher, reflecting a lower
probability of variation in dead loads. For a typical member with Qk = 0.5 Gk, maximum
ULS loading would be 13.6% lower than for BS 8110. The use of the same value for γG
throughout also reduces the effect of pattern loading, thus marginally reducing span
moments.

The loading code, EN 1991-1-1, stipulates values of imposed loads that vary only
marginally from current UK practice (e.g. 3 kN/m2 for offices). This code stipulates weights
for both construction materials and stored materials, and it should be noted that the density
of normal weight reinforced concrete should be taken as 25 kN/m2.

2.2 Cover
Nominal covers required for durability and bond are fairly similar to BS 8110. However,
nominal cover to EC2 is in two parts, Cnom= Cmin+ ∆c, where ∆c is a design tolerance
varying from 0 to 10mm, depending upon quality assurance level. This can have the effect
of increasing cover to slabs when larger diameter bars are used, as Cmin ≥ bar φ and ∆c must
be added.

2.3 Materials EC2 BS 8110


Partial factor, concrete: γc = 1.5 γc = 1.5
Partial factor, steel: γs = 1.15 γs = 1.05
Rod Webster Concrete Innovation & Design Page 1
VIETCONS EDUCATION www.vietcons.org
The practical use of Eurocode 2

At first inspection, the higher γs factor in EC2 would appear disadvantageous. However, this
difference is almost exactly neutralised by the introduction of reinforcing steel with fyk =
500 N/mm2.

2.4 Stress block – flexure


Eurocode 2
εc fcd = ηαcc fck /γc
d2 εsc Fc
x As2 λx Fsc
neutral axis
h d z
As Fst
εs

Section Strain Stress


fck = characteristic concrete cylinder strength (equivalent to 80% cube strength).

For fck ≤ 50 N/mm2, η = 1, εc = 0.0035, αcc = 1.0 and λ = 0.8. As γc is the same for both
codes, this results in concrete design strengths being 19.4% higher than in BS 8110 below.
This difference gives advantage in terms of reinforcement areas because of the resulting
increase in the lever arm, z.
εc = 0.0035 fcd = 0.67 fck /γc
d’ εsc Fc
x As’ 0.9x Fsc
neutral axis
h d z
As Fst
εs

Section Strain Stress

BS 8110

2.5 Stress block – columns


In BS 8110, an identical stress block is used for both pure flexure and bending with axial
load. In EC2 however, εc the limiting concrete compressive strain, starts to reduce when the
neutral axis x drops outside of the section height, h. This strain reaches a lower bound value
(0.00175 for fck ≤ 50 N/mm2) when the section is in pure compression.
Rod Webster Concrete Innovation & Design Page 2
VIETCONS EDUCATION www.vietcons.org
The practical use of Eurocode 2

The diagram below demonstrates this procedure. Effectively, the strain diagram has a
“hinge point”, which falls at h/2 for normal strength concretes. This process is easily
automated, but is not suited to hand calculation, so it is best accomplished by spreadsheet.

As few columns are very close to being in pure compression, this gradual reduction in
strain, and hence compressive stress, has less effect than one might imagine.

0.0035 max 0.00175x /(x-h/2) 0.00175


x
h/2
hinge
h d point
x
εs

0.00175 min 0.00175


General relationship When x > h Pure compression

EC2 strain relationship at ULS (fck ≤ 50 N/mm2)

2.6 Redistribution
EC2 BS 8110
Neutral axis limit: x/d ≤ δ - 0.4 x/d ≤ βb - 0.4
Redistribution limit: 30% classes B & C 30% generally
20% for class A rebar 10% sway frames > 4 storeys
0% in columns 0% in columns
Limitations: Adjacent spans ratio ≤ 2

The EC2 x/d limit reduces for concrete with fck > 50 N/mm2, otherwise both codes are very
similar.

2.7 Beam shear


A strut-and-tie model is used for shear reinforcement to EC2, which can have a varying
angle θ between the compressive struts and main tension chord. Cot θ is normally taken as
the maximum value of 2.5, but may be as low as 1.0 if required for high shear forces.

For UD loading, EC2 BS 8110


Shear resistance: ν = 0.7 – fck/200 ≥ 0.5
k = 1 + √(200/d) ≤ 2 vc = from Table 3.8
ρ1 = Asl /bwd ≤ 0.02
At support face: VRd,max = 0.9bwd.fcd /(cotθ + tanθ) Vmax = 0.8√fcu ≤ 5
At d from support: VRd,ct = 0.12k(100ρ1fck)1/3 Vc = vc.bvd
If VRd,ct ≥ VEd nominal links If Vc ct ≥ V, nominal links
Rod Webster Concrete Innovation & Design Page 3
VIETCONS EDUCATION www.vietcons.org
The practical use of Eurocode 2
Links: Asw /s = VEd /(0.9d.ν.fcd cotθ) Asv /sv =1.05 bv(v-vc) /fyv
Nominal links: Asw /s ≥ 0.5ν.fcdbw /fywd Asv /sv ≥ 0.42bv /fyv

Understandably, these approaches are somewhat different although both methods are simple
enough to apply. One can see from the above formulae that when more than nominal links
are required, EC2 ignores any contribution from the concrete. The strut-and-tie method
produces an additional tension in the main steel where the compression strut meets this
steel. This effect is catered for by applying the “shift rule” when detailing (see Section 3).

2.8 Punching shear


The calculation of punching shear is basically similar to BS 8110, except that the control
perimeter is at 2d, rather than 1.5d from the column face, and follows a locus from the
column face, rather than being rectangular in shape.

2d 1.5d

EC2 BS 8110
Basic control perimeter: At 2d at 1.5d
Control perimeter shape: Rounded corners Rectangular
Flat slab shear enhancement factors
Internal: 1.15 1.15
Edges: 1.4 1.4 or 1.25
Corners: 1.5 1.25

When links are required, EC2 allows a contribution of 75% of the concrete shear resistance
(unlike beam shear), and a radial distribution of links is assumed. An outer perimeter, at
which no further links are required, is based upon the link arrangement rather than the basic
control perimeter.

The much higher enhancement factor of 1.5 for corner columns may prove critical in some
circumstances, when sizing flat slabs for shear. However, the method as a whole seems very
logical and may result in fewer links and be simpler to detail than the BS8110 method.

Rod Webster Concrete Innovation & Design Page 4


VIETCONS EDUCATION www.vietcons.org
The practical use of Eurocode 2

2.9 Span to depth ratios


EC2 BS 8110
K factors from Table 7.4 used in
Basic L/d ratios: From Table 3.9
equations 7.14a & b
Tension steel
In equations From Table 3.10
modifier:
Compression steel
In equations From Table 3.11
modifier:
Interpolated between Table
Flanged sections: 1 ≥ 1 – 0.2bw/bf /3 ≥ 0.8
3.9 values
Only used if there are brittle partitions
Long span modifier: Flat slabs: 8.5 /L ≤ 1 10 /L ≤ 1
Otherwise: 7 /L ≤ 1
Service stress Formulae included in Table
310 /σs (steel service stress)
modifier: 3.10

These two methods are very similar, but in practice, Eurocode 2 effectively allows
marginally shallower members than BS 8110. This is likely to be because the EC2 ratios
have made no allowance for early age overloading during construction, which can increase
the degree of cracking, particularly in slabs.

2.10 Maximum bar spacing


For normal internal exposure, EC2 recommends a maximum crack width of 0.4mm
compared to 0.3mm in BS 8110. However, the maximum bar spacings in Table 7.3 are
somewhat less than those now commonly used in the UK. This will tend towards the use of
slightly smaller diameter bars in slabs. The actual calculation of crack widths to clause 7.3.4
allows more flexibility.

2.11 Beam flange widths


To both codes, effective flange widths may be calculated directly from the distances
between points of contraflexure, but the default values below give an indication of
comparative values.
EC2 BS 8110
Simple supports, L Simple supports, L
Effective span, spans: End span, 0.85L End span, 0.85L
Internal span, 0.7L Internal span, 0.7L
Cantilever, L.
Effective span, supports: Not applicable
Others, 0.15L either side of support.
[b1/5+Leff /10]≤Leff /5
Effective bf, T-beam: plus [b2/5+Leff /10]≤Leff /5 bw+Leff /5 ≤ bw+b1+b2
≤ bw+b1+b2
Effective bf, L-beam: bw+{[b1/5+Leff /10]≤Leff /5} ≤ bw+b1 bw+Leff /10 ≤ bw+b1
b1 and b2 are the actual flange outstands on either side of the web
Rod Webster Concrete Innovation & Design Page 5
VIETCONS EDUCATION www.vietcons.org
The practical use of Eurocode 2
It should be noted that EC2 requires a portion of beam support steel to be spread across the
width of flange. This is why a method is also provided for assessing the widths of tension
flanges.

2.12 Flat slabs


For flat slabs, the two codes are almost identical, the relevant EC2 clauses having been
drafted in Britain. Slightly more latitude is suggested however, for the apportioning of
moments between column strips and middle strips.

Mt,max, the limit on moment transfer into edge/corner columns, is approximately 10% lower
than for BS 8110.

2.13 Columns
Some of the terminology in Eurocode 2 relating to column design may be slightly
unfamiliar, with minimum eccentricities being described under “imperfections” and
buckling etcetera falling within “second order effects”. Alternative design methods are
given, but the “curvature” method is similar in approach to current practice. As with BS
8110, the column design process is quite tedious to perform manually, but is relatively easy
to automate. The simplified method given for carrying out biaxial bending checks is more
logical than in BS 8110, and is simple to apply.

A comparison between the EC2 and BS column design processes is shown in the flowcharts
below.

Rod Webster Concrete Innovation & Design Page 6


VIETCONS EDUCATION www.vietcons.org
The practical use of Eurocode 2

3 Detailing
3.1 General
EC2detailing rules are slightly more complex than for BS 8110. It will no longer be possible
to make simple assumptions, such 35 or 40 diameters for an anchorage length, and
technicians will need to learn the necessary skills, as there are differing anchorage rules for
different types of member. There are also many small changes to be learned, such as the
detailing of beam support steel within flanges, minimum reinforcement percentages, and
new rules regarding the staggering of laps.

3.2 The shift rule


This is the recommended method for working out curtailment points for beam
reinforcement, which at the same time ensures the provision of sufficient steel near to
supports, to accommodate the additional tensile forces generated by the strut-and-tie shear
action described in 2.7.

Basically, the bending moment envelope is “shifted” a distance between 0.45d and 1.125d
and bars should have an anchorage length beyond their relevant “shifted” point of being no
longer required.

4 Unfamiliar processes
4.1 Strut-and-tie models
The strut-and-tie method should be used for the design of D-regions, which are described as
“discontinuities in geometry or action”. Some such discontinuities are frame corners,
corbels, or abrupt changes in section. It is also important to note that this method is implied
within the shear design process described in 2.7 and 2.8 above.

ac
FEd
HEd
Ftd aH
θ 2
z0 Typical node model
d hc for a corbel
HEd 1 Fwd

σRd,max
FEd

Rod Webster Concrete Innovation & Design Page 7


VIETCONS EDUCATION www.vietcons.org
The practical use of Eurocode 2
Although widely used in other European countries, this approach, while not being
particularly complex, will be unfamiliar to many designers in the UK, so both engineers and
technicians are likely to require guidance.

5 EC2 overview
5.1 General
The areas covered by this document are not exhaustive; only what are considered to be the
more important and commonly used procedures have been discussed. Eurocode 2 is a very
comprehensive code and also includes rules for precast concrete, post-tensioned members
etcetera, but the focus here has been on everyday insitu reinforced concrete design.

5.2 Code philosophy


The general philosophy of EC2 is quite different from that found in BS 8110. The Eurocode
is less empirical and more logical in its approach. For example, variables such as partial
factors for materials are shown within formulae, rather than being “built in” as part of an
obscure number. If one wishes to go into greater detail, there are appendices to the code that
give derivation formulae for items such as creep coefficients and shrinkage strains, which
are most helpful when attempting to automate the design process.

EC2 makes no attempt to be a design “guide”; it is a code giving general rules. There are no
simplified tables of moment or shear factors for example, as one would be expected to look
for these in separate design guides or standard textbooks.

In my view, EC2 has great potential of being accepted as a very good replacement for BS
8110. Inevitably there will be those who wish to resist any change, but I am sure that, after
an initial learning period, the superiority and economic advantages of EC2 will universally
recognised.

5.3 What is needed?


To smooth the transition to EC2, the following tools will be required; preferably to be
available before the predicted formal release of the new code in early 2003.

• General design guides


• Worked examples
• A “Concise EC2”
• A full set of design spreadsheets
• Comparative and calibration studies
• An EC2 version of “Economic Frame Elements”

Hopefully, specialist software houses can also be encouraged to update their programs in
due time. Of prime importance will be the availability of updated finite element software, as
moments generated by programs written to the ENV version of EC2 will not be correct.

Rod Webster Concrete Innovation & Design Page 8


VIETCONS EDUCATION www.vietcons.org
The practical use of Eurocode 2

5.4 “Factors of safety”


There has been recent discussion regarding comparative “factors of safety” between BS
8110 and EC2 (also CP49!), which shows a massive misunderstanding of the basic
principles of limit state design.

• A true factor of safety can only be determined by comparing design loading with that at collapse.
• Partial factors for materials and loading are not safety factors; they only reflect degrees of
confidence.
• Any basic understanding of statistics proves that to simply multiply together sets of factors or
probabilities is completely meaningless.

The economic advantages of EC2 for flexural design are far greater than can be assessed by
looking at the partial factors for loading and materials alone.

• For similar characteristic loading, ULS loading can be 10% to 15% less.
• Rebar design stresses are almost identical, in spite of the differing γ factor.
• The difference in pattern loading may marginally increase support moments but reduce span
moments.
• For the same concrete mix, EC2 gives a concrete stress 19.4% higher than BS 8110, which in turn
increases the lever arm z.
• More generous span-to-depth ratios can lead to shallower members.

These economies would seem very significant. Shear and column design do not appear to
have been trimmed in the same way, but this must reflect our increasing understanding of
concrete design. Slabs are by far the most economically critical elements, and here there is
advantage.

Rod Webster Concrete Innovation & Design Page 9


VIETCONS EDUCATION www.vietcons.org

BubbleDeck Voided
Flat Slab Solutions

Technical Paper

BubbleDeck® Design and


Detailing Notes – guidance to
engineers and detailers

October 2007
VIETCONS EDUCATION www.vietcons.org

BubbleDeck - guidance to engineering designers and detailers

Engineering design

Generally:

The engineering designer should be very familiar with the principals of slab design
and particularly flat slabs as well as having a good grounding in general structural
engineering.

It is recommended, as a minimum, to have read a general text on flat slab design


and the appropriate sections of Concrete Society Technical Report TR43[i] and
TR58[ii] (Note TR43 is specifically for post tensioned slabs but there is useful and
relevant material there). Essential reading also is Eurocode 2[iii] – at least the
sections on flexure and shear, with particular reference to punching shear.

CIRIA Report 89[iv] and 110[v] are also important background reading (although the
latter is somewhat obsolete, it contains useful material).

The engineer wishing to explore in greater depth should read Nielsen[vi]. This is
especially useful text as Nielsen was an influential member of the EC2 drafting
committee and to a large degree, was responsible for bringing the code up to date
with recent advances in plastic theory instead of reliance on outdated empirical
practices and over-reliance on elastic methods.

It is also helpful to read through the various reports of testing and studies done on
BubbleDeck Slabs in Europe.

All design work should be checked or reviewed by a competent person. It is not


recommended to rely on Local Authority Building Control Checking as some
checking engineers lack the specialised knowledge and experience to properly check
advanced RC designs.

The analysis and calculation of resistances for BubbleDeck is much the same as for
ordinary slabs except for some additional criteria. It is essential that the engineering
designer has an understanding of analytical manual methods, particularly yield line
theory, and an understanding of the principals and application of finite element
analysis. In the latter case an understanding of linear elastic and non-linear methods
is necessary.

Material properties:

Shear:

The shear resistance of BubbleDeck is a slightly conservative value, taken from


tests, which we use in design: 0.6 times the shear resistance of a solid slab of the
same thickness. If this is exceeded by the applied shear, at a column for example,
we leave out the balls and use the full solid shear values. Test conducted in
Germany, Denmark and Holland have shown the resistance to vary from about 65%
to 90% of a solid slab.
VIETCONS EDUCATION www.vietcons.org

Flexure:

Standard strength parameters and properties are used as for solid slabs.

Deflection:

Span depth ratio calculations for deflections are very approximate and are not
appropriate in flat slabs of irregular layout except for the most simple or unimportant
cases. FE modelling, including non-linear cracked section analysis is used to
calculate the deflection using normal structural concrete with a Young’s Modulus
(secant) Ecm, multiplied by 0.9 (see above) and a tensile strength, fctm multiplied by
0.8 (to reduce the crack moment as mentioned above – this is mainly significant in
the computation of uncracked curvatures where the geometry of the concrete section
is significant but is of increasingly negligible significance after cracking).

It is not presently possible to calculate for the difference in age related properties in
the filigree and in-situ concrete parts. This is not considered to be a significant
weakness.

Design methods:

Generally:

For ULS, elastic or plastic methods may be used to determine the applied actions.
The engineer should, however, be aware of the fundamental differences between the
two theories.

For flexural design, plastic theory may lead, in practice, to more efficient use of
reinforcement. This is usually applied, in the case of slabs, by the yield line theory –
the most celebrated exponent of this being K W Johansson. Johansson[vii] published
a comprehensive work on the practical use of yield line theory as well as his original
work on the theory itself. Kennedy and Goodchild[viii] have published a useful and
very readable introduction to the use of yield line theory also. Yield line theory is a
very powerful tool by virtue of the relatively simple procedures involved leading to
economic reinforcement quantities. It is not without need for caution, however, and
care needs to be excercised not to overlook SLS concerns.

The main reason for the economy of yield line design is that collapse mechanisms
are found (usually in an upper bound analysis) that involve the whole, or a very large
part, of a reinforcement zone in yielding since it can be shown that the whole must
fail before the structure can fail globally (bearing in mind there may be many upper
bound mechanisms that need to be checked). This is in contrast to elastic design,
which usually results in a fairly heterogeneous moment field for which the designer
attempts to fit a practical arrangement of reinforcement. In fact, Nielsenvi states that
the elastic theory can lead to an optimal arrangement of reinforcement and, in
addition, that there is no philosophical objection to the use of plastic theory in
designing the reinforcement for applied actions determined from the elastic theory. It
is evident from this that the use of elastic theory and, in this particular context elastic
moment results for slabs, it is only significantly uneconomic if the designer is too un-
conservative about how the moment result field is covered by the reinforcement
provision and if there is no allowance for yielding and redistribution.
VIETCONS EDUCATION www.vietcons.org

For example, FE results for a slab may show a small but irregular area of high design
moment. The designer may apply rebar to this in a rationalised zone, probably
rectangular, which actually extends over areas where the design moments are very
low. It would be possible, with appropriate experience and judgment to adjust
downwards the quantity of reinforcement so that it actually yields at the intense
moments and redistributes moment to the less utilised areas. This might be checked
by utilising a work equation in the same way as yield line design is carried out. It is
obviously important to ensure that the work done, the dissipation, in yielding a
reinforcement zone balances the work done by the external loads. In an
approximation, one could check that the dissipation of the applied reinforcement
exceeds that of the required reinforcement from the elastic results.

Codes and published methods often give weight to concepts of column strips and
middle strips but these are usually difficult to apply in irregular slabs. TR43 gives
guidance on this, for example, and suggests that the column strip is determined as
0.4 of the distance from the column centreline to the zero shear line. Some methods
further divide the column strip into an inner column strips and outer column strips. It
is recommended in most UK practice to concentrate most of the reinforcement, say
2/3 of that in the column strip in to the inner column strip so that the reinforcement
provision will be greatest where the service moments, tending to the elastic end of
the spectrum, are greatest and thus where most needed to resist cracking and limit
rotation contributing to deflection. To prevent absurd concentration of rebar, one may
take the reinforcement for the average moments for the inner column strip and
provide this for the full width of that strip.

Another phenomenon tending to produce in economy from yield line design is that it
utilises the technique of allowing support and span moments to yield according to the
reinforcement chosen in such a way that the relative quantities in the top of the slab
at supports and in the bottom at mid-span are optimised to what is available and
practical.

There is, however, an important feature of yield line design that must not be
overlooked: It design for ULS only and assumes that a collapse mechanism can exist
which mobilises all the concrete and steel used. This implies that the slab is
sufficiently ductile in all respects and requires that steel can reach the strains
required without exceeding the ultimate strain and that the concrete does not crush
or crack excessively. Furthermore, it does not check the conditions at SLS and if
over-reliance is placed on ductility it can sometimes lead to excessive cracking if
large rotations occur at SLS which cannot be accommodated by the rebar supplied
without large tensile strains in the concrete.

There may also be an important point to observe if excessive yielding occurs where
one relies on shear resistance – punching shear at columns for example. According
to modified compression field theory, it can be shown that shear softening may be
significant.

This is where the advantage of FE analysis and design are most significant; even if
linear elastic models are used (there are non-linear plastic FE methods in existence
but they are not widely used). Modern software is available which simulates non-
linear behaviour, including the effects of cracking in an iterative process on the
elastic stiffness method and these have been shown to give good results. Using
these tools, checks on the SLS behaviour, including cracking and deflection can be
carried out as well as a ULS design indicating where yield limits may occur.
VIETCONS EDUCATION www.vietcons.org

The FE methods also have the advantage of combining all the static analyses and
checking into one process that can be efficiently managed.

Shear:

The shear resistance of BubbleDeck is taken as 0.6 times the shear resistance of a
solid slab of the same thickness. If this is exceeded by the applied shear, at a column
for example, we leave out the balls and use the full solid shear values. Using
Eurocode 2iii (or any other code for that matter, with slight differences) one may
calculate the applied shear at 2d and subsequent perimeters from the column face
as per the code requirements, as well as at the column face itself. This would then be
compared to the calculated resistance.

. If the applied shear is less than the un-reinforced hollow slab resistance, no further
check is required.
. If the applied shear is greater than the hollow slab resistance we omit balls and
make it solid then check the solid part.
. If the resistance is still greater than the solid slab resistance and less than the
maximum allowed, we provide shear reinforcement.
All is exactly as solid flat slab design. Additionally one places bottom bars as per
CIRIA report R89iv, designed to protect against progressive collapse – these bars
may be checked using Rasmussen’s dowel calculation so that they can sustain, say
75% of the accidental limit state shear force.

Punching shear, in difficult or complex cases, may also be checked using methods
described in Nielsenvi. Indeed it is always a good idea to check using more than one
method or theory as this can expose anomalies or mistakes that must be checked.

In calculating the shear resistance care and judgment should be exercised in


employing formulae which include a scale factor. The scale factor in shear is real but,
according to Reganiv, there is evidence that it is diminished if the aggregate is also
scaled. It must be remembered that aggregates are often smaller for the smaller
BubbleDeck slabs and thus it is prudent to set the scale factor to the value it would
have for a slab of 450mm thickness – in EC2 this amounts to setting k = 1.7.

At edge and corner columns, as well as at eccentric loaded columns and transfer
loads, torsion and moment capacity should be checked. Nielsen gives methods for
this. The designer should be aware that the resistance of the slab at edge and corner
columns may be governed by torsion and flexure as well as punching shear. In fact it
is possible that flexural/tensional resistance at edges and corners will make punching
shear calculations at these positions irrelevant.

