Professional Documents
Culture Documents
A4 Panathur Schedule
A4 Panathur Schedule
A4 Panathur Schedule
CONSTRUCTION OF NRO - PLOT SIZE 38 M X 25 M
D E T A I L E D B A R C H A R T - 7 W E E K S
10-Aug-19
12-Aug-19
13-Aug-19
14-Aug-19
15-Aug-19
16-Aug-19
17-Aug-19
18-Aug-19
19-Aug-19
20-Aug-19
21-Aug-19
22-Aug-19
23-Aug-19
24-Aug-19
25-Aug-19
11-Aug-19
5-Aug-19
6-Aug-19
7-Aug-19
8-Aug-19
9-Aug-19
Total Project 5-Aug 21-Sep
3 CANOPY
Excavation soil upto 1.50 m 10-Aug 12-Aug
Foundation - PCC 1:4:8 mix 13-Aug 15-Aug
RCC HYSD Steel Bars 14-Aug 15-Aug
Foundation - RCC 1:11/2:3 16-Aug 20-Aug
RCC Pedestal 21-Aug 25-Aug
Backfilling 22-Aug 26-Aug
4 Front Culvert
Exit and Entry Approach Alternatvely
Excavation 13-Aug 15-Aug
PCC 16-Aug 16-Aug
RR Masonry 17-Aug 19-Aug
RCC Slab 20-Aug 20-Aug
Open Drain wall 2 sides 21-Aug 21-Aug
Backfilling 22-Aug 22-Aug
Open drain
Excavation 27-Aug 28-Aug
PCC 28-Aug 28-Aug
RR Masonry 29-Aug 31-Aug
5 SALES BUILDING
Exe.soil upto 1.5M 10-Aug 10-Aug
PCC for footing 10-Aug 11-Aug
Steel binding for Footing 11-Aug 13-Aug
RCC for sales bldg footing 14-Aug 16-Aug
Column rcc upto plinth 17-Aug 18-Aug
Back filling foundation 19-Aug 20-Aug
Excavation, PCC & bar bending for Plint 20-Aug 21-Aug
Shuttering for PB 21-Aug 21-Aug
Placing of PB Reinforcement 22-Aug 22-Aug
RCC for Plinth Beam 23-Aug 23-Aug
RCC Column upto roof beam 24-Aug 26-Aug
BW upto FFL 24-Aug 26-Aug
Back filling basement 27-Aug 28-Aug
Sand filling & PCC for flooring 28-Aug 29-Aug
Masonry work including lintel 26-Aug 31-Aug
Bar bending & Shuttering for roof 1-Sep 3-Sep
RCC 1:1.5:3, for slab 4-Sep 4-Sep
Plastering Inside 8-Sep 10-Sep
Plastering Outside 10-Sep 12-Sep
Tiling 11-Sep 12-Sep
P & L IPS flooring 50 mm thick 11-Sep 12-Sep
Water ProofingSales bldg. roof top 6-Sep 7-Sep
S/F Plain/Frosted glass 12 mm thick 13-Sep 14-Sep
P & F Frame work for fixed glass 13-Sep 14-Sep
SANITARY 8-Sep 10-Sep
Construction of septic tank 2-Sep 9-Sep
Construction of soak pit 3-Sep 10-Sep
Painting 14-Sep 18-Sep
Electrical fitting fixing and finishing 9-Sep 21-Sep
Handingover 21-Sep 21-Sep
U T H - PANATHUR
O - PLOT SIZE 38 M X 25 M
C H A R T - 7 W E E K S
### ### 24 ### ### 27 ### ### 30 ### 32 33 ### 35 ### ### 38 ### ### 41 ### ### 44 ### 46 ### 48
26-Aug-19
27-Aug-19
28-Aug-19
29-Aug-19
30-Aug-19
31-Aug-19
10-Sep-19
13-Sep-19
14-Sep-19
15-Sep-19
16-Sep-19
17-Sep-19
18-Sep-19
19-Sep-19
20-Sep-19
21-Sep-19
12-Sep-19
11-Sep-19
1-Sep-19
2-Sep-19
3-Sep-19
4-Sep-19
5-Sep-19
6-Sep-19
7-Sep-19
8-Sep-19
9-Sep-19
R E T A I L S O U T H - PANATHUR
CONSTRUCTION OF NRO - PLOT SIZE 38 M X 25 M
D E T A I L E D B A R C H A R T - 7 W E E K S
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47
Sl No. Description Start Date End date
6 DRIVE WAY & ROAD WORK
230mm soling 21-Aug 26-Aug
230mm thick compacted W.M.M using
stone agg.50-75mm
27-Aug 29-Aug
Laying of Hume pipe for Rainwater 17-Aug 18-Aug
Laying of Hume pipe for cables 17-Aug 18-Aug
Laying of paver block 8-Sep 10-Sep
Approach work Bitumen/Paver 12-Sep 14-Sep
7 PUMPS Island
Excavation for rain water chamber 10-Aug 12-Aug
PCC below 150 mm dia hume pipe 13-Aug 14-Aug
150 dia Hume pipe laying from rain 15-Aug 16-Aug
Installation of Pump inlcuidng stand
Electrical cable laying for pump 23-Aug 25-Aug
Commisioning of pumps 27-Aug 29-Aug
Pump Island granite fixing 11-Sep 13-Sep
8 PIPE LINES
Excavation for Product line tranch 15-Aug 12-Aug
PCC for trench 13-Aug 14-Aug
Masonry wall for trench 15-Aug 21-Aug
Laying of product line 22-Aug 24-Aug
Filling of trench with sand 25-Aug 25-Aug
Pre cast slab on Trench 26-Aug 31-Aug
9 KERB WALL
Excavation ordinary soil upto 1.5m 9-Sep 11-Sep Foundation - PCC 1:4:8 mix 12-Sep 12-Sep
Brick Masonry in foundation in C.M1:6 13-Sep 15-Sep
Cement Plastering 12mm Tk 16-Sep 18-Sep
Painting with White cement paint
(snowcem)-2 Coats
16-Sep 18-Sep
13-Aug 14-Aug
15-Aug 21-Aug
22-Aug 24-Aug
25-Aug 25-Aug
26-Aug 31-Aug