Construction Simulation An Introduction: Tim O'Leary Construction Solutions Europe & Africa

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 46

© 2009 Bentley Systems, Incorporated

Construction Simulation
An Introduction
Tim O’Leary
Construction Solutions Europe & Africa
Solutions

CADASTRE
CADASTRE AND
AND LAND
LAND
BRIDGES
BRIDGES BUILDINGS
BUILDINGS DEVELOPMENT
DEVELOPMENT CAMPUSES
CAMPUSES COMMUNICATION
COMMUNICATION
SS

ELECTRIC
ELECTRIC AND
AND METALS
METALS AND
AND POWER
POWER
GAS
GAS UTILITIES
UTILITIES FACTORIES MINING OIL
OIL AND
AND GAS
GAS GENERATION
GENERATION
FACTORIES MINING

© 2009 Bentley Systems, Incorporated


WATER
WATER AND
AND
RAIL
RAIL AND
AND TRANSIT
TRANSIT ROADS
ROADS WASTEWATER
WASTEWATER

2 | WWW.BENTLEY.COM
Construction Simulation

CONSTRUCTION Best practices and the challenges


TODAY in applying them

BENTLEY’S
Proven solution to plan, process and
CONSTRUCTSIM
OVERVIEW
status construction

• VPM • Status tracking


USING
• Data Reorganisation • Work Packs
CONSTRUCTSIM
• 4D playback • Look ahead planning

© 2009 Bentley Systems, Incorporated


• Greater workforce productivity
BENEFITS • Shorter project time
• Substantial cost savings

3 | WWW.BENTLEY.COM
Overview

Construction Best
Practices

Software Technology ConstructSim

© 2009 Bentley Systems, Incorporated


Virtual Plant
Model

4 | WWW.BENTLEY.COM
Current Major Issues

Engineering
1, 2
7 3, 4, 5
6, 8

Delivery + Fabrication
1, 2
7 3, 4, 5
1. Poor communications 6, 8
between
disciplines and functions Installation
2. Concurrent engineering 1, 2
9 3, 4, 5
3. Fast-track projects 6, 8
4. Limited resources
5. Ageing skilled workforce
Testing
1, 2
6. Schedule / install by area –

© 2009 Bentley Systems, Incorporated


9 3, 4, 5
test and turnover by systems
6, 8
7. Short time between
AFC/IFC and constructiona) Engineering deliverables Systems Turnover
8. Many revisions b) Materials availability
9. Operate in “scramble” mode
c) Allocation of materials
and work with whatever is
available d) Fabrication deliverables

5 | WWW.BENTLEY.COM
Common Questions
Is the planned What is the exact
schedule How will engineering
progress to date? changes affect work
achievable?
content, cost and
schedule?

How will the


schedule be kept
given the changing
circumstances?

What effort is
needed to
complete?

© 2009 Bentley Systems, Incorporated


What will be
the project impact be if
materials are delayed?

6 | WWW.BENTLEY.COM
Workflow Planning

Define Priority
Engineering Areas Early on in
Design

Suppliers / IFC
Constructor
Fabricators Drawings

Automate MTOs

Last Planner
Create Work
Packs

© 2009 Bentley Systems, Incorporated


Lean Construction

Issue work to the Validate


field that can be Constraints
done

7 | WWW.BENTLEY.COM
Linear Definition of Priorities

Construction
Ideal Construction Sequence
Based on Turnover Systems

Drawings Materials Installation Testing Completion


Issued Delivery Complete Complete Date

Systems
Engineering Delivery Installation Testing
Turnover

© 2009 Bentley Systems, Incorporated


Definition of Priorities

8 | WWW.BENTLEY.COM
Managing Work Buffers to Speed Projects

Engineering

Delivery + Fabrication

Installation

Testing

© 2009 Bentley Systems, Incorporated


Systems Turnover

9 | WWW.BENTLEY.COM
Construction Simulation

CONSTRUCTION Best practices and the challenges


TODAY in applying them

BENTLEY’S
Proven solution to plan, process and
CONSTRUCTSIM
OVERVIEW
status construction

• VPM • Status tracking


USING
• Data Reorganisation • Work Packs
CONSTRUCTSIM
• 4D playback • Look ahead planning

© 2009 Bentley Systems, Incorporated


• Greater workforce productivity
BENEFITS • Shorter project time
• Substantial cost savings

10 | WWW.BENTLEY.COM
ConstructSim Approach

• Drive priorities based on “ideal” construction


sequence based
on turnover systems
• Expedite both engineering and fabrication to
deliver against ideal plan
• Allocate materials based on priorities
• Accurately track effort for completion
• Manage work-fronts effectively
as constraints change on site