If shear reinforcement is required, a conservative assumption is to design the


reinforcement to sustain the entire shear without the concrete contribution. This will
assist in avoiding complications with strain softening in intense shear situations at the
expense of slightly more shear steel.

The valid detail for the joint at columns or walls is to arrange the filigree to embed
into the columns or walls so that shear over the full section can be mobilised.
Sometimes there will be requests for a joint around the column where the filigree
does not reach the face of the support – usually by a distance of 40mm to 50mm –
this is highly undesirable and complicates the shear design and there is no validated
method of design. If the detail is unavoidable one may, with care, be able to design
VIETCONS EDUCATION www.vietcons.org

the section assuming the filigree to be ineffective near the column or wall but this will
produce a greatly reduced shear resistance. At some distance from the column, if the
shear reinforcement elements are properly anchored in the filigree and in-situ parts
(that is anchored outside the main reinforcement planes), it may be argued that the
section can be re-combined and the full section used for these outer perimeters. This
leaves some scope for engineering judgment.

Punching shear reinforcement may take the form of purpose made rebar, studs or
Lenton Steel Fortress, according to practical constraints. It is important to apply
these properly and to pay attention to the anchorage requirements of any system.
Shear heads may also be design for extreme situations and may be structural steel
or rebar beams. ACI318-05[ix] gives recommendations for the design of these.

Longitudinal shear is only critical at high rates of change of applied moments (which
is of course gives the maximum transverse shear). Within the span, the rate of
change of moment tends to be less than close to the supports. The areas close to
supports are usually solid however, and the filigree is in compression, so the intensity
of longitudinal shear near the supports is mitigated. If a check is necessary, EC2
gives values for shear between concrete cast at different times as well as the method
for calculating the applied shear (the change in moment divided by the distance
between the section considered and the point of zero moment, on average). The
girder webs may be taken into account in reinforcing the interface but only one
diagonal in every pair unless otherwise can be justified due to the web angle.

Flexure:

A standard method may be used provided that the depth of concrete in compression
does not overlap the ball zone by more than 20%. This is almost always the case in
all but extremely heavily stressed slabs.

The maximum moments are usually over the columns or supports. This means the
compression is in the slab bottom here, and this is usually in a solid zone, so the
restriction on the depth of compression need not necessarily apply at columns and
supports.

A rectangular stress distribution or other appropriate distribution may be used in the


concrete. EC2 contains a useful and simple method but other plastic methods may
be used.

Steel should be ductility class B, especially if plastic design is used, unless special
calculations prove class A to be satisfactory. This should ensure that the yield strain
limit is not reached prematurely in the reinforcement.

The engineer should exercise a degree of judgment when interpreting the results of
FE analysis, especially if it is a linear elastic analysis. There are many mathematical
anomalies that can occur which can distort the results one way or another.
Singularities, for example, can occur at concave corners and point loads and
supports – these lead to absurdly high design moments. Some software uses peak
smoothing algorithms and, if these are not available, manual averaging or taking
moment at the support face may be an expedient choice.

Even with cracked section iterative analysis, high concentrations of moment and/or
VIETCONS EDUCATION www.vietcons.org

torsion can occur in corners and, although this is a reflection of reality, they can lead
to very high reinforcement requirements. In manual analysis, and indeed in yield line
methods, these peaks are averaged out by implied yielding. This is legitimate
provided always that the structure, or any substructure, is globally elastic at SLS and
provided that the rotations implied by the yielding do not lead to excessive cracking
(and consequent increase in deflection), particularly at the top of the slab at columns.
Excessive cracking here may also indicate that shear strength is compromised. For
these reasons, it is recommended that the top tension steel is bunched toward the
centre of such supports – such practice is mentioned in several codes and literature.

Deflection:

Span depth ratio methods are not recommended, except in checking and
approximate or relatively unimportant cases. FE analysis is recommended for all
slabs as there is no practical manual method that can be used with confidence. Even
unidirectional spans can be very tedious in the computation of deflections.

Where accurate deflections are required, the software runs iteratively, calculating
modified and cracked element properties at each stage of the iteration, using the
applied reinforcement, until convergence is reached. The deflection using this
method has been shown to have good agreement with tests conducted at the ECBP
at Cardington (see Concrete Society Technical Report TR 58ii).

Short term loadings cases are usually patterned, subject to engineering judgment,
(chequerboard or parallel strips depending on the characteristics of the project) using
the “Frequent Combination” set out in Eurocode 0 and using combination factors “y1”
as appropriate. For long term loading, the “Quasi-permanent combination” is used
with combination factors “y2” as well as creep coefficient and shrinkage curvature
parameters if necessary. Shrinkage curvature is generally of low order compared to
extrinsic effects – L/1500 has been quoted as an order of magnitude of the defection
component due to this.

The combination factors now available in EC0 represent a statistical method of


estimating which part of the imposed load is variable and which is invariable.

For simplicity, and where it can be justified, the engineer may estimate long term
loadings using the total permanent load and 50% of the imposed load without great
loss of accuracy. This is likely to be good enough for most ordinary building projects.

Non-linear, iterative analysis can take a long time on complex or large slab models
so it is not generally efficient to run such an exacting analysis on every slab and
every load case. Partial models can be constructed to model limited parts of slabs
and reasonably good results can be obtained with the exercise of some prudence. It
is recommended to calibrate such partial models by comparing them to the full model
under comparable conditions so that the approximation represented by the partial
model can be validated. In a similar way, elastic results may be used as a broad
approximation provided they use a modified elasticity and that this is calibrated
against a more rigorous analysis.

Creep and shrinkage have been shown by tests to be only marginally higher than a
solid slab of similar dimension. Due to the precision of serviceability calculations this
small difference is usually ignored.
VIETCONS EDUCATION www.vietcons.org

Vibration:

RC slab structures are generally less susceptible to vibration problems compared to


steel framed and light weight skeletal structures, especially using thin slabs.

However, BubbleDeck is light and is not immune from vibration in all cases so this
must be checked just as it should be in appropriate solid slab applications.

Where deflections are large, as indicated by the static design, it is often an indication
that the structure is sensitive to vibration SLS issues.

The lighter weight of BubbleDeck may be exploited if it can usefully alter the modal
frequencies of a slab – generally raising them compared to a solid slab. The most
effective weapons against vibration, particularly resonant vibration, are stiffness and
damping. If we consider damping to be similar to solid slabs, and concentrate on
stiffness, we may observe that a BubbleDeck slab can provided over 2_ times the
stiffness obtained from a solid slab for the same quantity of concrete used. This can
be exploited in vibration sensitive applications.

At the present time, the static modification to the flexural stiffness is applied.
However, future work may show that the static stiffness is not the same as the
flexural stiffness in BubbleDeck slabs but the difference is thought to be minor
compared to the effects of inaccuracies in modelling vibration problems.

TR43i should be used for the procedures for determining vibration sensitivity and
modal superposition may used to determine the response for given excitation.

Fire resistance:

The fire resistance of the slab is a complex matter but is chiefly dependent on the
ability of the steel to retain sufficient strength during a fire when it will be heated and
lose significant strength as the temperature rises. The temperature of the steel is
controlled by the fire and the insulation of the steel from the fire. The degree to which
weakening of the steel is significant is related to the service stress at FLS.

The design then reduces to a determination of the combination of the amount of steel
and amount of concrete cover to attain a balance of steel temperature and stress that
allows the structure to remain stable at FLS.

Advance or more complex design and analysis may include the determination of
temperature profiles in the time domain, of cooling and the even effects of quenching
by fire fighting water.

A basic design may make use of the data tabulated in the BD technical manual for
cover required for various fire resistance periods and steel stress. An analysis may
be carried out for FLS loading (roughly 0.7 of the ULS loading but this should be
calculated according to EC2-1-2) and the applied moments obtained. This will allow
the designer to check various sections, using calculated moment curvature
relationships, to determine the steel stress corresponding to the FLS moments.
When these steel stresses are known they may be interpolated in the tabulated data
and cover or fire resistance thus estimated.
VIETCONS EDUCATION www.vietcons.org

A question that frequently arises concerns the pressure in the bubbles during
heating. Calculations have been carried out by Jørgen Breuning to show that this is
not a serious issue. In any case, all concrete is cracked and, in a fire, it is likely that
the air would escape and the pressure dissipated.

If the standard bubble material is used (HDPE), the products of combustion are
relatively benign, certainly compared to other materials that would also be burning in
the vicinity. In an intense, prolonged fire, the ball would melt and eventually char
without significant or detectable effect.

Seismic design:

This is a specialist area outside the scope of this brief technical note. However, the
concerns in Seismic design are largely similar to any flat slab structure.

Punching shear under seismic conditions is the most critical issue and damage at the
slab-column junction during sway reversals should be properly considered as well as
amplification of the punching shear due to the vertical component of ground
acceleration.

In computing the building’s response, the seismic designer should be closely


engaged with determination of the mass and the effect of this on modal spectrum.
Using BubbleDeck a significant reduction of mass in the floor plate may be realised
together with an increase in modal frequency and reduction in the sway forces due to
lateral acceleration.

Detailing:

BubbleDeck demands more from the detailer than normal flat slab design – of this
there is no doubt. The geometrical discipline required to coordinate the layering and
spacing of factory fixed and site fixed rebar as well as the bubble module is far more
demanding and requires an attention to detail greater than ordinary detailing.

The BubbleDeck geometry is founded on the module size which, until recently,
comprised 200mm, 250mm, 300mm, 350mm, and 400mm. Larger sizes have been
added but the rules applying to the geometry still apply.

. The ball diameter is always 0.9 of the module.


. The effective depth, except with heavy reinforcement may be approximated as
equal to the module.
. The cover to the bubbles should be at least one ninth of the ball diameter.
The cover to the bubbles and to the reinforcement may vary, of course, and this may
require adjustments to be made. Slightly more concrete that standard may be poured
to achieve a range of sizes intermediate to those imposed by the fixed module sizes.

The filigree or ‘biscuit’ standard thickness is 60mm or 70mm depending on size of


bottom steel. The bottom edges have a 6mm x 6mm bevel. At least two edges of
every unit must have 25mm x 25mm bevel on the top to ensure that the splice bar
has a filet of site concrete to seal it against attack by fire.

At a very early stage, the detailer should draft the sections to be used in a project
and verify the reinforcement geometry and especially the mesh spacing and girder
VIETCONS EDUCATION www.vietcons.org

size required.

Although the edge distance of the balls to the edge of the units, at internal edges that
will be concreted, may follow the natural module; the cover to the bubble may be
insufficient at the outside of the slab so it may be necessary to leave out a row of
balls or otherwise plan the spacing with this in mind. Fixings are frequently made to
edges of slabs so a slightly wider solid edge zone is often no bad thing.

Mesh will generally need to be custom mesh and it should be noted that machine
made meshes usually have one or more of the following restrictions:

. Max. bar size 16mm


. Longitudinal bar spacing increments of 50mm c/c (eg 50mm / 100mm / 150mm /
200mm, etc.)
. Min. distance from last bar to end 25mm
. Cross wire spacing sometimes in 25mm increments but may be unrestricted
according to machine type.
Girders are supplied in height increments of 10mm but some suppliers may supply
any size. The diagonals should be 63° approximately and must be welded securely
to the longitudinal bars (See CUR86 for a useful specification).

The standard girder spacing, as outlined in CUR86 is two balls maximum. Greater
spacing than this is possible but the unit may be too flexible and crack more easily
during transit or handling. The longitudinal girder bar should be 10mm minimum for
the 200 and 250 modules and at least 12mm for 300 modules and above. The girder
web bar may usually be 7mm or 8mm and 8mm is preferred except in light
applications.

The section should be drafted so that the correct ball spacing is produced and so that
the bubbles are restrained against movement laterally or vertically by at least two
bars at the bottom and two bars at the top. It is usually sufficient to have two long
bars in the bottom mesh controlling the position and two transverse bars at the top. It
is imperative that the ball cannot rise up more than a few millimetres when placed in
the casting bed. The top mesh should be low enough in the section to permit the top
site steel to be placed allowing for some tolerance.

The detailer should note that the ball will float up, during casting in the factory, until it
is in contact with the closest top mesh bars. This means that the top mesh will
usually control the height of the ball.

The top mesh does not usually fulfil an important function in the permanent state,
except for an crack purposes, and is more significant in the temporary state (lifting
and when spanning between props) when it has the important purpose of stabilising
the top of the girder against lateral buckling. Clearly it also traps the bubbles in place.

Loose bars, not welded in the mesh, may be detailed to fit between the mesh bars,
secured by tying wire, to achieve localised increases in steel area.

Splice bars are placed on top of the filigree and should be detailed so that they have
adequate clearance, spacing and anchorage. It will generally be more efficient to
provide more of smaller bars than few of larger ones. Anti-progressive-collapse bars
will also pass through columns in two directions and lay directly on the filigree.
VIETCONS EDUCATION www.vietcons.org

Top site steel is detailed and placed in the normal way – as for solid slabs. A heavy
zone of steel will usually occur over columns with lighter steel on the column lines
between these zones. In curtailing the top steel, it is advantageous to do so in a way
that does not result in the bars ending very close to a unit joint and thus complicating
placement of splice mesh.

Where the top main site steel does not already form a top splice to the top mesh,
narrow sheets of top mesh are used to lay over the joints to complete a continuous
top reinforcement.

All edges of the slab must be fitted with U-bars, whether they are support edges or
not. This provides for the tensional resistance required at slab edges and the
satisfaction of the correct conditions for the development of the Kirchhoff boundary
forces. This is especially important near supports, like columns, and corners.

Shear reinforcement should be long enough to achieve correct cover top and bottom
but must be anchored in the top and bottom steel zones. The lateral spacing should
be as close to 0.75 times the effective depth as practicable, but not greater. For
radial arrangements of shear reinforcement, the circumferential spacing should be
similar in the case of the first element perimeter, which should be placed at a
maximum of approximately 0.375 times the effective depth from the face of support.
There will almost inevitably be conflict with the mesh and site steel and the spacing
should be varied by as small an amount as possible to clear this. In cases where
there is doubt about the suitability of a position, and extra element may be placed
adjacent.

To close the edge of the mesh and to provide transverse reinforcement to prevent
separation of the filigree at the joints, the edges of the units should have Ø8mm hook
bars, along the edge, hooked around the bottom mesh and top mesh edge bars.

The mesh should be welded to the top and bottom of the girders and the welds
should be sufficiently close together to resist pull-out from the filigree during lifting
and should provide sufficiently close spacing to the top girder bar so that it does not
buckle when in compression. Triangular or three bar girders have better resistance
but are more difficult to install with sufficient space for the bubbles and other steel.

It is suggested that the welds between the mesh and the girders should be at a
maximum spacing of 600mm spacing. The welds should not be too far apart as they
may allow the girder to pull out to easily from the filigree during lifting. They may also
provide insufficient restrain to the girder top bar which must be prevented from
buckling, especially when it is spanning across the props on site and supporting the
concrete pouring operation.

If fixings are to be made to the top of the slab when it is exposed to the weather, a
hole should be drilled right through to enable trapped water to drain out.

References
[i] Technical Report 43, Post Tensioned Concrete Floors – Design Handbook, The
Concrete Society.

[ii] Technical Report 58, Deflections in Concrete Beams and Slabs, The Concrete
VIETCONS EDUCATION www.vietcons.org

Society.

[iii] Eurocode 2 Eurocode 2: Design of concrete structures - Part 1-1: General rules
and rules for buildings, British Standards Institution.

[iv] CIRIA Report 89, Behaviour of Reinforced Concrete Flat Slabs, P E Regan,
CIRIA, 1981.

[v] CIRIA Report 110, Design of Reinforced Concrete Flat Slabs to BS8110, CIRIA,
Revised Edition 1994.

[vi] Limit Analysis and Concrete Plasticity, M P Nielsen, CRC Press, 2nd Edition 1998.

[vii] Yield Line Formulae for Slabs, K W Johansson, Concrete Society

[viii] Practical Yield Line Design, Gerrard Kennedy and Charles Goodchild, British
Cement Association 1st Edition 2003

[ix] ACI318-05, Building Code Requirements for Structural Concrete (ACI 318-05)
and Commentary (ACI 318R-05)

BubbleDeck UK
White Lodge,
Wellington Road,
St. Saviour,
JERSEY, C.I.
JE2 7TE

T: +44 (0)1534 725402


F: +44 (0)1534 739115
E: info@BubbleDeck-UK.com
W: www.BubbleDeck-UK.com
VIETCONS EDUCATION www.vietcons.org

Appendix D Comments to Eurocodes 2


VIETCONS EDUCATION www.vietcons.org

Draft BD Annex to EC2

Bending:
Flexural or bending behaviour is elementary. Use the EC2 recommended procedures.
To avoid the situation that would exist if the depth of concrete in compression overlaps the ball zone, the
depth in compression must be limited so that the depth does not overlap by more than 20% of the
compression zone depth.

Deflection:
Methods:
Deflection is calculated from integration of curvatures or by software. If the latter is used, the engineer must
ensure that the procedure either uses an appropriate procedure for cracked section analysis or use
appropriate corrections to the modulus of elasticity.
The EC2 method for manual design closely resembles, and incorporates procedures for including the effects
of cracking and tension stiffening, methods developed by Branson and also Nielsen. It is proposed that
Nielsen’s method and notation may be used as it is reasonably clear and concise.
In the case of two-way spans, the spans in each direction must be evaluated separately and then the results
combined in a rational way.
Each span is divided into sections, usually equal lengths, and the curvatures computed for each from the
expression κ = M/EI. The curvature should be modified using Nielsen’s procedure, taking into account the
ratio of the cracking moment to the applied moment at the section. The curvatures at each section must then
be integrated twice on the span to produce the deflected profile. A classic procedure for this is due to
Timoshenko and the conjugate beam analogy may be used.
In the case of irregular plan forms and irregular spans, it is unlikely that hand methods will produce anything
better than an approximate estimate and computerised FE modelling will be necessary. FE Modelling using
non-linear and cracked section analysis has been shown to produce good results. Analysis using the gross
section properties must be avoided unless careful correlation of the equivalent elastic modulus is used. Any
software used must possess well documented explanations of the procedures used, must also have some
form of validation and be obtained from a reputable company with appropriate quality assurance procedures.
Loading:
Slabs should be checked for long term and short term loading. Long term loading will normally be modelled
by the application of a creep coefficient, and may include shrinkage curvature deflections, although the latter
is usually of secondary magnitude. The creep coefficient should be determined with reference to the age art
which the deflection is required but is will usually be of the order of 2.
The appropriate combination of loading in EC2, which refers to EC0 and EC1, for long term loading, is the
“Quasi-permanent” combination. This requires the application of the full permanent load plus a proportion of
the imposed load. Combination factors for the invariable part of the imposed load are given and these depend
on the structure’s use – they range generally from 0.3 to 0.7. However, since deflection calculations are
necessarily approximate, a combination factor of 0.5 may be applied to imposed loads without meaningful
loss of accuracy.
For short term loading, the “Frequent combination” is usually appropriate. Again combination factors are
given to represent the variable parts of imposed loads and they again depend on the use of the structure.
These may be applied to obtain an estimate of immediate deflection using short term material properties and
loading on adjacent spans may be investigated if appropriate. It is important to note that the deflection due to
imposed load only may not be obtained directly due to the non-linear effects of cracking so an analysis must
be carried out for permanent and imposed load as well as permanence load only and the imposed load
deflection obtained by subtracting one from the other.
Deflection limits should be obtained wherever possible from the client or building user. However, the
guidance on appropriate limits given in EC0 and EC2 may also be used.
Pre-camber may be specified to mitigate the effects of deflection. As a guide, such pre-camber should not
normally exceed Span/250 approximately.
It should be noted that large deflections, especially due to the permanent load alone, may indicate potential
vibration sensitivity that should be subject to a specialist investigation.
VIETCONS EDUCATION www.vietcons.org

References:
1. Enochsson, Ola & Dufvenberg, Peter - Concrete Slabs Designed With Finite Element Methods - Lulea
University of Technology.

2. Ferenc, Németh - Calculation of Reinforced Concrete Plates with non-orthogonal


reinforcement - Budapest, September, 1999

3. Eurocodes 0, 1 and 2.

4. Whittle RT - Design of reinforced concrete flat slabs to BS8110 - CIRIA Report 110 (2nd Ed. 1994)

5. Regan PE - Behaviour of reinforced concrete flat slabs - CIRIA Report 89.

10. Technical Report 43 - Concrete Society.

11. Technical Report 58 - Concrete Society.


VIETCONS EDUCATION www.vietcons.org

Appendix E Shear according to Eurocodes 2


VIETCONS EDUCATION www.vietcons.org

BubbleDeck International
VIETCONS EDUCATION www.vietcons.org

BubbleDeck International
VIETCONS EDUCATION www.vietcons.org

BubbleDeck International
VIETCONS EDUCATION www.vietcons.org

BubbleDeck International
VIETCONS EDUCATION www.vietcons.org

BubbleDeck International
VIETCONS EDUCATION www.vietcons.org

BubbleDeck International
VIETCONS EDUCATION www.vietcons.org

BubbleDeck International
VIETCONS EDUCATION www.vietcons.org

BubbleDeck International
VIETCONS EDUCATION www.vietcons.org

BubbleDeck International
VIETCONS EDUCATION www.vietcons.org

BubbleDeck International
VIETCONS EDUCATION www.vietcons.org

Appendix F BubbleDeck Standard Details


VIETCONS EDUCATION www.vietcons.org

Detail 01
BubbleDeck Versions

Cross sections only

BubbleDeck Type A - Bubble lattice - in situ version

BubbleDeck Type B - BubbleDeck filigree slabs - semi precast version

BubbleDeck Type C - BubbleDeck elements - precast version


Cross section
X
Y Y
Longitudal steel (x) : black marking
Transverse steel (y) : dotted marking

splicebars

girder
VIETCONS EDUCATION

splicebars
www.vietcons.org

Detail 02
Cross section:
Hairpin at free perimeter X
Y Y

Longitudal steel (x) : black marking


Transverse steel (y) : dotted marking

hairpin (placed on site)


VIETCONS EDUCATION
www.vietcons.org

Detail 03
X
Cross Section: Y Y
Slab on wall (beam)

Longitudal steel (x) : black marking


Transverse steel (y) : dotted marking

hairpin ( placed onsite according to instructions )


VIETCONS EDUCATION

Ball can be omitted


if shear forces are high min 50
www.vietcons.org

Detail 04
Cross section:
Slab above wall - continuous slabs X
Y Y

Longitudal steel (x) : black marking


Transverse steel (y) : dotted marking

splice bars
VIETCONS EDUCATION

splice bars

Ball can be omitted


if shear forces are high Min 50 Min 50

Wall
www.vietcons.org

Detail 05
VIETCONS EDUCATION www.vietcons.org

Detail 06
Above column
No shear reinforcement

Solid (if needed)


VIETCONS EDUCATION www.vietcons.org

Detail 07
Above column
Shear reinforcement in one direction

Solid

Shear reinforcement Shear reinforcement


VIETCONS EDUCATION www.vietcons.org

Princip Detail 08
Example of
Intense Shear reinforcement above column
born in element units

Shear reinforcement Shear reinforcement


VIETCONS EDUCATION www.vietcons.org

Appendix G Examples
VIETCONS EDUCATION www.vietcons.org

Calculation Examples

1. Test 8 x 8

2. Millennium Tower

3. Shear

4. Project Arup in Spain

5. Test 9 x 12

6. Parking

7. Steel

8. Moment Curves, India

9. Project Herstedlund in Denmark

10. Professor Kiss, Romania

11. Keops – Project City Hall, Denmark

12. Deflection
VIETCONS EDUCATION www.vietcons.org

Example 1 Test 8 x 8
VIETCONS EDUCATION www.vietcons.org

Example 1

Calculations

Dead load g = 4.50 kN/m2


Live load q = 20.0 -
----------------------
∑p = 24.5 kN/m2

Calculations are made with p = 1 kN/m2


x is measured from support

Model 1 max negative moment

per m width m,x = p (L – x) 2 / 6


x = 0.0 m max m’ = 1 (4.2 – 0) 2 / 6 = 2.94 kNm/m
see figure 2 eff. B’ = 8.20 m
full B’ = 11.4 -
with p = 24.5 kN/m2
we have eff. m’d = 2.94 * 24.5 * 11.4/8.2 = 100 kNm/m
Y10/125 m’ = 60 -
+ Y14/125 above col. see figure 2
area 2.4 x 2.4 m m = 120 * 2 * 2.4 / 8.2 = 70 -
ok, total m = 60 + 70 = 130 -
more than eff. m’d = 100 -

Max deflection
m is written at the form m,x = p L 2(1 – x/L) 2/ 6
to be used in excel program for deflexion
moment- and deflexion are calculated in excel form
4 dead load
5 dead load plus imposed load
the calculation is executed with Y20 above columns regarding the deflections
VIETCONS EDUCATION www.vietcons.org
Example 1

Model 2

cantilever L = 2,0 m
per m width m,x = p (L – x) 2 / 2
x = 0.0 m max m’ = 1 (2.0 – 0) 2 / 2 = 2.00 kNm/m
with p = 24.5 kN/m2
we have eff. m’d = 2.0 * 24.5 = 50 kNm/m
Y10/125 m’ = 60 -
+ Y14/125 above col. see figure 2
2 x 2.4 m m = 120 * 2 * 2.4 / 8.0 = 70 -
ok, total m = 60 + 70 = 130 -
more than eff. m’d = 50 -

Model 3
Aas we here have only an example and it is obvious there will be no perceptible deviation
it is sufficient to regard only the simple part A (triangle) point forces at edge yielding is not
regarded

moment balance
simple moment m,0 * 6.4 = 24.5 * 6.4 * 4.7 2 / 6 = 577 kNm/m
m,0 = 90 -
m’ = 24.5 * 2.0 2 / 2 = 50 -
max m = 90 – 50 = 40 -
Y10/125 m = 60 -

2
VIETCONS EDUCATION www.vietcons.org
Example 1

Model 4
It is directly seen:
The positive moment is obviously less than negative moment in model 1
The simple moment between columns is less than the real moment of the triangle figure
why regarding a 1.0 m strip between columns is sufficient
max m,0 = 24.5 * 5.0 2 / 8 = 76 kNm/m
less than the moment in model 3

Model 5

simple moment m,0 = 24.5 * 5.1 2 / 8 = 80 kNm/m


m’1 = 24.5 * 2.0 2 / 2 = 50 -
m’2 = 24.5 * 1.0 2 / 2 = 10 -
m = 80 – (50 + 10) 0.5 = 50 -
Y10/125 m = 60 -

3
VIETCONS EDUCATION www.vietcons.org
Example 1

Model 6
the full yield line moment is less the individual yield line moments

At columns

Column ø 250 mm
load area max A = 4.1 * 4.1 – 0.5 * 4.0 (2.4 + 1.6) = 24.8 m2
load max P = 24.8 * 24.5 / 1000 = 0.61 MN
shear max τ = 0.61 / π (0.25 + 0.28) 0.28 = 1.30 MPa
more than

τ ,d = 0.12 * ν * f,cd v = 2 / √f,ck = 0.37


τ ,d = 0.12 * 0.37 * 20 = 0.84
τ ,d = 0.12 * 0.48 * 20 = 1,15 ?
reinforcement necessary

shear strength
x = 0.25 + 0.28 P,u = 0.08 * 0.77 * 20 * π (0.25 + 0.28) 0.28 E-3
= 0.57 MN
0.08 * 4.22 = 0.34 = ν (gl)
4.22 * 0.18 = 0.76 = ν (ny)
0.76 * 0,08 = 0.06 = eff ν => 0.06 * 20 = 1.20 = τ > f,ct

facade and house end m = p a + p a 2 /2


corner m * 2a√2 = 2 * 2 p a * a √2 /2 + 2 p a 2 * a √2 /3
m = p a + p a 2 /3
less than m,fac.

4
VIETCONS EDUCATION www.vietcons.org

Test slab - 8000 x 8000 x 280 mm figure 1 and 2

1:100

figure 1 8.1

1.5

4.2
8.2 4.5
9.4
8.0

5.0

3.5

1.5

2.0 5.1 1.0

figure 2 8.1

1.5

4.5
8.0

5.0

3.5

1.5

2.0 3.0 2.1 1.0

5.1
VIETCONS EDUCATION www.vietcons.org

Test slab - 8000 x 8000 x 280 mm figure 3 and 4


1:100

figure 4

1.5

4.5

m
5.0
7.0

3.5

1.5

2.0 5.0 1.0

figure 3 4.7 m*tan53gr

3.0 4.0
6.4

2.8
m

8,0

6.4
VIETCONS EDUCATION www.vietcons.org

Test slab - 8000 x 8000 x 280 mm figure 5 and 6


1:100

figure 5

1.5

4.5

5.0 m

3.5

1.5

2.0 1.0

figure 6 4.3
3.2

4.1
m,0

m,0

3.4

3.9
m,0

2.4
VIETCONS EDUCATION www.vietcons.org

Vietnam / test A1 encl 4 corner


Moment & deflexion - 4,2 m cantilever - short term - working load

Moment is given by m,x = - P * 0,7 * L * (1-x/L) - p*L*L * (1-x/L) (1-x/L) / 6


Curvature is estimated as m,x / EI,c if m,x < m,w
m,w / EI,c + 1,3 ((m,x-m,w) / EI,w) if < m,x / EI,w and if m,x > m,w

m,0 = 0,0 kNm EI,w = 0,0 Span L = 4,2 m Steel b.s. xxx mm2 xxx
P = 0,0 kN/m EI,w = 17,0 MNm2 Height h = 280 mm Steel t.s. xxx0 mm2 xxx +
p = 4,5 kN/m2 EI,w = 17,0 MNm2 Column ø 250 mm Steel t.s. 000 mm2 (ø 00)
m,w = 45,3 kNm EI,c = 41,0 MNm2 Concrete 30 MPa

section load mom. crack. mom. curvature increase inclination defl. increase deflection deflection correct
x/L (-) m,g m,w (-) m/EI dv = dL* m/EI v (= Q,k) du=v*dL u =u,x+du u.korr.
kNm/m kNm/m 1/m E-3 E-3 E-3 mm mm mm
1 0.00 18.4 45.3 0.45 0.05 -0.05 -0.01 0.0 0.0
2 0.05 16.6 45.3 0.40 0.09 -0.13 -0.03 0.0 0.0
3 0.10 14.9 45.3 0.36 0.08 -0.21 -0.04 0.0 0.0
4 0.15 13.3 45.3 0.32 0.07 -0.28 -0.06 -0.1 -0.1
5 0.20 11.8 45.3 0.29 0.06 -0.34 -0.07 -0.1 -0.1
6 0.25 10.3 45.3 0.25 0.05 -0.39 -0.08 -0.2 -0.2
7 0.30 9.0 45.3 0.22 0.05 -0.44 -0.09 -0.3 -0.3
8 0.35 7.8 45.3 0.19 0.04 -0.48 -0.10 -0.4 -0.4
9 0.40 6.6 45.3 0.16 0.03 -0.51 -0.11 -0.5 -0.5
10 0.45 5.6 45.3 0.14 0.03 -0.54 -0.11 -0.6 -0.6
11 0.50 4.6 45.3 0.11 0.02 -0.56 -0.12 -0.7 -0.7
12 0.55 3.7 45.3 0.09 0.02 -0.58 -0.12 -0.8 -0.8
13 0.60 2.9 45.3 0.07 0.02 -0.60 -0.13 -0.9 -0.9
14 0.65 2.3 45.3 0.05 0.01 -0.61 -0.13 -1.1 -1.1
15 0.70 1.7 45.3 0.04 0.01 -0.62 -0.13 -1.2 -1.2
16 0.75 1.1 45.3 0.03 0.01 -0.62 -0.13 -1.3 -1.3
17 0.80 0.7 45.3 0.02 0.00 -0.63 -0.13 -1.5 -1.5
18 0.85 0.4 45.3 0.01 0.00 -0.63 -0.13 -1.6 -1.6
19 0.90 0.2 45.3 0.00 0.00 -0.63 -0.13 -1.7 -1.7
20 0.95 0.0 45.3 0.00 0.00 -0.63 -0.13 -1.9 -1.9
21 1.00 0.0 45.3 0.00 0.00 -0.63 -0.13 -2.0 -2.0
sum

50.0

40.0
load mom. (-) m,g kNm/m
30.0 crack. mom. m,w kNm/m

20.0

10.0

0.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

1.00

0.50
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
-0.50

-1.00

-1.50 curvature (-) m/EI 1/m E-3


deflection u.korr. mm
-2.00

-2.50
VIETCONS EDUCATION www.vietcons.org

Vietnam / test A1 encl 5 corner


Moment & deflexion - 4,2 m cantilever - short term - working load

Moment is given by m,x = - P * 0,7 * L * (1-x/L) - p*L*L * (1-x/L) (1-x/L) / 6


Curvature is estimated as m,x / EI,c if m,x < m,w
m,w / EI,c + 1,3 ((m,x-m,w) / EI,w) if < m,x / EI,w and if m,x > m,w

m,0 = 0,0 kNm EI,w = 0,0 Span L = 4,2 m Steel b.s. xxx mm2 xxx
P = 0,0 kN/m EI,w = 17,0 MNm2 Height h = 280 mm Steel t.s. xxx0 mm2 xxx +
p = 25,4 kN/m2 EI,w = 17,0 MNm2 Column ø 250 mm Steel t.s. 000 mm2 (ø 00)
m,w = 45,3 kNm EI,c = 41,0 MNm2 Concrete 30 MPa

section load mom. crack. mom. curvature increase inclination defl. increase deflection deflection correct
x/L (-) m,g+q/2 m,w (-) m/EI dv = dL* m/EI v (= Q,k) du=v*dL u =u,x+du u.korr.
kNm/m kNm/m 1/m E-3 E-3 E-3 mm mm mm
1 0.00 100.1 45.3 5.30 0.56 -0.56 -0.12 0.0 0.0
2 0.05 90.4 45.3 4.55 0.96 -1.51 -0.32 -0.1 -0.1
3 0.10 81.1 45.3 3.84 0.81 -2.32 -0.49 -0.4 -0.4
4 0.15 72.4 45.3 3.17 0.67 -2.99 -0.63 -0.9 -0.9
5 0.20 64.1 45.3 2.54 0.53 -3.52 -0.74 -1.5 -1.5
6 0.25 56.3 45.3 1.95 0.41 -3.93 -0.83 -2.3 -2.3
7 0.30 49.1 45.3 1.39 0.29 -4.22 -0.89 -3.1 -3.1
8 0.35 42.3 45.3 1.03 0.22 -4.44 -0.93 -4.0 -4.0
9 0.40 36.1 45.3 0.88 0.18 -4.62 -0.97 -4.9 -4.9
10 0.45 30.3 45.3 0.74 0.16 -4.78 -1.00 -5.9 -5.9
11 0.50 25.0 45.3 0.61 0.13 -4.91 -1.03 -6.9 -6.9
12 0.55 20.3 45.3 0.49 0.10 -5.01 -1.05 -7.9 -7.9
13 0.60 16.0 45.3 0.39 0.08 -5.09 -1.07 -9.0 -9.0
14 0.65 12.3 45.3 0.30 0.06 -5.15 -1.08 -10.1 -10.1
15 0.70 9.0 45.3 0.22 0.05 -5.20 -1.09 -11.1 -11.1
16 0.75 6.3 45.3 0.15 0.03 -5.23 -1.10 -12.2 -12.2
17 0.80 4.0 45.3 0.10 0.02 -5.25 -1.10 -13.3 -13.3
18 0.85 2.3 45.3 0.05 0.01 -5.26 -1.11 -14.4 -14.4
19 0.90 1.0 45.3 0.02 0.01 -5.27 -1.11 -15.5 -15.5
20 0.95 0.3 45.3 0.01 0.00 -5.27 -1.11 -16.6 -16.6
21 1.00 0.0 45.3 0.00 0.00 -5.27 -1.11 -17.8 -17.8
sum

120.0

100.0
80.0 load mom. (-) m,g+q/2 kNm/m
crack. mom. m,w kNm/m
60.0

40.0
20.0

0.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

10.00

5.00

0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
-5.00

-10.00 curvature (-) m/EI 1/m E-3


deflection u.korr. mm
-15.00

-20.00
VIETCONS EDUCATION www.vietcons.org

Example 2 Millennium Tower


Weena Toren Drawing no 2
1 2 3 4 5 6 7 8 9 10
Bubble Elements
1:200
4500 3600 3600 3600 5400 3600 3600 3600 4500
Date 17.07.97

Elements (m)

5400
e 1 2,7 x 9,3
e2 - 8,4
e3 - 7,8
e4
F e5 - 6,9
e6 - 4,8
e3 e1 e7 - 3,9

3600
E

e7

9000
e5 e2 e6
VIETCONS EDUCATION

3600
C

5400
A
www.vietcons.org

13 x 2790 J. BREUNING
Consulting Engineer
Bubble-Deck 330 mm / Concrete 15 MPa Rösevangen 8
Steel mesh bottom side element ø 12/150 mm DK-3520 Farum
Steel mesh top side element ø 06/150 mm Suppl. reinforcement ø 10/150 over walls is not shown Tlf. + 45 42 95 59 59
Drawing no 100
Weena Toren CL

1 2 3 4 5 6 7 8 9 10
Element plan
1:200
4500 3600 3600 3600 5400 3600 3600 3600 4500
Date 22.01.98

H
Elements (m) :

e1 3.0 x 9.00

e2 3.0 x 9.00/7.40

5400
e3 3.0 x 7,40

F e1 e1 e2 e3 e4 3.0 x 7,80

e5 3.0 x 6,90 special

3600
in situ
E

e4

e5
VIETCONS EDUCATION

e4 e4 e5

9000
e4

3600
C
e1 e2 e3

5400
www.vietcons.org

A J. BREUNING
Consulting Engineer
Rösevangen 8
DK-3520 Farum
Tlf. + 45 42 95 59 59
Weena Toren Yield line fig.
1 2 3 4 5 6 7 8 9 10 no. 7b
Basic Plan
1:200
4500 3600 3600 3600 5400 3600 3600 3600 4500
Date 17.07.97

H
4,0
3
2,
,2 C

5400
12 5 5,6 4,0
8,

2 B 8,0
6,
F
A 4,5

6
3,
1,2

3600
1,0 10,0
E
2,7
VIETCONS EDUCATION

9000
D

3600
C

5400
www.vietcons.org

A
J. BREUNING
Consulting Engineer
Rösevangen 8
DK-3520 Farum
Tlf. + 45 42 95 59 59
1,0 1,8 1,7 4,4

2,8 6,1

4,4 A

6,1 6
8,

8900
1,7

6,
5
B
4
VIETCONS EDUCATION

1,8 2,
2,8
C
1,0

7
1,

9,
4
11
,0
www.vietcons.org
VIETCONS EDUCATION www.vietcons.org

Example 4 Project Arup in Spain


VIETCONS EDUCATION www.vietcons.org
VIETCONS EDUCATION www.vietcons.org
VIETCONS EDUCATION www.vietcons.org
SPAIN

16200
16.2 20.1 22.0

14.3 (u=50%) 16.9 (u=60%)


0.25 0.35

11800 14850
Adjusted proposed system ARUP / SPAIN

1:50

2A 2C (= 2B’ with increased length) 2A 2C 2A 2C

16200
16200
16200

16200
16.9

20.1 22.0

16200
16200
16200

14.3
VIETCONS EDUCATION

16200
16200
16200

11800 14850 11800 14850 11800 14850

old system new system (or mirrored) new system


staggered columns
formal lines of
www.vietcons.org

distance between columns distance between columns max yielding and max deflexion

JB Consultancy
VIETCONS EDUCATION www.vietcons.org

Note 1 10-5-2009

Spain Arup structural options

rough investigation of mutual proportions between deflexions between different columns


assumed same EI over all

model 2A length diagonal 1 diagonal 2 cross m2/m1 (L2/L1)4

ca moment *) L 2 / 16 L 2 / 13 L 2 / 10 L 2/ 8

ca. deflection **) L 4 / 160 L 4 / 130 L 4 / 100 L 4 / 80

distance in m 16.2 20.1 14.3 11.8 17%

ratios m 430 1250 420 240 34%

in relation to cross 1.8 5.2 1.8 1.0

model 2C length diagonal 1 diagonal 2 cross

ca moment *) L 2 / 16 L 2 / 13 L 2 / 10 L 2/ 8

ca. deflection **) L 4 / 160 L 4 / 130 L 4 / 100 L 4 / 80

distance in m 16.2 22.0 16.9 14.8 35%

ratios m 430 1800 815 600 45%

in relation to cross 0.7 3.0 1.4 1.0

*) used likely moment ratios (only to adjust the pure L4 ratios) – but the conclusion is clear,
the capacity of the deck is improved more than 100%.

**) based on δ ≈ mL2 / 10


VIETCONS EDUCATION www.vietcons.org

Example 5 Test 9 x 12
VIETCONS EDUCATION www.vietcons.org

Example 5

TEST MODEL 340 mm BubbleDeck slab 9.0 x 12.0 m

Materials

Concrete f,ck = 35 MPa , f,cd = 35/1,5 = 23 MPa


Steel f,yk = 500-550 MPa , f,yd = 500/1,2 = 420 -

Load

BubbleDeck 340 mm g 5.4 kN/m2


uniform test load - up to q 10.0 -
--------------
ultimate load p 15.4 kN/m2

Rough calculation
Based on p as variable

Model A 9.0 x 12.0 m slab


supported on 4 columns
X direction = element direction

in Y-direction slab span L,y = 2.4– 7.2 – 2.4 m

cantilever L = 2.5 m
2
m’ = p * 2.4 / 2 = 2.9 p kNm/m

with p = 15.4 ultimate m’ = 15.4 * 2.9 = 45 kNm/m


covered by 2*3m Y12/150 m’ = 90 * 2 * 3.0 / 9.0 = 60 -
regular top mesh is ignored

inner bay L = 7.2 m


2
m,0 = p * 7.2 / 8 = 6.5 p kNm/m
m’ = 2.9 p -
m = 6.5 – 2.9 = 3.6 p -

1
VIETCONS EDUCATION www.vietcons.org

with p = 15.4 ultimate m = 15.4 * 3.6 = 55 kNm/m


covered by Y12/150 m = 90 -

in X-direction slab span L,x = 1.8 – 5.4 – 1.8 m

cantilever L = 1.8 m
2
m’ = p * 1.8 / 2 = 1.6 p kNm/m

with p = 15.4 ultimate m’ = 15.4 * 1.6 = 25 -


covered by 2*3m Y12/150 m’ = 90 * 2 * 3.0 / 12.0 = 45 -

inner bay L = 5.4 m


2
m,0 = p * 5.4 / 8 = 3.6 p kNm/m
m’ = 1.6 p -
m = 3.6 – 1.6 = 2.0 p -

with p = 15.4 ultimate m = 15.4 * 2.0 = 30 kNm/m


covered by Y10/150 m = 60 -

Shear
column D = 300 mm
load Q = 15.4 * 12.0 * 9.0 / 4 = 410 kN
massive τ = 0.41 / π (0.3 + 0.34) * 0.34 = 0.60 MPa
hollow τ = 0.60 / 0.6 = 1.00 MPa
in distance 0.9m hollow τ = 0.41 / π (0.3 + 0.6) 0.34 *0.6 = 0.70 MPa

2
VIETCONS EDUCATION www.vietcons.org

Test model / Vietnam


Plan 1:100
Reinforcement bottom side

Date 06.08.2008

Y14/300 lap splices bottom side Y14/150 Y14/300

1400 1400 1400 1400

1.8

Y10/150
Y12/150

5.4
D=1.5 m

1.8

5 elements
D=1.5 m 2.4 x 9.0 m
no bubbles free choice type A or type B

2,4 7,2 2,4

D=300
VIETCONS EDUCATION www.vietcons.org

Example 6 Parking
BubbleDeck International
Model A / 340 mm deck J. Breuning * Consult
Rösevangen 8
Columns in grid 12.0 x 12.0 m DK - 3520 Farum
Ph/fax +45 44 95 59 59
1:100

17,0

5.0 5.0 7,0 5,0


VIETCONS EDUCATION

12.0
www.vietcons.org
VIETCONS EDUCATION www.vietcons.org

Juni 2001

Parking – Model A

390 mm BubbleDeck slab

J. BREUNING
Consulting Engineer
Rösevangen 8
DK-3520 Farum
Tlf. + 45 42 95 59 59
VIETCONS EDUCATION www.vietcons.org

Overview

Temporary calculation

Enclosure 1 Material consumption

2 Yield line models

3 Cross section calculation

4 Moment- og deflection by total load

5 Moment- and deflection by permanent load

6 Shear calculation

Drawing 1 Ground profile 1:100

2 Inner section / plan & elevation 1:200

3 Inner section / plan of elements & top reinforcing columns

4 Shear reinforcing above columns

5 Detail of element

6 Deck geometry 1:4


VIETCONS EDUCATION www.vietcons.org

Inner section 16.0 x 16.0 m 340 mm BubbleDeck

CALCULATION BASIS

Materials (consumption : encl. 1)


Concrete f,ck = 35 MPa , f,cd = 35 /1.8 = 19 MPa
f,tk = 1.9 - f,td = 1.9/1.8 = 1.1 -
Steel f,yk = 550-560 MPa , f,yd = 56 /1.4 = 400 -

BD design moments
steel ø10 ø12 ø14 ø16 ø20 ø25 ø35
mom. kNm/m 60 86 117 153 240 375 735
used directly in the calculations

Load
BubbleDeck 340 mm g,0 = 7.30 kN/m2
Other load g,1 = 0.70 -
----------------------
Permanent load g = 8.00 kN/m2
Variable load q = 4.00 -
---------------------
Total load p 1.0 g + 1.0 q = 12.00 kN/m2
Design load
Danish. p,d = 1.0 g + 1.3 q = 13.20 -
p,a = 1.0 g + 0.5 q = 7.60 -

European p,d = 7.3 + 4.7 * 1.5 = 14.40 kN/m2


here the design moments can be raised

4
VIETCONS EDUCATION www.vietcons.org

Load on inner column

one deck Q,d = 14.4 * 16 * 16 = 3690 kN

column diameter, chosen D = 600 mm


compression column p,c = 1550 / π 0.2 2
= 12340 kN/m2
radius slab yield cirkel R = 0.2 (12340 / 10.8) 1/3 = 2.1 m
Extension topside reinf. a = 2.1 + 0.9 = 3.0 -

necessary moment
at column ø 400 ms + m’s = 3690 / 2π (1 + 5 * 0.3 / 16) = 537 kNm/m

choice of effective moment


bottom min. 2ø14/175 ms = 240 kNm/m
top min. ø 8+20/175 m’s ≈ 38 + 240 = 280 -
ms + m’s ≈ 240 + 280 = 520 -

Shear stress at column


estimated column diameter D = 400 mm
max column load P,1 = 1.55 MN
shear stress column τ,sol = 1.55 / π (0,4 + 2 * 0.34) 0.34 = 1.34 MPa
allowed without reinforcing t,35 = 0.133 * 35 0,5 = 0.79 -

concrete 35 MPa can easily be reinforced.


calculation is shown in encl. 7.
balls left out r = 1.5 m t,holl = 1.55 / 2 π 1.5 * 0.34 * 0.6 = 0.81 MPa

Bearing capacity / Moment distribution

after axis L = 16.0 – 0.4 = 15.6 m


simple slab moment max m,0 = 14.4 *15.6 2/ 8 = 440 kNm/m
support moment ø8+ø 20 (8m) m’ = 38 + 240 *8 / 16 = 160 -
max. m,d = 440 - 160 = 280 -
bottom ø12/150 m = 86 -
(girder ø10/600 m = 60 * 0.15/ 0.60 = 15 -)

simple slab moment min m,0 = 185 *5.6 / 10.8 = 95 kNm/m


support moment max m’ = = 115 -
min. m,d = 95 - 115 = - 20 -
top ø 8/150 m’ = - 38 -
5
VIETCONS EDUCATION www.vietcons.org

Deflection – inner section

is estimated in the elastic stage – with the load distributed in both directions (symmetry).