© 2009 Bentley Systems, Incorporated


11 | WWW.BENTLEY.COM
Client Feedback
Increase field Save time and cost on
productivity 7 – 25% Brownfield projects
– Streamline sequencing – TIC $50M – Savings $1M
– Reduced rework – Completed 1 month
– Automated production ahead
of work packages of schedule
– Work packages are
executable

Piping Welding

© 2009 Bentley Systems, Incorporated


ConstructSim
2x faster 1.8x faster

12 | WWW.BENTLEY.COM
Diesel Refinery: $2M Savings in Mechanical Sub Change Orders

Background
– New Refinery Unit - TIC $320M
– Lump Sum Contract with Mechanical Sub
– ConstructSim Pipe purchased by Owner and
utilized by Construction Management firm

ConstructSim Use Case


“ ConstructSim enabled
us to recover project – Excessive change order submitted by
schedule losses, and Mechanical Sub
complete on time - – Actual progress not in alignment with
without paying for

© 2009 Bentley Systems, Incorporated


progress reported
unwarranted change – ConstructSim used to analyze change order
orders.” and update progress reporting system
Claim: $2.5M
Settled: $0.5M

13 | WWW.BENTLEY.COM
Offshore Platform: Saved $17M, Reduced Schedule 3 Months

Background
– Deepwater Offshore Platform - $150M
– Time and materials contract with Fab Yard
– ConstructSim Pipe purchased by Owner and
utilized by module Fab Yard contractor

ConstructSim Use Case


“ The labour efficiency
we obtained using – ConstructSim used to re-baseline
ConstructSim enabled project schedule
us to save 3 months – Development of crew-level work face
and U.S.$17M, as well

© 2009 Bentley Systems, Incorporated


plans with ConstructSim
as reduce the punch list – Project completes on time, under budget,
items by over 99%.” and sails away with only 7 punch list items
(compared to 1000’s for other projects)

14 | WWW.BENTLEY.COM
ConstructSim Provides Measureable Savings

Reduce Impact
of Change

Reduce
Wasted Time

Minimize
Rework 1% to 5% TIC
Reduce
Lengthy

© 2009 Bentley Systems, Incorporated


Planning Process

Streamline
Materials
Management

15 | WWW.BENTLEY.COM
Who Uses ConstructSim?

© 2009 Bentley Systems, Incorporated


Engineers and Constructors, Ltd.

16 | WWW.BENTLEY.COM
ConstructSim Solves Complex Planning and
Execution Problems Work the Plan
ConstructSim

• Owners Reporting & Simulation

• Construction
Managers
• Constructors

CAD Databases Project Schedule

Virtual

© 2009 Bentley Systems, Incorporated


Plant Model

Materials Management Project Controls


System Database

17 | WWW.BENTLEY.COM
Construction Simulation

CONSTRUCTION Best practices and the challenges


TODAY in applying them

BENTLEY’S
Proven solution to plan, process and
CONSTRUCTSIM
OVERVIEW
status construction

• VPM • Status tracking


USING
• Data Reorganisation • Work Packs
CONSTRUCTSIM
• 4D playback • Look ahead planning

© 2009 Bentley Systems, Incorporated


• Greater workforce productivity
BENEFITS • Shorter project time
• Substantial cost savings

18 | WWW.BENTLEY.COM
Using Bentley’s
ConstructSim Status
Tracking

Week 1
4D Work
Playback Packs

Automatic Look
Data Ahead
Organization ConstructSim Planning

© 2009 Bentley Systems, Incorporated


Virtual
Plant Model

19 | WWW.BENTLEY.COM
Project Schedule Integration

MTO
From CAD +
Production Information

Schedule ConstructSim

© 2009 Bentley Systems, Incorporated


Task Templates &
Work Steps Standard Norms

20 | WWW.BENTLEY.COM
Project Milestones

Project Project Project Project


Milestone 1 Milestone 2 Milestone 3 Milestone N

Rules
Rules Rules Rules
Of Of Of Of
Progress Progress Progress Progress

Engineering Fabrication Installation Testing


Initial Design Drawings Install Completions
Final Design Received Test Commissioning
Check 1 In Production Hand over Etc. Etc.