Short term deflection

is estimated for
span, between axis L = 12.0 – 0.3 = 11.7 m
diagonal L = 12.0 * 1.41 – 0.3 = 16.6 -

and the moment distribution (elastic)


average m m,0 < q * L 2 / 12 = q * 12
and final deflection u ≈ 1.5 * u (average)

permanent load (g) , encl. 4 m,0 = 12 * 5.6 = 67 kNm/m


steel m’ = 115 -
more than 100% fixed eff. m’ ≈ 67 * 2 / 3 = 45 -

load (g + q/2) , encl. 5 m,0 = 12 * 7.6 = 91 kNm


steel m’ = = 115 -
more than 100% fixed eff. m’ = 91 * 2 / 3 = 60 -

total load (g + q) , encl. 6 m,0 = 12 * 9.6 = 115 kNm/m


steel m’ = 115 -
more than 100% fixed eff. m’ = 115 * 2 / 3 = 77 -

calculation is shown for


load g+ q g + q/2

deflection with factor 1.5 u,d = 1.5 * 5.0 8 xx mm


deflection permanent load u,g = 1.5 * 2.4 4 xx -
------------------------
deflection variable load 4 x
mm
less than L/500 = 16600 / 500 = 33 mm
control
full elastic u (g+q),x = 9.6 * 11.7 4 / 549 * 76.7 = 4 mm
u diag = 4 * 1.5 = 6 -
ok.
VIETCONS EDUCATION www.vietcons.org

Steel consumption

Model B 450 mm deck - 16 x 16 m

Steel 500-550 MPa

steel bottom y 14/100 24.8 kg/m2


steel top y 10/200 6.3 - 31.1 kg/m2
---------------

girders per 600 y 8/10 1.9 / 0.6 = 3.2 -


---------------
elements 34.3 kg/m2

on site (estimated)

lap splices 15% of 31.1 = 4.7 kg/m2


top mesh columns y 16/150 25.4 * 8 2 / 16 * 16 = 6.4 -
shear reinforcement = 1.0 -
--------------
total 46.4 kg/m2
BubbleDeck International
Model B / 280 mm deck J. Breuning * Consult
Rösevangen 8
Columns in grid 9.6 x 9.6 m (or less) DK - 3520 Farum
Ph/fax +45 44 95 59 59
1:100
17,1

5,0 5,0 7,1 5,0


VIETCONS EDUCATION

9.6
www.vietcons.org

9.6 7.5 4.8


VIETCONS EDUCATION www.vietcons.org

Juni 2002

Parking – Model B.1

280 mm BubbleDeck slab

J. BREUNING
Consulting Engineer
Rösevangen 8
DK-3520 Farum
Tlf. + 45 42 95 59 59
VIETCONS EDUCATION www.vietcons.org

Overview

Temporary calculation

Enclosure 1 Material consumption

2 Yield line models

3 Cross section calculation

4 Moment- og deflection by total load

5 Moment- and deflection by permanent load

6 Shear calculation

Drawing 1 Ground profile 1:100

2 Inner section / plan & elevation 1:200

3 Inner section / plan of elements & top reinforcing columns

4 Shear reinforcing above columns

5 Detail of element

6 Deck geometry 1:4


VIETCONS EDUCATION www.vietcons.org

Inner section 9.6 x 9.0 m 280 mm BubbleDeck

CALCULATION BASIS

Materials (consumption : encl. 1)


Concrete f,ck = 35 MPa , f,cd = 35 /1,8 = 19 MPa
f,tk = 1.9 - f,td = 1.9/1,8 = 1,1 -
Steel f,yk = 550-560 MPa , f,yd = 56 /1,4 = 400 -

BD design moments
steel ø10 ø12 ø14 ø16 ø20 ø25 ø35
mom. kNm/m 60 86 117 153 240 375 735
used directly in the calculations

Load
BubbleDeck 280 mm g,0 = 4.50 kN/m2
Other load g,1 = 0.20 -
----------------------
Permanent load g = 4.70 kN/m2
Variable load q = 4.00 -
---------------------
Total load p 1.0 g + 1.0 q = 8.70 kN/m2
Design load p,d = 1.0 g + 1.3 q = 9.90 -
p,a = 1.0 g + 0.5 q = 6.70 -

4
VIETCONS EDUCATION www.vietcons.org

Load on inner column

One deck Q,d = 9.90 * 9.6 * 9.0 = 850 kN

column diameter, chosen D = 400 mm


compression column p,c = 850 / π 0.2 2
= 6770 kN/m2
radius circle yield line R = 0.2 (6770 / 9.9) 1/3 = 1.8 m
Extension topside reinf. a = 1.8 + 0.7 = 2.5 -

necessary moment
at column ø 400 ms + m’s = 850 / 2π (1 + 5 * 0.2 / 9.3) = 122 kNm/m

choice of effective moment


bottom min. ø10/125 ms ≈ = 60 kNm/m
top min. ø6+12/125 m’s ≈ 21 + 86 = 107 -
ms + m’s ≈ 60 + 107 = 167 -

Shear stress at column


estimated column diameter D = 400 mm
max column load P,1 = 0.85 MN
shear stress column τ,sol = 0.85 / π (0.4 + 2 * 0.28) 0.28 = 1.00 MPa
allowed without reinforcing t,35 = 0.133 * 35 0,5 = 0.79 -

concrete 35 MPa can easily be reinforced.


calculation is shown in encl. 7.
balls left out r = 1.0 m t,holl = 0.85 / 2 π 1.0 * 0.28 * 0.6 = 0.80 MPa

Bearing capacity / Moment distribution


after axis max L = 9.6 – 0.3 = 9.3 m

simple slab moment max m,0 = 9.9 * 9.3 2/ 8 = 107 kNm/m


support moment ø6+ø12 (5m) m’ = 21 + 86 * 5 / 8.5 = 70 -
max. m,d = 107 - 70 = 37 -
bottom ø10/125 m = 60 -
(girder ø10/750 m = 60 * 0.125/ 0.75 = 10 -)

simple slab moment min m,0 = 107 * 4.7 / 9.9 = 50 kNm/m


support moment max m’ = = 70 -
min. m,d = 50 - 70 = - 20 -
top ø 6/125 m’ = - 21 -

5
VIETCONS EDUCATION www.vietcons.org

Deflection – inner section

is estimated in the elastic stage – with the load distributed in both directions (symmetry).

Short term deflection

is estimated for
span, between axis L = 9.6 – 0.3 = 9.3 m
diagonal L = 12.0 * 1.41 – 0,3 = 16.6 -

and the moment distribution (elastic)


average m m,0 < q * L 2 / 12 = q * 12
and final deflection u ≈ 1.5 * u (average)

permanent load (g) , encl. 4 m,0 = 12 * 4.7 = 56 kNm/m


steel m’ = 70 -
more than 100% fixed eff. m’ ≈ 56 * 2 / 3 = 37 -

load (g + q/2) , encl. 5 m,0 = 12 * 6.7 = 80 kNm


steel m’ = = 70 -
more than 100% fixed eff. m’ = 80 * 2 / 3 = 53 -

total load (g + q) , encl. 6 m,0 = 12 * 8.7 = 105 kNm/m


steel m’ = 70 -
equal to 100% fixed eff. m’ = 105 * 2 / 3 = 70 -

calculation is shown for


load g+ q g + q/2

deflection total load u,p = 4.4 xx mm


deflection permanent load u,g = 2.5 xx -
------------------------
deflection variable load u,q 2 x
mm
less than L/500 = 9300 / 500 = 19 mm
diagonal u,q = 2 * 1.5 = 4 mm
ok.
VIETCONS EDUCATION www.vietcons.org

Model B 280 mm deck - Steel consumption

Steel 500-550 MPa

steel bottom y 10/125 10.2 kg/m2


steel top y 6/125 3.6 - 13.8 kg/m2
---------------

girders per 750 y 8/10 1.9 / 0.75 = 2.5 -


---------------
elements 16.3 kg/m2

on site (estimated)

lap splices 15% of 20.8 = 3.1 kg/m2


top mesh columns y 12/125 14.6 * 5 2 / 8.5 * 9.6 = 4.5 -
shear reinforcement = 1.0 -
--------------
total 24.9 kg/m2
VIETCONS EDUCATION www.vietcons.org

Example 8 Moment Curves, India


VIETCONS EDUCATION www.vietcons.org

Plan Test model


1:100 280 mm BubbleDeck

Slab supported along periphery by bearing walls

2100
6000

3700
80
50
B
30 (25) 30
40 (45)

3700
6000

2100
A

6000 6000 6000


1 2 3

80
BubbleDeck International
Rösevangen 8
DK - 3520 Farum
40 (45)
Ph/fax +45 44 95 59 59
Project model B

390 mm BubbleDeck
Slab is supported along periphery by columns

Yield lines (max. moment)


1:200

5000

C
12 Y25 2000

5000 4400

m,x

12250
7400

4000
VIETCONS EDUCATION

B
3600

m’=2m
3700
7400

m,x

12250
m,y
4400
www.vietcons.org

A
BubbleDeck International
10800 10800 10800 Rösevangen 8
DK - 3520 Farum
1 2 3 4 Ph/fax +45 44 95 59 59
Project model C

280 mm BubbleDeck Slab supported exclusively by columns and stair walls

Yield lines (max. moment)


1:200

2400 3600
C
m,xo
2400

2400
3600
3900

m,xi

12250
9850

5900

m’=2m
VIETCONS EDUCATION

4000

m,yi

m,yo

12250
2400
www.vietcons.org

A
2400 BubbleDeck International
3400 5000
Rösevangen 8
8400 10800 10800 DK - 3520 Farum
1 2 3 4 Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org

Example 9 Project Herstedlund in Denmark


VIETCONS EDUCATION www.vietcons.org

September 2007

Herstedlund Fælleshus

Dokumentation af bæreevne
390 mm BubbleDeck

BubbleDeck Danmark ApS


Rösevangen 8
DK-3520 Farum
Tlf. + 45 42 95 59 59
VIETCONS EDUCATION www.vietcons.org

Indholdsfortegnelse side 2

390 mm dæk

Beregningsforudsætninger og antagelser 3
Lastgrundlag for beregning 4
Nødvendige undersøgelser 5
Udhæng 5
Selvbærende udhængende pladefelt 6
Indre fag / mellemfag 7
Revnevidder 7
Forskydning v. vægge 8
Søjler 9
Nedbøjninger 11

Bilagene 3.... viser spændingstilstanden i de aktuelle dæk ved designlast


4.... viser moment- og nedbøjningsforløb for egenlast (hvis relevant)
5..... viser moment- og nedbøjningsforløb for last g+q/2 (hvis relevant)
6..... viser moment- og nedbøjningsforløb for last g+q (hvis relevant)
7..... viser forskydning samt armering omkring søjler

Arbejds skitser til støtte for beregninger og endfelige tegninger


1. undersøgte overside momenter
2. undersøgte underside momenter
3. anvendt last(areal) for søjler
4. forskydnings armering ved indvendig søjle G7
5. forskydnings armering ved facade søjle G2
6. vridnings armering ved skævt udhængende pladefelt

Skitserne må forventes korrigeret i endeligt projekt


VIETCONS EDUCATION www.vietcons.org

BEREGNINGSFORUDSÆTNINGER

DS 410 , DS 411 1999


Sikkerhedsklasse normal
Kontrolklasse normal
med opgradering til BubbleDeck international standard
svarende til EC 2 for så vidt angår materiale- og styrke parametre
dette grundlag ligger over DS sikkerhed

Materialer , sikkerhedskoefficienter & regningsmæssige værdier

Beton f,ck = 35 MPa , f,cd = 35 /1,5 = 23 MPa


f,tk = 1,9 - f,td = 1,9 /1,5 = 1,3 -
Stål f,yk = 500-550 MPa , f,yd = 500 /1,2 = 420 -
Last f,g = 1,2
f,q = 1,5

BD design momenter ved 2 stål per basismodul 350 mm (γ,s = 1,2 og γ,c = 1,5)

stål mm ø6 ø8 ø10 ø12 ø14 ø16 ø20 ø25


moment kN 20 40 60 90 120 160 240 360

afrundede værdier, anvendes direkte i beregningerne – afrundinger uden mærkbar indflydelse


anvendte stål ø10, ø14, ø20 kan direkte ombyttes gennem halvering eller fordobling af antal

Bemærkninger

Bilagene 3... viser spændingstilstanden i dækket ved understøtninger og i feltmidte ved design last.
Betonkonstanter ændres ikke ved lavere last (arbejdslast).
Der regnes med 100% fri nyttelast. Filigrandragere er ikke medtaget i beregningerne.
Under hensyn til dækkets størrelse udføres alle elementer med ens armering.
Der kan forekomme små afvigelser i målsætning - men disse er uden betydning.
Der arbejdes meget groft og på den sikre side – overalt ud fra modullinier.
VIETCONS EDUCATION www.vietcons.org

Regningssmæssige Laster

Dæk over stue


BubbleDeck 390 mm g,0 = 25,0 * 0,39 * 0,65 = 6,3 kN/m2
extra påstøbning 60 mm g,1 = 1,5 -
anden hvilende last g,1 = 1,0 -
-----------------------
permanent last Σ g,k = 8,8 kN/m2
oplyst variabel last (ψ = 0,5) q,k = 5,0 -
-----------------------
karakteristisk last sum p,k = 1,0 g + 1,0 q = 13,8 kN/m2

design last p,d = 1,2 * 8,8 + 1,5 * 5,0 = 18,0 kNm/m2


arbejdslast 50%qk p,w = 1,0 * 8,8 + 0,5 * 5,0 = 11,3 –
eller p,w/p,d = 11,3 / 18,0 = 0,63

Façader oplyst g = 4,6 kN/m


p,d = 4,6 * 1,2 = 5,5 -

Trappe oplyst g = 2,7 kN/m


q = 8,7 -
design last p = 1,2 * 2,7 + 1,5 * 8,7 = 16,3 -

Lygtebom q = 1,0 kN/m


kan ignoreres
såvel med hensyn til størrelse som med hensyn til placering
VIETCONS EDUCATION www.vietcons.org

Nødvendige undersøgelser

Under hensyn til fladestørrelse og planløsning anvendes samme dæk overalt.


Det skønnes derfor tilstrækkeligt at undersøge følgende i etageadskillelse 1

Kritiske/dimensionsgivende områder er

1. 3,8 m udhæng generelt - felt G-I


2. udhæng hjørne 5,3 m - over søjle modul G-7, se 4. og nedbøjning
3. selvbærende pladefelt HI-12 - vridning i frit indadgående hjørne
4. største søjlekraft og moment - over søjle modul G-7
5. søjler, forskydning og moment i dæk - ved facadesøjle G-2
6. største positive moment i ”mellemfag” - modul 2-7
7. negativt moment i ” mellemfag” - modul 2-7

1. Udhæng se skitse 1
plademomenter generelt
spænd L = 3,8 m
dæk i middel m’ = 18,0 * 3,8 2 / 2 = 130 kNm/m
facade + 5,5 * 3,8 = 20 -
-----------------------
m,udh = 150 kNm/m
armering overside i een stribe á 7,5 m (1 søjle)
4Y8/350 + 2Y20/350 (over 4,0m)
giver disponibelt m = 2 * 40 + 240 * 4,0 / 7,5 = 210 kNm/m

i afstand fra rand L = 3,8 – 2,0 = 1,8 m


m = 18,0 * 1,8 2 / 2 + 5,5 * 1,8 = 40 kNm/m
4Y8/350 m = 80 -

2. Hjørne
moment m,skrå = m,udh * 0,7 = 105 kNm/m
nedbøjning u,skrå = u,udh * 1,4 se nedbøjning
VIETCONS EDUCATION www.vietcons.org

3. Selvbærende plademodul ca. 1,7 x 1,7 m se skitse 1 og 6

trappe (skønnet bredde 1,2 m) p = 16,3 * 1,2 / 1,7 = 11,5 kN/m


svarende til 2 x facade á p = 5,5 -
moment i snit linie 2
façade og trappe m’ = 5,5 (3 * 1,9 2 * 0,5 /1,7 + 1,9) = 28 kNm/m
dæk + 18 * 1,9 2 * 0,5 = 15 -
total moment i linie 2 m’ = 28 + 15 = 43 -
født oversidearmering 2Y6/175 m’ = 2 * 20 = 40 -
der lægges ekstra Y10/175 m’ = 60 -

momentet betyder et vridende moment i pladedel 1-9, G-I om søjleunderstøtningslinie G


med punktunderstøtninger i G2 og G7.
bøjende moment over feltbredde B = = 1,7 m
giver totalt vridningsmomentet V = 43 * 1,7 = 73 kNm
vridningen vil kunne spredes over væsentlig større dækbredde men af simple og praktiske
hensyn regnes vridningen formelt optaget og armeret for i eet BD-modul, der kan lignes med
et prismatisk rør (der kan regnes både kvadratisk og cirkulært) og
med randareal bestemt ved A = 0,39 2 – 0,25 π * 0,315 = 0,074 m2
og middeltykkelse hvis cirkel t = 0,074 / π * 0,35 = 0,067 m
hvis kvadrat t = 0,074 / 4 * 0,35 = 0,053 -
hvilket giver forskydn.spænding ν,b = 0,073 / 2 π * 0,175 2 * 0,067 = 5,67 MPa
2
henholdsvis ν,b = 0,073 / 2 * 0,35 * 0,053 = 5,62 -
ok. der regnes ν,b = 5,65 -
mindre end
tilladeligt skrå tryk i cellevægge σ,d = ν,t * f,cd = 0,7 (0,7 – f,ck / 200) f,cd
= 0,7 (0,7 – 35 / 200) 23 = 8,55 Mpa
der indlægges et rørgitter af bjl Y14/175 med Y20 i hjørner
der ses bort fra netarmering i over- og underside
bøjler A,w = 154 / 175 = 0,88 mm2/mm
længdejern A,L = 1260 / 4 * 350 = 0,90 -
disp. V = E -6 * 2 *350 2 (0,88*0,90) 0,5 * 420 = 92 kNm
større end V,d = 73 -
VIETCONS EDUCATION www.vietcons.org

4 Længste mellemfag se skitse 2

L = 5 * 1670 – 450 - 250 = 7,7 m


max m,0 = 18,0 * 7,7 2 / 8 = 130 kNm/m
overførte negative momenter
egenlast udhæng min m’1 = 8,8 * 3,8 2 / 2 + 4,6 * 3,8
= 63 + 17 = - 80 kNm/m
min m’2 = 4,6 * 0,4 = 0 -
resulterende max m = 130 – (80 + 0) 0,5 = 90 -
4Y10/350 underside m = 2 * 60 = 120 -
tilstrækkeligt – samme armering i begge retninger

min m,0 = 8,8 * 7,7 2 / 8 = 65 kNm/m


fra udhæng max m’1 = 18,0 * 3,8 2 / 2 + 5,5 * 3,8
= 130 + 21 = 150 kNm/m
max m’2 = 5,5 * 0,4 = 0 -
resulterende min m = 65 – (150 + 0) 0,5 = - 10 -
4Y8/350 overside kan tage m = 2 * 40 = - 80 -
tilstrækkeligt – samme i begge retninger

Revnevidder i h.t. DS 411 afsn. 6.3

miljø - passivt (afdækket)


der undersøges for max forekommende moment - i overside over søjler se søjler
momenter i underside i indvendige felter er nær 0.

aktivt betonareal A,cef = 1000 * 60 = 60 000 mm2/m


sum af ståldiametre ∑ d,w = (4 * 8 + 2 * 20) / 0,35 = 206 mm/m
revneparameter a,w = 60 000 / 206 = 290
stålsp. g+0,5q (bilag 3s,d) σ,swL = 240 * 11,3 / 18,0 = 150 MPa
max. revnevidde w = 5 * 10 – 5 σ,s (a,w) 0,5
= 5 E-5 * 150 * 290 0,5 = 0,13 mm
VIETCONS EDUCATION www.vietcons.org

Forskydning – vægge i trapperum

der forekommer ingen udprægede hjørner


lasten regnes jævnt fordelt max Q = 18,0 * 6,8 * 0,5 = 60 kN/m
hul τ = 0,06 / 0,39 * 0,8 * 0,6 = 0,32 MPa
(indre højde i BD er 0,8 h og red.faktor BD er 0,6)
ok - een række kugler udelades (standard)
ved de 2 vægsøjler indlægges i element et (standard) forskydningsgitter, jf. søjler
armering er gennemgående over vægge, ingen særskilt forankring

5 Søjler se skitse 3, 4 og 5

max søjle last i G7 S = 18,0 (7,7*0,6 + 3,8)(6,9*0,6 + 3,8)


+ 5,5 (2 * 3,8 + (6,9 + 7,7) 0,5) = 1280 kN

façade søjle G2 (uden knast) S = 18,0 (7,7*0,5 + 0,3)(6,9*0,6 + 3,8)


se selvbær. pladefelt (knast) + 18,0 * 1,9 * 1,9 + 3 * 1,9 * 5,5 = 690 kN

tillægsreaktioner fra vridning ΔR = 73 / 7,7 = 10 kN


uden betydning

Moment omkring søjler se skitse 3

armering udføres ens over søjler


nødvendig (KWJ) m,s + m’s = P / 2π (1 + 5 * c / L )
= 1280 / 2π (1 + 5 * 0,15 / 7,5) = 185 kNm/m
langtids spændingstilstand er vist i excel bilag 3sd-L

u.s. min. 4Y10/350 m,s = 2 * 60 = 120 -


o.s. 4Y8/350 + 2Y20/350 m’s = 2 * 40 + 240 = 320 -
disponibel min. m,s + m’s = 120 + 320 = 440 -
tværsnittet er normaltarmeret jf. excel bilag 3su-k
VIETCONS EDUCATION www.vietcons.org

Forskydning omkring søjler

Søjle G2 se skitse 5

der regnes uden nedtrapning af last P = 690 kN

der armeres med forskydningsgitre af bjl Y14/175 se skitse 3 og 4


gitteret tager per snit/bjl (0,30 x 0,175m) Q = 154 * 2 * 0,42 = 130 kN

forskydningsperimeter måles midt brudkegle

første snit r = 0,35m brudkegle 0,15 – 0,55m


giver forsk.perimeter u,350 = (0,15 + 0,20) π + 2 * 0,3/2 = 1,40 m
og forskydningsareal A,350 = 1,40 * 0,39 = 0,55 m2
max massiv τ = 0,69 / 0,55 = 1,3 Mpa
mindre end τ = 0,25 * f,cd = 0,25 * 23 ≈ 6,0 -
og mindre end τ = 0,5 * f,cds = 0,5 * 12 ≈ 6,0 -

i afst. r = 0,75m brudkegle 0,55 – 0,95m


u,750 = 0,75 π + 0,3 = 2,65 m
A,750 = 2,65 * 0,39 = 1,05 m2
massiv τ = 0,69 / 1,05 = 0,66 Mpa

i afst. r = 1,15m brudkegle 0,95 – 1,35m


u,1150 = 1,15 π + 0,3 = 3,90 m
A,1150 = 3,90 * 0,39 = 1,50 m2
massiv τ = 0,69 / 1,50 = 0,46 Mpa
hul τ = 0,69 / 1,50 * 0,6 = 0,77 Mpa
hult tværsnit ok
mindre end tilladeligt τ = 0,12 ν f,cd
= 0,12 * 0,34 * 23 = 0,94 MPa
udtrykket for τ er på den sikre side, idet det mormmæssigt er knyttet til ydre periferi i brudkegle
og ikke som her anvendt middelsnit.
VIETCONS EDUCATION www.vietcons.org

10

Søjle G7 se skitse 4
se også excel kontrol bilag 7

første snit r,u = 0,35m brudkegle 0,15 – 0,55m


giver forsk.perimeter u,0,35 = 0,35 * 2 π = 2,20 m
og forskydningsareal A0,35 = 2,20 * 0,39 = 0,85 m2
max massiv τ = 1,28 / 0,85 = 1,50 Mpa

mindre end τ = 0,25 * f,cd = 0,25 * 23 ≈ 6,0 MPa


og mindre end τ = 0,5 * f,cds = 0,5 * 12 ≈ 6,0 -

i afst. r,u = 0,75m brudkegle 0,55 – 0,95m


u,0,75 = 0,75 * 2 π = 4,70 m
A,0,75 = 4,70 * 0,39 = 1,84 m2
massiv τ = 1,28 / 1,84 = 0,70 Mpa
udføres massivt

i afst. r,u = 1,15m brudkegle 0,95 – 1,35m


u,1,15 = 1,15 * 2 π = 7,20 m
A,1,15 = 7,20 * 0,39 = 2,80 m2
massiv τ = 1,28 / 2,80 = 0,45 Mpa
hul τ = 0,45 / 0,6 = 0,75 Mpa
tillades hult
τ mindre end tilladeligt τ = 0,12 ν f,cd
= 0,12 * 0,34 * 23 = 0,94 Mpa

de beregnede felter og overgangene mellem dem er jævnt dækket


VIETCONS EDUCATION www.vietcons.org

11

Nedbøjninger
Der vurderes kun deformationer (vinkeldrejninger undersøges ikke).
I bilagene 3 er angivet betondata, spændinger og tøjninger i relevante lastsituationer.
I bilagene 4 vises nedbøjning for egenlast/permant last (hvor det skønnes nødvendigt). Udgår
I bilagene 5 er angivet nedbøjning for arbejdslast/sædvanlig last (g + 0,5 q)
Langtids nedbøjning kan med tilstrækkelig nøjagtighed regnes 3,5 gange korttids nedbøjningen.
Kun udhæng/hjørner har egentlig interesse. Kun langtids vurdering er relevant.

Udhæng 3,8 m se excel bilag 3ud-L og 5u-L


middelnedbøjning beregnet for arbejdslast (w)
dæk p,w = 18,0 * 0,63 = 11,3 kN/m
facade P,g = = 4,6 kN
udhæng L = 3,8 m
bilag 5u_L u,w = 10 mm
urevnet tværsnit u,g ≈ 10 * 8,8 / 11,3 = 8 -
bevægelig last u,q/2 = 10 – 8 = 2 -
korttids kan regnes u,w = 10 / 3,5 = 3 -
støbes med pilhøjde f ≈ 7 -

Hjørner kan regnes u,wL = 1,4 * 10 ≈ 14 mm


kontrol excel bilag 5u,hj-L

Indre felt excel bilag 3md-L og 5m-L

bilag 5m_L u,w = 5 mm


urevnet tværsnit u,g ≈ 5 * 8,8 / 11,3 = 3 -
bevægelig last u,q/2 = 2 -
korttids u,w = 5 / 3,5 = 1 mm

Yderligere undersøgelser er overflødige

19.09.2007
Jorgen Breuning
VIETCONS EDUCATION www.vietcons.org

Bilag 3sd_L
Herstedlund

Tværsnitsanalyse plade over søjler - designlast - langtid

Basis for calculation :


modulus of elasticity E,c = E,s / 5,6 (1 + 13 / f,ck) = 35 700 / (1 +13 / f,ck)
uncracked section EI,c = E,c * 0,9 * b * h pot3 / 12
cracked section EI,w = 0,33 * E,c * y pot3 + A' * E,s (y - 0,125 h,e) pot2 + A * E,s (h,e - y) pot2
cracking moment m,w = (0,1 * f,ck) pot 0,5 * h pot2 / 3
neutral axis y = is found by iteration until (T- C) = 0

Choice
m(g+q/2) MNm 0,170
f,ck MN/m2 35
f,yk MN/m2 550
E,s MN/m2 200000
E,c MN/m2 7407
A,s m2 E-6 2376 4Y8/350 2Y20/350
A',s m2 E-6 900 4Y10/350
h m 0,390
h,e m 0,350
Calculation
estimate y m 0,1280 0,1281 0,1282 0,1283 0,1284 0,1285 0,1286 0,1287 0,1288 0,1289
h,c=0,8y m 0,1024 0,1025 0,1026 0,1026 0,1027 0,1028 0,1029 0,1030 0,1030 0,1031
h,int m 0,2988 0,2988 0,2987 0,2987 0,2986 0,2986 0,2986 0,2985 0,2985 0,2984
C MN 0,569 0,569 0,569 0,569 0,569 0,569 0,569 0,569 0,570 0,570
stress,c MN/m2 5,19 5,19 5,18 5,18 5,18 5,18 5,17 5,17 5,17 5,16
strain,c 0,00070 0,00070 0,00070 0,00070 0,00070 0,00070 0,00070 0,00070 0,00070 0,00070
strain,s 0,00122 0,00121 0,00121 0,00121 0,00121 0,00120 0,00120 0,00120 0,00120 0,00120
stress,s MN/m2 243 243 242 242 241 241 240 240 240 239
T MN 0,578 0,577 0,575 0,574 0,573 0,572 0,571 0,570 0,569 0,568
T-C MN 0,0086 0,0075 0,0064 0,0053 0,0041 0,0030 0,0019 0,0008 -0,0003 -0,0015
EI,c MNm2 33,0 33,0 33,0 33,0 33,0 33,0 33,0 33,0 33,0 33,0
EI,w MNm2 29,8 29,8 29,8 29,8 29,8 29,8 29,8 29,8 29,8 29,8
m,w kNm/m 94,9 94,9 94,9 94,9 94,9 94,9 94,9 94,9 94,9 94,9
VIETCONS EDUCATION www.vietcons.org

Bilag 3su_k
Herstedlund

Tværsnitsanalyse plade over søjler - ultimativ last - kort tid

Basis for calculation :


modulus of elasticity E,c = E,s / 5,6 (1 + 13 / f,ck) = 35 700 / (1 +13 / f,ck)
uncracked section EI,c = E,c * 0,9 * b * h pot3 / 12
cracked section EI,w = 0,33 * E,c * y pot3 + A' * E,s (y - 0,125 h,e) pot2 + A * E,s (h,e - y) pot2
cracking moment m,w = (0,1 * f,ck) pot 0,5 * h pot2 / 3
neutral axis y = is found by iteration until (T- C) = 0

Choice
m(g+q/2) MNm 0,320
f,ck MN/m2 35
f,yk MN/m2 550
E,s MN/m2 200000
E,c MN/m2 26031
A,s m2 E-6 2376 4Y8/350 2Y20/350
A',s m2 E-6 900 4Y10/350
h m 0,390
h,e m 0,350
Calculation
estimate y m 0,0740 0,0741 0,0742 0,0743 0,0744 0,0745 0,0746 0,0747 0,0748 0,0749
h,c=0,8y m 0,0592 0,0593 0,0594 0,0594 0,0595 0,0596 0,0597 0,0598 0,0598 0,0599
h,int m 0,3204 0,3204 0,3203 0,3203 0,3202 0,3202 0,3202 0,3201 0,3201 0,3200
C MN 0,999 0,999 0,999 0,999 0,999 0,999 1,000 1,000 1,000 1,000
stress,c MN/m2 15,04 15,03 15,01 14,99 14,98 14,96 14,94 14,93 14,91 14,90
strain,c 0,00058 0,00058 0,00058 0,00058 0,00058 0,00057 0,00057 0,00057 0,00057 0,00057
strain,s 0,00216 0,00215 0,00214 0,00214 0,00213 0,00213 0,00212 0,00211 0,00211 0,00210
stress,s MN/m2 431 430 429 427 426 425 424 423 422 420
T MN 1,024 1,021 1,018 1,016 1,013 1,010 1,007 1,004 1,002 0,999
T-C MN 0,0254 0,0224 0,0194 0,0165 0,0135 0,0106 0,0076 0,0047 0,0018 -0,0011
EI,c MNm2 115,8 115,8 115,8 115,8 115,8 115,8 115,8 115,8 115,8 115,8
EI,w MNm2 39,8 39,8 39,8 39,8 39,8 39,8 39,8 39,8 39,8 39,7
m,w kNm/m 94,9 94,9 94,9 94,9 94,9 94,9 94,9 94,9 94,9 94,9
VIETCONS EDUCATION www.vietcons.org

Bilag 3ud_L
Herstedlund

Tværsnitsanalyse plade i udhæng - designlast - langtid

Basis for calculation :


modulus of elasticity E,c = E,s / 5,6 (1 + 13 / f,ck) = 35 700 / (1 +13 / f,ck)
uncracked section EI,c = E,c * 0,9 * b * h pot3 / 12
cracked section EI,w = 0,33 * E,c * y pot3 + A' * E,s (y - 0,125 h,e) pot2 + A * E,s (h,e - y) pot2
cracking moment m,w = (0,1 * f,ck) pot 0,5 * h pot2 / 3
neutral axis y = is found by iteration until (T- C) = 0

Choice
m(g+q/2) MNm 0,150
f,ck MN/m2 35
f,yk MN/m2 550
E,s MN/m2 200000
E,c MN/m2 7407
A,s m2 E-6 1534 4Y8/350 2Y20/350 x 4,0/7,5
A',s m2 E-6 900 4Y10/350
h m 0,390
h,e m 0,350
Calculation
estimate y m 0,1070 0,1071 0,1072 0,1073 0,1074 0,1075 0,1076 0,1077 0,1078 0,1079
h,c=0,8y m 0,0856 0,0857 0,0858 0,0858 0,0859 0,0860 0,0861 0,0862 0,0862 0,0863
h,int m 0,3072 0,3072 0,3071 0,3071 0,3070 0,3070 0,3070 0,3069 0,3069 0,3068
C MN 0,488 0,488 0,488 0,488 0,489 0,489 0,489 0,489 0,489 0,489
stress,c MN/m2 5,26 5,26 5,25 5,25 5,25 5,24 5,24 5,23 5,23 5,23
strain,c 0,00071 0,00071 0,00071 0,00071 0,00071 0,00071 0,00071 0,00071 0,00071 0,00071
strain,s 0,00161 0,00161 0,00161 0,00160 0,00160 0,00160 0,00159 0,00159 0,00159 0,00158
stress,s MN/m2 323 322 321 321 320 319 319 318 317 317
T MN 0,495 0,494 0,493 0,492 0,491 0,490 0,489 0,488 0,487 0,486
T-C MN 0,0066 0,0055 0,0045 0,0034 0,0023 0,0012 0,0001 -0,0009 -0,0020 -0,0031
EI,c MNm2 33,0 33,0 33,0 33,0 33,0 33,0 33,0 33,0 33,0 33,0
EI,w MNm2 21,8 21,8 21,8 21,8 21,8 21,8 21,8 21,8 21,8 21,8
m,w kNm/m 94,9 94,9 94,9 94,9 94,9 94,9 94,9 94,9 94,9 94,9
VIETCONS EDUCATION www.vietcons.org

Herstedlund Bilag 5u-L

Moment & nedbøjning 3,8 m pladefelt - brugslast , langtid

Moment is given by m,x = - P*L (1-x/L) - 0,5 p*L*L (1-x/L) (1-x/L)


Curvature is estimated as m,x / EI,c if m,x < m,w
m,w / EI,c + 1,3 ((m,x-m,w) / EI,w) if < m,x / EI,w and if m,x > m,w

m,0 = 0,00 kN EI,w = 0 Span L = 3,8 m Steel b.s. xxx mm2 ø 10


P = 4,6 kN/m EI,w = 21,8 MNm Height h = 390 mm Steel t.s. xxx mm2 ø 8 +
p = 11,3 kN/m EI,w = 21,8 MNm Column ø 400 mm Steel t.s. xxx mm2 (ø 00)
m,w = 95 kN/m EI,c = 33,0 MNm2 Concrete 35 MPa

section load mom. crack. mom. curvature increase inclination defl. increase deflection deflection
x/L m,g+q/2 m,w (-) m/EI dv = dL* m/EI v (= Q,k) du=v*dL u =u,x+du u.korr.
kNm/m kNm/m 1/m E-3 E-3 E-3 mm mm mm
1 0,00 99,1 95,0 3,12 0,30 -0,30 -0,06 0,0 0,0
2 0,05 90,2 95,0 2,73 0,52 -0,82 -0,16 -0,1 -0,1
3 0,10 81,8 95,0 2,48 0,47 -1,29 -0,24 -0,2 -0,2
4 0,15 73,8 95,0 2,24 0,42 -1,71 -0,33 -0,5 -0,5
5 0,20 66,2 95,0 2,01 0,38 -2,09 -0,40 -0,8 -0,8
6 0,25 59,0 95,0 1,79 0,34 -2,43 -0,46 -1,2 -1,2
7 0,30 52,2 95,0 1,58 0,30 -2,73 -0,52 -1,6 -1,6
8 0,35 45,8 95,0 1,39 0,26 -3,00 -0,57 -2,2 -2,2
9 0,40 39,9 95,0 1,21 0,23 -3,23 -0,61 -2,7 -2,7
10 0,45 34,3 95,0 1,04 0,20 -3,42 -0,65 -3,3 -3,3
11 0,50 29,1 95,0 0,88 0,17 -3,59 -0,68 -4,0 -4,0
12 0,55 24,4 95,0 0,74 0,14 -3,73 -0,71 -4,7 -4,7
13 0,60 20,0 95,0 0,61 0,12 -3,85 -0,73 -5,4 -5,4
14 0,65 16,1 95,0 0,49 0,09 -3,94 -0,75 -6,1 -6,1
15 0,70 12,6 95,0 0,38 0,07 -4,01 -0,76 -6,9 -6,9
16 0,75 9,5 95,0 0,29 0,05 -4,07 -0,77 -7,6 -7,6
17 0,80 6,8 95,0 0,20 0,04 -4,11 -0,78 -8,4 -8,4
18 0,85 4,5 95,0 0,14 0,03 -4,13 -0,79 -9,2 -9,2
19 0,90 2,6 95,0 0,08 0,01 -4,15 -0,79 -10,0 -10,0
20 0,95 1,1 95,0 0,03 0,01 -4,15 -0,79 -10,8
21 1,00 0,0 95,0 0,00 0,00 -4,15 -0,79 -11,5
sum

120,0
100,0
80,0 load mom. m,g+q/2 kNm/m
60,0 crack. mom. m,w kNm/m
40,0
20,0
0,0
-20,0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

4,00
2,00
0,00
-2,00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

-4,00
-6,00
-8,00
-10,00 curvature (-) m/EI 1/m E-3
deflection u.korr. mm
-12,00
VIETCONS EDUCATION www.vietcons.org

Herstedlund Bilag 5u,hj-L

Moment & nedbøjning 5,3 m hjørneudhæng - brugslast , langtid

Moment is given by m,x = - P*L (1-x/L) - 0,5 p*L*L (1-x/L) (1-x/L)


Curvature is estimated as m,x / EI,c if m,x < m,w
m,w / EI,c + 1,3 ((m,x-m,w) / EI,w) if < m,x / EI,w and if m,x > m,w

m,0 = 0,00 kN EI,w = 0 Span L = 5,3 m Steel b.s. xxx mm2 ø 10


P = 3,3 kN/m EI,w = 21,8 MNm Height h = 390 mm Steel t.s. xxx mm2 ø 8 +
p = 1,9 kN/m EI,w = 21,8 MNm Column ø 400 mm Steel t.s. xxx mm2 (ø 00)
m,w = 95 kN/m EI,c = 33,0 MNm2 Concrete 35 MPa

section load mom. crack. mom. curvature increase inclination defl. increase deflection deflection
x/L m,g+q/2 m,w (-) m/EI dv = dL* m/EI v (= Q,k) du=v*dL u =u,x+du u.korr.
kNm/m kNm/m 1/m E-3 E-3 E-3 mm mm mm
1 0,00 70,9 95,0 2,15 0,28 -0,28 -0,08 0,0 0,0
2 0,05 64,8 95,0 1,96 0,52 -0,80 -0,21 -0,1 -0,1
3 0,10 59,0 95,0 1,79 0,47 -1,28 -0,34 -0,3 -0,3
4 0,15 53,4 95,0 1,62 0,43 -1,71 -0,45 -0,6 -0,6
5 0,20 48,1 95,0 1,46 0,39 -2,09 -0,55 -1,1 -1,1
6 0,25 43,1 95,0 1,31 0,35 -2,44 -0,65 -1,6 -1,6
7 0,30 38,4 95,0 1,16 0,31 -2,75 -0,73 -2,3 -2,3
8 0,35 33,9 95,0 1,03 0,27 -3,02 -0,80 -3,0 -3,0
9 0,40 29,7 95,0 0,90 0,24 -3,26 -0,86 -3,8 -3,8
10 0,45 25,8 95,0 0,78 0,21 -3,47 -0,92 -4,7 -4,7
11 0,50 22,1 95,0 0,67 0,18 -3,64 -0,97 -5,6 -5,6
12 0,55 18,7 95,0 0,57 0,15 -3,79 -1,01 -6,6 -6,6
13 0,60 15,5 95,0 0,47 0,12 -3,92 -1,04 -7,6 -7,6
14 0,65 12,7 95,0 0,38 0,10 -4,02 -1,07 -8,6 -8,6
15 0,70 10,1 95,0 0,30 0,08 -4,10 -1,09 -9,7 -9,7
16 0,75 7,7 95,0 0,23 0,06 -4,16 -1,10 -10,8 -10,8
17 0,80 5,6 95,0 0,17 0,05 -4,21 -1,12 -11,9 -11,9
18 0,85 3,8 95,0 0,12 0,03 -4,24 -1,12 -13,0 -13,0
19 0,90 2,3 95,0 0,07 0,02 -4,26 -1,13 -14,1 -14,1
20 0,95 1,0 95,0 0,03 0,01 -4,27 -1,13 -15,2
21 1,00 0,0 95,0 0,00 0,00 -4,27 -1,13 -16,4
sum

100,0

80,0 load mom. m,g+q/2 kNm/m


60,0 crack. mom. m,w kNm/m

40,0

20,0

0,0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
-20,0

4,00
2,00
0,00
-2,00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
-4,00
-6,00
-8,00
-10,00
-12,00
curvature (-) m/EI 1/m E-3
-14,00
deflection u.korr. mm
-16,00
VIETCONS EDUCATION www.vietcons.org

Bilag 3md_L
Herstedlund

Tværsnitsanalyse plademidte - designlast - langtid

Basis for calculation :


modulus of elasticity E,c = E,s / 5,6 (1 + 13 / f,ck) = 35 700 / (1 +13 / f,ck)
uncracked section EI,c = E,c * 0,9 * b * h pot3 / 12
cracked section EI,w = 0,33 * E,c * y pot3 + A' * E,s (y - 0,125 h,e) pot2 + A * E,s (h,e - y) pot2
cracking moment m,w = (0,1 * f,ck) pot 0,5 * h pot2 / 3
neutral axis y = is found by iteration until (T- C) = 0

Choice
m(g+q) MNm 0,090
f,ck MN/m2 35
f,yk MN/m2 550
E,s MN/m2 200000
E,c MN/m2 7407
A,s m2 E-6 900 4Y10/350
A',s m2 E-6 576 4Y8/350
h m 0,390
h,e m 0,350
Calculation
estimate y m 0,0860 0,0861 0,0862 0,0863 0,0864 0,0865 0,0866 0,0867 0,0868 0,0869
h,c=0,8y m 0,0688 0,0689 0,0690 0,0690 0,0691 0,0692 0,0693 0,0694 0,0694 0,0695
h,int m 0,3156 0,3156 0,3155 0,3155 0,3154 0,3154 0,3154 0,3153 0,3153 0,3152
C MN 0,285 0,285 0,285 0,285 0,285 0,285 0,285 0,285 0,285 0,285
stress,c MN/m2 3,88 3,88 3,88 3,87 3,87 3,87 3,86 3,86 3,86 3,85
strain,c m/m 0,00052 0,00052 0,00052 0,00052 0,00052 0,00052 0,00052 0,00052 0,00052 0,00052
strain,s m/m 0,00161 0,00161 0,00160 0,00160 0,00159 0,00159 0,00159 0,00158 0,00158 0,00157
stress,s MN/m2 322 321 320 320 319 318 317 316 316 315
T MN 0,290 0,289 0,288 0,288 0,287 0,286 0,285 0,285 0,284 0,283
T-C MN 0,0046 0,0039 0,0031 0,0023 0,0016 0,0008 0,0001 -0,0007 -0,0014 -0,0021
EI,c MNm2 33,0 33,0 33,0 33,0 33,0 33,0 33,0 33,0 33,0 33,0
EI,w MNm2 14,3 14,3 14,3 14,3 14,3 14,3 14,3 14,3 14,3 14,3
m,w kNm/m 94,9 94,9 94,9 94,9 94,9 94,9 94,9 94,9 94,9 94,9
VIETCONS EDUCATION www.vietcons.org