© 2009 Bentley Systems, Incorporated


Check 2 Shipped
Check 3
Approval

21 | WWW.BENTLEY.COM
Automatic Data
Organization Status
Tracking

Week 1
4D Work
Playback Packs

Automatic Look
Data Ahead
Organization ConstructSim Planning

© 2009 Bentley Systems, Incorporated


Virtual
Plant Model

22 | WWW.BENTLEY.COM
ConstructSim Automatic Data Reorganization for
Construction Tasks

© 2009 Bentley Systems, Incorporated


23 | WWW.BENTLEY.COM
4D Playback Status
Tracking

Week 1
4D Work
Playback Packs

Automatic Look
Data Ahead
Organization ConstructSim Planning

© 2009 Bentley Systems, Incorporated


Virtual
Plant Model

24 | WWW.BENTLEY.COM
4D Playback to Optimize and Communicate the
Construction Sequence

© 2009 Bentley Systems, Incorporated


25 | WWW.BENTLEY.COM
Status Tracking Status
Tracking

Week 1
4D Work
Playback Packs

Automatic Look
Data Ahead
Organization ConstructSim Planning

© 2009 Bentley Systems, Incorporated


Virtual
Plant Model

26 | WWW.BENTLEY.COM
On-Demand Status Tracking and Visualisation

© 2009 Bentley Systems, Incorporated


27 | WWW.BENTLEY.COM
Tracking Equipment Delivery

© 2009 Bentley Systems, Incorporated


28 | WWW.BENTLEY.COM
Pipe Delivery Status Visualization

© 2009 Bentley Systems, Incorporated


29 | WWW.BENTLEY.COM
Area 08
(Mod and
Non-Mod Pipe)

© 2009 Bentley Systems, Incorporated


Pipe Delivery Status Visualization
30 | WWW.BENTLEY.COM
Pipe Delivery Status
Visualization
Area 11
Area 15

Pipe Delivery Status Visualization


Area 02

© 2009 Bentley Systems, Incorporated


Pipe Hydro Test Status Visualization
33 | WWW.BENTLEY.COM
Area 06

© 2009 Bentley Systems, Incorporated


Pipe Hydro Test Status Visualization
34 | WWW.BENTLEY.COM
© 2009 Bentley Systems, Incorporated
Area 16

Pipe Hydro Test Status Visualization


35 | WWW.BENTLEY.COM
Work Packs Status
Tracking

Week 1
4D Work
Playback Packs

Automatic Look
Data Ahead
Organization ConstructSim Planning

© 2009 Bentley Systems, Incorporated


Virtual
Plant Model

36 | WWW.BENTLEY.COM
Fast, Easy Work Pack Creation

© 2009 Bentley Systems, Incorporated


37 | WWW.BENTLEY.COM
Look Ahead Planning Status
Tracking

Week 1
4D Work
Playback Packs

Automatic Look
Data Ahead
Organization ConstructSim Planning

© 2009 Bentley Systems, Incorporated


Virtual
Plant Model

38 | WWW.BENTLEY.COM
Work Pack Reports and Look Ahead Planning
to Streamline Scheduling

© 2009 Bentley Systems, Incorporated


39 | WWW.BENTLEY.COM
Construction Simulation

CONSTRUCTION Best practices and the challenges


TODAY in applying them

BENTLEY’S
Proven solution to plan, process and
CONSTRUCTSIM
OVERVIEW
status construction

• VPM • Status tracking


USING
• Data Reorganisation • Work Packs
CONSTRUCTSIM
• 4D playback • Look ahead planning

© 2009 Bentley Systems, Incorporated


• Greater workforce productivity
BENEFITS • Shorter project time
• Substantial cost savings

40 | WWW.BENTLEY.COM
ConstructSim Benefits for Owner Operator

• Enables schedule date to be


met

• Reduces costs

• Provides an insight to
project progress

• Potential to shorten schedule


and achieve additional
production

© 2009 Bentley Systems, Incorporated


41 | WWW.BENTLEY.COM
ConstructSim Benefits
for Construction Managers

• Saves 1-5% TIC or 7 – 25%


of field man-hours

• Reduced claims litigation

• Greater control and visibility


of project

• Start up date controlled /


compressed

• Know where you are at and

© 2009 Bentley Systems, Incorporated


what needs to be completed

42 | WWW.BENTLEY.COM
ConstructSim Benefits for
Direct Hire Contractors

• Reduces wasted time on-site

• Improves field productivity by 7 -


25%

• Reduces rework and out of


sequence work

• Maximises productivity of on-site


equipment e.g. cranes / scaffold

• Improves co-ordination between

© 2009 Bentley Systems, Incorporated


disciplines

43 | WWW.BENTLEY.COM
Cost Savings
Co-ordination between disciplines to maximise
effectiveness of resources such as scaffolding / cranes

Work pack planning man-hours


REDUCE Wasted field man-hours
Rework
“Punch list” items

REMOVE “Out of sequence” work

SAVE Between 1% - 5% of TIC

© 2009 Bentley Systems, Incorporated


ACHIEVE On-time project completion

44 | WWW.BENTLEY.COM
© 2009 Bentley Systems, Incorporated
Thank you

Sustaining Infrastructure
Additional Information

• Streamlining Materials

• Planning Levels

• Additional Details

• Electrical / Instrumentation

© 2009 Bentley Systems, Incorporated


46 | WWW.BENTLEY.COM

You might also like