Ramboll Bilag 5m_L

Moment & nedbøjning midte 7,7 m pladefelt - arbejdslast - lang tid

Moment is given by m,x = 4 m,o (x/L) (1 - (x/L)) - (x/L) (m,1 - m,2) + m,1
Curvature is estimated as m,x / EI,c if m,x < m,w
m,w / EI,c + 1,3 ((m,x-m,w) / EI,w) if < m,x / EI,w and if m,x > m,w

m,0 = 85 kN EI,w = 14,3 MNm2 Span L = 7,7 m


m,1 = - 00 kN EI,w = 0 MNm2 Height h = 390 mm
m,2 = - 100 kN EI,w = 21,8 MNm2 Column Ø = 300 mm
m,w = 95 kN EI,c = 33 MNm2 Concrete 35 MPa

section load mom. crack. mom. curvature curv. increase inclin. in (1) inclination defl. increase deflection deflection
x/L m (g+q/2) m,w m/EI dL* m/EI v(1)=Q(1),k v = Q,k du=v*dL u =u,x+du u.korr.
kNm/m kNm/m 1/m E-3 E-3 E-3 E-3 mm mm mm
1 0,00 -100,0 -95,0 -3,18 -0,61 -0,61 -0,61 -0,23 0,0 0,0
2 0,05 -78,9 -95,0 -2,39 -0,92 -0,87 0,31 0,12 -0,2 -0,2
3 0,10 -59,4 -95,0 -1,80 -0,69 -0,62 1,00 0,39 -0,1 -0,1
4 0,15 -41,7 -95,0 -1,26 -0,49 -0,41 1,49 0,57 0,3 0,3
5 0,20 -25,6 -95,0 -0,78 -0,30 -0,24 1,79 0,69 0,8 0,8
6 0,25 -11,3 -95,0 -0,34 -0,13 -0,10 1,92 0,74 1,5 1,5
7 0,30 1,4 95,0 0,04 0,02 0,01 1,90 0,73 2,3 2,3
8 0,35 12,4 95,0 0,37 0,14 0,09 1,76 0,68 3,0 3,0
9 0,40 21,6 95,0 0,65 0,25 0,15 1,51 0,58 3,7 3,7
10 0,45 29,2 95,0 0,88 0,34 0,19 1,17 0,45 4,3 4,3
11 0,50 35,0 95,0 1,06 0,41 0,20 0,76 0,29 4,7 4,7
12 0,55 39,2 95,0 1,19 0,46 0,21 0,30 0,12 5,0 5,0
13 0,60 41,6 95,0 1,26 0,49 0,19 -0,18 -0,07 5,1 5,1
14 0,65 42,4 95,0 1,28 0,49 0,17 -0,68 -0,26 5,0 5,0
15 0,70 41,4 95,0 1,25 0,48 0,14 -1,16 -0,45 4,8 4,8
16 0,75 38,8 95,0 1,17 0,45 0,11 -1,61 -0,62 4,3 4,3
17 0,80 34,4 95,0 1,04 0,40 0,08 -2,01 -0,78 3,7 3,7
18 0,85 28,4 95,0 0,86 0,33 0,05 -2,35 -0,90 2,9 2,9
19 0,90 20,6 95,0 0,62 0,24 0,02 -2,59 -1,00 2,0 2,0
20 0,95 11,1 95,0 0,34 0,13 0,01 -2,72 -1,05 1,0 1,0
21 1,00 0,0 95,0 0,00 0,00 0,00 -2,72 -1,05 0,0 0,0
sum 1,49 -1,22
load mom. m (g+q/2) kNm/m
150,0
crack. mom. m,w kNm/m
100,0

50,0

0,0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
-50,0

-100,0

-150,0

6,00 curvature m/EI 1/m E-3


deflection u.korr. mm
4,00

2,00

0,00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
-2,00

-4,00
VIETCONS EDUCATION www.vietcons.org

Herstedlund Bilag 7

Forskydning omkring søjle ø 300


Dat. 19.09.2007

Statik snitradius r (n) = r (n-1) + 0,5 x h


kontrolsnitflade A,r = h x 2 x pi x r
forskydningskraft i kontrolflade Q,r = P - p x pi x r x r
forskydningsspænding t,r = Q,r / A,r
betontrækspænding f,ctk = (0,1 x f,ck) pot 0,5
0,12 ν f,cd gennemlokning uden stål t,b = 0,16 x f,ck pot 0,5
skrå betontryk u. 45 gr (=2t), max f,cds = (0,7-(f,ck/200)) x f,cd

Statiske parametre
stål beton beton beton beton søjlelast dæklast dækhøjde søjleradius
f,y f,ck f,tk t,b f,cds P p h r (o)
MPa MPa MPa MPa MPa MN MN/m2 m m
550 35 1,87 0,95 12,25 1,280 0,018 0,39 0,15

snit (0-) 1 (1-) 2 (2-) 3 (3-) 4 (4-) 5 (5-) 6 (6-) 7 (7-) 8


rm 0,35 0,54 0,74 0,93 1,13 1,32 1,52 1,71
A m2 0,42 0,66 0,90 1,14 1,38 1,62 1,86 2,09
Q MN 1,27 1,26 1,25 1,23 1,21 1,18 1,15 1,11
t MPa 3,01 1,91 1,39 1,08 0,88 0,73 0,62 0,53
t,b MPa 0,95 0,95 0,95 0,95 0,95 0,95 0,95 0,95
Q,b mass 0,40 0,63 0,85 1,08 1,30 1,53 1,76 1,98
Q,b hul 0,24 0,38 0,51 0,65 0,78 0,92 1,05 1,19

Q,stål mass 0,87 0,64 0,40 0,15 -0,10


bjl K10 13,2 9,7 6,0 2,3 -1,4
bjl K12 9,2 6,7 4,2 1,6 -1,0
bjl K14 6,8 4,9 3,1 1,2 -0,7

Q,stål hul 1,03 0,89 0,74 0,58 0,43 0,26 0,10 -0,07
bjl K10 15,7 13,5 11,2 8,9 6,5 4,0 1,5 -1,1
bjl K12 10,9 9,3 7,8 6,2 4,5 2,8 1,0 -0,8
bjl K14 8,0 6,9 5,7 4,5 3,3 2,0 0,7 -0,6

massiv -------> valg --------->

blå tal = massivt dæk , røde tal = hult dæk


VIETCONS EDUCATION www.vietcons.org

Herstedlund Fælleshus, Herstedvester Dæk 1 - BD 395


Tegning 121 Elementplan incl kugler
Dato 15.01.08
1:100
Y
Rev.

X X

1 2 3 4 5 6 7 8 9

1670 1670 1670 1670 1670 1670 1670 1670


A
1670

B
1670

C
1670

D
1670

E
1670

F
1670

G
1670

H
1670

Red marking
for orientation of element

Steel lattice - stirrups Y14/175 BubbleDeck Danmark ApS


Røsevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org

Tidlig arbejdsskitse - mål ikke justeret (ikke nødvendigt) Skitse 1

Vurdering af udhæng / oversidemomenter 1:100

Dækket udføres overalt med samme armering

undersøgelse overflødig
2500

indspænding vilkårlig m,i

(2a)

p,g = 8,8 kN/m2 7000

(2) P,g = 4,6 kN/m

(1)

P,g = 4,6 x 2
4000
p,d =18,0 kN/m2
P,g = 4,6 (3)

P,g = 4,6 kN/m

2000 7500 4000

moment (1) er farligere end (2), (2a), (3) og m,i


VIETCONS EDUCATION www.vietcons.org

Tidlig arbejdsskitse - mål ikke justeret Skitse 2

Vurdering af momenter i indv. felter 1:100

Dækket udføres overalt med samme armering

undersøgelse overflødig
2500

indspænding

(6’) , (7’)
7000

max neg mom (7) 8,8 kN/m2 18,0 kN/m2

(5)

4000

max pos mom (6) 18,0 kN/m2 8,8 kN/m2

2000 7500 4000

(6) er farligere end (6’)


(7) er farligere end (7’)
VIETCONS EDUCATION www.vietcons.org

Tidlig arbejdsskitse - mål ikke justeret Skitse 3

Vurdering af last(areal) over søjler 1:100

Dækket udføres overalt med samme armering

undersøgelse overflødig
2500

indspænding

(0,5 L) (0,6 L)
7000

2,5 4,0
(0,6 L)

(5) (4) 4,0

4000

18,0 kN/m2

P,g = 4,6 kN/m

2000 7500 4000


VIETCONS EDUCATION www.vietcons.org

Forskydningsarmering Skitse 4
Søjle G7
1:20
gitre kan forskydes frit inden for halv modul (170 mm)

1100
1/2 bjl 8 12 8 1820 kN
1800
1/2 bjl 10 8 10 1820 kN

2600
1/2 bjl 8 520 kN

8 520 kN
VIETCONS EDUCATION www.vietcons.org

Forskydningsarmering Skitse 4A
Søjle G7
1:20
gitre kan forskydes frit inden for halv modul (170 mm)

1100
1/2 bjl 8 12 8 1820 kN
1800
1/2 bjl 14 10 8 10 14 2860 kN

2600
1/2 bjl 4 8 4 1040 kN

8 520 kN
VIETCONS EDUCATION www.vietcons.org

Forskydningsarmering Skitse 5
Søjle G2
1:20

r = 0,55 r = 0,95 r = 1,35

1/2 bjl 14 18 12
910 kN 1160 kN 780 kN

vridningsgitter (rødt) medregnes ikke til forskydning


VIETCONS EDUCATION www.vietcons.org
Skitse 6

Princip af vridningsgitter
1:5

forskydningsarmering
ikke indtegnet

sammenholdes
m. elementplan

Y20

Y8

Y20

315 x 275

Y14 bjl/175

Y20

Y10

30
100
150
VIETCONS EDUCATION www.vietcons.org

Example 10 Professor Kiss, Romania


VIETCONS EDUCATION www.vietcons.org

May 2009

TEST

of

280 mm BubbleDeck slab

Test Model defined by

Total slab size 12 x multiple 6 m


Supported along edges on bearing walls
Supported internal in 6 m grid on columns
VIETCONS EDUCATION www.vietcons.org

Remarks to Calculation

In the attempt to make the project both general and simple (easy understandable) are chosen
following practical procedures – with weight on simplicity :

Only uniformly distributed load is regarded – because full maximum uniform load will reveal
the wanted most critical picture of both the shear around columns and the sagging moment at
slab middle. Variation in imposed load will only influence temporary deflection.

Firstly, calculation is based on arbitrary (variable) load p – to make a simple, flexible and fast
tool to calculating and controlling the sagging moment and the deflexion on site through the test.
Secondly, these expressions are made numerical replacing load p with wanted actual load.
This general setup also shows how simple calculations can be made by hand.

Calculations are executed with only two significant digits rounded up – more have no relevancy
(neither regarding the theoretical calculations nor the practical exactness of execution on site).
Calculations are based on f,ck 35 MPa but using 25 MPa will not influence strength only flexure.

Further calculation is carried out as traditional 2-bay one-way calculation (elastic state),
X direction is chosen as element direction (length),
the slab is fully symmetrical around the column lines in both X- and Y-direction.
slab is regarded 100% fixed at internal column line (simple, well balanced choice),
slab is carried out without moment transfer to columns (charnier).

Stress, strain and stiffness are normally not calculated - but is here shown in encl. 3 at slab
middle for supposed design load.

Concerning Shear.
The old word “Theory is one thing – practice another” should be remembered when dealing
with shear. Two matters should be taken in consideration.

One, as shear reinforcement only has relevancy in very small areas compared with other
reinforcement, there is no argument in favour of spending time on sophisticated calculations
when simple expressions can be used – and furthermore safe using the lower limit of factors.
Simple formulas results in easy calculation and easy and safe control.

Two, as the execution on site of reinforced shear zones often is quite “out in the blue” or
without reasonable relation to the project design, the shear not only has to be calculated safe
but also be designed in a manner that it cannot be executed wrong.

Minor deviations between calculations and drawings are not corrected – if regarded insignificant.

Text in Italic is meant as explanations/guidance.


VIETCONS EDUCATION www.vietcons.org

NUMERICAL CALCULATION BASIS

Used safety factors (Euro-Code modified to BubbleDeck standard)

Loads Permanent load f,g = 1.2


Imposed load f,p = 1.5

Materials Concrete f,c = 1.5


Steel f,y = 1.2
this set of factors will cover all situations and combinations to a reasonable degree

Used materials and design values

Concrete f,ck = 35 MPa , f,cd = 35 /1,5 = 23 MPa


f,tk = √0.1 f,c = 1,9 - , f,td = 1,9 /1,5 = 1,3 -
Steel, min f,yk = 500 - , f,yd = 500 /1,2 = 420 -

Basic BD design moments m,y ≈ 0.6 d,y 2 (where d is the bar diameter)

steel (2 bars/ball) Y6 Y8 Y10 Y12 Y14 Y16 Y20 Y25


mom. kNm/m 20 40 60 90 120 150 240 360
are used directly in the calculations
the values are estimated on basis of the used factors and rounded up (no significant deviation)
note, Y10, Y14 and Y20 can be directly mutual substituted through the factor 2 (double or half)

Loads

BD slab, 280 mm g,0 4.5 kN/m2


other dead load g,1 1.0 -
---------------
Σg 5.5 -
usual imposed load (+ services) q 8.0 -
---------------
characteristic load p = 13.5 kN/m2

design load p,d = 1.2 * 5.5 + 1.5 * 8.0 = 18.6 -


rounded up p,d = 19.0 -
working load p,w = 1.0 * 5.5 + 0.5 * 8.0 = 9.5 -
rounded up p,w = 10.0 -
p,w / p,d = 10 / 19 ≈ 0.50
VIETCONS EDUCATION www.vietcons.org

PRACTICAL CALCULATION PROCEDURE

Main (design) forces on model based on random load (for quick load variations)
and calculated one-way after axes

Slab moments double bay (M,x) - and End bay

eff. span L,x = 6.0 – 2 * 0.1 = 5.8 m

simple sagging moment, m,0 = p * L2 / 8


= p * 5.8 2 / 8 = 4.2 p
support moment, chosen
at column m’1 = max m’d = m,0 = 4.2 p -
at wall m’2 = 0
sagging moment in general m,d ≈ m,0 – 0.5 (m’1 + m’2)
actual ≈ 4.2 – 4.2 * 0.5 = 2.1 p -

not fully correct but Ok, simple and practical – compare correct value encl.6 and annex 1
(under general circumstances also the hogging (negative) slab moment has to be controlled
but not necessary for the test).

Slab moments multiple bay (M,y) see sketch


eff. L = 6.0 – 2 * 0.1 = 5.8 m
m,0 = p * 5.8 2 / 8 = 4.2 p
support moment at column
inner section
design max m’d = m,0 * 2 / 3 = 2.8 p -
sagging (design) moment m,d = 4.2 – 2.8 = 1.4 p -
outer section as X-direction

Shear compare loads with yield line figure – encl.

is calculated for circular columns (the essential free inner columns) –


(square columns are not recommendable but accepted - if used, calculation is on safe side)

column is calculated as D = 300 mm


load inner column Q,d ≤ p * 6 * 6 * 1.25 = 45 p
load outer column Q,d ≤ p(3+3*1,25) * 6 * 1.25 = 50 p
load wall column Q,d < p * 6 * 6 * 0.5 = 18 p
wall and corner columns are not calculated (executed, based on result from inner column)
VIETCONS EDUCATION www.vietcons.org

NUMERICAL CALCULATION loads, see pg. 2

static depth of slab d = 250 mm


design load p,d = 19 kN/m2
working load p,w = 10 -

values quoted in round figures (compare with more exact yield line estimate, encl. B)

Moments (X) double bay (see encl. 3 and 6)

sagging moment m,d = 2.1 * p,d = 2.1 * 19 = 40 kNm/m


bottom mesh Y08/125 m = 40 -

would be allowed but in practice is recommended always to work with some margin and
experience tells that utilization of steel about 70-80% of max. will balance deflections.

better choice
bottom mesh Y10/125, m = 60 kNm/m
top mesh Y06/125

fixing moment (100%) m’d = 4.2 * p,d = 4.2 * 19 = 80 kNm/m


only mesh above column is regarded effective (see drawing 4)

Y14/125 x 4m, average m’ = 120 * 4 / 6 = 80 kNm/m


slab mesh Y6/125 above column is ignored

Moments (Y) multiple bay (see encl. 3 and 6x)

sagging moment m,d = 1.4 * p,d = 1.4 * 19 = 27 kNm/m


is covered by
bottom mesh Y08/125 m = 40 kNm/m
top mesh Y06/125

fixing mom. preconditioned m’d = 2.8 * p,d = 2.8 * 19 ≈ 50 kNm/m

ok, less than disposable


steel Y14/125 x 4m m’ = 120 * 4 / 7.5 = 64 -
(could use Y12/125 m’ = 90 * 4 / 7,5 = 48 - )
VIETCONS EDUCATION www.vietcons.org

Deflections from working load, see encl. 5

Double bay

Is generally calculated for working load (average long term load).


In this estimate for test is only regarded the short term situation.
In uncracked state the deflection for dead load can be estimated directly from the ratio p,g / p,w
In cracked state the dead load deflection is calculated individually and deflection for live load is
determined as the difference between deflection for working load and deflection for dead load.

working load m,0w = 0.5 * m,0d = 0.5 * 80 = 40 kNm/m


100% fixed => max m’ = m,0 = 40 -

moment and deflexion is calculated in excel program, encl.5


(but approximately figures can be found from usual known simple formulas)

encl 5 : average δ,w = 4.0 mm


uncracked => dead load δ,g = 4.0 * 5.5 / 10.0 = 2.2 mm

design load m,0d = 0.5 * m,0d = 0.5 * 80 = 40 kNm/m


100% fixed max m’ = m,0 = 40 -

moment and deflexion is calculated in excel program, encl.5


(but approximately figures is found from usual known simple formulas)

In encl. 6 is shown deflection for full design load.

Multiple bays - deflection could be ignored –


but is shown to complete the example
VIETCONS EDUCATION www.vietcons.org

Shear

calculation based on the diagonal stringer method


see Annex A
V,d = v ,d * u * d = 0,16 * u * d * f,ck
V,cd = v ,cd * u * d = 0,11 * u * d√* f,ck

d is the effective depth


regarded surface marked dark grey
d

u,n

V,0

45
u,0 u,n
d/2

u,0 = 3 (D + 2d) circular column


u,0 = 4 (D + 2d) square column
u,n = u,0 + n * 6 d

D d d d d d

Actual stringer values

angle concrete pressure θ = 45 o


angle reinforcement α = 90 o
eff. stringer depth is borne d (≈ 0.9 h) = 0.25 m
(= static depth of BubbleDeck)

with concrete 35 MPa :

effectiveness factor v = 0.7 – f,ck / 200


= 0.7 – 35 / 200 = 0.52
is calculated in general (safe) v = 0.5

max allowed max shear stress v,d = ½ * v * f,cd


= ½ * 0.5 * 23 = 5.70 MPa

allowed concrete stress σ,d = (1+cot2 θ)/(cot θ+cot α) v,d


actual (θ = 45 0 , α = 90 0 ) = 2 * 5.70 = 11.4 MPa

concrete alone v,c = ½ * f,td


actual = 0.5 * 1.30 = 0.65 MPa
VIETCONS EDUCATION www.vietcons.org

Actual calculation

at inner column D = 300 mm


with load Q,d = 50 p
= 50 * 19.0 = 0.95 MN

shear stress estimated in ring sections


of width = effective slab thickness =
static depth BubbleDeck d = (0.9 * h) = 0.25 m

control perimeter u,0 = π (D + 2d)


= π (0.30 + 2 * 0.25) = 2.50 m
control surface A,0 = u,0 * d = 0.63 m2

v = 0.95 / 0.63 = 1.50 MPa


ok, less than v,d = 5.70 -
but need reinforcement, more than v,c = 0.65 -

absorbed by concrete V,c = v,c * A,0


= 0.65 * 0.63 = 0.40 MPa

shear to be taken by steel N,0 = (0.95 – 0.41) 1000 = 540 kN


6 closed links Y12 yield N = 6 * 2 * 113 * 0.400 = 550 kN

successive calc. at perimeter u,n = u,0 + n * 6 d


if necessary

control
at perimeter u,5 = u,0 + 5 * 6 d
= 2.50 + 5 * 6 * 0.25 = 10.0 m
shear surface A,5 = 10.0 * 0.25 = 2.50 m2

actual load V,5 = 0.95 – 19.0 * π * 1.10 2 /1000


= 0.84 – 0.05 = 0.79 MN

if massive section v,5 = 0.79 / 1.64 = 0.48 MPa


ok
if hollow section v,5 = 0.48 / 0.6 = 0.80 MPa
absorbed by concrete V,c = 0.65 * 1.64 * 0.6 = 0.64 -

necessary steel N,5 = (0.84 – 0.64) 1000 = 200 kN


3 closed links Y12 N = 3 * 2 * 113 * 0.400 = 270 kN
VIETCONS EDUCATION www.vietcons.org

Working (support) paper correct values according to preconditions

Moment calculation (for p=1) see yield figure encl

Outer slabs

1. chosen support moment m’ = m


gives moment balance per m

slab part A 2m = 3.4 2 / 2 = 5.78


m = 2.89
slab part B m = 2.4 2 / 2 = 2.88

the yield line figure is correct m = m’ ≈ 2.90


with p,d = 19 kN/m m,d = 19 * 2,9 = 55 kNm/m

this choice could have been made as the reinforcement Y10 would be sufficient

2. chosen support moment m’ = 2m


gives moment balance per m

slab part A 3m = 3.7 2 / 2 = 6.84


m = 2.28
slab part B m = 2.1 2 / 2 = 2.20

the yield line figure is correct


slab part B’ will give smaller m than B
and design moment can be set m,d = 0.5 m’ ≈ 2.2

with p,d = 19 kN/m m,d = 19 * 2,2 = 42 kNm/m


m’ = 2 * 42 = 84 -
5% higher than the used simple method, but the deviation is acceptable.

X-direction continuous slabs, symmetry

slab part A 3m = 3.0 2 / 2 = 4.5


sagging moment m,d = 1.5
support moment m’ = 2m,d ≈ 3.0

with p,d = 19 kN/m m,d = 19 * 1.5 = 30 kNm/m


m’ = 2 * 30 = 60 -
VIETCONS EDUCATION www.vietcons.org

Annex A
Simple procedure for calculation punching shear - see draft

the shear should be investigated for the situations


v,c < 0.5 f,td no reinforcement is required
0.5 f,td < v,c < 0.5 f,cd reinforcement required
v,c > 0.5 f,cd thicker slab or stronger concrete
in combination with v,bub = 0.6 v,solid

(1) estimate shear at column face – in a slab of thickness h


as v = V/d*u
where d is effective slab depth ≈ 0.9 * h
and u is periphery in a distance d from column
(there are no grounds to investigate closer to column)

(2) estimate the necessary steel at column face section


as N = V – V,c0
where V,c0 = 0.5 f,td * u,0 * d
and u,0 = π (D + 2d)
use this steel amount out in slab as long as it is practical convenient, or

(3) the steel can be reduced successively according to reduced N,n = V – V,n
where V,n = 0.5 f,td * u,n * d
and u,n ≈ u,0 + n * 6 d

If it is preferred to work on basis of full deck thickness can be used following rewriting

(1) v = 1.1 * V / h * u
where h is the full slab height
d ≈ 0.9 * h (static depth)

and by controlling sections with mutual distance h,


the corresponding steel can be estimated directly at any section as N = 1.1 * V

(2) estimate the necessary steel at column face section


as N = 1.1 * V – V,c0
where V,c0 = 0.5 f,td * u,0 * h
and u,0 = π (D + 2h)
use this steel amount as long as it is practical convenient, or

(3) the steel can be reduced successively according to N,n = 1.1 * V – V,n
where V,n = 0.5 f,td * u,n * h
and u,n ≈ u,0 + n * 6 h
VIETCONS EDUCATION www.vietcons.org

Because of its nature the present calculation is a mix of general procedure and the actual test.

Simple procedure design strength.

for uniform loads

1. estimate two loads


design loads p,d characteristic loads multiplied by respective code factors
recommended 1.2 on dead load and 1.5 on live load
working load p,w dead loads multiplied by 1.0 and live loads multiplied by 0.5

2. calculate design load on column (internal) as P,d = 1.25 * a * b * p,d


where a and b are the modules in the two directions

3. control moment for P,d and calculate necessary reinforcement above column
(not necessary if moment will be chosen more than sagging moment)

4. chose support moment, recommended m’ = m,0 with one fixed support


m’ = m,0 * 2/3 with two fixed supports

5. calculate the sagging moment as m,d = m,0 – m’ (middle slab)

6. chose reinforcement mesh according to BubbleDeck standard moment sheet.

7. control sagging moment and top side mesh for combination full support moment and
minimum slab load

8. calculate shear according to annex A


reinforce with closed baskets built into the element canals in agreement with BubbleDeck
recommendations.
VIETCONS EDUCATION www.vietcons.org

Specific calculation of crack bottom side during long term use under working (utility) load

The slab has uniform reinforcement in both main directions.


That means the cracking is also uniform distributed and can be regarded working over a larger
area independent of the individual bars.

Estimated by the formula w,cr = 2.5 * 10 – 5 σ,s √ a,w (EC adjusted by DK)
with
active concrete area A,cef = 1000 * 50 = 50 000 mm2/m
sum of steel diameters, ø12/100 ∑ d,w = 10 * 12 = 120 mm/m
crack parameter a,w = A,c eff / Σ ø
= 50 000 / 120 = 420
steel stress (see encl. 3mL) σ,swL = 170 MPa
max. crack width w,cr = 5 * 10 – 5 σ,s √ a,w
= 2.5 E-5 * 170 * √ 420 = 0.10 mm

Compared with the steel strain ε,s = 0.00086 mm/mm


distributed per bar (mesh) a = 100 mm
see encl. 3mL ε,s = 0.00086 * 100 = 0.09 mm
we have a very good agreement

BD always recommends working on basis of the real behaviour rather than using empirical formulas.
VIETCONS EDUCATION www.vietcons.org
VIETCONS EDUCATION www.vietcons.org
VIETCONS EDUCATION www.vietcons.org
VIETCONS EDUCATION www.vietcons.org
VIETCONS EDUCATION www.vietcons.org

Example 11 Keops – Project City Hall, Denmark


VIETCONS EDUCATION www.vietcons.org

Ph/fax +45 44 95 59 59
Elementer og stød

BubbleDeck Danmark
Dæk over etage 1
o.s.: Y8

DK - 3520 Farum
1:200
u.s.: Y8 u.s.: Y10
Plan

Rösevangen 8
700 3000

2500.8005 C 2500.10210 L
9

2500.8005 2500.9150

2500.8005 2500.9150

2500.8005 C 2500.10210 L
8

Note: Fugearmering fra huldæk til BubbleDeck som anført på LH: 4.301
2500.8005 2500.9150
CL

2500.8005 2500.9150

2500.8005 C 2500.10210 L
7

stød o.s.: Y6
u.s.: Y8
2500.8005 2500.9150

2500.8005 2500.9150

2500.8005 C 2500.10210 L
6

2500.8005 2500.9150

2500.8005 2500.10210 M

2500.8005 C 2500.10210 K
5

Stødjern skal lægges per 125 mm


stød u.s.: Y10

2500.8005 2500.10210 J
Rådhusparken , Glostrup

2500.8005 2500.10210 J
Tegning No. 120 A

ø6 - 600 mm
ø8 - 700 mm
ø10 - 800 mm

2500.8005 C 2500.10210 K
4
Dato 03.06.2003

2005.8005 A1 2005.10210 A1
3

stød u.s.: Y10


A

D
Rådhusparken , Glostrup X Basis Armering
Tegning No. 130 A Dæk over etage 1
CL
Dato 03.06.2003 1:200
Y

3 4 5 6 7 8 9

3500 7500 7500

3500
3255

Y6/125 o.s.

Y8/125 u.s.
Y8/125 o.s.
7500

7500
Y8/125 u.s.
VIETCONS EDUCATION

2750

C
Y6/125 o.s. Y6/125 o.s.
6750

Y8/125 u.s. Y8/125 u.s.


7400

Y6/125 o.s.

7500
Y10/125 u.s.

Y6/125 o.s.
Y6/125 o.s.

Y10/125 u.s.
Y8/125 + Y8/250 u.s.
3400

se tegning 151
D

10755 18995
www.vietcons.org

BubbleDeck Danmark
Rösevangen 8
Stødarmering : Se Tegning nr. 120 A Note : Fugearmering fra huldæk til BubbleDeck som anført på LH: 4.301
DK - 3520 Farum
Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org

o.s.: Y8

Ph/fax +45 44 95 59 59
Elementer og stød

BubbleDeck Denmark
Dæk over etage 2
u.s.: Y8

DK - 3520 Farum
700

1:200
Plan

Rösevangen 8
E3000.9255 B 3000.5500 B
9

E3000.9255 A 3000.5500 A

E3000.9255 3000.8960 G

1500.9255 B 1500.5500 B
8

Note: Fugearmering fra huldæk til BubbleDeck som anført på LH: 4.302
3000.9255 A 3000.5500 A

1500.9255 1500.5500
CL

3000.9255 B 3000.5500 B
7

2500.9255 A 2500.5500 A

stød o.s.: Y6
u.s.: Y8
3000.9255 3000.8960 F

2000.9255 B 2000.5500 B
6

3000.9255 A 3000.5500 A

1500.9255 1500.5500

3000.9255 B 3000.8960 D
5

Stødjern skal lægges per 125 mm

3000.9255 A 3000.8960 A
stød u.s.: Y10
Rådhusparken , Glostrup

3000.9255 3000.8960
Tegning No. 220 A

ø6 - 600 mm
ø8 - 700 mm
ø10 - 800 mm

3000.9255 C 3000.8960 C
4
Dato 14.04.2003

1755.9255 A1 1755.8960 A1
3

stød u.s.: Y10


A

D
Rådhusparken , Glostrup X Basis Armering

Tegning No. 230 A Dæk over etage 2


CL
Dato 03.06.2003 1:200
Y

3 4 5 6 7 8 9

3500
3255

Y6/125 o.s.

Y8/125 u.s.
Y8/125 o.s.

7500
7500

Y8/125 u.s.

Y6/125 o.s.
VIETCONS EDUCATION

2750

Y8/125 u.s.
C
6150

Y8/125
Y8/125

Y8/125 u.s.
Y6/125 o.s.

7500
7400

Y6/125 o.s.
3400

Y8/125 u.s.
D

10755 18995
www.vietcons.org

BubbleDeck Danmark
Rösevangen 8
Stødarmering, se Tegning nr. 220 A Note: Fugearmering fra huldæk til BubbleDeck som anført på LH: 4.302
DK - 3520 Farum
Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org

o.s.: Y8

Ph/fax +45 44 95 59 59
Elementer og stød

BubbleDeck Danmark
Dæk over etage 3
u.s.: Y8

DK - 3520 Farum
700

1:200
Plan

Rösevangen 8
2500.8005 B 2500.6750 B
9

2500.8005 A 2500.6750 A

2500.8005 2500.6750

2500.8005 B 2500.6750 B
8

Note: Fugearmering fra huldæk til BubbleDeck som anført på LH: 4.303
2500.8005 A 2500.6750 A

2500.8005 2500.10210 L
CL

2500.8005 B 2500.6750 B
7

2500.8005 A 2500.6750 A

stød o.s.: Y6
u.s.: Y8
2500.8005 2500.6750

2500.8005 B 2500.6750 B
6

2500.8005 A 2500.6750 A

2500.8005 2500.6750

2500.8005 B 2500.10210 D
5

Stødjern skal lægges per 125 mm

2500.8005 A 2500.10210 A
stød u.s.: Y10

2500.8005 2500.10210
Rådhusparken , Glostrup
Tegning No. 320 A

3005.8005 C1 3005.10210 C1
ø6 - 600 mm
ø8 - 700 mm
ø10 - 800 mm
4
Dato 03.06.2003

2750.8005 A1 2750.10210 A1
3

stød u.s.: Y10


A

D
Rådhusparken , Glostrup Basis Armering
Tegning No. 330 A X
Dæk over etage 3
Dato 03.06.2003 CL 1:200

Y
3 4 5 6 7 8 9

3500 7500 7500 7500

A
Y6/125

3500
Y8/125
3255

Y8/125

Y8/125
7500

7500
VIETCONS EDUCATION

2750

C
6150

Y8/125
Y8/125

Y8/125
Y6/125
Y6/125
Y8/125

7500
7400

Y6/125
Y8/125
3400

10755 18995
www.vietcons.org

BubbleDeck Danmark
Rösevangen 8
Stødarmering, se Tegning nr. 320 A Note: Fugearmering fra huldæk til BubbleDeck som anført på LH: 4.303
DK - 3520 Farum
Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org

Ph/fax +45 44 95 59 59
o.s.: Y8

Elementer og stød

BubbleDeck Danmark
Dæk over etage 4
u.s.: Y8

DK - 3520 Farum
700

1:200
Plan

Rösevangen 8
2500.7955 B 2500.4500 B
9

2500.7955 A 2500.4500 A

2500.7955 2500.4500

2500.7955 B 2500.4500 B
8

Note: Fugearmering fra huldæk til BubbleDeck som anført på LH: 4.304
2500.7955 A 2500.4500 A
CL

2500.7955 2500.4500

2500.7955 B 2500.4500 B
7

2500.7955 A 2500.4500 A

stød o.s.: Y6
u.s.: Y8
2500.7955 2500.4500

2500.7955 B 2500.4500 B
6

2500.7955 A 2500.4500 A

2500.7955 2500.4500

2500.7955 B 2500.7960 D
5

Stødjern skal lægges per 125 mm

3005.7955 A 3005.7960 A
Rådhusparken , Glostrup

3005.7955 3005.7960
Tegning No. 420 A

ø6 - 600 mm
ø8 - 700 mm
ø10 - 800 mm

2445.7955 A 2445.7960 A
4
Dato 03.06.2003

D
Rådhusparken , Glostrup X Basis Armering
Tegning No. 430 A Dæk over etage 4
Dato 03.06.2003 CL 1:200
Y

3 4 5 6 7 8 9

3500 7500 7500 7500

A
955

3500
B

Y8/125
Y6/125
7500

7500
Y6/125 o.s.
Y8/125 u.s.
VIETCONS EDUCATION

C
Y6/125 o.s. Y6/125 o.s.
4500

Y8/125 u.s. Y8/125 u.s.

Y8/125
Y8/125
7400

7500
Y8/125
Y6/125
3400

8455 18995
www.vietcons.org

BubbleDeck Danmark
Stødarmering, se Tegning nr. 420 A Note: Fugearmering fra huldæk til BubbleDeck som anført på LH: 4.304 Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
standard elementets oversidenet afskæres i nødvendigt omfang Rådhusparken, Glostrup
4 Y20 o.s. (L = 1350) Tegning nr. 151
Dato 03.06.2003
4 U-bjl Y10, L 350

4 Y20

bjl Y12/125

65 8 Y20
15/25

600
2 bjl Y 12/125

2 Y20 u.s. 6 Y20 u.s.

L = 1550 L = 2050
40 60 1000

U-bjl ø6/250
i dette elem.
VIETCONS EDUCATION

se element E3000.8960 L

Detail af konsol

600
1:10

se også tegn 151A


1:2,5

standard elementets oversidenet afskæres


www.vietcons.org

BubbleDeck Danmark
U-bjl ø6/250 Rösevangen 8
I dette element
DK - 3520 Farum
Ph/fax +45 44 95 59 59
CL
Rådhusparken, Glostrup
Detail af konsol
Tegning nr. 151A
1:2,5
Dato 03.06.2003

overside net bortskæres

20
4 Y20

230
U-bjl Y10 bjl 2Y12/125
h,udv = 204
VIETCONS EDUCATION

8 Y20

30
600
www.vietcons.org

BubbleDeck Denmark
Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
Rådhusparken, Glostrup Gangbro etage 2
Tegning nr. 251 Element 3005.10210 F
Dato 12.06.2003
Plan 1:50

6
Snit : se tegn. 252 og 351

D C

1000 6 Y16 (red)


L = 4500

3317
40 4 Y16 (blue)
L = 4500

147

1322
VIETCONS EDUCATION

3005

4 U-bjl Y10

217
2854

959
5 Y16 (L=2700) med sort farve
Elementet afskæres efter de skrå punkterede linier on site

2283
I kanter lægges U-bjl Y6/500 (L=250) on site (bjl se tegn 351)
60 3400 4000 2750
www.vietcons.org

10210 BubbleDeck Denmark


100

7
Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
Rådhusparken, Glostrup Gangbro etage 2 modul 8-9
Tegning nr. 252
Element 3005.10210 G
Dato 12.06.2003
Plan 1:50

8
Snit og details tegn. 252 A

1000 6 Y16 (red)

1745
L = 4500
6 Y16 (blue)
L = 4500

485

205

L = 350
1806

U-bjl Y10/500
3005
VIETCONS EDUCATION

994
714
Elementet afskæres efter de skrå punkterede linier on site
I kanterne lægges U-bjl Y6/500 (L=250) on site (se bjl tegn. 351)
I trappeside lægges extra U-bjl Y6/500 (L=350) (se tegn.252 A)

2750
60 3400 4000 2750

10210
100 væg
www.vietcons.org

BubbleDeck Denmark
D C Rösevangen 8
DK - 3520 Farum

9
Ph/fax +45 44 95 59 59
Rådhusparken, Glostrup Gangbro etage 2 modul 8-9
Tegning nr. 252 A Element 3005.10210 G
Dato 14.04.2003
Rev. 12.06.2003 : element mål ændret Details 1:10 og 1:20

trappe

girder

slant girder
U-bjl Y10/500

girder

U-bjl Y10/500
VIETCONS EDUCATION

girder

Plan 1:20

cut on site
250/350 girder girder
Snit A-A 1:10

Snit : se også tegn. 351


bjl Y6/250 Y14
www.vietcons.org

BubbleDeck Denmark
Rösevangen 8
60 Y16 DK - 3520 Farum
short girder Y8
Ph/fax +45 44 95 59 59
Rådhusparken, Glostrup
Element 2500.10210 D
Tegning nr. 253 og 353
Dato 12.06.2003 Plan 1:50

Snit : se tegn. 351

d = 1500
40 1000 4 Y16 (red) udeladte bobler
L = 4500
2 Y16 (blue) d = 320 hul
L = 4500

5
3 U-bjl Y10
L = 350

1860
2500
VIETCONS EDUCATION

U-bjl Y6/500
L = 250

1 Y16 á 2000 I top og bund


lægges on site før montage

60 3400 4000 2750

100
10210
www.vietcons.org

D C BubbleDeck Denmark
Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
Rådhusparken , Glostrup
Gangbro etage 3
Tegning No. 351
Element 2500.8960
Dato 14.04.2003
D C 1:50 og 1:10
1000 8 Y16
L = 4500
stop extra girder 6 Y16
U-bjl Y6/500 extra girder L = 4500
Plan 1:50 L = 250 L = 3700

L = 350
1800
2500

U-bjl Y10/500
extra U-bjl Y6/500, L = 350
ved trappe
40 2 U-bjl Y6

60 3400 4000 2750


VIETCONS EDUCATION

10210
100 væg
1 Y16 I top og bund lægges
I element før montage
250 350 extra girder
Snit 1:10

U-bjl Y6/500 extra Y6/500


I rand ud for trappe
Y16
L = 350
L = 250

Y8
www.vietcons.org

350 1800 50 200 50 BubbleDeck Denmark


2500 Rösevangen 8
DK - 3520 Farum
Ph/fax +45 44 95 59 59
VIETCONS EDUCATION www.vietcons.org

Appendix H Brochure UK – Site Installation


CI/SfB
VIETCONS EDUCATION (23) Eq4
www.vietcons.org

Part 2 September2008

BubbleDeck
Structure Solutions
R

U N I T E D K I N G D O M

Site Erection &


Installation Manual
Type A - Filigree Elements

The Original Voided Flat Slabs


with BubbleDeck
VIETCONS EDUCATION www.vietcons.org

Site Erection and Installation Manual


Type A – Filigree Elements

BubbleDeck is a structural voided flat slab system that reduces Pre-Construction Planning
dead weight of a floor slab by 33%, allowing longer spans
We believe the key to achieving a successful construction build is
between column supports and a whole range of other design,
meticulous preparation and planning, with good communication. Well in
cost and construction benefits. The system eliminates secondary advance of construction commencing on site BubbleDeck’s managerial
supporting structure such as beams – the completed floor slab and technical team will closely work with you - advising on and defining
a detailed programme for the timing and phasing of drawing
spans in two directions directly onto pre-cast / in-situ reinforced
preparation, drawing review, drawing sign-off approval, element
concrete columns or structural walls. manufacture and element delivery to site – to match your strategic
approach and reflect your overall construction programme.
BubbleDeck is usually manufactured as partly pre-cast filigree
Please take into account there is a lead in period from the date of
elements, combining the benefits gained from off-site MMC
placing your BubbleDeck order – typically 3 weeks for our design /
techniques of factory manufacture in controlled conditions, general arrangement drawing work plus 9 weeks for preparation,
ensuring quality control and consistency, with on-site completion producing production / installation drawings and manufacturing of the
of the final concrete pour, resulting in a seamless completed floor elements (on larger projects drawing and manufacturing will be
undertaken in phases to match your construction programme) – before
slab - without the issues associated with fully pre-cast methods
we can commence site deliveries. Between these periods you need to
arising from dry joints resulting in noise transfer needing allow sufficient time for submitting our design / general arrangement
additional work to seal gaps, and need for structural toppings drawings to your Approved Inspector and receiving Building control
with additional construction layers. When the site topping approval, although in special circumstances and smaller projects we can
reduce these periods if our other commitments allow.
concrete has been cast a BubbleDeck structure is complete –
providing integral overall building stability, fire resistance, The pre-construction planning stages comprises:-
weatherproofing, and sound insulation. 1. Issuing to us frozen ‘For Construction’ Architects / Engineers general
arrangement plans, sections and relevant details in ,dwg file format
together with final loading information and firm order / deposit
Site erection and installation is simple and fast, well within the payment.
capabilities of any competent concrete contractor or sub- 2. Preparation by us of BubbleDeck full engineering design and general
contractor. On previous projects over 800m2 of BubbleDeck has arrangement plans, showing element layout, and submission to you
for review and technical approval.
been erected and completed within 4 working days. The elements
3. Submission by you of our design / drawings to Approved Inspector.
are manufactured 3 metres wide (upon request prior to ordering Referral to us of any queries and us providing answers / further
2.4 metres wide where site access is restricted) and the length is information as may be required.
varied, to suit project floor-plate configuration and transport 4. Confirmation from you Building Control approval receipt and issuing
to us sign-off approval of BubbleDeck design / general arrangement
efficiency, up to a maximum of 10 metres long.
drawings.
5. Develop together programme for production / installation drawings,
For more background information about the BubbleDeck system manufacturing and delivery to site
please study our separate Product Introduction Brochure prior to 6. Preparation by us of a detailed programme for production /
installation drawings, manufacturing and delivery to site. Review by
reading further.
you and issuing to us programme approval.
R

VIETCONS EDUCATION www.vietcons.org

U N I T E D K I N G D O M
Project: Le Coie Hotel Jersey Status: Issue 04 - 4th June 2004
Subject: Programme for production, manufacture & delivery of BubbleDeck floors
Date: 4th June 2004
Floortype: BD 280
Quantity: 7.484 m2

appr. 2004
quantily Week Commencing 3/5 10/5 17/5 24/5 31/5 7/6 14/6 21/6 28/6 5/7 12/7 19/7 26/7 2/8 9/8 16/8 23/8 30/8 6/9 13/9 20/9 27/9 4/10 11/10 18/10 25/10 1/11 8/11 15/11 22/11 29/11 6/12 13/12
m2 / Calendar Week No. 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
Stage Project Week No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
< Factory Closed >
1st floor 936
Blocks A-D 1
2
3
4
5 Last date reinf order/change prodn date> 4 weeks production < Production = 936 m2
6 < 7 loads @ approx 134 m2 per trailer
7 A-B C-D
2nd floor 1,044
Blocks A-D 1
2
3
4 < 9 hoisting beds returned to factory
5 Last date reinf order /change prodn date > 2 wk production 3 wk production < Production = 1,044 m2
6 < 8 loads @ approx 130 m2 per trailer
7 A-B C-D
3rd floor 1,053
Blocks A-D 1
2
3
4 < 9 hoisting beds returned to factory
5 Last date reinf order /change prodn date > 5 weeks production < Production 1,053 m2
6 < 8 loads @ approx 132 m2 per trailer
7 A-D
4th floor 798
Blocks B-D 1
2
3
4 < 9 hoisting beds retu
5 Last date reinf order /change prodn date > 4 weeks production < Production 798 m2
6 < 6 loads @ approx 1
7 B-D
5th floor 594
Blocks C & D 1
2
3
4
5 Last date reinf order /change prodn date > 4 weeks production < Prod
6
7
6th floor 294
Block C 1
2
3
4
5 Last date reinf order /change prodn date > 4 weeks production
6
7 * NOTE: For transport effic
total #REF! AND delivered together in
KEY PERIOD PER FLOOR
1. BDCI - Provisional production drawings 2 Weeks
2. ACM / DTM check provisional production drawings 2 Weeks
3. BDCI - Final production drawings 1 Week
4. ACM / DTM - formal approval final production drawings 1 Week
5. BDCI - Factory production 4 weeks
6. BDCI - Delivery period 2 weeks
7. ACM - Erection

Main Contractors last date for FULL delivery

BubbleDeck Drawing / Planning Pre-Cast Element Erection


Manufacturing / Delivery
Programme Prior to us commencing preparation production / installation drawings (see Stage 7, left) you
7. Confirm to us your planned sequence of erecting the BubbleDeck must confirm to us your planned sequence of erecting the BubbleDeck elements on site during
elements on site. construction. This sequence has to be incorporated on our drawing element numbering at an
8. Confirm to us your requirements for any phasing, day joints, and early stage and passed to our factory in order to ensure a) the correct element edge profiles
service riser holes above 250mm diameter you want pre-forming are manufactured, and b) plan the sequence of manufacturing / transporting elements.
in the factory. a) Element Edge Profiles: Longitudinal edges of elements require different detailing dependant
9. Planning by you of fixed / mobile crane provision and location upon their position – see drawing below showing slab edge cross-sections element as planned.
providing adequate capacity to lift heaviest elements. It is important the large splay shown on the right hand longitudinal edge is present at every
10. Advising us of your arrangements for site access and any access junction between two elements to provide adequate concrete cover, for fire resistance and
restrictions / procedures. durability performance, to the loose reinforcement splice bars laid across the elements joints on
11. Providing our advice on technical and practical construction top of the pre-cast concrete layer.
issues. Direction of Site Erection
12. Selection by you of preferred propping system and arranging
propping beam layout to be issued to us for review and
comment.
13. Preparation by us of production / installation drawings (projects
Detail of Element Longitudinal (Variable up to 10m long) Edges
above 2,000 m2 in phases as programmed) and submission to
you for review and formal sign-off approval.
14. Preparation by us of Quality and Delivery Control forms showing
planned loading of elements onto our transport trailers,
submission to you for review and approval. Detail of Element Short (3m or 2.4m long) Edges

page 2
VIETCONS EDUCATION www.vietcons.org

BubbleDeck’s Construction Package


Our Services and Products Our design
service includes
full engineering
calculations and
site installation
drawings.

Planning Pre-Cast Element Erection As part of our comprehensive service we will supply you with the following
continued construction information, advice, products and assistance:-
b) Manufacturing and Transporting Sequence: We
Project Stage Service / Product
will programme the order of manufacturing
elements and loading of the elements onto our BubbleDeck Design Engineering Design of BubbleDeck floor slabs & drawings. Submitting
transport to reflect, as closely as practically design to you for review and sign-off. Liaison with you about any checking
engineer / Approved Inspector queries and providing further information
feasible, your planned erection sequence. However,
as required.
for transport efficiency and safety, some elements
have to be loaded on the transport trailers out of BubbleDeck Drawing Preparation of manufacturing and construction drawings comprising i)
Production Element layout plan, ii) Loose bottom reinforcement (site installation), iii)
sequence to their erection order (e.g. small
Loose top reinforcement (site installation), iv) Bubble pattern v) Pre-cast
elements have to be stacked on top of larger reinforcement (incorporated into elements at factory). Submitting
elements), in which case these elements can be drawings to you & Consultants for review and sign-off.
temporarily lifted off and stored elsewhere on site Preparing programme for manufacture and supply of products to site,
Construction Planning
while the transport trailer is unloaded. The order of agreeing with you and placing orders for materials and manufacturing.
loading elements onto the transport trailers will be Preparation of bar bending schedules of loose site reinforcement for
shown on our Quality and Delivery Control form. supply to site by others.
Providing site operatives with product induction seminar.

Formal drawing review & sign off Product Advice Providing our advice on technical and practical construction issues.
prior to manufacture and Support BubbleDeck Site Erection and Installation Manual.
BubbleDeck Health & Safety Policy Guidance.
Once you have reviewed and we have received Quality and Delivery Control Forms.
your sign-off of our production / installation
Manufacturing Product Manufacture of prefabricated BubbleDeck elements comprising top &
drawings we can then implement manufacture of bottom mesh reinforcement / girders joining top / bottom mesh together /
materials and the elements and be ready to additional bar reinforcement / plastic bubble void formers (Type A Filigree
commence site deliveries of prefabricated elements with 70mm pre-cast concrete layer encasing bottom mesh
reinforcement).
BubbleDeck elements within advised
manufacturing lead-in period. Loose Reinforcement Preparing loose site reinforcement bar bending schedules for supply to
site by others.
We appreciate progress of construction on site can Site Delivery Monitoring and arranging delivery of prefabricated BubbleDeck
be affected by many external factors including elements to site, on time, using between 8 metre to 13.6 metre long
flatbed trailers.
exceptionally adverse weather and other events
Loan of BubbleDeck lifting chainsets during site installation for lifting and
beyond your control. If you need to change the placing BubbleDeck elements.
programming of BubbleDeck deliveries and/or
Site Support Technical advice and guidance to yourselves and site operatives on site
manufacture in response to such events please
installation & construction works.
immediately inform us so we can then re-
programme to your requirements. Once Site Inspections Site inspections of BubbleDeck installation & loose reinforcement checking
prior to casting of in-situ concrete.
BubbleDeck trailers have left our factory we regret
we are unable to defer site delivery without Insurance / Guarantees Following completion of works on site and account settlement entering
into suitable Collateral Warranty/s (subject to wording acceptable to our
passing on additional transport and storage /
Insurers) as may be required and provision of our Professional Indemnity
trailer hire costs. We have even advanced deliveries & Product Liability Insurance cover.
to keep up with quicker than expected progress
constructing BubbleDeck slabs on site.

page 3
R

VIETCONS EDUCATION www.vietcons.org


Concrete Column / Wall
Construction U N I T E D K I N G D O M

Important: In accordance with good practice and British Standards DO


NOT overpour r.c. columns / walls in order to avoid reducing the slabs
effective depth at support locations. Only use enough concrete to
bring r.c. columns / walls up to the underside of the BubbleDeck flat
slab level. In the event r.c. columns / walls are concreted above this
level our Site Advisor/Inspector may require the concrete to be cut
down around the perimeter of r.c. columns / walls to ensure adequate
connection with the BubbleDeck slabs.

Combined Column / Wall & BubbleDeck Construction Method

While sequencing of site operations is your responsibility to decide we recommend the most efficient method, saving valuable site time
and overheads, is to plan construction of supporting r.c. columns and walls together with the BubbleDeck floor slab in one combined
erection operation as detailed in the following table:-

Stage Operation Activities

1 Column / wall reinforcement a) Fabricate & erect r.c. column & wall reinforcement.
& formwork b) Fabricate formwork shuttering with horizontal plywood top flange
(Prior to BubbleDeck element delivery) 200mm wide extending out from vertical shuttering & bracket supported
by vertical shuttering.

2 Temporary Propping a) Erect Temporary Propping beams. (Refer to Stage 1 on page 5)


(Prior to BubbleDeck element delivery) b) Erect formwork shuttering and (when suitable stable propping such as
SGB GASS system is used) brace upper formwork off temporary propping
frames.

Note: When column / wall formwork is to be braced off slab it will be


more convenient to erect this before erecting temporary propping)

3 BubbleDeck Element Erection Receive, lift and place BubbleDeck elements onto temporary propping
beams. (Refer to Stage 2 on page 6)

4 Loose Reinforcement Install BubbleDeck loose reinforcement (Refer to Stage 3 on page 8)

5 Slab shuttering Fabricate and erect perimeter & tolerance joint shuttering (Refer to Stage
4 on page 9)

6 Slab Preparation Prepare columns, walls and BubbleDeck slab for concreting (Refer to Stage
5 on page 9)

7 BubbleDeck Site Inspection Notify us of the date set for concreting (Refer to Stage 6 on page 10)

8 Pouring Site Concrete Pour concrete firstly into columns and walls, vibrate and compact. Then as
a continuous process pour concrete onto BubbleDeck slabs (Refer to Stage
7 on page 10)

This combined erection method has the advantages of a) Condensing a two stage sequence (erecting & casting
columns / walls first and then BubbleDeck slabs second) into a one stage sequence; b) Providing s stable & firm
platform for casting columns / walls; c) Eliminating separate concrete deliveries for columns / walls and slabs;
and d) ensuring a good bond between column / wall and BubbleDeck slab site concrete.

page 4
VIETCONS EDUCATION www.vietcons.org

Site Erection and Installation


Type A – Filigree Elements

Stage 1 – Erect Temporary Propping


During erection each slab must be placed on suitable temporary
Back-Propping
propping beams arranged in parallel rows mounted on props
sufficient to adequately support the weight of the pre-cast filigree
When consecutive floor slabs within one block are
elements plus the loose reinforcement fixed on site, concrete
to be constructed above each other either: a) the
poured on site and all other site construction loads applied during
slab below the one being constructed must be
final pouring of the concrete topping and curing of the slab.
back-propped, or alternatively b) each completed
slab must be self-supporting within the maximum
• The maximum distance between propping beams must not be
allowed deflection.
greater than 1.8 metres or as advised
• The maximum distance of the propping beams from slab edges
Option a) Prior to erecting propping for the next,
must be as follows:
subsequent, slab above the completed slab
- from an edge where a slab is supported on brick or
remove the propping from below the completed
concrete walls – 800mm (minimum 50 mm support)
slab and erect back-props at 2.4m intervals
- from an edge next to construction tolerance joints –
(without parallel beams) at either mid-span or
200mm
third-span, dependant upon length of spans
involved.
Propping beams must be at right angles to the direction of the
reinforcement girders pre-cast in the element. Normally the girder
Option b) Prior to erecting propping for the next,
reinforcement is placed parallel to the length of each slab but this
subsequent, slab above loosen the props below
must always be checked against the manufacturing and installation
the completed slab, to allow the floor to reach it’s
drawings. The propping beams, and individual props below, must
maximum deflection, and then tighten the props
form a stable platform prior to placing filigree elements onto them
again. This is to ensure additional loads from the
and maintained stable during casting of the site concrete.
slab being erected above are taken on its own
props rather than adding to loads onto the floor
Important: Removal of the temporary propping is NOT
directly below, avoiding weight accumulation from
allowed before each slab is cured sufficient to support its
consecutive floors placing unnecessary strain on
own weight and temporary construction loads.
props and other construction elements.

Typical cross-section of temporary propping system

page 5
R

VIETCONS EDUCATION www.vietcons.org

U N I T E D K I N G D O M

Typical arrangement of Loaded trailers


props and propping beams arriving on site

Following your inspection the delivery driver will require you to sign the Quality and
Stage 2 Delivery Control Form to confirm you have received the elements, which will be retained
– Delivery, Lifting by him / her for our records. After removing all the filigree elements from the flatbed
trailer the wooden transport packing beams / blocks must be replaced back onto the
and Placing Elements trailer before it leaves site, for return to our factory and re-use. Any transport materials
Site Delivery: We deliver the elements on flatbed that are not returned to our transport operator will be contra-charged by us to your
trailers typically between 12m to 13.6m long, excluding account.
drivers cab. The filigree elements will be stacked on top
of each other up to a maximum 2.5 metres overall Offloading Filigree Elements: It is your responsibility to provide attendance and
height. For example, with BD280 slabs there will be adequate mechanical equipment (fixed or mobile crane with typical 6 Tonne lifting
maximum 7 layers of slabs, with a transport height of capacity) for offloading elements from the trailers upon their arrival at site. For optimum
250mm each plus wooden packers typically 50mm deep working efficiency we recommend you plan site operations to allow the filigree
separating each element, making an overall height of 2.1 elements to be lifted off the trailers and moved straight into their final position
metres above the trailers bed. Each individual load will on the temporary propping.
be planned so the weight of a load will be a maximum
29 Tonnes and you must provide suitably hard and level However, for transport efficiency and safety some elements are loaded onto the trailer
access for our delivery transport to reach the offloading out of sequence to their erection order, in which case or in the event of site
position you have determined. circumstances preventing final placing the filigree elements can be temporarily stored
elsewhere on site. The elements must be transversely supported on timber packers laid
Important: between the bubble rows (sat on the top reinforcement mesh) at maximum 1.8 metres
Upon arrival of the delivery trailers on site it is centres resting on flat, level, ground and protected from soiling by mud, dirt, or other
your responsibility to carefully inspect the filigree materials. Elements can be stacked on top of each other to a maximum 7 layers high.
elements for quality and to ascertain any damage
that has been incurred during transport. Any While we will organise and plan deliveries in accordance with your programme
damage to the filigree elements, or other as earlier agreed with us (refer to Pre-construction Planning on page 1) we are
unacceptable characteristics, must be reported by unable to accept any responsibility for any delays with deliveries or construction
you to us by entering the details on our Quality progress arising from events outside our control such as unexpected access
and Delivery Control Form and faxing this back to restrictions or force majeure.
our Head Office within 2 hours of trailer arriving
on site. Once the elements have been lifted off the Lifting and Placing Filigree Elements: The filigree elements must ONLY be lifted by
trailer we may be unable to determine when any the lattice beam girder reinforcement. Lifting hooks must ALWAYS be attached under the
damage occurred and in this event we cannot
upper angles of the girder reinforcement diagonal web bars. Lifting hooks must NEVER
accept responsibility.
be attached to the upper reinforcement mesh as this would be unsafe.

page 6
VIETCONS EDUCATION www.vietcons.org
Lifting
element
into
position

Stage 2 - Delivery, Lifting and Placing Elements


continued

Positioning of Filigree Elements on Propping: It is important the


elements are lifted into position in the planned erection system, and care
is taken with correct positioning of the elements. Each element must be
Lifting positioned the correct way round (often obvious from position of column
hooks under cut outs and building shape, but please refer to element installation
girder drawings) so the top chamfer along the longitudinal edge is butted up to
diagonal
the adjacent elements vertical longitudinal edge. Adjacent elements must
web bars
NOT have their top chamfers facing together.

Important: During final positioning of the elements ensure


the bubble pattern between adjacent elements are aligned as
shown on the installation drawings, so the spaces between bubble
rows on adjacent elements align to facilitate inserting splice
reinforcement across the joint between elements.

It is your responsibility to organise and provide suitable lifting


equipment. All lifting equipment must be tested and certified
capable of lifting a minimum of 6 Tonnes, appropriate for the
purpose as described below, and must meet all legal health and
safety requirements.

Each individual element requires the use of EIGHT lifting hooks, in 2


parallel rows of 4 hooks each attached around the lattice girders
positioned approx. 1/5 of the total element length in from each end.
The upper part of the hoisting system (4 suited chains) must be at least
6 metres minimum in length. Chain branches to the eight lifting hooks
Aligning bubbles between elements
must be equal lengths. When in use, care should be taken that lifting
forces are equal at each lifting hook point and the element remains For quick installation of the bottom splice reinforcement we recommend
horizontal during lifting. Before lifting attach suitable ropes at two when the first element is in final position the bottom splice bars are
opposite corners of the element for guiding element into position on temporarily slid fully in between the bubble rows on top of the pre-cast
the propping beams. concrete layer before the adjacent element is placed. At a later stage
please remember to slide the bottom splice bars back across the element
Typical lifting
chain joint between the bubble rows in the adjacent element, so the bars are
configuration finally positioned half in one element and half in the adjacent element
prior to concreting.

page 7
R

VIETCONS EDUCATION www.vietcons.org

Stage 3 U N I T E D K I N G D O M

– Fixing Loose Site Reinforcement.


We provide site installation drawings for loose site reinforcement (supplied by others)
fixed at the bottom of the slab (directly on top of the pre-cast concrete filigree
permanent formwork without spacers or on top of site shuttering on spacers) and
reinforcement fixed at the top of the slab (directly onto top mesh reinforcement),
together with accompanying bar bending schedules. These must be studied and closely
followed at all times, if you have any question please call our Site Advisor/Inspector or
Head Office for assistance. The sequence for fixing loose reinforcement is at your
discretion, however we recommend the following procedure is adopted:-
Sliding bottom splice bar central over joints
Typical Installation / Fixing Procedure
Reinforcement
Site Adjustment of Filigree Elements: The filigree elements are
Type
designed and manufactured to suit the buildings configuration and
1. Bottom Joint Inserted loose between every bubble directly on top of the pre-
column / wall layout. They arrive on site with cut-outs / recesses /
Splice Bars cast concrete biscuit permanent formwork. If they have been
steps for column or wall positions (including a 50-100mm inserted into one element during lifting elements into position,
construction tolerance margin between r.c. columns / walls and the as we recommend, then simply slide the bars across the joint
pre-cast concrete layer) and larger service holes already formed, between adjacent elements to sit with equal lengths both sides
of the joint between elements.
therefore they should not require any site adjustment. However it
has been known for columns to be erected out of position on site 2. Bottom Shear Inserted loose between bubbles in positions shown on drawings
and in this unusual event it is possible to carefully alter the filigree Bars across holes, openings and returns in slabs where applicable
element with a disc cutter to maintain the margin between r.c. 3. “Beam Strips” Where applicable assemble bars into cages and fix between
columns / walls and the elements pre-cast concrete biscuit. within Slab and / or around columns (as shown on drawings)
Depth
Important: The upper and diagonal bars in the lattice 4. Perimeter Slide hairpins in between bubble rows and slide in top / middle
beam girder reinforcement must NOT be cut on site as they Hairpins / Bars / bottom edge bars around slabs perimeter, tying to hairpins as
have an important structural function both during lifting and shown on drawings
once in place. 5. Column Shear Insert bottom bars across columns directly on top of the pre-
Reinforcement cast concrete bottom formwork. Fix bars over top mesh
reinforcement (between the bubbles) across and around column
Do not cut top bar Lattice beam girder heads as shown on drawings, tying in place to mesh.
Note: where shear studs or shear rails have been pre-cast into
element at factory there may not be any bars to be fixed on site.
6. Top Joint / Element joint splice reinforcement comprising either individual
Top bar short bars or purpose made mesh sheets (supplied by others)
Reinforcement are placed with the bars between bubble rows and tied in place
equally across the joint between adjacent elements. In certain
areas, for engineering reasons, additional top bar reinforcement
will be required (supplied by others) which must be laid
between bubble rows (not across top of bubbles) directly onto
and tied to top mesh reinforcement, as shown on the drawings.
The first layer of top additional bar reinforcement must be laid
across top of lower bars of top mesh reinforcement to avoid
unnecessarily reducing top concrete cover.
Do not cut diagonal bars Other Loose As building configurations vary it is not possible to describe all
Reinforcement possible non-typical loose reinforcement configurations (such as
Cut-Outs, Recesses and Service Holes: During the manufacturing cages for steps between main slab and cantilever slab) requiring
site fixing. This non-typical reinforcement will be shown and
process polystyrene void formers are fixed in these locations to create
detailed on the site installation drawings.
areas without any concrete bottom biscuit. During erection of the
elements these are quickly broken out with a suitable chisel and mallet. Important: Top joint and additional bar reinforcement first
layer must be laid between bubble rows (not across top of
bubbles) straight onto top of lower bars of top mesh
reinforcement to avoid excessive layers of steel and
difficulty with achieving required concrete cover.
page 8
VIETCONS EDUCATION www.vietcons.org

Stage 4
– Constructing Shuttering
Once the perimeter loose reinforcement has been
installed work on erecting perimeter and
construction joint shuttering can commence.
Temporary works are your responsibility to
determine, but our recommendations are:-

Location Shuttering Erection Procedure Stage 5


Perimeter Shuttering Cut sheet of 18mm ply into strips to width of finished slab – Preparation for
depth. Fix 75x50mm battens along back edge at top and
bottom. Where BD element is tight to edge of finished slab Concreting
simply plug and screw through bottom batten & ply shuttering
straight into centre of pre-cast concrete permanent formwork The pre-cast concrete permanent formwork edges are
edge. Fix top of ply shuttering by wire tying back to top mesh manufactured to a high accuracy and care taken to get
reinforcement from screws fixed into top batten. a tight joint during laying the elements can render joint
filling unnecessary. When joints between slab elements
When an in-situ concrete edge strip has been planned to make have not been closely butted they must be filled to
up the overall floor-plate width then construct perimeter
prevent grout seepage. Should this be required joint
shuttering with timber gallows brackets & plywood perimeter /
filling can be undertaken with either mortar grout or a
soffite shuttering in traditional manner, except bracket bottom
batten can be plugged and screwed to underside of pre-cast small bead of silicone sealant inserted at the bottom of
concrete permanent formwork. the splay joint between elements. This is most easily
undertaken prior to installing the loose splice
Construction Tolerance Cut sheet of 18mm ply into strips 150mm wide, plug and screw reinforcement.
margin around r.c. 50x50 battens to face of r.c. columns / walls (top 18mm below
columns / walls * slab soffite), slide ply into position. Plug and screw external Important:
edge of ply shuttering into underside of pre-cast concrete – expanding foam must NOT be used for joint
permanent formwork. filling as the uncontrollable thickness can
adversely reduce concrete cover to splice
* Note: When our combined column / wall and reinforcement impairing durability and fire
BubbleDeck construction method is adopted (see page 6) resistance of the finished slab.
the pre-assembled column / wall formwork top flange
eliminates any need for this operation. Prior to pouring topping concrete remove element
labels, unused tying wire, unused reinforcement, loose
Construction tolerance Cut sheet of 18mm ply into strips 180mm wide and prop up to
concrete and all other debris or foreign matter. Then
joints between groups underside of pre-cast concrete permanent formwork.
immediately before placing in-situ concrete power-wash
of elements
top of the pre-cast concrete permanent formwork to
Note: We can manufacture and supply pre-cast into
clean off residual dirt and moisten the pre-cast concrete
surface.
edge of elements a pre-foabricated “BubbleDeck Quick

Edge” steel permanent formwork, eliminating the need Important:


for constructing perimeter shuttering on site – enquire
– maintain the pre-cast concrete biscuit top
surface, particularly during hot weather, in a damp
for further details at time of placing order. (not wet) condition to ensure a good bond
between the pre-cast concrete permanent
formwork concrete and the in-situ concrete.

page 9
R

VIETCONS EDUCATION www.vietcons.org

Stage 7 – Pouring Topping Concrete


Important: When ordering concrete please take into account the volume taken up by the
bubble void formers mean the concrete volume is NOT arrived at by taking the pour area x
depth from top of shuttering to pre-cast concrete permanent formwork. The concrete volume to
order can be estimated, dependant upon BubbleDeck slab depth type, from the following table:-

When pouring concrete Overall Slab Depth Concrete pour Volume Max aggregate
BubbleDeck
evenly distribute across Slab Type (inc. pre-cast filigree) m / m plan area
3 2
size
BD230- A 230 mm 0.112 10mm
the area and avoid placing BD280 -A 280 mm 0.147 10mm
in heaps. Due to the BD340 -A 340 mm 0.192 15mm
BD390 -A 390 mm 0.224 15mm
limited space between the BD450- A 450 mm 0.271 15mm
bubbles a thin vibrating BD550- A 550 mm 0.360 15mm
BD650- A 650 mm 0.420 15mm
Pouring, Vibrating poker MUST be used to compact the concrete,
& Floating Site remove any entrained air and to ensure a good flow around the bubbles. Avoid separation occurring due to the vibrating
Concrete
of shuttering, reinforcement and/or bubbles that can result in segregation of the concrete mix. Once the concrete has
been poured a steel beam or power float is then used to level the top and finish to an even and level surface.

Stage 6 Stage 8 – Removing Temporary Propping


– BubbleDeck Site During construction planning we will confirm to you the minimum period for removal of propping before back-propping.
This is usually between 3 to 5 days from pouring of the site concrete as long as the early concrete test results have
Inspection confirmed the site concrete has reached at least 60% of its final design strength, but can vary dependant upon our floor
Once you are able to predict when all slab design, strength of site concrete, and ambient temperatures.
loose reinforcement will be fixed
please contact our Site Once you have received the 3-5 day concrete test results please forward them to our Head Office, our technical team will
Advisor/Inspector to notify the date then confirm to you it is acceptable to remove temporary propping. If you are then proceeding to construct another floor
you intend to pour concrete and immediately above the one just completed please refer to the section about Back Propping on Page 5 of this Manual.
arrange our site inspection. He will
then arrange for our technical
Subsequent Site Operations
representative to visit site and Lightweight Fixings
There is a minimum of 20mm concrete below the centre of each bubble, but just a short distance away from the bubble centre the
undertake a full inspection of the
concrete depth quickly increases to 70mm plus up the side of each bubble. Therefore fixings for attaching light and medium
ht weig
BubbleDeck element and loose
articles can be made using normal methods (plug & screw / expanding anchors, etc.) to provide adequate fixings for wiring
reinforcement installation. Following conduits, small cable trays, small ventilation ducts and the like.
inspection our technical
representative will issue you with an Heavy Weight Fixings
inspection record listing any work Where stronger fixings are required to resist higher pull out (downward) forces from heavy loads to be suspended from te the soffi
we recommend our Bubble layout drawings are inspected to determine where fixings will occur directly below or close to the edge
that needs to be undertaken prior to
of a bubble. Where fixing locations and lengths are likely to project into a bubble void we recommend Hilti HIT HY20 Injection
site concreting, or confirming the Resin Anchor with HIT sieve, item no. 00068613, are used. Hilti also produce a range of other fixing systems designedg for fixin
installation is ready for concreting through into voids.
and the work is to our approval.
Holes through slabs
Important: Holes can easily be diamond core drilled through the completed BubbleDeck slab. Due to the two way spanning attributes of
– While we always seek to provide BubbleDeck slabs there are few limitations on the positioning of holes, except near columns where loads are transferred
e from th
a quick and efficient service we slab into the columns and shear forces are highest.
do need at least 2 working days
notice of any site concrete pour to Service risers larger than 250mm square should be designed into the slab for forming in the factory & boxed out on osite prior t
be able to ensure our inspection pouring insitu concrete. Pipe holes up to around 250mm diameter are best diamond core drilled after casting of slabs to ensure
team are available to attend site. optimum vertical alignment. There is great flexibility where these can be placed because the slab will span around such
The holes.
It is essential we are able to only limitations are to avoid cutting off too much support when holes are formed near supporting columns / walls, orf a series o
inspect prior to site concreting in holes in a row in certain situations, but these can be allowed for during design stage.
order to be able to cover your
project with our Professional Prior to forming holes in completed slabs larger than 250mm diameter, within 500mm of a supporting column / wall,
Indemnity and Product Liability or multiple holes in close proximity please refer to our Technical Department for advice before undertaking such works.
Insurance cover.
page 10

You might also like